BILL OF QUANTITY (BOQ)

Pekerjaan Beton dan Pasangan

1 Kolom 15/20 8 Acian


P = 0.20 m Dinding = 54.24 m2
L = 0.15 m Kolom 1 = 12.60 m2
T = 4.00 m Kolom 2 = 3.96 m2
N = 10.00 kolom Kolom 3 = 2.52 m2
Volume = 1.20 m3 Kolom 4 = 1.08 m2
Ring Balok = m2
2 Sloof 15/20 Acian = 74.40 m2
P = 30.20 m
L = 0.15 m 9 Beton Bawah Lantai
T = 0.20 m P = 5.85 m
Volume = 0.91 m3 L = 9.80 m
T = 0.05 m
3 Ring Balok 13/20 Volume = 2.87 m3
P = 30.20 m
L = 0.13 m 10 Beton Rabat
T = 0.20 m P1 = 20.00 m
Volume = 0.79 m3 L1 = 0.92 m
T = 0.10 m
4 Pondasi Batu Kali Volume 1 = 1.84 m3
L. Atas = 0.25 m
L.Bawah = 0.50 m P2 = 8.00 m
T = 0.50 m L2 = 0.90 m
P = 32.00 m T = 0.10 m
Volume = 6.00 m3 Volume 2 = 0.72 m3

5 Pas. Batu Kosong (Aanstamping) P3 = 8.00 m


P = 32.00 m L3 = 0.40 m
L = 0.50 m T = 0.10 m
T = 0.10 m Volume 3 = 0.32 m3
Volume = 1.60 m3

6 Pas. Dinding 1/2 Bata V 1+2+3 = 2.88 m3


P1 = 3.60 m
L1 = 5.70 m 11 Manhole
Luas 1 = 20.52 m2 P1 = 0.60 m
L1 = 0.60 m
P1 = 1.00 m T = 0.10 m
L1 = 6.60 m Volume = 0.04 m3
Luas 2 = 6.60 m2
P2 = 2.40 m
Luas 1+2 = 27.12 m2 L2 = 0.10 m
T = 0.20 m
7 Plasteran Dinding Volume = 0.05 m3

Luas = 27.12 m2 V 1+2 = 0.08 m3


N-Area = 2.00 Area
Plaster = 54.24 m2
BILL OF QUANTITY (BOQ)

Pekerjaan Tanah dan Pasir Pekerjaan Atap

1 Galian tanah pondasi Batu Kali 1 Kuda-Kuda


P = 32.00 m P1 = 6.62 m
L = 0.50 m L1 = 0.50 m
T = 0.60 m N = 8.00 m
Volume = 9.60 m3 Luas 1 = 26.48 m2

2 Urugan Tanah Kembali P2 = 5.52 m


V Galian = 9.60 m3 L2 = 0.50 m
V.Batu 1 = 6.00 m3 N = 8.00 m
V.Batu 2 = 1.60 m3 Luas 2 = 22.08 m2
V Urugan = V.Gali-V.Batu
Urugan = 2.00 m3 L.Atas = 4.00 m
L.Bawah = 12.00 m
3 Timbunan Tanah T = 4.41 m
Luas = 57.62 m2 Luas 3 = 35.28 m2
Tebal = 0.10 m
Volume = 5.76 m3 P4 = 0.50 m
L4 = 0.50 m
4 Pasir Urug N = 55.00 m
Luas = 57.62 m2 Luas 4 = 13.75 m2
Tebal = 0.05 m
Volume = 2.88 m3 Luas 5
(L3-L4)x2 = 43.06 m2
Pekerjaan Lantai
1+2+5 = 91.62 m2
1 Lantai Keramik 40x40
P1 = 10.00 m 2 Bubungan Atap
L1 = 6.00 m P1 = 10.40 m
Luas 1 = 60.00 m2 P2 = 11.90 m
Dinding = 1.72 m2 P3 = 4.00 m
Kolom = 0.30 m2
Manhole = 0.36 m2 P = 26.30 m

Lantai = 57.62 m2 3 Listplank


P1 = 7.80 m
Pekerjaan Pengecatan P2 = 22.80 m

1 Pengecatan P = 30.60 m
Luar = 27.12 m2
Dalam = 27.12 m2
Kolom = 20.16 m2
Luas = 74.40 m2