Professional Documents
Culture Documents
Adapting Probabilistic Methods
Adapting Probabilistic Methods
Adapting Probabilistic Methods
This paper was selected for presentation by an SPE Program Committee following review of Proved reserves were defined, in part, as those volumes of
information contained in an abstract submitted by the author(s). Contents of the paper, as
presented, have not been reviewed by the Society of Petroleum Engineers and are subject to recoverable hydrocarbons with “... a high degree of confidence
correction by the author(s). The material, as presented, does not necessarily reflect any
position of the Society of Petroleum Engineers, its officers, or members. Papers presented at that the quantities will be recovered. If probabilistic methods
SPE meetings are subject to publication review by Editorial Committees of the Society of
Petroleum Engineers. Electronic reproduction, distribution, or storage of any part of this paper
are used, there should be at least a 90% probability that the
for commercial purposes without the written consent of the Society of Petroleum Engineers is quantities actually recovered will equal or exceed the
prohibited. Permission to reproduce in print is restricted to an abstract of not more than 300
words; illustrations may not be copied. The abstract must contain conspicuous estimate.” This definition implies that satisfying the P-90
acknowledgment of where and by whom the paper was presented. Write Librarian, SPE, P.O. criteria is sufficient to define proved reserves. We will discuss
Box 833836, Richardson, TX 75083-3836, U.S.A., fax 01-972-952-9435.
later in this paper why defining proved reserves as the P-90 of
any distribution is not always appropriate. Also, the
Abstract definitions do not specify at what level the evaluator should
apply the P-90 test (i.e. is it at the field level or the total
Probabilistic methods have introduced inconsistent portfolio level).
interpretations of how to apply these methods while
complying with reserve certification guidelines. The objective Probable reserves were then described in the SPE/WPC
of this paper is to present and discuss some pitfalls commonly definitions as those recoverable hydrocarbon volumes that “...
encountered in the application of probabilistic methods to are more likely than not to be recoverable. In this context,
evaluate reserves. Several Regulatory Guidelines that should when probabilistic methods are used, there should be at least
be followed during the generation of recoverable hydrocarbon a 50% probability that the quantities actually recovered will
distributions are discussed. An example also is given to equal or exceed the sum of estimated proved plus probable
understand the evolution of reserve categories as a function of reserves.”
probabilities.
Possible reserves were defined as those recoverable
Most of the conflicting reserve interpretations can be hydrocarbon volumes that “... are less likely to be recoverable
attributed to the current SPE/WPC reserve definitions where than probable reserves. In this context, when probabilistic
reserve categories are expressed in terms of probabilities of methods are used, there should be at least a 10% probability
being achieved. For example, proved reserves are defined as that the quantities actually recovered will equal or exceed the
those hydrocarbon volumes with at least a 90 percent sum of estimated proved plus probable plus possible
probability of being equaled or exceeded (P-90). reserves.”
Unfortunately, these definitions alone fall short as guidance on
how to derive the distributions from which these percentiles The United States Securities and Exchange Commission
will be calculated. A simple example of this problem is the (SEC) does not recognize probable and possible reserves. The
derivation of an exploratory prospect hydrocarbon resource SEC’s guidelines for reporting proved reserves are set forth in
distribution. While a P-90 can be calculated from this its Regulation S-X, Rule 4-10 and subsequent clarifying
distribution, no proved reserves should be assigned to the bulletins. In Regulation S-X, Rule 4-10 there are no guidelines
prospect until it has actually been drilled and proven for the interpretation of probabilistic analysis. The Regulation
economical. defines proved reserves as those recoverable hydrocarbon
volumes with “... reasonable certainty to be recoverable in
Introduction future years from known reservoirs ...”
In 1997 new reserve definitions were drafted and introduced Both the SPE/WPC and SEC proved reserve definitions have
by the SPE and the World Petroleum Congress (WPC). For the several other requirements that are usually applicable to
first time, these reserve definitions included some language to
2 H. G. ACUÑA, D. R. HARRELL SPE 63202
deterministic methods that may conflict with probabilistic necessarily be the same as the needs arising from lending
analysis if not properly incorporated. Evaluators of reserves institutions or stockholders. While the reserve evaluation
should exercise caution when using probabilistic methods to should allow the explorationists “... to dream a little but still
ensure compliance with the definitions of reserves adopted by hold them accountable,” the lenders should be able to “...
the SEC and the SPE/WPC. Caution is required because there sleep well at night knowing their money takes no inordinate
are certain situations where indiscriminate application of risks.” This is an obvious conclusion since the lenders’
probabilistic methods may produce results that are inconsistent exposure to the downside risk is much greater than their
with the reserve definitions. For example, the SEC definition exposure to the upside. Lending institutions do not particularly
of proved reserves does not explicitly recognize the use of the benefit from having large project upsides with low
probabilistic method, and in no way allows for the probabilities since they generally lend money at fixed rates. It,
probabilistic method to be used in such a manner as to violate thus, follows that lending institutions are much more
any term of that definition. interested in the quantification of the downside risks and not
so for the upside. About the stockholder, Capen wrote that he
In this paper, we will first present a short definition of “... cannot afford biased estimates lest the buy and sell signals
probabilistic analysis and the risks and benefits of using this get all confused and cost him money.”
technique. Next, we will address some significant
shortcomings in the current reserve definitions, and then, we Probabilistic analysis is not a substitute for the reserve
will present some examples on how some of these guidelines adopted by the SPE/WPC and the SEC. A common
shortcomings can be addressed in the evaluation of reserves. but, in our opinion, unacceptable trend in reserve evaluations
has been to rely on probabilistic evaluations to boost reserve
Discussion of Probabilistic Analysis of Reserves values if they cannot be supported by deterministic methods.
This generally results from the aggregation of various
The probabilistic analysis of reserves relies on the use of distributions as will be discussed later in this paper.
probabilistic techniques to estimate the uncertainty of the Probabilistic methods should not be considered as a sequence
recoverable hydrocarbon volumes. In its purest sense, these of simple mechanical steps to reach the desired outcomes. In
probabilistic methods are used to collect and organize, fact, probabilistic analysis requires as much, if not more, good
evaluate, present and summarize data. These methods provide judgement than deterministic methods for assigning reserves.
the tools to analyze large amounts of representative data so
that the significance of that data’s variability and Probabilistic methods are most suitable for early hydrocarbon
dependability can be measured and understood. resource/reserve evaluation. They provide flexible modeling
techniques to evaluate variable interactions and outcome
Probabilistic analysis should be considered an important tool options. Therefore, these methods require a customized
for internal company analysis to understand and rank its approach to correctly model the variable interactions.
hydrocarbon reserves and resources and associated risks. This
method provides the tools to identify the upside and the Unfortunately, the great flexibility of probabilistic analysis
downside hydrocarbon potential to better organize the makes this method easy to abuse. Restricting the probabilistic
company’s portfolio and to more efficiently allocate capital analysis to the guidelines provided by the reserve definitions
and manpower resources. However, it should be understood can help to standardize the results for reserve reporting
that the objectives of a hydrocarbon property ranking study purposes. In the next section we first explore some of the
and a SPE/WPC or SEC reserve reporting evaluation might be shortcomings of the current definitions and then we will
different. For example, companies may have their own present some examples for the practical application of reserve
guidelines to group and analyze hydrocarbon assets to allocate definitions and probabilistic analysis.
company resources or for property acquisitions. These
company guidelines may vary from project to project or year Conforming with the Reserve Definitions
to year (depending on pricing assumptions) and may be
different from those guidelines provided in the SPE/WPC and The primary factor for inconsistent reserve reporting
SEC definitions. It becomes then the primary challenge of the evaluations is the description of reserves as percentiles of a
evaluator to reconcile both evaluations. distribution. In the current SPE/WPC definitions, proved
reserves are defined as P-90, the proved plus probable as P-50,
E.C. Capen1 discussed this issue of having different objectives and the proved plus probable plus possible (3P) as P-10.
and different audiences for the evaluation of reserves. He
correctly remarked that the evaluation needs of the These percentiles for the different reserve categories have
explorationists, geologists and geophysicists may not been interpreted by some as finally quantifying the meaning of
the phrases, “high degree of confidence,” “more likely than
1
E. C. Capen: “A Consistent Probabilistic Definition of not” and “less likely to be recoverable than probable”
Reserves,” SPE Reservoir Engineering Journal, February reserves. The industry was quick to adopt these percentile
1996, pp 23-28. definitions at face value. Unfortunately, the SPE/WPC
SPE 63202 ADAPTING PROBABILISTIC METHODS TO CONFORM TO REGULATORY GUIDELINES 3
definitions do not provide direct guidance on how the From Figure 2, one can see that there are different values of
distributions are to be generated. Consequently, what may be a recoverable oil that fit the definition of P-90 for proved
P-90 to one evaluator may be something else to another reserves. While it is important to generate and understand the
evaluator. potential for the entire structure, it is obvious from this simple
example that for reserve reporting purposes the definition of
The definitions state without qualification that the percentile proved reserves based on a P-90 definition may not be enough.
tests are sufficient for the establishment of reserves if the
probabilistic method is used, irrespective of other aspects of For reserve reporting, one also should incorporate all the
the definitions. Thus, the definitions permit the calculation of guidelines that traditionally may be associated with
at least two values of reserves, those estimated by the deterministic methods. For example, can the structure on the
deterministic method (honoring all terms of the definitions) opposite side of the tested fault block be considered as a
and those estimated by the probabilistic method. Figure 1 known reservoir? If not, should it be left out of the analysis of
illustrates this point. proved reserves? Similarly, the volumes of rock below the
LKO may not be included.
Figure 1: Example of Early Reserve Assessment
Application of these guidelines would then result in the
determination of proved reserves from the first distribution in
Figure 2. This distribution is what we would call the proved
reserve distribution. Subsequently, the question is whether
after restricting the distribution to account for various reserve
guidelines, one should still use a P-90 to estimate the proved
reserves. To answer this, let us first examine the approach that
would have been taken in a deterministic analysis.
resource base can be backcalculated from a second for example, that if the exercise at hand is to evaluate field
distribution that has not been constrained by the proved level reserve potential, then the distributions of reservoir
guidelines. If the opportunity for upside is large or if the field properties should be the distribution of average field
is in the very early stages of development, reportable proved properties.
reserves may only represent a small fraction of the overall
distribution (i.e., a percentile higher than P-90). This paper deals, however, with the restrictions that may be
imposed in a probabilistic evaluation by the definitions. As
On the other hand, if the current stage of field development is previously stated, certain variables may not be represented in a
such that the “proved” distribution is the same as the overall distribution fashion for reserve reporting purposes. The
distribution, then proved reserves may be better represented by objective of the definitions is not to limit the understanding of
the P-50 of that distribution. the hydrocarbon assets, but rather to ensure that the reported
reserves, in particular proved reserves, are evaluated
In fact, it follows from this discussion that the percentiles consistently.
applicable to each of the reserve categories are dynamic
throughout the life of the reservoir and are not a fixed value. For example, some of the geologic variables to consider may
Obviously, during the early field development stages be:
reportable proved reserves may represent only a small • Water-Hydrocarbon Contact
percentile of the overall reserve and resource opportunity. • Gas-Oil Contact
With increased development and decreased uncertainty, • Bulk Rock Volume
proved reserves may approach a P-50 or expected value. • Net-to-gross ratios
• Porosity
The second approach is similar to what has been discussed, • Water Saturation
except that proved reserves are estimated deterministically.23
• Cutoff values
That value would then be compared to the unrestricted
• Reservoir Facies Distribution
distribution of recoverable hydrocarbons to determine its
corresponding percentile. By determining the proved reserves
The first geologic variable listed in bold letters above is
deterministically, conforming with the regulation guidelines
directly affected by the definition of reserves. While there may
and using expected values of rock properties and engineering
be some uncertainty as to the exact location of the fluid
factors, the evaluator is basically determining the expected
contacts, the reserve definitions are very clear in that for
value of the proved distribution as previously defined.
proved reserves fluid contacts should not be speculated upon.
Therefore, under the current definitions, the generation of the
Evaluation Variables
proved hydrocarbon-in-place distribution should incorporate
the LKO value and not a distribution of the contacts.
In general when estimating reserves, the evaluator deals with
However, it may be reasonable to expect that more
three types of variables: 1) Geologic, 2) Engineering and 3)
hydrocarbons may exist below the LKO depth.
Economic. Each of these variables may have degrees of
uncertainty that may be represented as distributions.
Engineering examples of variables that may be directly
affected by the reserve definitions are: 1) well spacing, 2)
This paper does not deal with the aspects of generating the
recovery factors, and 3) implementation of secondary and
random variable distributions or the correlations between
tertiary projects. While downspacing or the implementation of
them. Nor does this paper address the issues of properly
secondary projects may result in increased recoveries, the
incorporating the reservoir physics to represent the actual
definitions prevent us from speculating on these results unless
producing mechanisms in the probabilistic model. Obviously,
there have been successful tests or pilots. Therefore, it would
the evaluator should be familiar with how the data were
be an inconsistent application of these guidelines if the
collected and what they represent. Also, the reader should be
incorporation of these operating practices in the probabilistic
aware that throughout the discussion of reservoir variables,
analysis increases the estimate of proved reserves. Reserve
scale consistency between the variable distributions and the
distributions that incorporate the results from waterflooding
model to which they apply should be maintained. This means,
projects yet to be tested through pilots may result in
2 overstating proved reserves, as currently defined, particularly
Patricelli, J.A., McMichael, C.L.: “An Integrated
during the aggregation of multiple field reserves. The subject
Deterministic/Probabilistic Approach to Reserve
of reserve aggregations is discussed in the next section.
Estimations,” JPT (Jan. 1995) pp. 49-53.
3
Nangea, A.G., Hunt E. J.:” An Integrated
The reserve definitions are even less flexible when it comes to
Deterministic/Probabilistic Approach to Reserve Estimation:
economic parameters. To categorize reserves as proved, those
An Update,” SPE 38803, presented at the 1997 SPE Annual
reserves have to be economical under current economic
Technical Conference and Exhibition held in San Antonio,
conditions. While it may be appropriate to incorporate
Texas, 5-8 October 1997.
SPE 63202 ADAPTING PROBABILISTIC METHODS TO CONFORM TO REGULATORY GUIDELINES 5
uncertainty and volatility in hydrocarbon prices, operating Figure 4: Secondary Recovery Factors
costs and development costs in probabilistic analysis, these
variables are generally fixed in the reserve definitions.
.013
While dealing with projects outside of North America, the
evaluator generally has to make assumptions regarding the .006
timing for infrastructure, such as pipelines and market
conditions, particularly for gas. While these considerations are .000
important for company planning purposes and can be 0.18 0.21 0.23 0.26 0.28
Recovery Factor
incorporated in risk economic models, they may prevent the
classification of proved reserves. In general, there must be
established infrastructure and product markets to classify Multiplying the original oil in place volumes by the primary
reserves as proved for SEC purposes. plus secondary recovery factors could then calculate reserve
estimates. The aggregated percentile recovery factors for all
To illustrate this problem, consider for example five oil fields five fields are shown in Table 1.
on primary depletion with recovery factors ranging between
12 and 18 percent for each field. As shown in Figure 3, these Table 1: Portfolio Primary plus Secondary Recovery Factors
recovery factors can be expressed as triangular distributions
with a P-90 of 12 percent and a P-10 equal to 18 percent with Recovery Factor (%)
a mean value of 15 percent. P-90 20.5
P-80 21.3
Figure 3: Primary Recovery Factors P-70 21.8
P-60 22.3
P-50 22.7
P-40 23.2
P-30 23.7
P-20 24.2
P-10 24.9
0.10 0.12 0.15 0.18 0.20
Recovery Factor Notice that the P-90 from the aggregated recovery factor
distribution is higher than the P-10 of the primary alone.
These fields are considered good candidates for secondary Obviously, disclosing proved aggregated reserves with an
recovery but no pilot has been implemented yet. The equivalent recovery factor of 20.5 percent would not be
additional recovery factors due to secondary projects are appropriate in this case.
estimated between 0 to 12 percent. These secondary recovery
factors can also be represented by triangular distributions with Although the aggregated recovery factor distribution shown in
a minimum of 0 and a P-10 of 12 percent as shown in Figure Figure 5 and Table 1 may be the correct outcome if all five
4. fields are waterflooded, these expectations can not be used to
book proved reserves at the current field development stages
and under the current reserve definitions. So what is the
6 H. G. ACUÑA, D. R. HARRELL SPE 63202
solution to this problem? Obviously, proved reserves should for the purpose of reserve reporting. No lending institution,
be based only on reserve distributions that have been derived market analyst or shareholder would be able to conduct
exclusively from primary recovery factors until the meaningful comparative reserves and income evaluations
appropriate waterflooding pilots have been implemented and between E&P companies without the standards.
response has been verified.
Dry Hole Risk Factor and Aggregation of
One may argue that calculating proved reserves based on Distributions
primary recovery factors in this example underestimates the
overall potential of the fields. Someone else may point out that One aspect that is often overlooked during the aggregation of
this conservatism is the reason for the reserve growth observed distributions is the fact that distributions may have different
with added development. While these arguments may be risk levels. Consistent with the accepted practice that the
correct, one should keep in mind that the reserve categories summation of proved, probable and possible deterministic
have meaning only within the context of their definitions. reserves is not appropriate without risk adjusting each reserve
Therefore in this example, proved reserves have meaning only category first, reserve distributions should not be aggregated
for those volumes calculated without consideration of unless they have been adjusted for their “dry hole” factor.
secondary recovery. Under the current definitions, secondary Consider for example the three fault blocks in Figure 6.
reserves without a successful pilot should be excluded from
the proved category regardless of the waterflooding Figure 6: Aggregation of Distributions
perspectivities of the field.
The individual reservoir variable distributions are applied to Figure 8: Comparison of Aggregated Distributions
the volumetric gas equation to estimate the original gas in
Cumulative Probability
place. The original gas-in-place is then multiplied by a
recovery factor, sampled from the recovery factor distribution, 1.000
Unrisked
to obtain the recoverable gas for each fault block. These
values are shown in Table 2. Risked
.750
Table 2: Recoverable Gas Volumes (MMscf) Table 3 compares the unrisked and risked aggregated gas
recoverable volumes from these three fault blocks.
Fault Block A Fault Block B Fault Block I
P-90 9,658 13,124 4,904 Table 3: Comparison of Recoverable Gas Volumes (MMscf)
P-80 11,517 15,655 5,852
P-70 12,818 17,539 6,508 Unrisked Risked
P-60 13,943 19,083 7,084 P-90 33,731 16,864
P-50 14,971 20,493 7,629 P-80 36,909 22,963
P-40 16,002 21,909 8,188 P-70 39,301 28,141
P-30 17,102 23,588 8,744 P-60 41,184 32,498
P-20 18,352 25,265 9,480 P-50 42,923 35,658
P-10 20,146 27,500 10,475 P-40 44,954 38,553
P-30 46,932 41,279
P-20 49,299 44,357
The aggregation of these three distributions results in the P-10 52,286 48,534
distribution of unrisked recoverable gas shown in Figure 7,
which assumes that all three fault blocks are successful. While the prior discussion of risk and aggregation of
distributions may be obvious to some, it is still common
Figure 7: Unrisked Aggregation of Fault Blocks A, B and I practice to see reserve distributions aggregated without
consideration for risk. The fact that data are presented in
Cumulative Probability distribution form can make it counterintuitive that additional
1.000 risking may be necessary prior to aggregation.
.000
The aggregation of company reserves has traditionally been
20,000 31,250 42,500 53,750 65,000
fairly straightforward. The summation of all individual proved
reserves within its portfolio provide the total company proved
Recoverable Gas (MMscf) reserves. Similar arithmetic is performed for probable and
possible reserves. This process has been slightly complicated
To calculate the risked and, therefore, more representative by the introduction of probabilistic evaluation of reserves and
recoverable gas distribution at this stage of development, one the current reserve definitions.
should apply the individual chances of success (COS) for each
fault block during the simulation. Figure 8 compares the It has been well established that the summation of individual
unrisked distribution with the risked distribution obtained by percentiles from various distributions is not equal to the same
assuming a COS of 100 percent in fault block A, 75 percent in percentile of the aggregate. Thus it follows that adding up the
fault block B and 50 percent in Fault block I. P-90, as defined for proved reserves, from the various reserve
8 H. G. ACUÑA, D. R. HARRELL SPE 63202
portfolio components will not be equivalent to the P-90 of the explain or disclose this risk to their investors? All these are
aggregated total. In fact, the summation of the P-90 will be, in real and difficult questions without simple solutions. As we
general depending on the number of uncorrelatable have mentioned earlier, the definitions provide no guidance
opportunities in the portfolio, much lower than the P-90 of the for the process of aggregating portfolios.
aggregate. On the other hand, the summation of the P-10 will
tend to exaggerate the upside and be much higher than the P- For reserve aggregation, we emphasize one more time that the
10 from the aggregated distribution. The reason for this is very evaluator should consider the audience for the report. Clearly,
simple -- the larger the amount of opportunities available to a this type of analysis is of great value for the company’s
company, the more it can diversify risk. In other words, internal resource allocation and portfolio risk analysis. It helps
independent opportunities will tend to compensate each other; the company understand the diversification of their portfolio.
some may be low and some may be high, thus reducing the It provides an insight to the impact that divesting fields and
uncertainty of the total portfolio outcome. The addition of properties may have on their overall risk profile. It helps the
individual P-50 values should approach the P-50 of the company measure the level of commitment necessary to reach
aggregated distribution, as long as the median and the mean a certain level of success.
are not too dissimilar.
However, for reserve reporting purposes and under the current
The obvious dilemma becomes how to report individual and definitions it may be difficult if not impossible to justify
total company portfolio reserves. To make matters worse, each proved reserves in this example. Under SEC guidelines, we
distribution in the reserve portfolio needs to be properly risked should not disclose any proved reserves. The P-90 volumes of
and may or may not comply with all the definitions. The the aggregated totals can not be allocated with reasonable
current definitions provide no wording for the proper method certainty to any specific field or prospect.
for aggregating reserves; neither do the definitions provide
guidance for the appropriate level of aggregation to apply the In fact, to realize the P-90 volumes (or any other percentile
percentiles associated with each reserve category. volume of the aggregated totals), the company would have to
be committed to the development of all ten fields regardless of
Consider, for illustration purposes, a company with only early disappointments or successes. The SEC/WPC provides
probable reserves from ten fields defined at the field level at no guidance to handle this type of problem probabilistically.
the P-50s. Recoverable hydrocarbon volumes above P-55 are However, the only justification to book proved reserves under
zero. That is, the prospects may have a COS of 55 percent. the SPE/WPC guidelines would be the fact that the aggregated
The following table shows the recoverable oil volumes for one P-90 value has a positive value. This, however, would conflict
field and the aggregates of two, three, five and all ten fields. with the grain of the remaining guidelines.
Table 4: Field Reserve Aggregation Example (MMBbl) Disclosing the aggregated volumes in this case as proved may
leave investors unprotected against portfolio changes,
1 Field 2 Fields 3 Fields 5 Fields 10 Fields divestitures, delayed or incomplete portfolio development. On
P-90 0.0 0.0 9.6 16.6 50.5 the other hand, not presenting this information at all does not
P-80 0.0 0.0 13.5 27.1 61.3 adequately reflect the upside of a company’s portfolio.
P-70 0.0 12.4 15.9 31.3 69.5
P-60 0.0 14.3 19.2 36.2 76.4 Until the reserve definitions are modified to accommodate this
P-50 10.9 15.9 26.1 42.0 82.7 type of problem and the investing public has been familiarized
P-40 13.2 17.8 29.4 45.8 88.8 on this subject, we would recommend against disclosing
P-30 14.7 21.4 32.3 50.4 94.9 aggregated proved reserves that can not be readily identified at
P-20 16.2 28.2 35.9 56.7 102.8 the individual field level. However, we would recommend
P-10 18.0 31.9 43.6 64.2 114.3 discussing these volumes and the overall risk profile of the
company that results from its existing portfolio in company
This simple example highlights the problem that one filings and reports. This allows investors to make their own
encounters when aggregating multiple fields. Although at the decisions based on their comfort level about the overall
individual field level none of the fields have proved reserves, company’s upside without the assumption of reasonable
the aggregated total shows significant reserves at the P-90 certainty associated with the proved reserve category.
level for three or more fields.
Example Problem
Should this company then be in a position of disclosing the
aggregated reserves as proved? If so, how should this In this example, we will walk through the analysis of reserves
information be disclosed to the investors and shareholders? as a gas exploratory prospect is first drilled. Figure 9 shows
What if the company decides to divest individual fields or all the Gross Hydrocarbon Isochor for this example.
of them? Prospective buyers may not pay anything for proved
reserves for the individual fields. How can the company then
SPE 63202 ADAPTING PROBABILISTIC METHODS TO CONFORM TO REGULATORY GUIDELINES 9
Figure 9: Gross Hydrocarbon Isochor distribution carries a much higher risk than a P-90 from a gas
reserves distribution. The salt dome prospect is not yet
considered a known reservoir and Table 5 shows the result for
a successful case without dryhole consideration. A similar
table, after applying the risk factors to each fault block
through correlated binomial distribution of the COS, could be
generated to get the risked recoverable gas distribution.
However, this still would not be enough to elevate any of the
gas volumes to a reserve category.
43,560 * * * * (1- )
OGIP =
7 2,6 2 2 8 0,3 4 2 8 8,0 6 1 9 5,7 8 1 1 03 ,5 00 0 .6 5 0 0 .7 4 0 0 .8 3 0 0 .9 2 0 1 .0 1 0
BG A
0 .1 1 0 0 .1 7 0 0 .2 3 0 0 .2 9 0 0 .3 5 0 0 .0 9 0 .2 9 0 .4 9 0 .6 9 0 .8 9
Table 6 compares the recoverable volumes of gas from the
two distributions. The second column shows the recoverable
0 .0 2 8 0 .0 3 0 0 .0 3 1 0 .0 3 3 0 .0 3 4
Table 5: Salt Dome Example Unrisked Recoverable Gas Proved to Entire Fault Block A
LKG (MMscf) After Drilling
MMscf (MMscf)
P-90 118,288 P-90 3,920 9,658
P-80 123,751 P-80 4,628 11,517
P-70 127,762 P-70 5,184 12,818
P-60 131,104 P-60 5,619 13,943
P-50 134,323 P-50 6,007 14,971
P-40 137,655 P-40 6,411 16,002
P-30 141,116 P-30 6,842 17,102
P-20 145,033 P-20 7,286 18,352
P-10 150,801 P-10 7,982 20,146
From the stage of field development it is obvious that there are Several observations can be made from Table 6 while
no bookable reserves for this prospect. Although we have determining the appropriate amount of reserves to be booked
derived a P-90 for a gas resources distribution, the P-90 of this from this fault block. First, notice that the P-10 from the
10 H. G. ACUÑA, D. R. HARRELL SPE 63202
proved distribution is less than the P-90 of the entire fault As we discussed earlier, these distributions are not risk-
block as defined from seismic. This results from the well consistent since fault block A has a penetration while the other
location, which is not the subject of the discussion. But if we two do not. During the aggregation of these three distributions
were to use the P-90 from the second distribution to determine one should apply the COS to determine the total probable and
the proved reserves, we would obviously be stretching the possible reserves from all three blocks.
volumes beyond those proved by the bit. Since this fault block
will most likely be a one well fault block, only performance This process was discussed earlier in the section dealing with
will be able to prove or disprove the geologic and seismic risk and aggregation of distributions. Assuming a COS of 100
assumptions that define the upside. percent for fault block A, 75 percent for fault block B and 50
percent for fault block I, the aggregated recoverable gas
Given the fact that there is no production data to verify the distribution shown in Table 9 is obtained. From this table the
upside from this fault block, one then has to look at the proved three fault block probable reserves are determined from the P-
reserve distribution. Consistent with our prior discussion, 50. Possible reserves for the same blocks are estimated from
proved reserves would be defined as the P-50 recoverable gas the P-10 of the same risk adjusted distribution.
volumes from this distribution. In this case, the 6,007 MMscf
are the expected recoverable gas volumes from the proved Table 9: Risked Recoverable Gas Fault Blocks A, B and I
distribution and are, thus, the proved reserves. The proved
plus probable reserves would be defined as the P-50 of the MMscf
entire fault block A distribution and the 3P reserves (proved P-90 16,864
plus probable plus possible) would then be estimated from the P-80 22,963
P-10 of the same distribution. Table 7 then shows the reserves P-70 28,141
per category for this fault block. P-60 32,498
P-50 35,658
Table 7: Gas Reserves Fault Block A P-40 38,553
P-30 41,279
Fault Block A (MMscf) P-20 44,357
Proved 6,007 P-10 48,534
Probable 8,964
Possible 5,175 Whether or not reserves can be assigned to any of the
remaining 5 blocks will depend on the certainty of the seismic
After determining the appropriate reserve levels for fault block analysis and the fault block COS observed in this gas
A, the question remains whether additional reserves can be province. Despite the mechanics of probabilistic evaluations,
booked for the remainder of the structure. Statistical the experience and good judgement from the evaluator are still
information on fault block success ratio in tested structures necessary and valuable. In this example, no reserves were
may be of some use if available. assigned beyond the two adjacent fault blocks resulting in total
reserves shown in Table 10.
Let’s first examine the two fault blocks adjacent to fault block
A. These blocks are fault blocks B and I in Figure 6. In our Table 10: Total Gas Reserves
opinion, it would not be appropriate to book proved reserves
for these fault blocks at this stage since the structures have not Fault Block A (MMscf)
yet been penetrated by a well. Probable and possible reserves Proved 6,007
can be booked based on seismic analysis and analogy to fault Probable 29,651
block A. Table 8 shows the unrisked recoverable gas for fault Possible 12,876
block A and each of the adjacent fault blocks.
As a final analysis, one can compare the current reserve base
Table 8: Recoverable Gas Volumes (MMscf) with the overall unrisked and risked gas resource distribution
to better understand the additional potential and prioritize
Fault Block A Fault Block B Fault Block I company resources. The unrisked distribution shows the
P-90 9,658 13,124 4,904 values of recoverable gas if all 9 fault blocks are successful.
P-80 11,517 15,655 5,852 The risked distribution was generated with a relatively high
P-70 12,818 17,539 6,508 (75 percent) correlation coefficient between adjacent fault
P-60 13,943 19,083 7,084 blocks’ COS. Table 11 shows the total recoverable gas
P-50 14,971 20,493 7,629 volumes for the entire structure.
P-40 16,002 21,909 8,188
P-30 17,102 23,588 8,744
P-20 18,352 25,265 9,480
P-10 20,146 27,500 10,475
SPE 63202 ADAPTING PROBABILISTIC METHODS TO CONFORM TO REGULATORY GUIDELINES 11
Conclusions