F-IMP-007 Monthly Planned Work Schedule and Progress Monitoring Report

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 1

Monthly Planned Work Schedule and

Progress Monitoring Report

For the month of: MARCH 2023 Cumulative month:


Project Name: CONSTRUCTION OF MEDICAL/QUARANTINE FACILITY
Location: PALINPINON, VALENCIA, NEGROS ORIENTAL
Date Start: MARCH 01,2023 Target Completion: MARCH 31,2023

Progress: Previous Month: 21.5025% Year To Date:24.55% Variance: -3.0475%


8.6276%
Problems Encountered: Actions Taken:
Slow processing of requested materials, because Complained about their system in the purchasing department. Because
some materials are not in the main warehouse. Their it is affecting the site activities.
sympos are not updated which can cause time loss –
2 to 4 days waiting time. Then we need to request it
again so that they can check in other stores.
Planned Activities:
Material Qty Required
Item No. Work Description Duration Weekly Schedule
Balance Projected W1 W2 W3 W4 W5
7.00 0.364 LS 0.136 LS OCCUPATIONAL SAFETY AND HEALTH 5 1 1 1 1 1
PROGRAM
12.00 138.7717 89.5 SQ.M CONCRETE (SEAVAN AND HALLWAY) 5 1 1 1 1 1
SQ.M
15.00 0.22 LS 0.10 LS FORMWORKS AND SCAFFOLDING 2 1 1
16.00 161.4292 161.4292 MASONRY WORKS 7 2 3 2
SQ.M SQ.M
24.00 0.95 LS 0.50 LS PLUMBING FIXTURES, SEWER LINE, 8 2 5 1
AND COLD WATER LINE
25.00 10 SETS 10 SETS PRE-FABRICATED CONTAINER HOUSE 21 7 7 7
Equipment Requirement
Estimated Schedule Prepared by:
Description Quantity
Duration W1 W2 W3 W4 W5
PRIME MOVER Trisha Marie A. Tan
BACKHOE 1 3 1 1 1
Date: 3/31/2023
DUMPTRUCK
BACKHOW W/ BREAKER
Approved by:
WATER TRUCK 1 30 1 7 7 7 8
Haizzel Joy A. Aguilar

Date: 3/31/2023
Manpower Requirement
Estimated Schedule
Remarks:
Designation Number Duration W1 W2 W3 W4 W5
FOREMAN 1 30 1 7 7 7 8
SKILLED LABORER 2 30 1 7 7 7 8
LABORER 4 30 1 7 7 7 8
SAFETY OFFICER 1 5 1 1 1 1 1
FIRST AIDER
PRIME MOVER OPERATOR AND HELPER
DUMPTRUCK DRIVER AND HELPER
BACKHOE OPERATOR 1 3 1 1 1
BACKHOE W/ BREAKER OPERATOR
WATER TRUCK DRIVER 1 30 1 7 7 7 8

F-IMP-007
Rev. 2 01/05/21