Requirement And Structure Work Programme

Staff
S.N Ready For The Start /Working Decription Of Work Requirement Of Machinery Requirement Of Item Contractor Contractor Name
Requirement
Breaker
Location Structure Size Hywa Jcb Excavator
Machine
Contractor Required With
1 92+685 MNB 1x12.0 Diversion Work Complete, And Ready For the Work . -
Shuttering Material
Contractor Required With
Diversion Work Complete but Electric Pole Diversion Side So When
2 96+111 MNB 1x12.0 Shuttering Material, Electric Pole -
Electric Pole Shift The Start The Work Of This Chainages 3 1 1 1 Dewatering Pump- 2 nos
Shifting Required
3 99+258 Slab Culvert 1x2.0 In Progress Available Vikas Mandal
Contractor Required With Current 3 Junior
4 100+196 MNB 1x10.0 Diversion Complete - Staff Available , 2
Shuttering Material
5 103+363 Slab Culvert 1x2.0 In Progress Available Nitin Contractor Staff on Leave
6 103+655 MNB 1x8.0 In Progress Available Rajput Construction Total 5 Junior
7 105+421 MNB 2x8.0 In Progress Available Rajput Construction Staff Working
8 111+904 Box Culvert 1x2.0x2.0 - On Site and Apart
9 113+119 Box Culvert 1x2.0x2.0 - For This Drain
10 113+595 Slab Culvert 1x2.0 - Rajesh Contractor Work And More
11 113+832 Box Culvert 1x2.0x2.0 - MNB Work Start
Contractor Required With then Require 2
12 114+285 Slab Culvert 1x2.0 -
Shuttering Material more Junior
13 114+798 Box Culvert 1x2.0x2.0 -
14 116+096 Slab Culvert 1x3.0 - Staff.
15 117+881 Slab Culvert 1x2.0 -
16 118+414 Slab Culvert 1x2.0 -
17 118+914 Slab Culvert 1x5.0 -
18 121+112 HPC(Widening) 3x1.0 In Progress Hume Pipe 3x1.0
19 122+941 Box Culvert 1x2.0x2.0 - Contractor Require
20 123+296 HPC 1x1.2 In Progress Hume Pipe 1x1.2 Mithun Contractor
21 123+681 HPC 2x1.2 In Progress Hume Pipe 8x1.2 Mithun Contractor
22 126+957 HPC 1x1.2 - Hume Pipe 5x1.2