Assignment 5 EV
Assignment 5 EV
Conclusion Based on TCPI: Project has less fund and more work, it is difficult to complete the work with
I am going to need extra cost of = $ 53097
Project Status SPI= 0.909 BS
overall CPI= 0.959 OV
Activities Status
Activity CPI COST Status SPI Schedule status
A 0.91 o 1.00 OS
B 0.80 o 0.80 BS
C 0.89 o 0.80 BS
D 1.50 u 1.50 AS
E 1.26 u 1.00 OS
F 0.72 o 0.80 BS
G 0.00 NA 0 NA
H 0.00 NA 0 NA
Project Performance Indicators
Percentage EV BCWP AC Actual SV CV SPI CPI EAC
completed at BAC x Cost of EV-PV EV-AC EV/PV EV/AC Estimate at
reported date : % Works Completion
From site % Performed ( AC/EV)*BAC
to be
given from
the site
Legend
O = Over budgte AS= Ahead schedule
U= Under budgte OS= On schedule
ON= On budget BS= Behind schedule
Project Future Indicators
ETC VAC Variance at Remaining Work EAC-AC Remaining TCPI using EAC
Estimate to Completion BAC-EV Funds ( BAC-
Complete VAC=BAC-EAC BAC-AC EV)/(EAC-AC)
EAC - AC
U= Q/S
0.000
1.200
1.950
0.875
0.000
1.352
1.000
1.000
1.07134815648748