Professional Documents
Culture Documents
Design of An Alternative Energy Plant For A Poultry Farm in Davao City
Design of An Alternative Energy Plant For A Poultry Farm in Davao City
Abstract — A poultry farm in Davao City was selected, and a grid-tied plant was designed to accommodate its
energy needs with the minimum of capital expense. Among available energy sources for a typical Davao City poultry
farm, poultry manure was selected due to its ready availability and the low capital cost required to construct a
biogas-fueled plant. Among a sample of five (5) poultry farms in Davao City, Morning Sun Poultry Farm was
selected for having the highest potential population of poultry, and was calculated to have an average power
requirement of 45.4 kW. The designed biogas plant has a digester volume of 997.2 m³, and was projected to produce
538.9 m³ of biogas per day (138.8 kW). The generator set is a 75 kVA PowerLink GXE60-6NG, with 36% full-load
efficiency. Together, the digester and generator can continuously produce a maximum of 49.97 kW when operating.
I. Introduction
Between poultry and livestock, poultry raising involves a great deal more electric energy
compared to animal feed to carry out (E. M. Barber et al. 1989). This is due in large part to high
Poultry farm heating is generally carried out through electric heating lamps or gas heating
lamps (Department of Agriculture - Cagayan Valley Region 2004). Electricity and LPG in Davao
City cost Php 13.6883 (DASURECO 2022) and approx. Php 7.11 (Department of Energy 2022),
operating on pure electricity would amount to Php 5.5M per annum, while operating gas burners
would amount to around Php 3M per annum. There are, therefore, significant savings to be made
1
if in-house energy production could be made to supplement consumption in any way, and in the
As poultry farms have free access to a feedstock of poultry manure, they also have an
opportunity to take advantage of this potential energy source. This paper aims to design an
economical plant that can best benefit a poultry farm operator and satisfy their farm's energy
needs when operating. To this end, all decisions made here were driven by the assumption that it
would be the poultry farm operator who would be financing the project: capital cost must be kept
under Php10M, while the project should achieve break-even on savings within five (5) years. A
II. Methodology
Although biogas from poultry manure is an obvious choice, it is necessary to account for
other possibilities. After inspecting satellite images via Google Maps, it was determined that
most farms in Davao City only have access to wind, solar, and manure resources.
Conventional fuels, such as coal, natural gas, and diesel fuels, were immediately rejected as
either the equipment necessary to convert these into electricity were too expensive (coal and
natural gas), or generation with the fuel is more expensive compared to grid electricity
(Php13.6883 (DASURECO 2022)); at Php 64.03 per liter (Department of Energy 2023 Jan 10)
and 37.184 MJ/L (Rentar Fuel Catalyst 2018), electricity from diesel would cost Php 15.50 per
2
This left conversion technologies for poultry manure, wind, and solar resources for
consideration under the ff. criteria: 1) land requirements, 2) day-night availability, and 3) capital
cost. In the end, biogas conversion of poultry manure was selected. Please see "3.1. Fuel and
A sample of five (5) poultry farms were taken from an area northwest of the urbanized city
proper, near the geometric center of the area recognized as Davao City. Google Maps was used to
find the poultry farms (in January 2023), and directly adjacent farms were avoided for inclusion.
A multi-attribute utility scoring model was used to select a site for which a biogas plant would
be designed. All multi-attribute utility models in this paper were performed in this manner:
Each attribute array (column) is normalized to values between 0 and 1, corresponding to the
"worst" and "best" values of that array; when the minimum value is considered "best"
("min-is-best"), the minimum value is normalized to 1; for "max-is-best," the maximum value is
normalized to 1. After normalization, fractional weights (which sum to one (1)), which encode
3
arbitrary preference, are multiplied element-wise to their corresponding attribute arrays. Adding
the weighted values of each candidate's record (row) results in their final utility score.
For site selection, only two attributes were considered: total farm housing area, and total free
area. Total farm housing area considers the total floor area visible from satellite images, which
could be reasonably assumed to be poultry housing sheds. Total free area is the total area of what
could reasonably be assumed as the full extent of the farm's property, sans existing structures and
obvious developments.
These attributes were assigned weights of 60% (housing area) and 40% (free area). It was also
desired for both to be maximized, firstly to have a large population from which to draw biogas
feedstock, and secondly so that any new biogas plant may fit on the existing property, forgoing
Figure 1. Biogas system diagram. This paper’s concerns are highlighted green.
4
The system chiefly consists of a mixer, digester, effluent treatment, gas holder (usually part of
the same physical structure as the digester), H2S scrubber, generator, and a grid interconnection
The system was designed with grid interconnection in mind. Off-grid systems are more
expensive, with the implied additional battery storage systems and redundant generators driving
up capital cost (Grid-Tied vs. Off-Grid Solar 2020 Jul 8). Moreover, biogas production is
unstable, fluctuating wildly with temperature and the biochemical composition of the feedstock
(International Renewable Energy Agency 2016). Grid interconnection also allows the grid to
handle power peaking profiles, which a poultry farm ought to have; heating is more necessary at
3. Generation selection
4. Digester redesign
2.4.1. Assumptions
There were several critical assumptions made to calculate site power requirements:
1. The farm has both chicks and adults in its poultry population.
5
4. Floor area is underutilized (Assumed area usage factor: 0.7)
5. Heating lamps do not run all the time. (Assumed usage factor: 0.2).
A commercially-available heating lamp (Chishtiya Poultry Services) was found and its specs
were used to estimate an average heating power coverage. The 2 kW lamp was reported to cover
Multiple assumptions have to be made at this point, lacking information on actual farm
operations, to estimate the floor area that must be heated. The utilized floor area was assumed to
be 0.7 times the available floor area of housing. The space requirements for layers are different
to those for broilers; for simplicity, the utilized floor area was assumed equally halved between
them:
𝐴𝑢𝑡𝑖𝑙 = 𝐴𝐿 + 𝐴𝐵 , where 𝐴𝐿 = 𝐴𝐵
(Eq. 1)
Each sub-area AL and AB were further partitioned into sub-allotments for young chicks, old
6
The area allotments for old chicks were considered to be roughly twice that as for young
chicks, and the remaining area after finding both allotments for young and old chicks were
sub-allotments in Eq. 2a as 𝐴𝐿𝑋 = 𝐴𝐿,𝑌𝐶 , 𝐴𝐿(2𝑋) = 𝐴𝐿,𝑂𝐶 , and 𝐴𝐿(1 − 3𝑋) = 𝐴𝐿,𝐴 . The
With the areas AL and AB known, it was necessary to initially assume an allotment X for the
young chicks. However, since it was additionally assumed that chicks consisted one-third (⅓) of
the overall poultry population, and chicks were known to occupy less space than adults, the
In order to meet this assumption, the area allotment for young chicks was adjusted; from the
given areas, and with space requirements known, it is possible to estimate the total chick and
adult population contained in those areas. The young chick area allotment X was then manually
adjusted until the ratio of chicks to the total population fell between 30% and 33.3%, finally
stopping at 𝑋 = 0. 05 .
7
Table 2. Poultry demographic calculation based on space requirements and area allotments.
OUTPUT
INPUT PARAMETER VALUE UNIT VALUE UNIT
PARAMETER
Layer space requirement (day-old 0.009677
to four weeks) 4 sqm/chick Total layers 229886 heads
Layer space requirement (4–8 0.019354
weeks) 8 sqm/chick Young chicks 47393 chicks
Layer space requirement (9+ 0.035483
weeks) 8 sqm/adult Old chicks 23696 chicks
Broiler space requirement 0.027870
(day-old to three weeks) 912 sqm/chick Adults 158797 adults
Broiler space requirement (3–4 0.046451
weeks) 52 sqm/chick Total broilers 86982 heads
Broiler space requirement (5+ 0.092903
weeks) 04 sqm/adult Young chicks 16456 chicks
Layers allotted area 6552 sqm Old chicks 9874 chicks
(Layer) Young chicks area 458.64 sqm Adults 60652 adults
(Layer) Old chicks area 458.64 sqm Total heads 316868 heads
(Layer) Adults area 5634.72 sqm Total layer chicks 71089 chicks
Broilers allotted area 6552 sqm Total broiler chicks 26330 chicks
(Broiler) Young chicks area 458.64 sqm Total adults 219449 adults
(Broiler) Old chicks area 458.64 sqm Total chicks 97419 chicks
(Broiler) Adults area 5634.72 sqm - - -
Total allotted for chicks 1834.56 sqm - - -
Finally, the heated floor area was taken to be the total area for all the chicks, since these are
the only part of the poultry population for whom heating is important (Department of Agriculture
- Cagayan Valley Region 2004). Incidentally, the ratio of the area allotted to chicks vs. the total
floor area of housing visible from satellite image was found to be 0.105 ≈ 0.1.
8
(Eq. 4)
where 0.1 is the estimated area allotment of chicks (as earlier), 9.29 is the heating lamp coverage
(in m²/kW), and A is the total floor area in m², and P h is given in kW.
Using an earlier estimation of poultry farm power consumption (see “2.4.1. Assumptions”,
no.7), the total power requirement can be estimated from a farm's total floor area as:
𝑃𝑡𝑜𝑡 = 1. 15𝑃ℎ
(Eq. 5a)
0.1𝐴
or 𝑃𝑡𝑜𝑡 ≈ 1. 15( 9.29 ) = 0. 0124𝐴
(Eq. 5b)
2.5. Digester Design
2.5.1. Overview
9
The digester design consists of a hollow cylindrical masonry (CHB) structure, waterproofed
both internally and externally, then, instead of a masonry roof, which is difficult to construct, it is
covered with two layers of flexible HDPE plastic sheets. As biogas is generated from the
fermentation chamber, it will collect and inflate the HDPE layer. Majority of the structure is
below ground. As biogas collects in the gas holder, slurry is pushed out of the outlet; a concrete
collar around the inlet ensures the slurry is trapped there, and so all overflow is hence only from
the outlet. The biogas’s pneumatic action causes a hydraulic level difference between the slurry
This design was chosen so that local labor could be easily tapped and directed for its
Note that the HDPE layer should be protected against kinetic strikes and thermal damage with
a cap of hard material like plywood or sheet steel, but it is not strictly necessary for the operation
of the digester; the actual form of its protection was left to the preference of the farm operator.
The parameters for estimating the necessary dimensions of the digester are:
● Geometric ratios
○ Diameter-to-height ratio
10
For calculating influent intake, please see the subsequent sub-sections, "Effect of HRT on
Per-capita Biogas Yield", "Estimating Required Biogas Production", and "Estimating Influent
Intake."
The scale of digesters is typically described in terms of the volume of the whole structure in
cubic meters (m³). The total volume is understood as the sum of the slurry/fermentation
chamber's and gas holder/chamber's volumes. It is thus necessary to assume a ratio between the
slurry chamber and the gas holder; there is no fixed rule, but ratios from 1:1 to 5:1 have been
(Eq. 6)
where HRT is the hydraulic retention time (in days), I is the influent intake rate (in m³/day), and
Rv is the ratio of the volumes of the fermentation chamber to the gas holder (dimensionless).
HRT was set to 40 days, and Rv to 4; please see subsection “Estimating Influent Intake” for that
Meanwhile, for this design’s right circular cylinder, the diameter can be found with this
formula:
(Eq. 7)
11
Finally, using the relation 𝑅𝑣 = 𝑉𝑓/𝑉𝑔 = 𝐻𝑓/𝐻𝑔 , which is true for any cylinder, the heights
of the gas holder, fermentation chamber, and the overall of the digester can be found with:
(Eq. 8a)
𝐻𝑓 = 𝑅𝑣𝐻𝑔
(Eq. 8b)
𝐻 = 𝐻𝑓 + 𝐻𝑔
(Eq. 8c)
It is important to keep track of the height of the fermentation chamber, in particular. This
design requires the waterline of the slurry to be below ground level so that the difference
between the slurry waterline and the outlet waterline creates a hydraulic head, which is the
Although the design assumes a right circular cylinder, the actual case is that the double HDPE
sheets will inflate as biogas is generated, and so the actual volume of the gas holder will change.
When fully inflated, the actual gas holder volume can be approximated by describing a spherical
(Eq. 9)
The digester's required influent intake cannot be calculated without knowing the per-capita
biogas yield.
12
Biogas production (in m³/day) from a control mass of manure/organic slurry is dependent on
Hydraulic Retention Time, or HRT, which is the average number of days that a control mass of
slurry spends in the digester before it eventually migrates to the digester's outlet.
The higher the HRT, the more biogas is yielded from a control mass. For most manure types,
an HRT of 60 days (Sajjad 2002) is enough to extract 100% of all potential biogas yield, while
an HRT of 15±5 days will extract 50% of the potential biogas yield, the exact HRT value wildly
depending on manure type. It is for this reason that HRT values typically range from 40 to 60
days, but even so, 5 days is not unheard of (Sarah House 2011).
Increasing HRT by D days will mean that the overall digester volume must also expand to
Sajjad quotes a biogas yield of 0.00776 to 0.0112 m³ per head of poultry per day, which was
understood to be data collected at a typical HRT; it was assumed that this data was applied at an
HRT of 60 days. By assuming 50% biogas yield at an HRT of 15 days, and a maximum yield of
0.0112 m³ per head of poultry per day at an HRT of 60 days, a piecewise linear equation was
constructed to approximate the biogas yield Y (in m³ per head of poultry per day) at a particular
(Eq. 10)
2.5.4. Estimating Required Biogas Production
To estimate the required biogas production (PB , in kW), the ff. equation was used:
13
(Eq. 11)
where Ptot is the total site power requirement, fr is the reserve factor (assumed 0.1), η𝑒 is the
generator’s electrical conversion efficiency (initially assumed as 0.4), and PF is the generator’s
power factor (assumed as 0.95, due to the site consumption being mostly from resistive loads).
3
𝑚 3600
To convert PB in kW to PB in m³/day, use 𝑃𝐵[ 𝑑𝑎𝑦 ] = 𝑃𝐵[𝑘𝑊] × 22500
(Eq. 11b), where
To estimate the digester's influent intake (in m³/day), the ff. equation was used:
(Eq. 12)
Where 𝑃𝐵 is biogas production in m³/day, 𝑎 is the unit animal discharge (taken to be 0.08
kg/adult/day (Tańczuk et al. 2019)), 𝑐𝑇𝑆 is the total solids concentration of poultry manure (
𝑐𝑇𝑆 = 0. 20 (R. W. Melse PhD and F.E. de Buisonjé BSc 2020)), 𝑌 is the per-capita biogas yield
in m³/day/adult, and 𝑐'𝑇𝑆 is the required total solids concentration (0.08, per recommendation of
Sajjad).
The equation already encapsulates the calculation of the number of heads-poultry required to
deliver the necessary animal waste, the total amount of animal waste they produce, the amount of
water necessary to add to dilute the total solids concetration to the required amount, and finally,
14
2.6. Generator Selection
Generator selection was carried out using multi-attribute utility scoring, with attributes being
"Prime Power Rating (kVA)" and "efficiency". A weight of 60% was assigned to Prime Power
Rating. Initial selection of candidates looked only for generators which were rated for prime
power, were rated between 60 kVA (close to site requirement) and 160 kVA (est. maximum
before generator will be loaded under 30%), and were fueled by natural gas.
The acquisition, or design and construction, of an H2S scrubber is outside of the scope of this
Biogas is composed of 60–90% methane, trace amounts (up to 0.5%) of hydrogen sulfide
(H2S), and the rest, carbon dioxide. Most problematic is H2S, which can drastically shorten the
life of generator components, and so it is necessary to remove it from the biogas before it enters
the generator.
15
One simple and robust technology is the "iron sponge," which reacts H2S with iron oxide,
forming iron sulfide. Exposing iron sulfide to atmospheric oxygen recovers the iron oxide, and
the sulfur is deposited as elemental sulfur. Hence, the original media is considered reusable,
A simple H2S scrubber can be constructed by fitting a barrel with gas inlet and outlet ports,
and then filling it with rusted iron, with the aim to maximize surface area. Using rusted 0000
grade steel wool is known to have a noticeable improvement over using rusted iron shavings, but
appropriate sizing is necessary to be able to adequately process the large volumes of biogas
moving through the scrubber. (Stephanie Lansing and Gary Felton 2018)
Residence Time (RT) is the average amount of iron oxide contact time that a volume of gas
experiences as it moves through the scrubber. RT values range from 1 to 15 minutes. (Stephanie
Hence, the ff. equation estimates the required scrubber volume (m³), given some desired
Residence Time (RT, in seconds) for a gas flow 𝑉˙𝑔 (in m³/s):
𝑉𝑠𝑐𝑟𝑢𝑏𝑏𝑒𝑟 = 𝑉˙𝑔(𝑅𝑇)
(Eq. 13)
When using poor-quality media, such as coarse, rusted iron scrap and filings, maximizing RT
is a must to make up for lower scrubbing rates; as of writing, a cursory internet search did not
reveal any Philippine company dealing in commercial H2S scrubbing at an agricultural biogas
plant scale, and so it is expected that the operator must improvise one and take this fact into
16
2.8. Economic Analysis
Compared to a simple masonry structure, the generator was expected to fail first; hence, the
plant lifetime was assumed at 15 years, which is similar to the lifetime of a diesel plant (Castalia
The total capital cost of the project was simplified and taken to be the cost of construction of
the biogas digester, plus the cost of the generator set and its installation.
The cost of construction of the biogas digester was estimated using quotes taken from
Productivity Ratio”, “Construction Labor Rates in the Philippines December 2019”, and
“Embankment Price List Philippines”. Using these prices, costs of labor, excavation, masonry
bricklaying, foundation laying, and waterproofing were estimated as a function of the dimensions
of the digester (surface areas, volumes, diameter, and height), which did demonstrate non-linear
behavior as the surface area-to-volume ratio of the digester changed when the parameters were
DIMENSIONS
Disk area 269.2712443 m^2
Circumference 58.17011476 m
Total height 3.70 m
17
Excavation surface area 470.689898 m^2
Number of digesters 1 digesters
Chambers inner wall surface area 484.6882398 m^2
Excavation volume 932.37 m^3
COSTING
The cost of the generator set was estimated using four (4) price quotes provided by Davao
City Industrial Supply and Services (2019), for 10, 25, 25, and 125 kVA ratings. Although an
exact quote for all power ratings could not be acquired, it was determined that the quote prices
2
(Q, in PHP) made a very good linear fit (𝑅 = 0. 9916) with the power rating 𝑃𝑔𝑒𝑛 (in kVA).
Php100,000.
The ff. operating costs were accounted: wages, water, maintenance, and logistics.
Wages were accounted by an “operator wage” and “consultant wage”: four (4) operators at
Php300,000 per year, and one (1) visiting biogas specialist/consultant at Php150,000 per year.
Water was estimated with Php30 per cubic meter. Maintenance was estimated with 3% of total
capital cost (in this case, around Php90,000) per year. Logistics, which includes the cost of
moving feedstock to the digester, was estimated at Php100 per day in moving equipment fuel
costs.
Differing inflation rates were applied to each one; water: 6%; wages: 4%; logistics: 7%; and
maintenance: 7%. These were applied arbitrarily, to reflect faster-rising prices in products
compared to labor.
Tying the plant to the grid would allow the grid to make up for deficiencies in unstable biogas
production. With the plant being rated below 100 kW, it is also a candidate for Net Metering;
excess production during daytime, when the farm would tend not to use its heating lamps, could
be sold back into the local distribution grid for credits. (Department of Energy Philippines n.d.)
19
For simplicity, feed-in tariffs and other financial considerations were omitted from
consideration. As such, when the plant produces in excess, the credit earned was assumed to be
20
Figure 4. Final digester dimensions (drawn as close to scale as possible).
After selecting a generator and determining digester parameters, the above system diagram
The designed digester is large, at 997 m³ and a diameter of around 18.5 m. This much,
however, is well within the range of digesters cataloged by Ludwig Sasse (1988). It requires 5.1
metric tons of new manure feedstock daily, with 7.7 metric tons of water mixed in. It is expected
to produce 538.92 m³-biogas/day, for which a conservative 5.6 m³ H2S scrubber is necessary for
continuous production (538.92 m³/day, or 138.8 kW) will only be able to run the generator at
70–80% load. Even so, the digester itself is also oversized (138.8 kW x 36% = 49.97 kW)
compared to the site requirements (45.41 kW), and so is expected to amply supply the site.
21
Figure 5. PowerLink GXE60-6NG: 75 kVA prime power rating, 36% efficiency (likely
full-load).
It should be noted that the consumption profile of a poultry farm was assumed to peak during
nighttime, when temperatures drop and heating becomes more necessary. If all heating lamps
were used during peak, peak consumption could reach 197.48 kW, which would outstrip the
designed plant’s own capacity. It was for this reason that a grid-tied interconnection was
considered necessary—besides grid-tied plants being regarded as far cheaper in capital cost than
completely off-grid systems (Grid-Tied vs. Off-Grid Solar 2020 Jul 8).
At an assumed capacity factor of 0.67, the plant is expected to generate 418,466.93 kWh/year,
Note that it is possible to raise the biogas production of the digester without changing its
physical design. By increasing the influent intake rate, the rate of manure being processed would
22
also increase, raising biogas production, but also necessarily decreasing hydraulic retention time,
and thus decreasing the biochemical conversion efficiency of the digester (m³/kg, biogas to slurry
influent). This biogas production increase will be of marginally decreasing utility, as well; the
higher the influent intake, the more labor and/or equipment is necessary, and the more water
On the other hand, this “trick” is beneficial to make up for any differences in practical
temperature fluctuations, feedstock composition, etc. If the plant designed here were to
underproduce in actual practice, all the operator would have to do is granularly increase the
The digester was estimated to cost ₱2,854,031.77 to construct (including labor), while the
23
Figure 7. First year operating expenses. This makeup was not predicted to appreciably change
In the first year, the operating cost of the plant was estimated at ₱1,616,664.96, of which
3.3. Cost-Benefit
Surprisingly, the plant was projected to pay back in less than one (1) year.
24
Thanks to the Net Metering scheme, the plant was expected to be able to earn Php4.17M in
credits. Together with plant lifetime savings of Php44.67M, the plant nets a benefit of
Php48.84M.
In reality, however, Net Metering credits are not transferable (Department of Energy
Philippines n.d.); the farm operator would not necessarily earn disposable cash, and so it would
make little sense for the farm operator to perpetually accumulate credits. In the first place, the
plant was oversized in order to accommodate the fact that biogas production is variable, and
It is more likely that the farm operator will willingly spend their accumulated credits and
underuse the plant, if only also to save on operating costs. In such a case, there would ideally be
zero credits by the end of the year, and only Php44.67M in benefit. This will come to a
25
IV. Conclusion and Recommendations
A biogas power plant was designed with a 997 m³ digester and 75 kVA natural gas generator
economical and attractive, ideally presenting a payback period of less than one (1) year, and
offering savings more than ten times that of the capital expense.
This design, however, omitted further details of the H2S scrubber, which is absolutely critical
to the life of the generator. There is also the fundamental issue that the design heavily relied on a
grid interconnection to handle peaking, not to mention that the usage factor of the heating lamps
was simply assumed with no solid grounds. Were the plant capacity requirement to go beyond
100 kW, it would legally no longer be a candidate for the Department of Energy’s net metering
scheme; the farm/plant operator would have to make for other grid interconnection
arrangements, which they may potentially have to fund out-of-pocket, or they would otherwise
Another area unexplored in this paper is cogeneration. Heating lamps come as either gas or
electric, and it is entirely possible to make more efficient use of biogas if it were fed straight into
gas burners rather than an electric generator. However, the site which this paper selected was
exceptionally large, to the point that, by own estimation, the selected site would have consumed
twelve (12) 11-kg LPG cylinders per day. This was assumed too labor-intensive to manage;
meanwhile, electrical infrastructure appeared far less demanding in operation, and was assumed
scheme to hectare-scale farms, transporting biogas for hundreds of meters towards hundreds of
26
Several shortcuts were taken to make the economic analysis. The financial effects of feed-in
tariffs were unaccounted, and many critical affairs, such as the maintenance costs of both the
digester and generator, or differing inflation rates for each plant input, were summarily assumed
as percentages of the capital cost, or given some arbitrarily-erratic value from the norm. The cost
of consultancy, as well, was not known. The cost of construction, including labor and materials,
should always be deferred to the locale of interest for accuracy—which this paper failed to do.
At the least, the generator cost estimation was grounded in prices offered by a Davao City
company, and the selected generator was of a brand known to be carried by that company, but
By far, what might be most difficult for the future designer is to find a biogas-compatible
generator. It may ease them to consider finding a source of diesel-to-natural gas or diesel-to-LPG
conversion kits, which will allow a broader scope of diesel generators to be included among
generator candidates.
Notes
1. The author previously estimated the power consumption profile of a poultry farm in an
27
References
Alibaba.com. 1.5mm Hdpe Waterproofing Membrane For Landfill Project In Philippines - Buy
Hdpe Waterproofing Membrane,Hdpe Waterproofing Membrane,Hdpe Waterproofing
Membrane Product. Alibaba.com. [accessed 2023 Jan 16].
https://www.alibaba.com/product-detail/1-5mm-HDPE-Waterproofing-Membrane-for_160015
4090971.html.
Castalia Strategic Advisors (last). 2015. Generation Cost Benchmarking. [accessed 2021 Nov 5].
http://www.erc.gov.ph/Files/Render/media/CASCON_GENCOSTBEN_FINAL.pdf.
Chishtiya Poultry Services. Electric Brooder, Chishmo 1000 Basic. indiamart.com. [accessed
2023 Jan 16].
https://www.indiamart.com/proddetail/electric-brooder-chishmo-1000-basic-1829468830.html
.
DASURECO. 2022. December 2022. [accessed 2023 Jan 14].
https://dasureco.com/december-2022/.
Davao City Industrial Supply and Services. 2019. For sale: Power GENERATOR (diesel,
gasoline, & gas). Facebook. [accessed 2023 Jan 4].
https://www.facebook.com/permalink.php?story_fbid=pfbid02RuAMEB7bXaBHsBdGsvHo4
b4JNGwsmeKsDaW4AeGqqNFAngWdBsNoYVLjMoGWjyNFl&id=123780495011222.
Department of Agriculture - Cagayan Valley Region. 2004. Tips on Poultry Raising Introduction.
[accessed 2022 Apr 13].
https://cagayanvalley.da.gov.ph/?smd_process_download=1&download_id=509.
Department of Energy. 2022. Prevailing Retail Prices of 2.7 Kg. to 11 Kg. Household LPG in
Mindanao as of December 06, 2022. [accessed 2023 Jan 14].
https://www.doe.gov.ph/sites/default/files/pdf/price_watch/lpg_min_2022-dec-06-09.pdf.
Department of Energy. 2023 Jan 10. Mindanao Prevailing Retail Pump Price (As of: January 10,
2023).
https://www.doe.gov.ph/sites/default/files/pdf/price_watch/petro_min_2023-jan-10.pdf.
Department of Energy Philippines. Net Metering Home. [accessed 2023 Jan 16].
https://www.doe.gov.ph/net-metering-home?withshield=1.
E. M. Barber, H. L. Classen, P. A. Thacker. 1989. Energy Use in the Production and Housing of
Poultry and Swine — An Overview. Can J Anim Sci. 69:7–21.
energypedia. 2016 Apr. Electricity Generation from Biogas. energypedia. [accessed 2023 Jan
16]. https://energypedia.info/wiki/Electricity_Generation_from_Biogas.
Grid-Tied vs. Off-Grid Solar: Which is Right for You? 2020 Jul 8. Unbound Sol. [accessed 2023
Jan 16]. https://unboundsolar.com/blog/grid-tied-vs-off-grid-solar.
28
International Renewable Energy Agency. 2016. Measuring small-scale biogas capacity and
production. Abu Dhabi: International Renewable Energy Agency.
John Poe Taylor. 2003. Removal of Hydrogen Sulfide from Biogas. [accessed 2023 Jan 5].
https://web.archive.org/web/20100626014530/http://www.cowpower.cornell.edu/project_docs
/Thesis_jpt7.pdf.
Ludwig Sasse. 1988. Biogas Plants. [accessed 2023 Jan 2].
https://www.susana.org/_resources/documents/default/2-1799-biogasplants.pdf.
R. W. Melse PhD, F.E. de Buisonjé BSc. 2020. Manure Treatment and Utilisation Options.
[accessed 2023 Jan 16].
https://www.wur.nl/en/show/Manure-treatment-and-utilisation-options.htm.
Rentar Fuel Catalyst. 2018. Why Diesel Engines are More Fuel Efficient than Gasoline Engines.
Fuel Catal. [accessed 2023 Jan 16].
https://rentar.com/diesel-engines-fuel-efficient-gasoline-engines/.
sajjad. 2002. Design of Biogas Plant. [accessed 2022 Dec 12].
https://sswm.info/sites/default/files/reference_attachments/BRC%20ny%20Design%20Biogas
%20Plant.pdf.
Sarah House. 2011. Design, construction and maintenance of a biogas generator. [accessed 2023
Jan 2].
https://oxfamilibrary.openrepository.com/bitstream/handle/10546/136537/tbn21-biogas-gener
ators-24062011-en.pdf?sequence=5&isAllowed=y.
Stephanie Lansing, Gary Felton. 2018. Hydrogen Sulfide (H 2 S) Removal at a Northeastern
Dairy Farm Digester using Iron Oxide: Case Study. Department of Environmental Science
and Technology, University of Maryland. [accessed 2023 Jan 5].
https://enst.umd.edu/sites/enst.umd.edu/files/files/documents/Extension/Case-Study_H2S-Re
moval-Iron-Oxide_UMD.pdf.
Tańczuk M, Junga R, Kolasa-Wiecek A, Niemiec P. 2019. Assessment of the Energy Potential of
Chicken Manure in Poland. Energies. 12:1244. doi:10.3390/en12071244.
29