0 | ZOA | Procurement Guidelines – Annex ZOA Country Colombia - Version date: 03-22-2022 | Status: Draft
Document Procurement guidelines – Annex for ZOA Colombia
name:
File name soft copy: ZOA Procurement guidelines Annex for ZOA Colombia
Version: 1.0
Version date: March 22, 2022
Owner: Betssy Quintero (MoO)
Status:
Approved by: Mike Boomer
Date approved:
Effective date:
TABLE OF CONTENTS
1 | ZOA | Procurement Guidelines – Annex ZOA Country Yemen - Version date: 05-08-2021 | Status: Final
1.1 Introduction to the procurement guidelines for ZOA Colombia
1.2 Date and effectiveness
1.3 Overall Procurement Process for ZOA Colombia
3 SUPPLIERS
3.1 Establishing supplier database (In addition to 3.1 and 3.2 in GPG)
3.2 Anti-terrorism vetting and Risk level (In addition to 3.3 in GPG)
Each section indicates if, and to which part of the general ZOA Procurement Guidelines the links to.
2 | ZOA | Procurement Guidelines – Annex ZOA Country Yemen - Version date: 05-08-2021 | Status: Final
1. INTRODUCTION
In the execution of its mandate, ZOA’s primary service is to implement projects in the Humanitarian
Sector. Our aim is to be good stewards of the funds entrusted to us, using them in the most effective
way in line with our mandate, while taking into account the complex and difficult contexts we are
working in. For this purpose, ZOA developed Procurement Guidelines. However, as the context is
different in each country we are working in, each country can have an amendment to the
procurement guidelines. This document is the Annex for ZOA Colombia.
The main differences in roles compared to what is described in the general ZOA Procurement Guidelines are:
Some of the thresholds for the procurement procedures are set at a lower level for Colombia.
For any procurement done at or via HQ on behalf of the Colombia program, the ZOA HQ Global Procurement
guidelines are applicable.
3 | ZOA | Procurement Guidelines – Annex ZOA Country Yemen - Version date: 05-08-2021 | Status: Final
1.2 Overall Procurement Process for ZOA Colombia
PURCHASE REQUEST
FORM (PRF)
4 | ZOA | Procurement Guidelines – Annex ZOA Country Yemen - Version date: 05-08-2021 | Status: Final
3 COMO PAGAMOS?
CADA MANERA DE PAGO TIENE SU COSTO. CUIDADO CON PROVEEDORES QUE COBRAN EXTRA POR PAGO CON TARJETA. SI EN LA SOLICITUD DE
COMPRA HAY QUE COMPRAR EN DIFFERENTES TIENDAS CON DIFFERENTES FORMAS DE PAGAR: HAGA UNA COPIA DE TODO LOS DOCUMENTOS
Y CON UN MARCADOR MARCAS EN LA SOLICITUD DE COMPRA QUE HAS COMPRADO CON ESE FORMA DE PAGO. POR CADA FORMA DE PAGAR
NECESITAMOS LOS DOCUMENTOS DE SOPORTE.
5 | ZOA | Procurement Guidelines – Annex ZOA Country Yemen - Version date: 05-08-2021 | Status: Final
Policies of Procurement in ZOA Colombia
Position Responsibility
Program Manager/ budget Authorises any purchase based on procurement plan, work plan and/
holder (p 26) or donor activity / budget plan
Reviews tender documents
Reviews QAM and approves decision
Reviews draft contract
Signs procurement documents within authorisation threshold
Country Director Authorises any purchase based on procurement plan, work plan and/
or donor activity / budget plan
Signs procurement documents within authorisation threshold
Signs waivers
Initiates contact with HQ for purchases above 50’000 EUR/60’000
USD
Procurement staff Responsible to start and complete procurement process as per ZOA
guidelines
Prepare request for quotations, tender documents, PO, contract,
payment requests
Conduct vetting of suppliers
Register suppliers in supplier list
Ensure all documentation is accurate, complete and stored
Finance staff Review budget availability and correct budget line
Provide advice on specific donor compliance guidelines if different
from ZOA guidelines
Review at the end of the procurement process (at payment stage) to
see if the documentation is complete and audit proof
Procurement Authorization and threshold levels for budgeted costs
Budget holder:
Additional guidelines
In case all submitted bids are 10% above PR value the PR needs to be re-authorized by the budget
holder by filling a form with justification.
Authorization of the purchase request and Purchase order by the budget holder is done before
financial review of documents
Payment request with supporting documents is reviewed by finance department before authorized for
payment by budget holder
Non-budgeted (not in proposal budgets or CSAP) items require approval from CD.
All procurement for each project will support the logistics department in planning and where needed/ possible
combine procurement for efficiency and cost effectiveness.
7 | ZOA | Procurement Guidelines – Annex ZOA Country Colombia - Version date: 03-22-2022 | Status: draft
The logistics department will develop a detailed procurement plan with timeline for all procurement for ZOA
Colombia throughout the year to ensure sufficient time is available in times of high procurement load. The
timetable will be updated on monthly basis by the logistic coordinator and procurement staff with support
from the MoO. On quarterly basis the plan is shared with the finance staff and PGMs for input and as part of
financial planning.
8 | ZOA | Procurement Guidelines – Annex ZOA Country Colombia - Version date: 03-22-2022 | Status: draft
Overview - Thresholds for procurement process / Required Documentation
Procedure Threshold Comments Timeline estimation Documentation needed for
payment
Direct purchase Items with an individual Approval of purchase by email or Items procured within 3 working Approved
without PR (petty value < 150 EUR approval on reimbursement form, no days reimbursement form
cash) prior finance review needed (details see Proof of payment
in petty cash guidelines, payments such
as monthly office services, casual office
cleaning. Admin registration.
Direct purchase Items with individual value Requester raises PR, authorized by Items procured within 3 working Signed PR
with PR between 150 – 1000 EUR budget holder and reviewed by finance days PO if raised
(P 23-24) staff Invoice
Proof of payment
Minimum Three Purchases with a value of QAM drafted by requester and Items procured within 2 weeks, Signed PR
quotes 1000 – 5000 EUR authorized by budget holder. unless stated different by donor Quotations
(p24) Procurement staff advises on the QAM. Signed QAM
Three or more quotation requests sent to Signed PO
trusted suppliers from the supplier list or Payment request
potential new suppliers simultaneously. Invoice
Proof of delivery
Proof of payment
Negotiated Purchases with a value of Bids summited in closed envelopes. Procurement process takes Signed PR
procedure (p24- 5000 –60,000 EUR Detailed RfQ /ToR (p25 GPG), drafted by between 3- 5 weeks, unless stated RfQ
26) requestor, approved by budget holder. different by donor Quotations
Signed contract instead of PO. Signed QAM
Budget holder reviews draft contract. Signed contract
Payment request
Invoice
Proof of delivery
Proof of payment
9 | ZOA | Procurement Guidelines – Annex ZOA Country Yemen - Version date: 05-08-2021 | Status: Final
Procedure Threshold Comments Timeline estimation Documentation needed for
payment
Open tender with Purchases with a value of Tender committee Procurement process takes Signed PR
national 60,000 – 300,000 USD between 5- 6 weeks, unless stated Tender dossier
publication (p27- (60,000 – 500,000 USD for PR approved by CD, procurement different by donor Minutes of tender
30) works contracts) documents verified by PC, contract meetings
signed by CEO Bids received
Signed QAM
HQ Approval
Signed contract
Payment request
Invoice
Proof of delivery
Proof of payment
International Purchases with a value Check with authorities if the specific Procurement process takes Signed PR
tender (p30-32) above 300,000 USD tender qualifies for international tender. between 5- 6 weeks, unless stated RfQ
(above 500,000 USD for If the authorities don’t approve different by donor Quotations
works contracts) international tender, a waiver should be Signed QAM
raised and a national tender will be HQ Approval
conducted. Signed contract
Payment request
Invoice
Proof of delivery
Proof of payment
10 | ZOA | Procurement Guidelines – Annex ZOA Country Yemen - Version date: 05-08-2021 | Status: Final
Local procurement
Where possible, ZOA Yemen promotes local economy in the communities we work. The companies in the
communities do not always have official registration of their business. Small businesses in Yemen are exempted
form tax and registration and therefore ZOA can work with them through a PO or contract, without requesting the
tax card or registration form.
For other businesses, ZOA is required to work with registered companies. Therefore, before signing any
commitment with the supplier, ZOA requests to receive a copy of the tax card and registration card. However,
some of the traders in the remote project sites don’t have registration cards. In order to support local traders and
to purchase locally where possible, purchases can be made from suppliers without a tax registration to a maximum
of USD 10,000 per supplier per year provided that this is accepted by the authorities.
On yearly basis, ZOA will write a letter to the authorities informing the authorities about ZOA’s general
commitment to support local traders and where possible to purchase locally for maximum amounts of USD 10,000
or YER equivalent with business that have no registration or tax cards to avoid fines from the tax authorities.
For amounts below USD 150, support staff can request a cash advance for direct purchase. Approval for this
request should be obtained from the budget holder, either through an email (prior approval) or through approval
on the re-imbursement form. Prior approval is recommended. Purchases without prior approval are at the risk of
the requester and the requester cannot claim any reimbursement in case the budget holder has rejected the
purchase.
Petty cash is never to be used for personal expenses, overtime, travel costs etc.
The cash advance must be settled at least at least monthly, before payroll. Once it is settled, a new advance can be
requested.
If, on a monthly basis, the advance is insufficient to cover incidental costs the advance can be settled and a new
advance requested in the same month.
On quarterly basis the finance department will share the budget codes and budget availability for rolling items
(such as stationaries, cleaning products, maintenance, hospitality etc.).
11 | ZOA | Procurement Guidelines – Annex ZOA Country Yemen - Version date: 05-08-2021 | Status: Final
Suppliers
The logistics department is responsible for the supplier database. MoO plans bi-annual/annual/monthly
evaluations of deliveries with other staff. The logistics coordinator makes sure supplier evaluations are done. Every
6 months the MoO will check the supplier evaluations for following criteria:
In addition to Section 3.3 in the ZOA Procurement Guidelines, Colombia has been determined a low risk
country. As per 2022:
1) There are less than 20 people and/or companies mentioned on the OFAC list that reside in Liberia
2) There are less than 20 people and/or companies mentioned on the Consolidated European Financial
Sanctions list that reside in Liberia
3) There are less than 20 people on the UN sanctions lists that reside in Liberia
4) It does not belong to the top 25 worst performing countries on the Transparency International List
Liberia is considered a low-risk country.
Based on the very low number of people on the sanction list, ZOA Colombia will only execute the
counter-terrorism check for contracts above international tender value and for purchases for a donor
who specifically requires these checks to be done. In cases of reasonable doubt about a supplier, a check
might also be executed. The Manager of Operations (MoO) is responsible to ensure sanction list checks
are done, when applicable.
12 | ZOA | Procurement Guidelines – Annex ZOA Country Yemen - Version date: 05-08-2021 | Status: Final