PROGRAM OF WORKS (POW)

SUMMARY OF WORK DESCRIPTION


Name of Project: HOUSE REPAIR

QUANTITY UNIT DESCRIPTION OF ITEM UNIT PRICE AMOUNT

I. Material Cost:

15 ply GI sheet 350.00 5,250.00


10 bag Cement 290.00 2,900.00
3 cum Sand 1,100.00 3,300.00
30 pieces Round steel bar (#10) 90.00 2,700.00
3 gal. Paint flat white (latex) 570.00 1,710.00
4 gal. Paint gloss white (latex) 680.00 2,720.00
25 length Deformed bar (10mm) 270.00 6,750.00
60 pieces Tiles (60x60) 120.00 7,200.00

Total Material Cost: 32,530.00


II. Labor Cost
Mason @500 x 12 days 6,000.00
Helper @350 x 12 days 4,200.00
Total Labor Cost: 10,200.00

TOTAL PROJECT COST: 42,730.00


Prepared by:

MARJORIE C. BARETA
Head Teacher III Approved by:

RICKY D. YAN
Chief CES, SGOD