Professional Documents
Culture Documents
Lecture 8 - Geotechnical Control (20.3.2023) PDF
Lecture 8 - Geotechnical Control (20.3.2023) PDF
Geotechnical Control
Ir Prof. Ken Ho
Principles of Landslide Risk
Management Pre-1869 Hong Kong
2
Hong Kong Skyline in 2020
N
ADVERSE SETTING OF HONG KONG
Land Area: 1,100 km2
Population: 7.8 million
Climate: sub-tropical
Rainy season: May to September
Rainfall: 2,300 mm (mean annual)
210 mm (1-hour record) HONG KONG
950 mm (24-hour record)
https://geology.com/world/world-
3
map.shtml
LANDSLIDE RISK MANAGEMENT
Landside risk management is the process of identifying the
landslide hazards and estimating the risk of hazards by
analyzing the likelihood and consequence of failure.
𝑅𝑖𝑠𝑘 = 𝑃𝑖 𝐸𝑖 𝑉𝑖 𝑈𝑖
𝑖 ➢ Avoidance (↓Ei)
➢ Stabilization or prevention (↓Pi)
consequence
➢ Mitigation (↓Vi)
probability ➢ Tolerance
➢ Risk transfer (e.g. insurance)
2019: Yuen Long Tai Tong 2018: Fan Kam Road, Kam Tin
(due to unauthorized site formation) (natural terrain landslide)
1991: Shau Kei Wan, Hong Kong 1998: Hang Lok Lane, Shatin, Hong6Kong
Blasting-induced failure Leakage of water mains
Human ‘fingerprints’ – What can go wrong?
Human Inadequacies Lack of design input
• Ignorance, e.g. incompetence during construction
• Carelessness, e.g. oversight of problems • Inadequate construction
• Complacency, e.g. unrealistic prediction, control
disregard of responsibility, commercial • Communication problems
pressure • Inadequate supervision
• Lack of design review
Design errors
• Inappropriate consideration
of safety-critical geological Poor judgement
features
• Invalid design methods • Throughout different
stages of design and
• Invalid design assumptions construction
• Adverse change in
environmental factors
Inadequate ground
Unforeseen ground conditions investigation
• Inadequate margin of safety and • Inappropriate interpretation of
design robustness information 7
DEFENCE SYSTEMS AGAINST FAILURE
James Reason (Swiss Cheese) Model
Destabilizing
action
hazard
identification
technical design
Independent checking
system
Warning +
alarms
emergency
response
8
EVOLUTION OF LANDSLIDE RISK
MANAGEMENT IN HONG KONG
9
Landslide Risk Management in Hong Kong
Late 1970s to
Pre-1970s Mid-1990s to
mid-1990s Mid-2000
mid-2000s
Empirical rules onwards
of thumb Applying
modern Enhanced
geotechnology risk Tackling
management new
challenges
10
Pre-1970s
Empirical rules
of thumb
Squatter dwellings
https://gwulo.com/atom/16197
13
Modern geotechnology + systems approach
Legislative Systematic
Customized R&D and Framework Retrofitting
Guidelines Technical & of
Advances Governance substandard
slopes
Engineering Land development Landslip Preventive
geological control Measures (LPM)
mapping Programme (risk-based
priority ranking system)
Statutory
Ground control
investigation
Landslide warning &
emergency response
Squatter
clearance
Standards for design, laboratory Geological and 14
testing and fieldworks groundwater models
1994: Kwun Lung Lau, Kennedy Town, Hong Kong
(5 fatalities)
15
Robust measures
Enhanced detailing in
slope drainage and
surface protection Public education &
publicity
Late 1970s to
Pre-1970s Mid-1990s to
mid-1990s
mid-2000s
Empirical rules
of thumb Applying
modern Enhanced
geotechnology risk
management
Risk-based
decision
making
Systematic landslide
investigation
Technical
review board and international
16
benchmarking
1999: Shek Kip Mei 1997: Sunny Villa
(relic failure) (past history of failure)
Looking for
Diamond Robbery fingerprints
Detective
To find:
• Sequence of events
• Multiple contributory
factors
• Root causes
Stable slope Fatal landslide
Forensic
Engineer 18
International best practice
Achievements
• Design based on sound geoscience principles
for this period
Enhanced professional awareness
and technical insights
• Actual performance of slopes under heavy rain
• Causes of failure of engineered slopes
Reflected by statistics
Unacceptable
ALARP
Acceptable
19
Landslide Risk Trend
Period I Period II Period III Period IV
1977: GEO
Risk increases due to population growth,
climate change and slope deterioration
Year 20
1990: Tsing Shan Debris Flow, 1999: Sham Tseng San Tsuen 21Debris
Hong Kong Flow, Hong Kong
New understanding of
natural hillside
• Ongoing hillside degradation
• Human influence
Late 1970s to
Pre-1970s Mid-1990s to
mid-1990s closer to steep Mid-2000
Developmentmid-2000s
Empirical rules natural hillside onwards
of thumb Applying
• Risk level comparable to man-made
modernslopes based Enhanced
on Quantitative Risk
geotechnology
Assessment (QRA)risk Tackling
management new
Climate change challenges
• Increasing frequency and severity of extreme rainfall
events – unprecedented challenge
• Multiple hazards
System components
1977: Set up GEO
Overall Landslide Risk
Land-use planning
Geotechnical control of new
development
Take enforcement action on
Contain risk from unauthorized site formation works
new development Discourage illegal cultivation
Upgrade and maintain government slopes
Reduce risk associated Promote private slope maintenance
with existing developments Mitigate natural terrain landslide hazards
Clear squatters from hilly terrain
Resilience measures Issue landslide warnings and erect warning
to minimize landslide signage
consequence Educate public on precautionary measures
Provide landslide emergency services
Promote capacity-building of the public &
enhance community resilience
Year
1950
1960
1970
1980
1990
2000
2010
2020
2030
23
Multi-pronged, Systems Approach for
Landslide Risk Management
GEO
Regulator
Safety manager
24
Collaboration by key stakeholders
Professionals
• Competence in terms of
technical expertise and
Governance professionalism
• Slope safety managers • Take up responsibility at
and regulators design and construction
stages
Human
Uncertainties General public & media
Policymakers
• Enhance public
• Allocators of human understanding, awareness,
and financial resources community preparedness
and resilience;
• Willing to follow temporary
evacuation orders;
• Discourage poor
anthropogenic practices;
25
• Enforcement actions
So far so good, but what next?
Last multiple-fatality
Annual Fatalities
landslide in 1994
B 29 yrs
Last fatal
每 landslide in 2008
年
死
亡
人
數
A
13 yrs
?
G
2023
47
Geotechnical Control
Geotechnical Engineering Office (GEO) was set up in 1977 as
a central authority to exercise geotechnical control on private
and public developments in Hong Kong
28
Geotechnical publications by GEO
• Geotechnical Manual for Slopes
• Highway Slope Manual
• GEOGUIDE
• GEOSPEC
• Technical Guidance Notes (TGN)
• GEO Publications
• GEO Reports
http://www.cedd.gov.hk
Home > Publications > GEO Publications
29
Avoid increase in landslide risk due to new developments
GEO is responsible for:
(a) ensuring that geotechnical considerations of new projects are
incorporated at the early stage of land-use planning, and
(b) checking all new slopes formed under private and public sector
projects in order to ensure that they are designed to modern safety
standards.
• Plan land-use
• Check all new slopes
(private and government)
• Audit sites during construction
30
Geotechnical Control of New Developments
Stages Objectives
Outline zoning plans, • Early identification of geotechnical
Master plan development, problems or constraints
strategic project schemes • Secure power under Town Planning
Ordinance for geotechnical control
Planning applications
- site-specific • Avoid hazardous areas (e.g. in-
principle objection as appropriate)
Land disposal; • Suitable clauses in land
feasibility study title documents (secure
power under the land lease)
34
Land-Use Planning Stage – an example
Natural terrain clause – to require
the developer to study natural
terrain hillside hazards and carry
out mitigation measures
Prior to the sales of private land, GEO advises Director of Lands to include
relevant geotechnical clauses (e.g. natural terrain clause) into the land
disposal or lease document
Edged Pecked
Green Area
Green Hatched
Black Area
Outside Works
Area
The Site
36
Geotechnical Control of
Private Developments
Key Parties Involved in Control of Private Development
Planner
Town Planning
Authorized Person Board
• As a Coordinator
Geotechnical
Director of Lands Engineering Office
Registered Structural Advise on Land-use
Engineer Planning
• Structural Elements
Exercise Geotechnical
Building Authority Control
Registered
Geotechnical Engineer
• Geotechnical Elements
38
Containing the risk arising from new developments
◼ Buildings Ordinance is enforced
by the Building Authority
◼ All buildings and street works in private lease land are governed
by the Buildings Ordinance
• Related Regulations
Building (Administration) Regulations
41
GEO’s Specific Roles in Private Developments
Drainage Plan
Superstructure Plan
43
Establishment of Registered Geotechnical Engineers
▪ A registrar was established under the Buildings Ordinance
in 2006 for Registered Geotechnical Engineer (RGE)
▪ The enactment of RGE is to ensure that only suitably
qualified and experienced geotechnical engineers will be
responsible for the design and supervision of geotechnical
works
▪ RGE must be a corporate member of the Hong Kong
Institution of Engineers in Geotechnical Discipline (i.e.
MHKIE(G) with proven technical competence) +
knowledgeable of the Buildings Ordinance and private
development control process
RGE’s Roles & Responsibilities
▪ Responsible for the investigation, design and supervision of
geotechnical works under the Buildings Ordinance
▪ Identify geotechnical
constraints at an early
stage
49
Foundation Plan
51
Prevention of
hydraulic failure
and assessment
of effects of
dewatering on
adjacent ground
Required where:
56
Supervision of Geotechnical Works
Directorate Site Supervisor (DSS) supervision is required for geotechnically difficult or sensitive sites,
e.g. sites where the works could pose adverse impact to life/property (see Section 7 of CoP for Site
Supervision 2009 for details)
Relevant qualification/experience for TCP T4/T1 under the RC’s stream is also needed for
geotechnical works (e.g. soil nails), and TCP T4 – CP logging geologist for GIFW
Level 1 = Inspection as and when required
Level 2 = Monthly inspection
Level 3 = Fortnightly inspection
Level 4 = Weekly inspection
Level 5 = Full-time inspection during site working hours
60
Quality Supervision of Soil Nailing Works
61
GEO’s Regulatory Role in Site Auditing
▪ Check that the site supervisory staff have performed their duties
under the BO
▪ Check any non-compliance of construction works and advise BA to
take statutory or disciplinary action
Non-compliance
works observed
(many struts missing)
Example of Enforcement Actions by Building Authority
▪ A person fell into a sinkhole
next to a private site in 2014
▪ Investigation by GEO found
that the sinkhole was the
result of defective works by
the contractors and that the
site supervisory staff failed to
take remedial actions to
rectify the situation
Area No. 4
▪ Area No. 3
(MTR Protection Zone) ▪ North Shore Lantau Designated Area –
complex geological ground condition
▪ Area No. 5
(Sewage Tunnel Protection Zone)
Special Geotechnical Control
in Mid-levels Scheduled Area
PNAP APP-30
(formerly PNAP 85)
66
Challenges posed by Mid-levels Area
• Steeply inclined terrain and dense urban development
• Adverse geology – thick colluvium overlying saprolites,
complex hydrogeology, of marginal stability (i.e. prone to
failure due to disturbance or removal of toe / passive
support)
• Many reported landslides affect the developed area, mostly
triggered by heavy rain
• Notable failures have occurred during construction stage
• 2 serious cases with massive fatalities:
• Po Hing Fong landslide killed 75 persons in 1925
• Po Shan Road landslide killed 67 persons in 1972
67
Mid-levels Moratorium (temporary
ban of new developments, 1979-1982)
• introduced in May 1979
• prohibited further building development in the Mid-
levels area up to 31.12.1981 (later extended to June,
1982)
• to enable Government to carry out an Area Study of
the geotechnical factors that should govern future
development [The Mid-levels Study]
68
The Mid-levels Study (1979-1982)
• Assessment of the regional geological and
hydrogeological conditions (extended monitoring
of groundwater response and soil suction),
including general stability conditions
• Consideration of measures to improve regional
slope stability
• Consideration of restrictions and special
geotechnical control measures to future
developments in the area
69
Special Geotechnical Control in Mid-levels
Key requirements introduced in Buildings Ordinance:
(A) require submission of Demolition Works Plan
(B) require submission of Ground Investigation Plan
(C) limit Bulk Excavation to specified levels
(D) require submission of Foundation Plan together with Site
Formation Plan
(E) can impose the Sequence of Works
(F) can exercise the special power regarding Groundwater
Drainage Works
(G) can impose, where appropriate, provision for resisting
Landslip Debris
(H) can require, where necessary, a Performance Review
70
(A) Demolition Works
Concern
• demolition operations reduction to the support of
slope & ground
• some past failures due to this cause
• important to maintain adequate ground support to
provide reasonable margin of safety of adjacent land
and structures
Legislative Power
B(A)R8(1)(baa) - prescribed constituents of a
demolition plan in the scheduled area – require
approval and consent
71
Demolition Plan
Remaining portion of Existing
Existing retaining wall
the building
building to be stabilized
by anchors/soil nails
demolished
Road
Anchors/
soil nails
Road
72
(B) Ground Investigation Works
Concern
• need to ensure sufficient data of adequate and
reliable quality for design
• G.I. for critical zones requires much higher
technical standard by contractors than is
commonly used in Hong Kong
• ensure adequate supervision
73
(B) Ground Investigation Works (Cont’d)
Legislation
• B.O. Sect. 2 – define “ground investigation”
• B.O. Sect. 17(1)6(c) – approval of GI plans and consent
to commence of GI works – requires acceptance of Site
Supervision Plan
• B(A)R8(1)(l) – prescribed constituents of a G.I. plan
74
(B) Ground Investigation Works (Cont’d)
Implementation by GEO
• GEOGUIDE on the required standards
• check adequacy & quality of proposed work, included:
location, size, depth, or the criteria for their determination,
of all exploratory work
equipment & procedures
sample selection criteria
specification, reporting format etc.
75
(B) Ground Investigation Works (Cont’d)
Implementation by GEO
• impose supervision requirements
• check actual site performance
• review and comment on G.I. report
• appointment of geotechnical consultant to design, arrange
and supervise G.I. works
• G.I. and laboratory works are to be carried out by
registered specialist contractor (RSC(GIFW)) and
HOKLAS accredited laboratories, using special techniques,
such as air-foam drilling (for bouldery colluvium and fill),
and other techniques for high quality samples
76
(C) Bulk Excavation Limit
Concern
• ML is a densely urbanised zone, previous
development dramatically modified natural
topography of the area
• unrestricted bulk excavation for basements & cuttings
would generally lead to an excessive reduction to the
support of a slope
• bulk excavation to be limited in order to minimise the
possible cumulative effect
77
Bulk Excavation Limits
B/L B/L
Existing
building
Road
Proposed
building
Existing
masonry
retaining
wall
Road
Determined Bulk
Excavation Limit
Proposed
piles
78
(C) Bulk Excavation Limit (Cont’d)
Legislation
• B(C)R21(2) – define “bulk excavation” means all
excavation except excavation for ground investigation,
public utility trenches, drains, sewers, piles & caissons
• B(C)R21(1) – bulk excavation in the scheduled areas shall
not be carried out below levels to be determined by the
Building Authority
• B(A)R8(1)bb(vii) – need to show envelope of all bulk
excavation
79
(C) Bulk Excavation Limit (Cont’d)
80
(D) Foundation / Site Formation Interaction
Concern
• need to assess the effects of the adopted foundation
system (surcharge or lateral loading) on adjacent
ground, structure, geotechnical features and
groundwater condition
Legislation
B(A)R11A - requires that the foundation plan and site
formation plan (and supporting documentation) to be
submitted together
81
Assessment of
groundwater
damming effects
due to foundations
in sloping ground
82
(E) Excavation & Lateral Support Plan
83
(F) Sequence of Work
Concern
• In some sensitive cases, construction of piles or deep
foundations and ground beams may be required
before the demolition of existing structures or any
bulk excavation in order to provide additional shear
resistance along the potential slip surfaces
84
(F) Sequence of Work (cont’d)
Implementation by GEO
• perhaps because of the existence of this power, it has been
common practice for the designer to voluntarily include as
necessary a satisfactory sequence of work on the plans for
approval minimal need to impose it in practice
• this power is also useful to ensure preventive work to existing
retaining wall and slope be carried out at an early date, say,
prior to bulk excavation
85
(G) Groundwater Drainage Works
beyond Site Boundary
Concern
• basements & retaining walls form continuous water-
tight barrier
• piles & caissons form partial barriers
• drainage measures to ensure new construction do not
adversely dam up groundwater flow resulting in rise in
groundwater table
• encroachment of neighbouring land to be granted if it
is in the interest of the stability of the neighbourhood
86
(I) Landslide Debris Impact
Concern
• Steep natural hillslope above developed area could be susceptible
to landslide
• of extent & practical difficulties to stabilise large area of
hillside not practicable to improve the Factor of Safety
88
Barrier Wall Integrated with
the Building Structure
Natural Slope
Main Building
B/L
Wall designed
to withstand
Car Park landslide impact
Access ramp
to car park
89
(J) Performance Review
Concern
• ground conditions & building works should be regularly
inspected and monitored during construction to ensure
that the geotechnical design assumptions remain valid, and
if not, appropriate design changes are made in a timely
manner
90
(J) Performance Review (Cont’d)
Legislation
B.O. Sect. 2 define “performance review”
B.O. 17(1)6(g) empower B.A. to lay down as a condition of
approval of S.F. plans the requirement to submit
a performance review to B.A. satisfaction prior to
O.P.
B.O. 21(6)f B.A. may refuse to issue O.P. if any performance
review requirement not met
B.O. 21(8) control the timing of submission of the
performance review to ensure adequate time for
B.A. to assess performance review report prior to
processing of O.P. application
91
(J) Performance Review (Cont’d)
92
(J) Performance Review (Cont’d)
Performance review may be imposed to works within the
scheduled areas or works outside the scheduled areas where :
93
Yuen Long and Ma On Shan
Scheduled Areas 2 and 4
Special geotechnical control for buildings founded on
marble with solution cavities
• Submit GI plan for approval
– minimum penetration of 20 m into
sound rock
• Include redundancy in pile design
• Performance review
• Long-term settlement monitoring
Note – The Designated Area of Northshore
Lantau is underlain by locally complex
geological conditions that may be problematic
to foundation construction for high-rise
buildings 94
Geotechnical Control on Existing Development
96
Long Term Monitoring
Post-Occupation Permit
(e.g. designed horizontal drains or
prestressed ground anchors)
97
97
Ensure that Private Owners Take
Responsibility for Slope Safety
110
Safety Screening Study of Private Slopes
• The Government performs a regulatory function of safety-
screening of selected private slopes under the Landslip
Prevention and Mitigation Programme (LPMitP)
• Under the LPMitP, 100 private slopes are selected for safety
screening study each year
• The main objective of the safety-screening study (i.e. Stage 2
Study) is to confirm whether prima facie evidence on a private
slope can be established for serving a Dangerous Hillside
(DH) Order
99
Dangerous Hillside Order
Buildings Ordinance Section 27A
Where in the opinion of the Building Authority any natural, formed or man-
made land, or any earth retaining structure, has due to any cause been rendered
so dangerous or liable to become so dangerous that it will collapse, or be
likely to collapse, either totally or partially, and thereby will cause, or will be likely
to cause, a risk of injury to any person or damage to any property, the
Building Authority may by order in writing served on the owner of the land or
structure, or on the person who under the terms of a Government lease is under
an obligation to maintain the land or structure, declare the land or structure to be
dangerous or liable to become dangerous
100
Incipient
instability
Slope FOS<1.1
by detailed
ground
investigation;
loose fill slope
Concrete wall
with low FOS
by detailed
ground
investigation;
old masonry
wall
Soil cut
too steep by
empirical
criteria
Landslip after
urgent repairs
Concrete wall
with low FOS
without site-
specific ground
investigation
Dangerous Hillside Order
• The DH Order is served to require the responsible owners
to carry out an investigation to confirm the stability
condition of the slope and, if found necessary, to carry out
upgrading works
• DH Order requires the owners to appoint Authorized
Person and Registered Geotechnical Engineer to carry out
an investigation of the feature concerned
• Submit remedial/preventive works proposals for
approval, if appropriate
Dangerous Hillside Order
If the owners do not carry out the investigation by the date
specified in the Order, the owners may be prosecuted in
accordance with Section 40(1B) of the Buildings
Ordinance
Owners find guilty of failing to comply the Order may
subject to a fine of $50,000 and to imprisonment of 1 year
and $5000 for each day failing to comply the order
The BA may carry out the investigation and any
subsequent works as default works under the Buildings
Ordinance and recover the costs involved from the lot
owners
Geotechnical Control of
Government Projects
GEO Policing Role for New Developments
“Private” Projects “Government” Projects
(Buildings Ordinance) (internal administrative process)
Category II
Periodic
inspections by a
SGE / RPE(G)
of the
geotechnical
design team
Category III
Full-time
supervision
112
1
1
3
Role of Computer Programs
• Computer programs are an important tool in the
engineer’s toolbox (vs closed form solutions vs empirical
assessment)
(1)Modelling errors
(2)Coding errors
(3)Human errors
(4)Discretization errors
(5)Errors originating from inappropriate boundary
conditions (or inappropriate initial conditions)
(6)Errors originating from inaccurate input
parameters
1
1
GEO Circular No. 35 - Prior Acceptance of
6
Computer Programs for use in Geotechnical
Engineering
• Sets out the policy and procedures adopted by the
GEO in the checking of geotechnical computer
programs
GEO Circular 35
• “Geotechnical computer programs which have not
been checked and pre-accepted by GEO should
not be used in geotechnical designs or studies
where errors could have significant safety or
financial implications.”
• Website : cedd.gov.hk
1
1
8
GEO Circular 35
• “Programs are further divided into programs
submitted to the BD for prior acceptance for
private sector projects, and programs submitted by
other departments/consultants/contractors for prior
acceptance for use in government projects.
The technical requirements for prior acceptance
shall be the same for all cases.”
Key to Effective Geotechnical Control in HK
• Exercised by a dedicated central government body
(i.e. GEO) with geotechnical expertise and resources
• Unified technical standards and sound geotechnical
practice accepted by the profession
• Comprehensive legal framework for private projects
and comprehensive administrative framework for
public projects
• Constraints are identified at the early stage (e.g.
land-use planning, land disposal, building plan, etc.)
• Appropriate policies, governance and processes
• Comprehensive site supervision requirements
119
Geotechnical Control of Private Development
Sources of Further Information
Website of DoJ on the Laws of Hong Kong (www.legislation.gov.hk)
Laws of Hong Kong Chapter 123 – Buildings Ordinance