ENF
Feature
Foundations avoid obstacle course
Bon gue gee
forms had been the only
obsiacle between 2 22-story.
air-rights building in Chicago
and its foundations, i would
have been sufficient to com-
cate foundation work, But
beneath the covered platforms
and tracks is 2 maze of tun-
nels—ineluding some sur-
prises. Existing structures
and the Chicago River hem
in the rectangular site 90 that
the most practical acess route
for materials was by rail, and
rail authorities would ‘only
allow the contractor to take
fone platform and two adja-
cent tracks out of commuter
service at any time during
construction.
‘The numerous restrictions
forced “straitjacket” schedule
ing. “Rather than the conven-
tional approach of working
many operations at once, we
knew we had to complete all
demolition, then all caisson
vk, and then all sirucural
sect ‘work,” says Ronald E.
Materick, president of ‘Tish-
available as a pedestrian river
crossing, and decided 6-ftedia
caissons” would take up too
much space. To get around
this, SOM tapered the tunnel
section of the caisson to 3 ft
‘across and put structural steel
inside the caisson.sleeve
“Penetrations at the tunnel
were critical, especially at the
river,” says ‘Tishman’s job
Superintendent Joseph N.
Victoria. “IE we fad failed to
hold back the river, we could
have flooded the entire down
town tunnel system.” :
Crews also had to avoid
existing platform piles. To do
this, SOM designed smaller
caissons and crews tied them
together with transfer gird-
Diving in, Other challenge
ing caisson work occurred at
the water’s edge, where divers
riled “underwater caisons
near an old river bypass. For
ths, Tishman bull a coffer
dam and filed it with grout,
leaving voids for the castons!
Also, divers demolished some
man Construction Corp.'s
Chicago office and construc-
tion manager for the job,
called Gateway IV.
Project architect-engincer,
the Chicago office of Skid-
warts of the bulkhead walls,
ine drilling and rock jacking
‘were necessary in places.
On the platforms, crews
had to partially disassemble:
existing parabolic steel shel-
more, Owings & Merrill,
(a Towers ==] puaza (SEG oULONG
ters because they would have’
devised a grid of drilled,
belled caisson piles that
would involve only eight of
the 11 tracks. Each subcontractor worked a platform at a time
‘completing work at all eight before the next subcontractor would
Begin any work at all “Before we got above the [racks] we hed
very litle flexibility,” says Materic
For example, the caisson subcontractor could not begin any
latform work until demolition work at all eight platforms had
Fetn completed. The contrador then drilled caieons, capped
them and temporarily patched each platform so it could be
returned to service until the stee! subcontractor began work,
Surprises. But even with careful sequencing, surprises snage
xed procedures. In one case, five caissons were to be drilled
jown the center of what turned out to be an unused 25-ft-dia
tunnel, about 25 f+ down, which crosses the river.
“Te was just too big to span,” says Norman A. Midthassel,
“Tishman’s project manager. The city wanted to keep the tunnel
7” ENA/Aprt 22, 1082
Tracko, tunnels crlescrose airrighta building foundation,
{te into the building obs
y. The shelters are being
replaced by a celling that is
below a plenum under the building lobby. But because the
platform shelters extend beyond the building plan, their ends
remain and had to be temporarily supported until the building's
steel columns—the shelters’ new permanent supports—were
erected.
‘A new diesel exhaust system in the ceiling over the tracks
replaces one removed with the shelters. In addition, the design
had to comply wth rail platform ceing height minimum a
17 M11 in. Crews worked to within an tnch of restrictions in
some places, says Midthassel. Space was tight in order to keep
the lobby close to grade. i
Although handicapped by anine-werbuilng trades ke,
Maicrick says, foundation work took only two weeks longer
than expected. But the obstacle-course site did add about 20% to
the cost of the foundation, he adds. aDUDGEON
jacks work!
7 (SINCE 1850)
|Showa With Leck-Nut Adopter)
BUY or RENT
For information about:
capacity 10.0 1,500
tons and delivery, please
call Jim Woodin,
(203) 327-7217 or write!
* DUDGEON *
TC Market Strest
Stamtord, CT 06802
‘iecle Number 9 on Reader Sorvice Cord
ENR EDITORIAL REPRINTS
Engineering New-Record wil be god make
raable at nominal ceat—sopelet of the
‘magazine eltoal conte cre or pas.
ach yeat, ENR handles requests for move
(hom 280,060 sch editor repens.
For quotations, wri to! McGrail Inc.
ERR, Att Junie Austin Reprat Dep. PO.
‘oe 692 Hightstown, NJ. C8520 (6B) 488.
10 ‘Est $494, giving lforaton on the
rile you with veiled. and inber of
Copies needed. Menino oder fr evo
‘ade repeats $0 copes. 7
with most of the original materials still
an old building?” Eustis asks,
‘This month, Sheraton will ask. the
commission to reconsider the question.
IE ic can't get the commission's o the
city’s support, it says it will be forced to
abandon the projet, Sheraton has a
ready spent about $3.5 million on site
acquisition, engineering and site work
for the hotel o
Test confirms caisson use
‘An unusual instrumented toad test on a
downtown Chicago site has confirmed
that ofien-used, high-beating-pressure,
widedeled caisson that goto hardpan
can eliminate the need for drilling to
[rock. Soils. consultants on the job. say
the caissons can save about $1 rnillion
‘on a typical Chicago high-rise.
“Load testing of caisson foundations
is generally not practical, due to, the
magnitude of load required,” says Clyde
Baker, vice president and senior princi-
Bal gusineer, ST Consultants Lt
jorthbrook, ill. He says in Chicago,
only two load tests have been per-
formed on caissons in the past 25 years
and none on downtown hardpan, The
code allows only 12 kips per sq ft for
hardpan caissons unless tests. show
ater capacity. This is often the case,
though with less extensive testing done,
‘The fully instrumented test was used
fon the 4l-story One Park Place office
building, designed by A. Epstein, and
Sons, Chicago. Schal Associates, Chicar
0, is the construction manager. ‘The
foundation design incorporates a 7-ft
thick mat foundation to spread loads to
a combination of new belled caissons
and existing straight-shaft caissons that
remain from a previous buildin
‘The mat “provides. a ready-made
large reaction {mass] for a caisson-toad
test” says Baker. A stress cell was em-
bedded in the mat before it was poured
and two were also put in the test cais-
son, to measure load pressure.
When the building could provide
weight to jack against, two hy-
jacks with a combined capacity
of 1,100 tons were used to load the
‘caisson t0 70 kips. Though the bell was
originally cut ata 45-deg angle, “due to
1 atu instumontod test provides new dal
additional excavation required, the final
angle ended up closer co 60 deg” sys
Baker. “But even with the bell we had,
at the high pressure, it should have
cracked and failed, theoretically.”
The xeason it held up, he maintains,
is because load calculations typically are
made based on the behavior of caissons
above ground, in an unconfined state.
“When” you have a bell in hardpan,”
says Baker, “the “unconfined” theory
isn’t applicable, T think (our results are]
an indication that, there is a beneft.to
the confinement.” Baker says that in
soine previously borderline cases, STS
can now securely recommend caissons
to hardpan instead of drilling to rock. O
OLYMPIC.
FOLDING BUILDINGS
+ 99% ASSEMBLED
+ SPANS 24°10 70"
+1070 30" EAVES.
+ INSULATED TO R-21.53
+ MOVE IT, REUSE IT
“SEND FOR COLOR BROCHURE”
OLYMPIC PREFABRICATORS
GIONW 44th St SEATTLE
5107 206-784-9111
Circa Raumbor TE on Reador Sorvico Gard
28 ENA/October 7, 1982
Salt licks Cleveland garage
A 12-year-old precast concrete garage at
the Cleveland Hopkins “Intefnational
Airport has been seriously damaged: by
deicing salt, and the city is planning as
much as $1 million in repairs,
‘Water and salt have apparently trick:
led along the garage's double-T beams
and collected at the inverted-T haunch-
cs that support them, according to ait-
port engineer Robert N. Volk, While
ood
ave
the double-Ts themselves are in
shape, some of the haunches
spalled and corroded, he says.
The city’s structural department has
determined that there is no immediate
danger, Volk says, but airport officials
are worried about the effects of freeze-
thaw cydles this winter, “We just don’t
‘want to take a chance,” he says,
“We have ‘some haunches that we