Final Term Project
Final Term Project
Final Term Project
12. Create a Project Organization chart: should be for only the project team (not the
company) along with the responsibility matrix. (4 marks)
Project Manager
Construction Accounting/
Manager Project Admin Commercial/ Quality Team Planning Team HR Team Designing Team
Procurement/Store
Estimating Staff
Safety Team Engineering
Consultant
Supervisor 1: Supervisor 2:
Procuring Team
Survey Team
Design, Drawing P
Recruitment and project
stakeholder S P
Vendor selection and
procurement S P P
Building layout and
Excavation S P
Construction Execution
and concreting work P
Construction progress
report and site records P
Review and approval of
IPC bills P S
Progressive payment
and cost recording S P
Project progress
tracking P S
Finishing, handover and
closing the project S P S
Stakeholders Project Project Construction Finance Consultant Site Material HR and Estimating Sub-
Sponsor Manager Project Team Engineer superintendent Suppliers Admin and Quality contractor
Activities Manager Team
Project Planning A R R I
Design, Drawings
and Approval I C A R
Estimate/Budget
allocation and time I I A C I R
schedule
Vendors selection
(sub- contractors/ I I A C C I I R I
suppliers)
Procurement/
Finance and I I A R I R C R
Accounting
Mobilization and
Reporting I C A R R
Excavation of
foundations I C A R
Concrete work on
foundations, floors I C A R
and superstructure
Work Progress
Tracking/ I A R I A
Time Schedule
Brick Veneer and
exterior finish I C A R R
HVAC work
I C A R
Electrical and
Plumbing work I I C A R C R
Interior finishing
work I C A C R A
Handover and
operations I R C A A I R
b. Project Team Charter
Mission As a students of construction Project Management course for the final term
And project constructing college restaurant in the college premises.
Objectives After completion of the construction of the restaurant building many students
facing challenges for outdoor food in the winter season will be benefited.
The funding source is from Canadore college and the approximate budget for
Budget the completion of this project is estimated to be $10,000,00.00
And From the cost of contingency fund allocated by the finance team every year this
Resources project needs some tools and equipment to function well.
On the job training is provided to the project staff before starting the
construction work, and near future there is a plan to train and operate the
restaurant.
Roles Project Sponsor, Project Manager, Construction Project Manager along with
And Admin/Finance and design team are associated with this project and each
Responsibilities personnel has contribution to this project.
The expert project team is involved for the completion of this project along side
with the sub-contractor.
Project Sponsor/Owner has full authority over this project.
Team Project Manager is the authentication person for the construction of this
Operations project and he has decision making power in any conflict.
The stakeholder register maintains the record of in and out of any team
member during the construction period.
The construction of new restaurant inside the college premises and scope of
Scope this project will include development and management of more than 200
seated restaurant. The restaurant will include a Conference Hall (80 customer
capacity) and a garden (50 customer capacity). The restaurant will also include
a 5-10 km home delivery radius. It will also need licensing for opening up of
a commercial restaurant in near future.
Performance There is a progress tracking system in the project team, in every consequence
Assessment the site superintended is responsible for the progress reporting and the budget
over run.
Construction Project Manager and Project Manager both are responsible and
accountable for the tracking of budget as per the work progress.
Guide Every day site superintended is responsible to communicate and work briefing
To for the crew member in the construction site and every individual will use
Communications emails for the communication.
At least twice a month each team member will be sitting together for the work
progress meeting and going ahead for any project issues.
The daily, weekly and monthly reporting mechanism will enhance the status of
construction project.
Change control board is abbreviated as CCB, as the project will receive change requests and these must be
evaluated by the change control board.
The board is responsible for reviewing and analyzing change requests. Once a change request is submitted,
this is analyzed by the CCB
The CCB include:
Project Manager
Experts
Construction Project Manager
Project Sponsor Project Sponsor/Owner
Change Request
Sub-Contractor
Reference List:
https://ilearn.canadorecollege.ca/d2l/le/content/371092/viewContent/2147020/View
https://www.sinnaps.com/en/project-management-blog/project-charter-example