Spe 77669 MS PDF

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 18

SPE 77669

Reservoir Management Scope In A Mature Niger Delta Field


Ikomi, J. G. (SPE); Nwosu, C. J. (SPE); Mandhane, J. M.; Akem, B. T. (SPE) / The Shell Petroleum Development
Company Of Nigeria, Port Harcourt

Copyright 2002, Society of Petroleum Engineers Inc.


However, due to some operational difficulties, the existing
This paper was prepared for presentation at the SPE Annual Technical Conference and completion accessories could no longer be retrieved, and a
Exhibition held in San Antonio, Texas, 29 September–2 October 2002.
sidetrack from the existing well was initiated, after
This paper was selected for presentation by an SPE Program Committee following review of
information contained in an abstract submitted by the author(s). Contents of the paper, as
abandoning the X and deeper Y reservoirs in the Awoba-2
presented, have not been reviewed by the Society of Petroleum Engineers and are subject to well. The sidetrack (Awoba-2ST) was planned at a maximum
correction by the author(s). The material, as presented, does not necessarily reflect any
position of the Society of Petroleum Engineers, its officers, or members. Papers presented at deviation of 6 degrees from kick-off (circa 10650 ftah) to
SPE meetings are subject to publication review by Editorial Committees of the Society of
Petroleum Engineers. Electronic reproduction, distribution, or storage of any part of this paper
achieve a maximum lateral displacement of 300 ft, at a total
for commercial purposes without the written consent of the Society of Petroleum Engineers is depth of 13240 ftvd. The revised plan would allow for the re-
prohibited. Permission to reproduce in print is restricted to an abstract of not more than 300
words; illustrations may not be copied. The abstract must contain conspicuous evaluation of the X (for possible completion in the sidetrack)
acknowledgment of where and by whom the paper was presented. Write Librarian, SPE, P.O.
Box 833836, Richardson, TX 75083-3836, U.S.A., fax 01-972-952-9435.
and the completion of the deeper Y reservoir.

On acquiring the log data in the Awoba-2ST, the X reservoir


Abstract showed clear evidence of preferential flushing when the
resistivity profile was compared to that of Awoba-2 prior to
An integrated petroleum engineering investigation of the production (see Figure 2 ).
Awoba field X reservoir (about 300 feet thick) was
necessitated by its puzzling production performance. Field Location and Data
Considered to be one of the largest hydrocarbon bearing The Awoba field straddles OMLs 18 and 24, some 40 km SW
reservoirs in the Awoba field, with an ultimate oil recovery of of Port-Harcourt Nigeria (fig. 1). The field was discovered in
52.5 MMstb, this reservoir produced only 13.7 MMstb dry oil 1982 by Awoba-2, and to date, a total of nine (9) wells have
and started cutting water. Results of a recent sidetrack from been drilled into the Awoba structure. There are 29
an existing well in the field have provided a basis for updating hydrocarbon bearing reservoir sands between 7000 and
existing static and dynamic models which in turn have 15000 ftss.
provided a framework for simulating the movement of water
and consequently improved reservoir management. The X is the third largest reservoir in Awoba Field, accounting
for about 17% of the field’s expectation STOIIP of 573.6
Introduction MMstb. The reservoir has been completed in five (5) wells,
Production from the completed interval on the X reservoir in Awoba-2, -3, -5, -6 and –8.
Awoba-2 had indicated a rapid increase in BS&W (see Figure
2), although the POWC from carbon-oxygen log of April 1998 Production started from Awoba-2 in 1992, and as at 1.1.2002
was estimated to be some 59 ftvd below the lower cumulative oil production from the reservoir is some 13.7
perforations. The withdrawal rate was also judged to be well MMbbls of oil, with current BS&W of 70% as seen in
below the critical rate for the onset of water coning. It was Awoba-3S.
suspected that the high BS&W from the completed interval
was the result of poor cement bond (Ref. 1). A rig re-entry, to Reservoir Geological Concept
effect some well repairs, was to afford the team the Environment of Deposition: The depositional environment of
opportunity to investigate the possibility of annular (casing- the Awoba X sand, as interpreted from core/well data,
formation annulus) communication due to probable poor zonal biostratigraphic/ichnofacies and sequence stratigraphy,
isolation during the cementation at primary completion. indicate the reservoir was deposited in a coastal/marginal
marine setting occasioned by fluctuations in sea level. The
Subsequent recovery action planned, included a remedial sedimentary setting is predominantly deltaic and comprises of
cement squeeze followed by re-perforation of the same shoreface and tidal channels/inlets deposits and marine shales.
interval.
2 J. IKOMI, J. MANDHANE, C. NWOSU, B. AKEM SPE 77669

Stratigraphic Setting: The entire X sequence is capped by an sands have the same reservoir characteristics as the top
interval consisting of highly argillaceous bioturbated offshore shoreface sands.
sandstone of the X reservoir a thickness of about 80 feet (Fig.
3). The sand represents a major backstepping of the delta 3-D Reservoir Static Model
shoreline as a precursor to the period of maximum flooding 3-D Static and Dynamic models were built for the X reservoir
represented by an overlying W shale. in 1998 in order to understand the behavioral patterns of the
subject reservoir. The model architecture was constrained by
The X sand is about 300 feet thick and can be observed field- structure map interpreted from a 3-D seismic survey over the
wide with a uniform thickness from the east to the west. field. The map was constrained to the well markers before the
Evidence from core data as well as logs indicates that the X model architecture was constructed. Average net-to-gross,
sand is made up of a mix of shore face sands and tidally porosity, and water saturation values from the petrophysical
influenced channel facies. evaluations were assigned to each layer by kriging. The
kriging parameters were chosen to emphasize continuity of
In terms of stratigraphy, this sand can be divided into three - rock properties in the strike orientation. The porosity model is
an upper part consisting of upper/lower shoreface sands, a shown in fig. 4.
middle part consisting of an amalgamation of tidal channel
bodies as evidenced from the degree of incision in each well Matrix permeability was calculated directly from the porosity-
and a lower part consisting of shoreface sands. permeability (phi-k) relationship derived from the core data.
However, this relationship showed a high degree of scatter in
The shoreface sands (about 180 feet thick) are made up of four the data and a misrepresentation of actual flow parameters (fig
(4) different parasequence sets comprising a series of cyclical 5). Thus, matrix permeability was considered as a major
upper shoreface-lower shoreface heterolithics formed during source of uncertainty in the dynamic simulations.
four different episodes of deposition. The upper shoreface
sands are very well developed and vary in thickness from Results of Side-track Well Drilling
forty-two (42) feet in some wells to twenty-two (22) feet in As stated earlier, a well re-entry into the Awob-2 was
others. It is noted that these shoreface sands can be correlated necessitated by a reported well head collapse in 2001. This
field-wide from the east to the west. The underlying lower collapse resulted from the corrosion of the 13-3/8" casing that
shoreface heterolithics are less thick and vary in thickness could no longer support the weight of both the 9-5/8" casing
from about ten (10) feet to about six (6) feet. and the well head. The well head was successfully repaired
but it became impossible to retrieve the Baker A5 packer.
In terms of reservoir quality, the upper shoreface sands show Subsequently, the completed X and Y sands were abandoned
good reservoir quality (average porosity of 23% and and a sidetrack well was planned from the existing Awoba-2
permeability of 574 mD) and sand development and could act (Ref. 2). A window was milled at a depth of 10,638 ftah and
as a good reservoir for hydrocarbon retention. The lower drilled directionally and built angle at 2.5deg/100 ft from
shoreface heterolithics are mainly made up of shaly materials 10,670 feet to a maximum inclination of 30.7deg. @ 11,916
with comparably poorer reservoir properties (average porosity feet along an azimuth of 126 degrees. A tangent section was
of 19% and permeability of 35 mD). This can act as baffle to drilled to TD at 13,406 ftah with a maximum deviation of 12
the vertical flow of hydrocarbon from the underlying channel degrees and then logged on wireline.
sands, in areas where the reservoir characteristics of the
heterolithics, is poorest. If this happens, there could be a The well logged a total of 404 feet net oil sand in four
possibility of some by-passed oil retention in the underlying different intervals including the X and Y. The contacts logged
channel sands. in the well were found consistent with those earlier logged in
Awoba-2. However, the logs from the sidetrack well indicated
Underlying the cyclical shoreface sands are a series of tidally flushed water zones on top of oil in the X reservoir (Fig. 6). It
influenced channels amalgamating into three main bodies with also showed an increase in Sw on the X reservoir which is
a NNE-SSW linear trend (fig. 3). The channels could attributable to the flushed interval. This meant that there may
collectively be as thick as 120 feet in some wells. be layers with large difference in permeability or probably two
Connectivity within the channel is expected to be very good as different reservoirs separated by shale within the X sand. This
evidenced from core data and sidewall samples description. shale layer is correlatable field-wide thus setting the stage for
These channels are made up of medium to coarse grained, a reassessment for the existing full field 3-D static model of
well-sorted sands and in terms of reservoir properties (average the X reservoir built in 1998.
porosity of 20% and permeability of 461mD), would rank high
in hydrocarbon retention. Generally, the contacts logged in the well were found
shallower by some 13-19 ft when compared within the average
The lowermost part of the Awoba X sand is made up of reservoir contact logged in the field.
shoreface sands and could be as thick as 40 feet. These
SPE 77669 RESERVOIR MANAGEMENT SCOPE IN A MATURE NIGER DELTA FIELD 3

With the above results, it was decided that the sidetrack well Table: 1
be completed on the Y only as a single string single FACIES FZI VALUES
completion, while a blue print should be evolved in Channel Sands 14.27
developing the X reservoir in the light of the new data. Upper Shoreface 7.54
Although this decision resulted in a decrease in the developed Lower Shoreface 4.55
ultimate recovery for the well (since only the Y was Shale 0.1
completed) it was felt that the reassessment of the present X Tidal Channel Sands 10.2
hydrocarbon ultimate recovery was not necessary.
The permeability as a function of FZI and porosity was thus
Optimized 3-D Models computed in LOGIC using the facies curve (geological
In the light of the results from the well 2 sidetrack drilling, a interpretation) as a basis for assigning FZI values to reservoir
better development scenario forecast from the X reservoir was intervals. The resultant curves were kriged and the resulting
required to support major capital expenditure. This was permeability model showed a sharp difference in permeability
achieved by numerically simulating the reservoir via static and parameters from one facies type to another. This thus
dynamic models subjected by history match. represents the true permeability properties of the X sand.
Static Model : As a result of the information derived from the Simulation Model : The X reservoir simulation study follows
sidetrack well showing clear evidence of differential flushing previous modelling attempts in 1998. The updated static
thus leaving behind some by-passed oil, there was need to re- model data created forms the basis for carrying out the
evaluate the 3-D static and dynamic models built in 1998. updated simulation study. Appropriate re-scaling for dynamic
model was done with the changes in the static property
The first area of uncertainty as earlier outlined is in the models. As stated earlier, the static model data was based on
derivation of the matrix permeability property. Matrix 3D seismic interpretation, infill mapping, petrophysical
permeability was calculated directly from the porosity- review; PVT properties review, recovery factors and resource
permeability relationship derived from the core data. It was volume review, production performance review and some
observed that some areas of low porosity particularly in the reservoir modeling analysis. The dynamic modeling process is
lower shoreface heteroliths were over represented in the 3-D as follows:
volume. As the permeability is determined from porosity via a
phi-k transform, this means that the permeability will also be a. Discretize reservoir and surrounding area rock into grid-
over represented as well in the lower shoreface heteroliths. blocks using the UPSCALER and the static model data. If
This will in turn lead to an undue increase in assigning flow appropriate, redo discretization to get better history match.
parameters in the dynamic model. Thus the actual b. Create and initialize the dynamic model by incorporating
permeability profile of the X reservoir was not adequately the X reservoir data and fluid properties.
represented. A possible improvement in the over c. Perform the history match by varying uncertain parameters,
representation of this permeability property is to apply the e.g., aquifer properties, Permeabilities, etc. Match the
concept of Flow Zone Indicators (FZI) in an alternate model. drainage point production history and bottom hole
pressure measurements.
The FZI concept was developed in Shell Nigeria with all the
different types of facies/genetic units found in the Niger Delta The static model has [X, Y, Z :: 89, 42, 466] 1,741,908 voxels
catalogued and assigned with flow parameters based on along the survey system. A voxel in the model has the
previously observed flow properties. The concept considers dimensions of [X, Y, Z :: 100 meters, 100 meters, 1 ft]. All of
that fact that permeability is related to porosity by the the wells penetrated identified five layers (four geological
mathematical expression: units), namely, X.11Top, X.12Top, X.13Top, X.14Top, and
X.14Bottom. Fault data was digitized using mid-point method
K=1014 (FZI)2 Q3 for verticalization.
(1-Q)2
where k is the permeability, FZI the flow zone indicator and Q A voxel equal to one grid block in the dynamic simulator
the porosity. The FZI for most facies/genetic units have been would have resulted in very large simulation model, which
catalogued by SPDC. For the facies identified in the X would be very slow on the computer. Therefore, the need to
reservoir, the respective FZI values are listed below: reduce number of grid blocks to appropriate size was very
high. As the x and y axis voxel had dimension of 100 meters,
there was no opportunity to reduce them. Therefore, only z
axis could be up-scaled. Initial attempts at history matching
using ten layers (also used while preparing an earlier 1998
model) resulted in premature water breakthrough. This was so
because restricting to ten layers resulted in almost no
4 J. IKOMI, J. MANDHANE, C. NWOSU, B. AKEM SPE 77669

opportunity to properly simulate four geological units. The end-point relative permeability (ref. 7) values in a set of 5
Generally, more layers are required in the top geological unit, curves for oil and water, kro and krw, were varied during the
which leaves lesser number of layers for the lower geological history match process until good history match of the water
units, and often, only one layer for the most bottom geological cut performance of all wells was attained. The data set is
unit. After many upscaling trials, it was decided to use 30 systematic and the Corey exponent and the end points
layers one of which is shown in figure 7. Then the next are reasonable.
decision point was how to distribute those layers in the
geological units. The following distribution seems to give the Well Completion Skin: The completion skin of 1, -3, -5, -5,
desirable results: and -3 for well 2, 3, 5, 6, and 8, respectively was simulated to
Top X.11 to Top X.12 : 12 layers have history match on the flowing bottom hole pressure. Well
Top X.12 to Top X.13 : 6 layers 2 is simulated with small skin damage, while all other wells
Top X.13 to Top X.14 : 8 layers are simulated without damage.
Top X.14 to Bottom X.14 : 4 layers
The distribution of layers was done to have as much as Aquifer Properties: Finite radial aquifer with inner radius of
possible uniform layer thickness to minimize convergence 5650 ft and outside radius 15 times that resulted in a good
problems. historical pressure data match.

Results Of History Match Discussion


The production history (oil rate, BSW, and cumulative fluid Figures 9 and 10 show the history match performance.
production) and bottom hole pressures were the history match
variables. The main variables employed in this history match The legend for the Figures 9 and 10 is as follows:
exercise were the aquifer size, aquifer response time and Oil Rate data: red circles
aquifer strength. A series of simulation runs were carried out Historical and History matched BSW: down triangle and
for history matching. First by maintaining fluid withdrawal continuous blue line
equal to the gross volumes while the aquifer data was matched Historical and History matched GOR: up triangle and
to get historical pressure match. A history match was continuous green line
attempted on BSW and oil production while still maintaining Historical and History matched static BHP: solid square
fluid withdrawal equal to the gross historical volumes. This and bold black line
was done after the adjustment of the relative permeability data. Historical and History matched flowing BHP: hollow
A good match on BSW means matching water breakthrough square and light black line
time and its performance. Then a good match on BSW will
result in complimentary good match in the oil volume since Figure 9 shows a relatively good match of oil rate for well 2
gross volumes were used as inputs. It is important that the (when seen along with the cumulative data, not reproduced
drainage point oil volumes be matched closely so as to obtain here). Water breakthrough from this well could not be
comparable cumulative oil production figures from the matched. By introducing simulated barriers to oil flow the
simulation model. Results obtained from the history match are water breakthrough was matched. Subsequent drilling and
discussed below. logging of well 2 sidetrack, due to safety problem, showed
water over oil. Stratified two permeability reservoir is more
Model Stability: The stability of the simulation model was likely petrophysical model for this reservoir. Good match on
tested by running it with no well producing. Results showed flowing and static pressure is noted.
that the model is stable and in equilibrium condition, i.e. no
flow across the grid-blocks. Figure 10 show a very good match of oil rate on X reservoir
basis (when seen along with the cumulative data, not
Porosity: The static model using the foregoing data resulted in reproduced here). Although water breakthrough time is earlier
a STOIIP of 102.2 MMstb compared to the desired then reported, but the breakthrough time, the overall BSW
expectation of 97.0. Although it was regarded as a good trend and amount of water production match is very good after
conformance for the STOIIP, the reservoir porosity was discounting excess water production from well 5 (not included
multiplied by 0.977 to match the desired STOIIP of 97.0 here as it has no significance to the objective of this paper).
MMstb. Very good match on static pressure is noted.

Relative Permeability: The average absolute horizontal The Figures 11 and 12 show the initial and at the end of the
permeability value was not changed in the process of getting a history match XZ saturation cross section for the Awoba
history match. The kv/kh was used as part of the history match well 2.
variable to get BSW match. Many cases were run and the best
results were obtained with kv/kh ratio of 0.35. The earlier As discussed before, the water over oil noted in the new
model used 0.4 as kv/kh ratio (fig. 8). sidetrack well 2 (drilled subsequent to this study) is not
evident in the above saturation cross-sections.
SPE 77669 RESERVOIR MANAGEMENT SCOPE IN A MATURE NIGER DELTA FIELD 5

The log data from the side-tracked well 2 has clearly inaccurate assignment of some modelling parameters. A
demonstrated preferential water movement above the reservoir simple characterisation of the subject reservoir shows that it
shale. Update of the simulation model and history match prior consists of an upper layer of good quality upper-shoreface
to proceeding with depletion scenario forecast cases is deposits, a middle layer of poor quality lower shoreface
highly recommended. heterolithics sitting right above a layer of good quality tidally
influenced channel sands. The bottom part of this reservoir is
Reservoir Management Strategy made up of a layer of medium quality shoreface sands. The
Integrating the above dynamic simulation results with the middle layer of poor quality heterolithics has acted as a baffle
results of the well 2 sidetrack drilled further provide a to vertical flow. As a result, the X reservoir has been
blueprint for managing the X reservoir. The work compartmentalized into three sub-units with each having its
provides further insight in to the anomalous production own fluid distribution confined within its sub-unit. In the
performance data. development of this reservoir, all 5 previous wells were
perforated on the top sand subunit. In that situation, the
As stated earlier, the 5 wells (2, 3, 5, 6 and 8) are producing hydrocarbon present is quickly depleted hence the early water
from the X reservoir. Historical production data reveal that breakthrough in well 2. Thus, the hydrocarbon in the
wells 5 and 6 which came on stream in 1992, were closed-in in unperforated middle subunit is by-passed and can not be
1993 and 1995 respectively for high water cut and produced until this layer is perforated.
corresponding low productivity circa 400-1000 bopd. Both
wells were initially producing about 2000 bopd each. Both The above assertion was confirmed by the results from a
wells were completed on the uppershoreface sand member. recent rig re-entry/sidetrack from an existing well -2. This rig
Results from the sidetrack indicate that this zone is flushed. re-entry/sidetrack exercise apart from confirming the above
On the other hand, the wells 3 and 8 which are located further discovery also showed clear evidence of preferential flushing
updip on this upper shoreface sand, are still producing almost in the upper member of the X reservoir, due to the contrast in
dry at about 3000 bopd each. Current water cut is put at about permeability between the upper/lower shoreface sands and
10%. Water broke through in May 1999. Therefore, it is their adjacent tidally influenced channel. The results of the
suspected that with time, the water leg in this reservoir will well sidetrack have thus further provided a blueprint for
move updip due to production thus flooding the perforations in understanding the reservoir characteristics as they relate to the
both wells. This will result in flushing as there is a limited anomalous production performance of this reservoir. With the
vertical communication arising from the presence of the knowledge gained by this exercise, a blueprint has been
heterolithic sand member. Thus there will be by-passed oil formulated to further manage the remaining reserves in the X
left below in the other sand members. Well 2, which is reservoir. This has been done, by evolving a reservoir
equally downdip has been known to cut water since 1996. In management strategy discussed above. With this, substantial
order to optimize production in this reservoir, wells 5 and 6 gains of better understanding the X reservoir have been
closed in for water should be reactivated by squeezing off the estimated at approximately US$10-15 million (risked) (being
existing perforations and perforating across the lower the cost of drilling 2 water-wet wells) for optimizing future in-
heterolithic sand member. Production from wells 3 and 8 can fill well positions.
be optimized through additional perforations across the lower
heterolithic sand member. Acknowledgements
The authors would like to thank SPDC management for
Any additional development well to be drilled will be permitting the publication of this paper. Eastern swamp asset
perforated in the heterolithic in order to optimally produce the team of SPDC-E. Also we acknowledge the contributions of
reservoir from the well. Messrs. Joe Ezeh, Joshua Itua, Linus Edet and other
colleagues in well engineering team. We thank Mr. Sam Udo
Conclusions for his support and encouragement.
An integrated petroleum engineering study of the Awoba X
reservoir combined with the sidetrack drilling of well 2 has References
helped in explaining the puzzling production performance of 1. "Development Strategy For A Niger Delta Brown Field,
this reservoir. by John G. Ikomi, Shell Nigeria; Offshore Technology
Conference Houston, Texas, May 2002.
A comprehensive re-interpretation of the reservoir geology in
order to understand and mitigate the anomalous production of 2. "Land Use Optimisation In SPDC-E: economic
the reservoir thus revealed a distribution of various facies with justification for minimising community and environmental
different reservoir characteristics from the top to the bottom of problems; John. G Ikomi & O.A. Eruja, Shell International
the reservoir. It is noted that the reservoir characteristic Exploration and Production Newsletter, The Hague,
exhibited by the X reservoir, was not fully comprehended in June 1996.
an earlier 3-D modelling exercise thus resulting in an
6 J. IKOMI, J. MANDHANE, C. NWOSU, B. AKEM SPE 77669

3. "Cawthorne Channel Node, Field Development Plan", June


2001, SPDC, Eastern Division. See, "Awoba Field
Development Concept Selection (DCS)" included in the
subject report.

4. "Annual Review of Petroleum Resources 1-1-2001", Part


2, East, SPDC.

5. "Awoba Field Review", SIEP 98-5236, EPT-IF, The


Hague, June 1998.

6. "Awoba Well 8, X reservoir PVT Laboratory Study


Report", Schlumberger, Port Harcourt, Nigeria,
December 1995.

7. "New Residual Oil Saturation Measurements for the Niger


Delta Show More Mobile Oil", Uzoh O.J., Ojo Sanni,
Bram Sieders and Pieter van den Heuvel, 2000 SPE
Nigeria Annual International Conference and Exhibition,
Abuja, Nigeria.

8. "Awoba Field Review, Basic Data Review and


Methodology, Volume 2", SIEP 97-5157, EPT-IF, The
Hague, September 1997.
SPE 77669

Awoba Field Location in Nigeria

LEGEND

LAND

AT

Niger River
LA
WESTERN SWAMP NT
IC

AMESHI
O

EASTERN SWAMP AND OFFSHORE


AKRI/OGUTA
CE

UGADA
20
A

EGBEMA
N

EGBEMA W.

ASSA NORTH
IBIGWE
BISENI ASSA OGUALI
SAMABIRI ADIBAWA
21 N.E.

ADIBAWA AHIA
OTAMINI
ZARAMA UBIE MINI NTA UBIMA

ETELEBOU UMUECHEM IMO RIVER


AWOBA FIELD
OBELE
NKALI
GBARAN RUMUEKPE OHURU
AGBADA
ISIMIRI OZA
OGBODO OBIGBO N. OBEAKP
NUN RIVER ENWHE ELELENW OKOLOMA
KOLO CR AKPO U
APARA A BANGHAN
R AKUBA AFAM
NUN RIVER. DEEP EGBOLOM AJOKPORI
SOKU BUGUMA TAI KOROKOR
OLOIBIRI ASARITORU ONNE O BOMU
DIEBU CR Port Harcourt IBIBIO AKATA
OKOROBA UBIMA
ORUBIRI ALAKIRI 11
EKULAMA ALAKIRI E. YORLA EKIM
IGBOMETURU BODO WEST ETEBI
UTAPATE
BUBOUWE-BOU SANT. BARB. KRAKAMA OPOBO AKAI
RESERVOIR MANAGEMENT SCOPE IN A MATURE NIGER DELTA FIELD

NEMC EAST BELEMA AWOBA AKASO AWOBA SOUTH


ELEPA NEMBE CR.ODEAMA CR

KALAEKULE
BIGHT OF BONNY

FIGURE 1
ATLANTIC OCEAN
7
8

A
Flushed
zone
B

C
J. IKOMI, J. MANDHANE, C. NWOSU, B. AKEM

Figure 2: Well 2 side-track X Reservoir Log Interpretation


SPE 77669
SPE 77669

Well 2 Well 3 Well 2st Well 8 Well 6 Well 5

1
1 1
1
1
2 1
2 2
2
2
3 2
3 3 3
3 3
RESERVOIR MANAGEMENT SCOPE IN A MATURE NIGER DELTA FIELD

Figure 3: Panel showing 3 sub-units of the X Reservoir


9
10
J. IKOMI, J. MANDHANE, C. NWOSU, B. AKEM

Figure 4: 3-D Porosity (Static) Model of the X Reservoir


SPE 77669
SPE 77669 RESERVOIR MANAGEMENT SCOPE IN A MATURE NIGER DELTA FIELD 11

Figure 5: 3-D Permeability (Static) Model of the X Reservoir


12

A
Water
zone
B
oil
zone
C
J. IKOMI, J. MANDHANE, C. NWOSU, B. AKEM

Figure 6: Well 2 side-track showing water above oil in the X Reservoir (By-passed oil)
SPE 77669
SPE 77669 RESERVOIR MANAGEMENT SCOPE IN A MATURE NIGER DELTA FIELD 13

Figure 7: Dynamic Simulation Model for Layer 4


14
J. IKOMI, J. MANDHANE, C. NWOSU, B. AKEM

Figure 8: Permeability X-section (Dynamic). Red colour represent poor reservoir


SPE 77669
SPE 77669 RESERVOIR MANAGEMENT SCOPE IN A MATURE NIGER DELTA FIELD 15

Figure 9: Well 2 Production Performance Match


16 J. IKOMI, J. MANDHANE, C. NWOSU, B. AKEM SPE 77669

Figure 10: X Reservoir Production Performance Match


SPE 77669 RESERVOIR MANAGEMENT SCOPE IN A MATURE NIGER DELTA FIELD 17

Figure 11: Saturation X-section through Well 2 at initial condition


18
J. IKOMI, J. MANDHANE, C. NWOSU, B. AKEM

Figure 12: Saturation X-section through Well 2 at end of history match


SPE 77669

You might also like