Rs Visuals Change Order Agreement
Timeline: 3-5 Working Days (Dates will beAs per Agreed Schedule)
Dear RS Visual,
We JP Architects writing this letter subject to exchange of service and punclist written below for
“No revision in Outdoor signage” and settlement of its payment to the supplier, the following are the
services to be render in exchange for the signage:
1. Cyclorama Revision
2. Door Jamb Dimension Correction
3. Gold Color of Rectangular Light (This item is for ordering of Gold, we will advise asap if the
material delivered for installation)
4. Glue of the Marble Background
5. Fixing of the Hardiflex Wall in Exterior Railing
6. Height Adjustment of Rectangular light from floor to ceiling original height
Kindly settle of atleast communicate with the signage supplier, thank you.
________________________ ______________________________
Architect RS Visuals