Project has to be completed within the original budget

Activity ID Budget at Planned Planned weekly Duration Completed PV=BCWS Budget


Completion Duration Cost BAC / at reported date Cost of Work
BAC Planned from the site Scheduled at
Duration reported date =
Planned weekly
cost x Duration
completed at
reported date

Indicators B C D=B/C E F= D*E

A 20800 4 5200 4 20800


B 36000 4 9000 2 18000
C 23400 3 7800 3 23400
D 13000 5 2600 1 2600
E 113200 2 56600 2 113200
F 170800 2 85400 1 85400
G 4000 1 4000 0 0
H 10400 2 5200 0 0
SUM 391600 263400
PV
EAC= $ 444,696.67
ETC= $ 195,216.67
VAC= -$ 53,096.67
TCPI= 1.07134815649

Conclusion Based on TCPI: Project has less fund and more work, it is difficult to complete the work with
I am going to need extra cost of = $ 53097
Project Status SPI= 0.909 BS
overall CPI= 0.959 OV
Activities Status
Activity CPI COST Status SPI Schedule status
A 0.91 o 1.00 OS
B 0.80 o 0.80 BS
C 0.89 o 0.80 BS
D 1.50 u 1.50 AS
E 1.26 u 1.00 OS
F 0.72 o 0.80 BS
G 0.00 NA 0 NA
H 0.00 NA 0 NA
Project Performance Indicators
Percentage EV BCWP AC Actual SV CV SPI CPI EAC
completed at BAC x Cost of EV-PV EV-AC EV/PV EV/AC Estimate at
reported date : % Works Completion
From site % Performed ( AC/EV)*BAC
to be
given from
the site

G H= B*G I J= H-F K= H-I L=H / F M= H/I N= I/H*B

100% 20800 22880 0 -2080 1 0.91 22880


40% 14400 18000 -3600 -3600 0.8 0.80 45000
80% 18720 21000 -4680 -2280 0.8 0.89 26250
30% 3900 2600 1300 1300 1.5 1.50 8666.66666667
100% 113200 90000 0 23200 1 1.26 90000
40% 68320 95000 -17080 -26680 0.8 0.72 237500
0% 0 NA 0 0 0 0.00 4000
0% 0 NA 0 0 0 0.00 10400
239340 249480 444696.666667
EV AC

t to complete the work within the budget

Legend
O = Over budgte AS= Ahead schedule
U= Under budgte OS= On schedule
ON= On budget BS= Behind schedule
Project Future Indicators
ETC VAC Variance at Remaining Work EAC-AC Remaining TCPI using EAC
Estimate to Completion BAC-EV Funds ( BAC-
Complete VAC=BAC-EAC BAC-AC EV)/(EAC-AC)
EAC - AC

O= N-I P= B-N Q= B-H R= N-I S= B-I T= QlR

0 -2080 0 0 -2080 0.000


27000 -9000 21600 27000 18000 0.800
5250 -2850 4680 5250 2400 0.891
6067 4333 9100 6067 10400 1.500
0 23200 0 0 23200 0.000
142500 -66700 102480 142500 75800 0.719
4000 0 4000 4000 4000 1.000
10400 0 10400 10400 10400 1.000
195217 -53097 152260 195217 142120 0.779954
TCPI using BAC (
BAC-EV)/(BAC-AC)

U= Q/S

0.000
1.200
1.950
0.875
0.000
1.352
1.000
1.000
1.07134815648748