Professional Documents
Culture Documents
13.02.2023 - Quotation Analysis For C523 Naga Laydown Area (With 30 1 Profit Margin)
13.02.2023 - Quotation Analysis For C523 Naga Laydown Area (With 30 1 Profit Margin)
A SITE GRADING
Clearing / Grubbing and stripping of top soil, hauling and disposal of unsuitable materials,
a garbage, vegetation / trees to the area within the substation designated by PESTECH / NGCP at lot 1.00 2,231,832.00 1,562,282.40 - By Others By Others By Others
Laydown Area 1 and Laydown Area 2 (approximate 4990 sq.m)
Backfilling to match existing ground level of approved materials, spreading / levelling and
b compaction (including FDT) approximate 300mm to 400mm depth at Laydown Area 1 and lot 1.00 10,623,323.00 7,436,326.10 - By Others By Others By Others
Laydown Area 2 (approximate 4990 sq.m)
4 Others -
a Laydown area 1&2 backfilling, compaction nd FDT lot 1.00 - By Others 1,500,000.00 1,500,000.00 -
Demolition of seclusion fence and concrete affected by the expansion of Control Building. But this
b is on hold due to security reason. lot 1.00 - By Others 250,000.00 250,000.00 -
c Cutting Trees lot 1.00 - By Others 350,000.00 350,000.00 -
D PRELIMS
2 Escodel Construction
2.1 Permits and Minucipal Fees
a Building Permit - - By Client -
b Location Clearance - - By Client -
c Barangay Clearance - - By Client -
d Mechanical Clearance - - By Client -
e Electrical Permit - - By Client -
f Plumbing / Sanitary Permit - - By Client -
g Fire Permit - - By Client -
h DOLCE Clearance - - By Client -
2.2 Occupancy Permit - By Client -
2.3 Premiums of Bonds and Insurnce (Bond, Taxes, Certificates) - -
a Contractor's All Risk Insurance (CARI) lot 1.00 - - 300,000.00 300,000.00 -
b Comprehensive General Liabilities Insurance (CHLI) lot 1.00 - - By Client -
c Performace Bond (30% of the contract DP) lot 1.00 - - 260,000.00 260,000.00 -
d Surety Bond ( 60% of the Contract Progress Billing ) lot 1.00 - - 520,000.00 520,000.00 -
e Guarantee Bond ( 10% of the Contract Retention ) lot 1.00 - - 150,000.00 150,000.00 -
2.4 Temporary Facilities - -
a Site Office and Conference Room lot 1.00 - - 450,000.00 450,000.00 -
b Temporary Water Meter, Lines and Consumption lot 1.00 - - By Client -
c Temporary Electrical Meter, Wires and Consumption lot 1.00 - - By Client -
d Temporary T&B Portalets lot 1.00 - - By Client -
e Temporary Fence/Board-Ups, If Required lot 1.00 - - 350,000.00 350,000.00 -
f Adequate Protective Coverings for complete works lot 1.00 - - 120,000.00 120,000.00 -
g Storage for materials lot 1.00 - - 75,000.00 75,000.00 -
2.5 Mobilization of Workers and Equipment - -
a Delivery & Hauling Materials lot 1.00 - - 200,000.00 200,000.00 -
b Equipment Scaffolding Systems, Platforms abd Work Tables lot 1.00 - - 650,000.00 650,000.00 -
c Handling of Materials lot 1.00 - - 75,000.00 75,000.00 -
2.6 Site Safety, Security, Health & Sanitation and Fire Protection Devices - -
a Safety Officers lot 1.00 - - 450,000.00 450,000.00 -
b Security Lights lot 1.00 - - 50,000.00 50,000.00 -
c Signages lot 1.00 - - 20,000.00 20,000.00 -
d Personal Protective Equipment (PPE's) lot 1.00 - - 185,000.00 185,000.00 -
e Fire Extinguisher (Pre-Requisite for Building admin) during construction units 8.00 - - 5,000.00 40,000.00 -
2.7 Construction Engineers (Supervisions) - -
a Project Managers lot 1.00 - - 1,200,000.00 1,200,000.00 -
b Technical Staffs (3 Tech Staff) lot 1.00 - - 1,500,000.00 1,500,000.00 -
c Warehouseman lot 1.00 - - 360,000.00 360,000.00 -
2.8 As-Built Plans - -
a Structural & Architectural Plans lot 1.00 - - 250,000.00 250,000.00 -
.
TOTAL FOR CIVIL WORKS (LAYDOWN AREA FOR NAGA SUBSTATION) 64,718,339.00 45,302,836.60 31,340,265.00 37,766,425.07 34,228,451.16 36,756,977.18
Profit / Loss (PHP) : (13,962,571.60) 7,536,411.53 11,074,385.44 8,545,859.42
Profit / Loss (%) : -31% 17% 24% 19%