STRUCTURE DRAWING STATUS AS ON 05.04.

2023
Drawing received from
Chainage (km) Proposed Details Submission Letter Date
Designer
Sr.
Remarks Latest Comment Drawing Approved Remarks
No. Type of
DPR CH DESIGN CH Span Arrangement R3 BBS R0 R1 Status Letter No.
Structure

EE office deny to receive


1 70.168 70.170 Pipe 1x1.2 dia New Balancing 22.03.2023
the structure drawing
2 * 71+298 RCC Solid Slab 1x10 MNB Required on urgent
3 71.634 71+632 Pipe 1x1.2 dia Reconstruction 22.03.2023 10.03.2023 EE office Awaited
4 71.974 71+970 Pipe 1x1.2 dia Reconstruction 22.03.2023 10.03.2023 EE office Awaited
Ground level of A1 & A2
in Section Y-Y and
5 72.171 72+150 Slab Bridge 3X9.0 MNB
abutment reinf. Drawing
is different.
6 72.584 72+560 Slab Bridge 1x10 MNB Required on urgent

EE office deny to receive


7 72.679 72+657 Slab 1 x 2.0m Reconstruction
the structure drawing

EE office deny to receive


8 73.012 73+008 Pipe 3x1.2 dia Reconstruction 22.03.2023
the structure drawing
9 73.684 73+681 Pipe 1x1.2 dia Reconstruction 22.03.2023 10.03.2023 EE office Awaited

EE office deny to receive


10 74.542 74+520 Slab 1 x 3.0m Reconstruction Not Start
the structure drawing

EE office deny to receive


11 74.704 74+710 Slab 1 x 2.0m Reconstruction Not Start
the structure drawing

12 75.796 75+794 Pipe 1x1.2 dia Reconstruction 22.03.2023 10.03.2023 EE office Awaited
13 75.957 75+936 Slab Bridge 2X8.0 MNB Not Start

Not Start Due to Canal


14 76.118 76+115 Pipe 1x1.2 dia Reconstruction 22.03.2023 10.03.2023 EE office Awaited
Water Issue

15 76.735 76+714 Slab Bridge 1X8.0 MNB Required on urgent Not Start

16 77.393 77+372 Slab Bridge 3X8.0 MNB Not Start

17 78.283 78+260 Slab Bridge 1X8.0 MNB Required on urgent Not Start

EE office deny to receive Not Start Due to Canal


18 78.876 79+054 Pipe 3x1.2 dia Reconstruction 22.03.2023
the structure drawing Water Issue

19 80.450 80+420 RCC T BEAM 2x21 MNB NIT Hard Copy received Not Start
20 80.664 80+642 Pipe 1x1.2 dia Reconstruction 10.03.2023 EE office Awaited Complete
21 81.086 81+065 Pipe 1x1.2 dia Reconstruction 10.03.2023 EE office Awaited Complete

Ground level of A1 & A2


in Section Y-Y and
Diversion Isuue
Integral Slab abutment reinf. Drawing
22 81.428 81+406 1x12 MNB Incomplete Due to
Bridge is different. Also
Electric Pole
Chainage mentioned in
template is two number.

EE office deny to receive


23 82.196 82+084 Slab 1 x 5.0m Reconstruction Work In Progress
the structure drawing
24 83.139 83+118 Pipe 1x1.2 dia Reconstruction 10.03.2023 EE office Awaited Complete
EE office deny to receive
25 83.653 83+651 Pipe 2x1.0 dia Widening 22.03.2023 Complete
the structure drawing
26 83.785 83+784 Pipe 2x1.2 dia Reconstruction 22.03.2023 10.03.2023 EE office Awaited Complete
27 83.977 83+890 Pipe 1x1.2 dia Reconstruction 10.03.2023 EE office Awaited Complete
28 84.568 84+546 Pipe Widening
EE office deny to receive
29 84.724 84+723 Pipe 4x1.0 dia Widening 22.03.2023
the structure drawing

30 85.267 85+248 RCC T Beam 3x18 MNB NIT Hard Copy received Not Start
31 85.577 85+574 Pipe 2x1.2 dia Reconstruction 22.03.2023 10.03.2023 EE office Awaited Complete

LHS Complete RHs


EE office deny to receive
32 86.291 86+322 Pipe 1x1.2 dia Reconstruction 22.03.2023 Balance Due to Electric
the structure drawing
Pole Issue

33 86.545 86+528 Pipe 1x1.2 dia Reconstruction 10.03.2023 EE office Awaited Complete

Integral Slab Not Start Due to Both


34 86.798 86+732 1x12 MNB Required on urgent
Bridge Side Farmer issue

35 86.905 86+887 Pipe 1x1.2 dia Reconstruction 10.03.2023 EE office Awaited Complete
EE office deny to receive
36 87.583 87+582 Pipe 2x1.0 dia Widening 22.03.2023 complete
the structure drawing
37 88.613 88+595 MNB Repairs balance

RHS Diversion Issue


38 89.746 89+732 Slab Bridge 4X9.0 MNB
Due to Water Pipe Line

LHS Diversion Isuue


39 89.951 89+935 Slab Bridge 3X8.0 MNB
due to Electric Pole

Not Start Weather


40 90.628 90+608 Major Bridge 4x21.0M MJB NIT Hard Copy received
Issue
41 92.078 92+060 Pipe 1x1.2 dia Reconstruction 10.03.2023 EE office Awaited Complete
42 92.653 92+636 Pipe 1x1.2 dia Reconstruction 10.03.2023 EE office Awaited Complete
Integral Slab
43 92.685 92+668 1x12 MNB Required on urgent Drawing Required
Bridge
EE office deny to receive
44 93.017 93+016 Pipe 3x1.0 dia Widening 22.03.2023 LHS In Progress
the structure drawing

EE office deny to receive


45 93.587 93+586 Pipe 3x1.0 dia Widening 22.03.2023 Complete
the structure drawing

EE office deny to receive


46 94.358 94+350 Slab 1 x 2.0m Reconstruction Not Start
the structure drawing
Integral Slab
47 94.694 94+676 1x12 MNB Required on urgent Drawing Required
Bridge
48 94.955 94+938 Slab 1 x 3.0m Reconstruction 10.03.2023 In Progress
49 95.546 Pipe 3x1.2 dia Reconstruction Complete

Page 1 of 2
Drawing received from
Chainage (km) Proposed Details Submission Letter Date
Designer
Sr.
Remarks Latest Comment Drawing Approved Remarks
No. Type of
DPR CH DESIGN CH Span Arrangement R3 BBS R0 R1 Status Letter No.
Structure

Drawing Required And


Integral Slab
50 95.992 95+975 1x12 MNB Required on urgent LHS Diversion Issue Due
Bridge
to Electric Pole

Drawing Required And


RHS Diversion Isuue
51 96.111 96+093 Slab Bridge 1X8.0 MNB Required on urgent
Due to Electric Pole
Height Issue

Not Required and LHS


52 96.291 96+291 Box 1 x 2.0m x 2.0m New Construction 20.03.2023 20.03.2023 EE office Awaited Diversion Isuue due to
Electric Pole Height

Diversion Issue Due to


EE office deny to receive
53 96.437 96+420 Slab 1 x 3.0m Reconstruction RHS SIDE Electric Pole
the structure drawing
Issue

LHS Side Farmer Land


54 97.084 97+066 Pipe 2x1.2 dia Reconstruction 10.03.2023 EE office Awaited Issue And RHS Water
Pipe Line Issue

Diversion Issue and Not


55 97.737 97+740 Box 2 x 3.0m x 3.0m Reconstruction 20.03.2023 20.03.2023 EE office Awaited Start Due To Village
Portion

Please change the FRL Diversion Issue and Not


56 97.946 97+910 Slab Bridge 2X8.0 MNB which is mentioned in Start Due To Village
Section A-A Portion

Please change the FRL &


Diversion Issue and Not
founding Level of P1
57 98.104 98+087 Slab Bridge 2X8.0 MNB Start Due To Village
which is mentioned in
Portion
Section B-B

EE office deny to receive


58 99.256 99+239 Slab 1 x 5.0m Reconstruction In Progress
the structure drawing

Not Required On Give


59 99.688 Box 1 x 2.0m x 2.0m New Construction Not received
Location

60 100.196 100+180 Slab Bridge 1x10 MNB Required on urgent Start Next Few Days
61 101.216 101+219 Pipe 2x1.2 dia Reconstruction 22.03.2023 10.03.2023 EE office Awaited Complete
62 102.526 102+509 MNB Repairs
EE office deny to receive
63 102.621 102+623 Pipe 2x0.9 dia Widening 22.03.2023
the structure drawing
64 102.509 102+509 MNB Repairs
65 103.360 103+344 Slab 1 x 2.0m Reconstruction 10.03.2023 In Progress
66 103.651 103+635 Slab Bridge 1X8.0 MNB Required on urgent Drawing Require
67 104.044 Slab Reconstruction 10.03.2023 Complete
68 104.258 104+242 Pipe 1x1.2 dia Reconstruction 10.03.2023 EE office Awaited
69 104.529 104+486 Major Bridge 5x24.0M MJB NIT Hard Copy received
70 104.836 104+820 Pipe 1x1.2 dia Reconstruction 10.03.2023 EE office Awaited
71 105.421 105+405 Slab Bridge 2X8.0 MNB In Progress

Page 2 of 2