Professional Documents
Culture Documents
Week 11
Week 11
It encompasses activities
within the shaded areas of Figure 11.1. The box entitled, “Shop-floor scheduling and control,” which we
refer to as shop-floor control, falls completely within PAC. Vendor scheduling and follow-up is depicted
as largely being part of production activity control, but not completely. Many firms, particularly those
with JIT material control approaches, assign most vendor scheduling to PAC. Order release (which
authorizes release of individual orders to the factory and provides accompanying documentation) is
similarly becoming more a part of PAC. In purchasing, procurement is seen as a professional activity
where information networks, relationships, terms, and conditions are established with vendor companies
outside of PAC, while release of individual orders and follow-up activities are a part of PAC.
Kontrol aktivitas produksi (PAC) menyangkut pelaksanaan rencana material. Ini mencakup kegiatan
dalam area yang diarsir pada Gambar 11.1. Kotak berjudul, "Penjadwalan dan kontrol lantai toko," yang
kami sebut kontrol lantai toko, sepenuhnya berada dalam PAC. Penjadwalan dan tindak lanjut vendor
digambarkan sebagian besar sebagai bagian dari kontrol aktivitas produksi, tetapi tidak sepenuhnya.
Banyak perusahaan, terutama yang dengan pendekatan kontrol material JIT, menetapkan sebagian
besar penjadwalan vendor ke PAC. Pelepasan pesanan (yang mengizinkan pelepasan pesanan individu
ke pabrik dan menyediakan dokumentasi yang menyertainya) juga menjadi bagian dari PAC. Dalam
pembelian, pengadaan dipandang sebagai aktivitas profesional di mana jaringan informasi, hubungan,
syarat, dan ketentuan dibuat dengan perusahaan vendor di luar PAC, sementara pelepasan pesanan
individu dan kegiatan tindak lanjut merupakan bagian dari PAC.
Queue time (the critical element) frequently accounts for 80 percent or more of total lead time; it’s the
element most capable of being managed. Reducing queue time means shorter lead time and, therefore,
reduced work-in-process inventory. This reduction requires better scheduling.
The bottom of Figure 11.3 shows an operation setback chart based on each part’s lead times. Here we
clearly see the implications of incorrect MRP lead time. If the MRP lead time for part E isn’t the one
week calculated from the routing data, the part will be released either early or late to the shop. Neither of
these is a desirable outcome. Note that Figure 11.3 shows that both parts D and E go through work center
101 for their first operation. The top of Figure 11.4 shows the partial schedule for work center 101, with
parts D and E scheduled according to the timing in Figure 11.3.
The bottom of Figure 11.4 shows two alternative detailed schedules for part D in week 1 at work center
101. The shaded portion represents the 1.8 days of lead time required for setup and run time. The early
schedule has part D loaded as soon as possible in the four days. The late schedule loads part D into the
latest possible time at work center 101. The key differences between the top and bottom of Figure 11.4
are the timing of the setup and run times. The blank area in both schedules includes queue time. Queue
time represents slack that permits the choice of alternative schedules—a form of flexibility. This slack
can be removed by good SFC practice; that is, this schedule allows 4 full days to complete part D, when
actual time on the machine is only 1.8 days. For the remaining 2.2 days, the part waits in a queue or is
moving between work centers.
The shaded portion of the schedules shown at the bottom of Figure 11.4 contains no queue time. These
schedules represent loading a particular job onto a particular work center for a particular time period. The
two alternatives in the bottom of Figure 11.4 are different loadings; one typically chooses between
alternative loadings to utilize the machine center effectively.
Waktu antrian (elemen kritis) sering menyumbang 80 persen atau lebih dari total waktu tunggu; itu adalah
elemen yang paling mampu dikelola. Mengurangi waktu antrian berarti waktu tenggang yang lebih
pendek dan, karenanya, mengurangi inventaris dalam proses. Pengurangan ini membutuhkan penjadwalan
yang lebih baik.
Bagian bawah Gambar 11.3 menunjukkan grafik kemunduran operasi berdasarkan waktu tunggu setiap
bagian. Di sini kita melihat dengan jelas implikasi MRP lead time yang salah. Jika MRP lead time untuk
bagian E bukan satu minggu yang dihitung dari data routing, bagian itu akan dirilis baik awal atau
terlambat ke toko. Tak satu pun dari ini adalah hasil yang diinginkan. Perhatikan bahwa Gambar 11.3
menunjukkan bahwa kedua bagian D dan E melewati pusat kerja 101 untuk operasi pertama mereka.
Bagian atas Gambar 11.4 menunjukkan jadwal parsial untuk pusat kerja 101, dengan bagian D dan E
dijadwalkan sesuai dengan waktu pada Gambar 11.3.
Bagian bawah Gambar 11.4 menunjukkan dua jadwal detail alternatif untuk bagian D dalam minggu 1 di
pusat kerja 101. Bagian yang diarsir mewakili 1,8 hari waktu tunggu yang diperlukan untuk pengaturan
dan waktu berjalan. Jadwal awal memiliki bagian D dimuat sesegera mungkin dalam empat hari. Jadwal
yang terlambat memuat bagian D ke waktu terakhir yang memungkinkan di pusat kerja 101. Perbedaan
utama antara bagian atas dan bawah Gambar 11.4 adalah waktu pengaturan dan waktu menjalankan. Area
kosong di kedua jadwal termasuk waktu antrian. Waktu antrian merepresentasikan kelonggaran yang
memungkinkan pemilihan jadwal alternatif — suatu bentuk fleksibilitas. Kendur ini dapat dihilangkan
dengan praktik SFC yang baik; yaitu, jadwal ini memungkinkan 4 hari penuh untuk menyelesaikan bagian
D, ketika waktu sebenarnya pada mesin hanya 1,8 hari. Selama 2,2 hari tersisa, bagian menunggu dalam
antrian atau bergerak di antara pusat kerja.
Bagian yang diarsir dari jadwal yang ditunjukkan di bagian bawah Gambar 11.4 tidak mengandung waktu
antrian. Jadwal ini mewakili pemuatan pekerjaan tertentu ke pusat kerja tertentu untuk periode waktu
tertentu. Dua alternatif di bagian bawah Gambar 11.4 adalah beban yang berbeda; orang biasanya
memilih antara pemuatan alternatif untuk memanfaatkan pusat mesin secara efektif.
Lead-Time Management
Many people think of lead time as a constant, such as p. In fact, it’s not a value to be measured as much
as a parameter to be managed. Of the four elements of lead time (run, setup, move, and queue), the last
two can be compressed with good PAC design and practice.
Lead time and work-in-process (WIP) are directly related. Moreover, some critical feedback linkages
operate. The longer the lead time is perceived to be, the longer the time between the order launching date
and due date. The longer this time, the more orders in the shop. The more orders in the shop, the longer
the queue time (and WIP); we have a self- fulfilling prophecy.
Some WIP is needed at work centers where high utilization is important. However, a basic principle of
MPC systems is to substitute information for inventory. The firm doesn’t need to have jobs physically in
front of machines. Orders can be held in a computer and converted to physical units only as needed. For
many plants, setup and run time constitute only 10 to 20 percent of total lead time. The rest is slack that
can be substantially cut.
One interesting question is how to manage lead time. This means changing database elements for both
SFC and MRP. One alternative is to go through the database and systematically change all lead times.
Reducing them could result in a transient condition of dry work centers at early gateway operations. This
might be a reasonable price to pay for the resulting WIP reduction.
Changing lead-time data elements naturally leads to the question of how they’re established in the first
place. For most firms, lead-time data are usually an input from some functional area, such as production
control. An alternative is to calculate lead time.
When we think about changing lead times as part of a management process, and when we remember that
SFC lead time must be in tune with MRP lead-time offset data, this approach has increasing appeal. One
firm calculated lead times as follows:
1. Nonqueue time for each operation was set equal to setup plus run (time per piece π lot size) plus move
times.
2. Nonqueue time was converted to days by dividing total hours by number of shifts per day, assuming
seven productive hours per day.
3. Queue time was set equal to two days if the next work center routing was in another department, one
day if it was in the same department but a different work center, and zero days if it was on the same
machine.
4. Lead time for the total order was the sum of the queue and nonqueue times. This time was calculated
with an average order quantity, rounded to a weekly lead time, and used for MRP lead-time offsetting.
Selecting queue time is the critical element in this formula. Values were chosen by taking a sample of 50
parts and using different queue time estimates to yield lead times consistent with production control
personnel opinions. The initial estimates were padded, but the company was not very concerned. Once the
system was in operation, estimates for queue times were systematically reduced a bit at a time. The result
was a managed approach to shorter lead times and reduced work in process.
Gantt Charts
Gantt or bar charts, like those in Figure 11.4, show a schedule. The operation setback chart in Figure
11.4 is very similar. It too is a schedule for when to make each of the five parts based on lead times that
include move and queue times.
One form of shop-floor control is to prepare operation setback charts similar to Figure 11.3 for each job,
and use them with the kind of data in Figure 11.3 to prepare Gantt charts, such as those in Figure 11.4.
The objective is to prepare a schedule for each machine center. This schedule can be based on the
assumptions in either the top or bottom of Figure 11.4; that is, the schedule may or may not use lead times
that include queue and move times.
The more usual practice is to prepare the detailed work center schedule without move and queue times.
Many firms’ systems do this. The typical approach is a schedule board with racks to hold pieces of
paper. Each paper is a job and its length represents the setup plus run time required.
The primary problem with this kind of system is updating. Actual data must be captured and integrated
into an ongoing replanning cycle. Moreover, a means to communicate with the shop floor is usually
required since schedule boards typically reside in planning offices. Many companies now use large flat
screen monitors positioned for easy viewing on the shop floor to display current job schedules.
Manajemen Lead-Time
Banyak orang menganggap lead time sebagai konstanta, seperti hal. Bahkan, itu bukan nilai yang akan
diukur sebanyak parameter yang akan dikelola. Dari empat elemen lead time (run, setup, move, dan
queue), dua elemen terakhir dapat dikompres dengan desain dan latihan PAC yang baik.
Lead time dan work-in-process (WIP) terkait langsung. Selain itu, beberapa tautan umpan balik kritis
beroperasi. Semakin lama waktu yang dianggap, semakin lama waktu antara tanggal peluncuran pesanan
dan tanggal jatuh tempo. Semakin lama saat ini, semakin banyak pesanan di toko. Semakin banyak
pesanan di toko, semakin lama waktu antrian (dan WIP); kami memiliki ramalan yang terpenuhi dengan
sendirinya.
Beberapa WIP diperlukan di pusat-pusat kerja di mana pemanfaatan tinggi penting. Namun, prinsip dasar
sistem MPC adalah mengganti informasi untuk inventaris. Perusahaan tidak perlu memiliki pekerjaan
secara fisik di depan mesin. Pesanan dapat disimpan di komputer dan dikonversi ke unit fisik hanya
sesuai kebutuhan. Untuk banyak pabrik, pengaturan dan waktu pengoperasian hanya 10 hingga 20 persen
dari total waktu tunggu. Sisanya kendur yang dapat dipotong secara substansial.
Satu pertanyaan menarik adalah bagaimana mengatur waktu tunggu. Ini berarti mengubah elemen basis
data untuk SFC dan MRP. Salah satu alternatif adalah melalui database dan mengubah secara sistematis
semua waktu tunggu. Mengurangi mereka dapat menghasilkan kondisi sementara pusat kerja kering di
operasi gateway awal. Ini mungkin harga yang wajar untuk membayar pengurangan WIP yang dihasilkan.
Mengubah elemen data waktu-memimpin secara alami mengarah pada pertanyaan tentang bagaimana
mereka dibuat di tempat pertama. Bagi sebagian besar perusahaan, data lead-time biasanya merupakan
input dari beberapa area fungsional, seperti kontrol produksi. Alternatifnya adalah menghitung lead time.
Ketika kita berpikir tentang mengubah waktu tunggu sebagai bagian dari proses manajemen, dan ketika
kita ingat bahwa waktu tunggu SFC harus selaras dengan data offset waktu tunggu MRP, pendekatan ini
meningkatkan daya tarik. Satu perusahaan menghitung waktu tunggu sebagai berikut:
1. Waktu nonqueue untuk setiap operasi ditetapkan sama dengan pengaturan plus lari (waktu per potong π
ukuran lot) ditambah waktu bergerak.
2. Waktu nonqueue dikonversi menjadi hari dengan membagi total jam dengan jumlah shift per hari,
dengan asumsi tujuh jam produktif per hari.
3. Waktu antrian ditetapkan sama dengan dua hari jika perutean pusat kerja berikutnya berada di
departemen lain, satu hari jika berada di departemen yang sama tetapi pusat kerja yang berbeda, dan nol
hari jika berada di mesin yang sama.
4. Waktu tunggu untuk total pesanan adalah jumlah waktu antrian dan nonqueue. Waktu ini dihitung
dengan jumlah pesanan rata-rata, dibulatkan menjadi waktu tunggu mingguan, dan digunakan untuk MRP
waktu tunggu offset.
Memilih waktu antrian adalah elemen penting dalam rumus ini. Nilai dipilih dengan mengambil sampel
50 bagian dan menggunakan perkiraan waktu antrian yang berbeda untuk menghasilkan waktu tunggu
yang konsisten dengan pendapat personel kontrol produksi. Perkiraan awal sudah diisi, tetapi perusahaan
tidak terlalu peduli. Setelah sistem beroperasi, perkiraan waktu antrian secara sistematis dikurangi sedikit
demi sedikit. Hasilnya adalah pendekatan yang dikelola untuk mempersingkat waktu memimpin dan
mengurangi pekerjaan dalam proses.
Gantt Charts
Gantt atau bar chart, seperti pada Gambar 11.4, menunjukkan jadwal. Bagan kemunduran operasi pada
Gambar 11.4 sangat mirip. Ini juga merupakan jadwal kapan harus membuat masing-masing dari lima
bagian berdasarkan waktu memimpin yang mencakup waktu bergerak dan antrian.
Salah satu bentuk kontrol lantai-toko adalah menyiapkan grafik kemunduran operasi yang serupa dengan
Gambar 11.3 untuk setiap pekerjaan, dan menggunakannya dengan jenis data pada Gambar 11.3 untuk
menyiapkan grafik Gantt, seperti yang ada pada Gambar 11.4. Tujuannya adalah untuk mempersiapkan
jadwal untuk setiap pusat mesin. Jadwal ini dapat didasarkan pada asumsi di bagian atas atau bawah
Gambar 11.4; yaitu, jadwal mungkin atau mungkin tidak menggunakan waktu memimpin yang termasuk
antrian dan waktu pindah.
Praktik yang lebih umum adalah menyiapkan jadwal pusat kerja yang terperinci tanpa waktu antrian dan
bergerak. Banyak sistem perusahaan melakukan ini. Pendekatan tipikal adalah papan jadwal dengan rak
untuk menampung potongan kertas. Setiap kertas adalah pekerjaan dan panjangnya mewakili pengaturan
plus waktu yang diperlukan. Masalah utama dengan sistem semacam ini adalah pembaruan. Data aktual
harus ditangkap dan diintegrasikan ke dalam siklus perencanaan ulang yang sedang berlangsung. Selain
itu, sarana untuk berkomunikasi dengan lantai toko biasanya diperlukan karena papan jadwal biasanya
berada di kantor perencanaan. Banyak perusahaan sekarang menggunakan monitor layar datar besar yang
diposisikan agar mudah dilihat di lantai toko untuk menampilkan jadwal pekerjaan saat ini.
If the ratio is 1.0, the job is on time. A ratio below 1.0 indicates a behind-schedule job, while a ratio
above 1.0 indicates an ahead-of-schedule condition. The rule is to always process that job with the
smallest critical ratio next.
▲ Shortest operation next: This rule ignores all due date information as well as all information about
work remaining. It simply says, take as the next job the one that can be completed in the shortest time at
the work center. This rule maximizes the number of shop orders that go through a work center and
minimizes the number waiting in queue.
In an MRP system, each shop order would be a scheduled receipt for the part. As such, the scheduled
receipt has a due date. From this due date, operational due dates could be established by backing off
expected operation times, if these data are needed to establish priority sequence. The great advantage of
this computer-based system is that, whenever the due date for a scheduled receipt changes, operation due
dates can be changed accordingly. These changes, in turn, lead to priority changes for shop-floor control,
resulting in an execution system that works on the most-needed shop orders first.
The objective is for high-priority jobs to move through the shop very quickly, while low-priority jobs are
set aside. In this way, the shop-floor control system can indeed execute the dictates of the detailed
material plan. In recent times, many companies have developed a preference for sequencing rules that are
easy to understand. One straightforward approach is to develop operation start and operation due dates,
and use them for determining priority sequence decisions. In a computer-based shop-floor control system,
due dates wouldn’t be printed on any shop paper that travels with the work-in-process inventory. The
shop paper would show the routing or sequence of operations (static data), but no due dates. The changing
(dynamic) due date information would be printed daily or be displayed on line in the form of a work
center schedule or dispatch list. It’s the dispatch list, not the traveling paper, that shows the priority
sequence. The dispatch list can be updated as rapidly as transactions are processed to the MRP database.
Jika rasionya 1.0, pekerjaannya tepat waktu. Rasio di bawah 1,0 menunjukkan pekerjaan di belakang
jadwal, sementara rasio di atas 1,0 menunjukkan kondisi di atas jadwal. Aturannya adalah untuk selalu
memproses pekerjaan itu dengan rasio kritis terkecil berikutnya.
▲ Operasi terpendek berikutnya: Aturan ini mengabaikan semua informasi tanggal tenggat serta semua
informasi tentang sisa pekerjaan. Itu hanya mengatakan, ambil pekerjaan berikutnya yang bisa
diselesaikan dalam waktu singkat di pusat kerja. Aturan ini memaksimalkan jumlah pesanan toko yang
melewati pusat kerja dan meminimalkan jumlah antrian yang menunggu.
Dalam sistem MRP, setiap pesanan toko akan menjadi tanda terima yang dijadwalkan untuk bagian
tersebut. Dengan demikian, tanda terima yang dijadwalkan memiliki tanggal jatuh tempo. Dari tanggal
jatuh tempo ini, tanggal jatuh tempo operasional dapat ditetapkan dengan mundur dari waktu operasi yang
diharapkan, jika data ini diperlukan untuk menetapkan urutan prioritas. Keuntungan besar dari sistem
berbasis komputer ini adalah bahwa, kapan pun tanggal jatuh tempo untuk perubahan tanda terima yang
dijadwalkan, tanggal jatuh tempo operasi dapat diubah sesuai dengan itu. Perubahan-perubahan ini, pada
gilirannya, menyebabkan perubahan prioritas untuk kontrol lantai toko, menghasilkan sistem eksekusi
yang bekerja pada pesanan toko yang paling dibutuhkan terlebih dahulu.
Tujuannya adalah agar pekerjaan dengan prioritas tinggi dapat bergerak cepat melalui toko, sementara
pekerjaan dengan prioritas rendah disingkirkan. Dengan cara ini, sistem kontrol lantai toko dapat benar-
benar melaksanakan dikte rencana material terperinci. Belakangan ini, banyak perusahaan telah
mengembangkan preferensi untuk aturan sekuensing yang mudah dipahami. Salah satu pendekatan
langsung adalah mengembangkan operasi mulai dan tanggal jatuh tempo operasi, dan menggunakannya
untuk menentukan keputusan urutan prioritas. Dalam sistem kontrol lantai toko berbasis komputer,
tanggal jatuh tempo tidak akan dicetak pada kertas toko apa pun yang bepergian dengan inventaris dalam
proses. Kertas toko akan menunjukkan perutean atau urutan operasi (data statis), tetapi tidak ada tanggal
jatuh tempo. Informasi tanggal jatuh tempo yang berubah (dinamis) akan dicetak setiap hari atau
ditampilkan secara online dalam bentuk jadwal pusat kerja atau daftar pengiriman. Ini adalah daftar
pengiriman, bukan kertas bepergian, yang menunjukkan urutan prioritas. Daftar pengiriman dapat
diperbarui secepat transaksi diproses ke database MRP.
Theory of Constraints (TOC) Systems
An increasing number of firms have been implementing a plant scheduling system that uses theory of
constraints (TOC) concepts. Initially, TOC scheduling systems were viewed as a replacement of an
integrated MPC system. In fact, TOC scheduling systems encompass the functions performed in the
engine and back end of Figure 11.1, but combine these functions so that material and capacity are planned
simultaneously. TOC systems accomplish many functions in the MPC framework, but not all.
TOC Scheduling
The scheduling approach used in TOC systems is called drum-buffer-rope. The bottleneck work centers
(constraints) are the drums, and are, therefore, used to control the workflow in a plant. Any resource
whose capacity is more than the demand is called a nondrum. The rope refers to “pull” scheduling at the
nonbottleneck work centers. The purpose of the rope is to tie the production at each resource to the drum.
Buffers exist at all of the bottleneck work centers, and the shipping dock, but not at nonbottleneck work
centers. These buffers are used to protect the throughput of the bottleneck work centers from the
inevitable minor fluctuations through the use of time buffers (WIP inventory) at a relatively few critical
points in the plant. The basic concept is to move material as quickly as possible through nonbottleneck
work centers until it reaches the bottleneck. The work at the bottleneck resources is scheduled for
maximum efficiency. Thereafter, work again moves at maximum speed to the shipping dock (finished
goods).
The diagram shown in Figure 11.5 outlines the basic TOC scheduling steps. TOC begins its process by
combining data in the bill of materials file with data in the routing file. The result is a network, or
extended tree diagram, where each part in the product structure also has its operational data attached
directly. These data are then combined with the MPS to form the “product network.” Figure 11.6 provides
an example of a TOC product network. Here, customer orders are linked to the final operation (such as
the final assembly process), which, in turn, is linked to previous operations (such as the detailed
fabrication steps for components), and then to raw materials. Additional data typically included in the
TOC files are capacities, maximum inventories, minimum batch quantities, order quantities, due dates,
alternative machine routing, labor constraints, and other data typically used in finite scheduling models.
In Figure 11.5, these data would be part of the “Resource description.”
Next, the product network and resource descriptions are fed into a set of routines that identify the
bottleneck resources. This routine combines the product network and resource information to form a TOC
network of the bottleneck resources. To determine the bottleneck resources an initial analysis is prepared
that provides reports indicating bottleneck resources. This involves using a rough-cut capacity planning
routine that provides much of the information of other capacity planning procedures. Because the TOC
product network includes both the parts and their routings, a pass through this network can result in an
estimate of the capacity required at each work center. Lot sizes at this rough-cut stage are based on lot-
for-lot rules. The resultant capacity needs, when divided by the number of weeks in the planning horizon,
are the average capacity requirements for each resource. When divided by the resource capacities, the
result is the average expected load.
As illustrated in Figure 11.7, the average loads on machine centers are sorted, and the most heavily
loaded are studied by analysts. Typical questions include: Are the data correct? Are the time standards
accurate? Can we easily increase capacity? Can we use alternative routings for some items? Any changes
based on these questions result in another run to see if the bottleneck resources change. Those work
centers in Figure 11.7 having a utilization exceeding 80 percent would be considered bottle neck work
centers.
At this point the TOC product network is split into two portions, as shown in Figure 11.5. The left-hand
portion incorporates all bottleneck resources and all succeeding operations, including market demand for
end products with parts that have processing on the bottleneck resources. This portion of the network is
forward finite loaded.
The right-hand portion includes all of the nonbottleneck resources. This portion of the network is not
forward finite loaded. Operation start dates/times are, however, established by using the setup times, run
times, and queue times for the non-bottleneck resource operations. An initial scheduling pass is made
through the product network, and the raw material release dates are offset from customer order due dates
by taking into account the processing and queue times for all part operations. In a second pass, however,
due dates for any part operations that feed bottlenecks are based on those established by the TOC
scheduling of bottlenecks.
Schedules for these part operations are set so that material will be available in time for the first operation
in the TOC network. This scheduling logic provides a dispatch list for the nonbottleneck resources.
One advantage of the TOC network split is that we can readily see where attention should be focused. Not
only is bottleneck capacity utilized more intensively by finite scheduling of this small subset of work
centers, but identifying bottlenecks allows us to target efforts in quality and production improvements on
these resources.
Penjadwalan TOC
Pendekatan penjadwalan yang digunakan dalam sistem TOC disebut drum-buffer-rope. Pusat kerja
bottleneck (kendala) adalah drum, dan oleh karena itu, digunakan untuk mengontrol alur kerja di pabrik.
Sumber daya apa pun yang kapasitasnya melebihi permintaan disebut nondrum. Tali mengacu pada
penjadwalan "tarik" di pusat kerja nonbottleneck. Tujuan tali adalah untuk mengikat produksi di setiap
sumber daya ke drum. Buffer ada di semua pusat kerja bottleneck, dan dok pengiriman, tetapi tidak di
pusat kerja nonbottleneck. Buffer ini digunakan untuk melindungi throughput pusat kerja bottleneck dari
fluktuasi kecil yang tak terhindarkan melalui penggunaan buffer waktu (inventaris WIP) pada titik kritis
yang relatif sedikit di pabrik. Konsep dasarnya adalah memindahkan material secepat mungkin melalui
pusat kerja nonbottleneck hingga mencapai bottleneck. Pekerjaan di sumber daya bottleneck dijadwalkan
untuk efisiensi maksimum. Setelah itu, pekerjaan kembali bergerak dengan kecepatan maksimum ke
dermaga pengiriman (barang jadi).
Diagram yang ditunjukkan pada Gambar 11.5 menguraikan langkah-langkah dasar penjadwalan TOC.
TOC memulai prosesnya dengan menggabungkan data dalam file bill of materials dengan data dalam file
routing. Hasilnya adalah jaringan, atau diagram pohon diperluas, di mana setiap bagian dalam struktur
produk juga memiliki data operasionalnya yang dilampirkan secara langsung. Data-data ini kemudian
digabungkan dengan MPS untuk membentuk "jaringan produk." Gambar 11.6 memberikan contoh
jaringan produk TOC. Di sini, pesanan pelanggan terkait dengan operasi akhir (seperti proses perakitan
akhir), yang, pada gilirannya, terkait dengan operasi sebelumnya (seperti langkah-langkah fabrikasi
terperinci untuk komponen), dan kemudian ke bahan baku. Data tambahan yang biasanya termasuk dalam
file TOC adalah kapasitas, inventaris maksimum, jumlah batch minimum, jumlah pesanan, tanggal jatuh
tempo, perutean mesin alternatif, kendala tenaga kerja, dan data lain yang biasanya digunakan dalam
model penjadwalan terbatas. Pada Gambar 11.5, data ini akan menjadi bagian dari "Deskripsi Sumber
Daya."
Selanjutnya, jaringan produk dan deskripsi sumber daya dimasukkan ke dalam serangkaian rutin yang
mengidentifikasi sumber daya bottleneck. Rutin ini menggabungkan jaringan produk dan informasi
sumber daya untuk membentuk jaringan TOC dari sumber daya kemacetan. Untuk menentukan sumber
daya bottleneck, disiapkan analisis awal yang menyediakan laporan yang mengindikasikan sumber
bottleneck. Ini melibatkan penggunaan rutin perencanaan kapasitas kasar yang menyediakan banyak
informasi dari prosedur perencanaan kapasitas lainnya. Karena jaringan produk TOC mencakup bagian-
bagian dan peruteannya, lintasan melalui jaringan ini dapat menghasilkan perkiraan kapasitas yang
diperlukan di setiap pusat kerja. Ukuran lot pada tahap pemotongan kasar ini didasarkan pada aturan lot-
untuk-lot. Kebutuhan kapasitas yang dihasilkan, ketika dibagi dengan jumlah minggu dalam cakrawala
perencanaan, adalah persyaratan kapasitas rata-rata untuk setiap sumber daya. Ketika dibagi dengan
kapasitas sumber daya, hasilnya adalah beban rata-rata yang diharapkan.
Seperti diilustrasikan dalam Gambar 11.7, beban rata-rata pada pusat-pusat alat berat disortir, dan beban
yang paling banyak dipelajari oleh para analis. Pertanyaan umum meliputi: Apakah datanya benar?
Apakah standar waktu akurat? Bisakah kita dengan mudah meningkatkan kapasitas? Bisakah kita
menggunakan rute alternatif untuk beberapa item? Setiap perubahan berdasarkan pertanyaan-pertanyaan
ini menghasilkan upaya lain untuk melihat apakah sumber daya bottleneck berubah. Pusat-pusat kerja
pada Gambar 11.7 yang memiliki pemanfaatan melebihi 80 persen akan dianggap sebagai pusat kerja
leher botol.
Pada titik ini jaringan produk TOC dibagi menjadi dua bagian, seperti yang ditunjukkan pada Gambar
11.5. Bagian sebelah kiri menggabungkan semua sumber daya bottleneck dan semua operasi yang
berhasil, termasuk permintaan pasar untuk produk akhir dengan bagian-bagian yang memiliki pemrosesan
pada sumber daya bottleneck. Bagian dari jaringan ini dimuat hingga ke depan.
Bagian kanan mencakup semua sumber daya nonbottleneck. Bagian dari jaringan ini tidak dimuat secara
terbatas. Tanggal mulai operasi / kali, bagaimanapun, ditetapkan dengan menggunakan waktu setup,
waktu menjalankan, dan waktu antrian untuk operasi sumber daya non-bottleneck. Pass penjadwalan awal
dibuat melalui jaringan produk, dan tanggal rilis bahan baku diimbangi dari tanggal jatuh tempo pesanan
pelanggan dengan memperhitungkan waktu pemrosesan dan antrian untuk semua operasi bagian. Namun
demikian, pada lintasan kedua, tanggal jatuh tempo untuk setiap bagian operasi yang mengumpan
kemacetan didasarkan pada yang ditetapkan oleh penjadwalan TOC dari kemacetan.
Jadwal untuk operasi bagian ini diatur sehingga bahan akan tersedia pada waktunya untuk operasi
pertama di jaringan TOC. Logika penjadwalan ini menyediakan daftar pengiriman untuk sumber daya
nonbottleneck.
Salah satu keuntungan dari pemisahan jaringan TOC adalah bahwa kita dapat dengan mudah melihat di
mana perhatian harus difokuskan. Kapasitas bottleneck tidak hanya dimanfaatkan secara lebih intensif
dengan penjadwalan yang terbatas dari subset kecil pusat kerja ini, tetapi mengidentifikasi bottleneck
memungkinkan kita untuk menargetkan upaya peningkatan kualitas dan produksi pada sumber daya ini.
Buffers
One issue with TOC is the assumption of certainty of the processing times. TOC buffers the schedules for
critical operations at bottleneck operations by using both safety stock and safety lead time. In scheduling
a sequence of jobs on the same machine, safety lead time can be introduced between subsequent orders.
This provides a cushion against variations adversely affecting the flow of jobs through this machine.
To protect against having these variations affect subsequent bottleneck operations on the same job, safety
lead time is employed. In this case, the start of the next bottleneck operation on the same job isn’t
scheduled immediately after the current operation is completed. A delay is introduced to perform the
buffering here. (Note: there can be another job in process during the delay; its completion will affect the
actual start date for the arriving job.) Each of these allowances means actual conditions will vary from the
TOC schedule.While the schedule for bottleneck resources is clear, an important question for the
supervisors at some point could easily be which job to run next at nonbottleneck resources. Such
decisions can be made by using a priority sequencing rule.
To ensure there’s always work at the bottleneck operation (to provide maximum output), there is safety
lead time in front of these work centers. Thus, whenever one job is completed, another is ready to go on
the bottleneck machine. Further, in order to protect the final assembly schedule against shortages that
could severely cut output, a safety stock of nonbottleneck operation completed parts is held before final
assembly. The idea is to not disrupt the flow of material from a bottleneck operation. Parts shortages that
can be made up by going through nonbottleneck operations won’t cut capacity.
Other management considerations also enter the TOC scheduling system to reduce the effect of
uncertainty. These include making realistic schedules that meet material and capacity limitations.
Considerations involving the appropriate level of work-in-process inventory, the capacity utilization
attainable, degree of schedule protection, and batch size controls can all be applied to the TOC procedure.
These help take into account the company culture as the TOC procedure is implemented.
Buffer
Salah satu masalah dengan TOC adalah asumsi kepastian waktu pemrosesan. TOC mendukung jadwal
untuk operasi kritis di operasi bottleneck dengan menggunakan safety stock dan safety lead time. Dalam
menjadwalkan urutan pekerjaan pada mesin yang sama, waktu keselamatan dapat diperkenalkan antara
pesanan berikutnya. Ini memberikan bantalan terhadap variasi yang mempengaruhi aliran pekerjaan
melalui mesin ini.
Untuk melindungi agar variasi-variasi ini tidak mempengaruhi operasi bottleneck berikutnya pada
pekerjaan yang sama, lead time keselamatan digunakan. Dalam hal ini, dimulainya operasi bottleneck
berikutnya pada pekerjaan yang sama tidak dijadwalkan segera setelah operasi saat ini selesai. Penundaan
diperkenalkan untuk melakukan buffering di sini. (Catatan: mungkin ada pekerjaan lain dalam proses
selama penundaan; penyelesaiannya akan mempengaruhi tanggal mulai sebenarnya untuk pekerjaan yang
tiba.) Masing-masing tunjangan ini berarti kondisi aktual akan bervariasi dari jadwal TOC. Sementara
jadwal untuk sumber daya bottleneck jelas , pertanyaan penting bagi pengawas di beberapa titik dapat
dengan mudah pekerjaan mana yang harus dijalankan selanjutnya dengan sumber daya nonbottleneck.
Keputusan semacam itu dapat dibuat dengan menggunakan aturan urutan prioritas.
Untuk memastikan selalu ada pekerjaan di operasi bottleneck (untuk memberikan hasil maksimum), ada
waktu tunggu keselamatan di depan pusat-pusat kerja ini. Jadi, setiap kali satu pekerjaan selesai, yang lain
siap untuk pergi pada mesin bottleneck. Lebih lanjut, untuk melindungi jadwal perakitan akhir terhadap
kekurangan yang dapat sangat memangkas output, stok keselamatan untuk operasi nonbottleneck
menyelesaikan komponen diadakan sebelum perakitan akhir. Idenya adalah untuk tidak mengganggu
aliran material dari operasi bottleneck. Kekurangan suku cadang yang dapat diperbaiki dengan melalui
operasi nonbottleneck tidak akan mengurangi kapasitas.
Pertimbangan manajemen lainnya juga masuk ke sistem penjadwalan TOC untuk mengurangi efek
ketidakpastian. Ini termasuk membuat jadwal realistis yang memenuhi batasan material dan kapasitas.
Pertimbangan yang melibatkan tingkat persediaan barang dalam proses yang tepat, pemanfaatan kapasitas
yang dapat dicapai, tingkat perlindungan jadwal, dan kontrol ukuran bets semuanya dapat diterapkan pada
prosedur TOC. Ini membantu memperhitungkan budaya perusahaan ketika prosedur TOC dilaksanakan.
Menjadwalkan Drum
Langkah pertama adalah menjadwalkan pesanan baru pada operasi bottleneck, disebut sebagai drum. Ini
dicapai dengan menggunakan logika berikut:
▲ Hitung waktu mulai paling awal pada kendala pertama dengan menambahkan waktu pemrosesan
sebelum kendala ke waktu tunggu bahan baku dan waktu buffer kendala pertama.
▲ Tempatkan pesanan setelah dan sedekat mungkin dengan waktu mulai paling awal pada kendala.
▲ Hitung waktu mulai paling awal pada kendala berikutnya (atau tanggal pengiriman) dengan
menambahkan waktu pemrosesan setelah kendala pertama dan waktu buffer berikutnya ke waktu
penyelesaian pada kendala saat ini.
Produk A dalam Gambar 11.8 menggambarkan logika ini. Perhatikan bahwa pada Gambar 11.8 waktu
pemrosesan untuk tiga operasi sebelum kendala pertama (pemesinan akhir) adalah 10 jam, waktu tunggu
bahan baku adalah nol (karena bahan ini ditebar), dan waktu buffer untuk kendala pertama (pemesinan
akhir) ) delapan jam. Akibatnya, waktu mulai paling awal pada kendala pertama adalah dalam 18 jam,
atau pada akhir jam 2 pada hari 3 (dengan asumsi pabrik bekerja satu shift delapan jam setiap hari).
Gambar 11.9 menunjukkan profil beban kerja drum (pusat kerja pemesinan akhir), yang menunjukkan
bahwa empat jam terakhir hari 3 belum dijadwalkan. Oleh karena itu, pesanan untuk Produk A
dijadwalkan mulai pada akhir jam 4 dan selesai pada akhir jam 8 pada hari ke 3.
Gambar 11.10 menunjukkan diagram alir proses dan menunjukkan tanggal kunci yang ditetapkan dengan
menggunakan logika penjadwalan TOC. Ini termasuk tanggal / waktu ketika pesanan dijadwalkan untuk
memasuki buffer pemesinan akhir, tanggal dimulainya operasi pemesinan akhir, tanggal pesanan untuk
memasuki buffer pengiriman, dan tanggal pengiriman pelanggan. Gambar 11.11 menunjukkan tanggal /
waktu ini untuk produk A. Pelepasan bahan baku untuk produk A direncanakan pada akhir jam 2 pada
hari 1, dan produk ini dijadwalkan untuk memasuki buffer pemesinan akhir pada akhir jam 12 (hari 2 ,
jam 4). Oleh karena itu pekerjaan ini diharapkan untuk menunggu delapan jam sebelum diproses pada
proses pemesinan bottleneck. Ini memastikan bahwa kesalahan dalam estimasi waktu pemrosesan tidak
memengaruhi utilisasi bottleneck 100 persen. Demikian juga, pesanan ini dijadwalkan untuk memasuki
buffer pengiriman pada akhir jam 24 (hari 3, jam 8) dengan pengiriman dijadwalkan untuk akhir jam 34
(hari 5, jam 2).
Pesanan dijadwalkan dengan menggunakan penjadwalan mundur terbatas. Logika ini dihasilkan sebagai
berikut:
▲ Kurangi buffer pengiriman dan waktu pemrosesan setelah batasan akhir dari tanggal pengiriman yang
dijadwalkan. Ini memberikan waktu penyelesaian terbaru.
▲ Tempatkan pesanan pada batasan terakhir (drum) sebelum dan sedekat mungkin dengan waktu
penyelesaian terakhir.
▲ Tentukan waktu mulai pada kendala terakhir dengan mengurangi waktu pemrosesan pada kendala dari
waktu penyelesaian.
▲ Kurangi waktu buffer kendala akhir dan waktu pemrosesan kembali ke waktu penyelesaian terbaru
dari kendala sebelumnya (atau waktu rilis bahan baku) dari waktu mulai kendala akhir.
▲ Setelah pelepasan bahan ditentukan, jadwal pengiriman bahan baku dapat ditentukan.
Produk C pada Gambar 11.8 menggambarkan logika penjadwalan ini. Tanggal pengiriman yang diminta
pelanggan untuk pesanan ini adalah akhir jam 8 pada hari 5 (atau jam 40 dalam contoh). Karena tidak ada
pemrosesan yang terjadi pada pesanan ini setelah drum (pemesinan akhir), waktu penyelesaian terakhir
dapat ditentukan dengan mengurangi waktu departemen pengiriman dua jam ditambah buffer pengiriman
delapan jam dari tanggal pengiriman yang dijadwalkan pada jam 40. Ini berarti bahwa waktu
penyelesaian terbaru untuk operasi pemesinan akhir adalah akhir dari jam 30, dan bahwa pesanan harus
memasuki buffer pengiriman pada waktu itu. Drum saat ini dijadwalkan untuk empat jam pertama pada
hari 4, sehingga produk C dapat dijadwalkan dari akhir jam 4 hingga 8 pada hari 4 (jam 28 hingga 32).
Tanggal rilis bahan baku terbaru dapat ditentukan untuk produk C dengan mengurangi waktu pemrosesan
sebelum drum dan waktu buffer drum dari waktu mulai drum. Dalam hal ini, 11 jam waktu pemrosesan
dan waktu buffer drum delapan jam dikurangi dari waktu mulai drum akhir jam 28 untuk menghasilkan
waktu pelepasan bahan baku pada akhir jam 9. Jadwal untuk produk C adalah juga ditunjukkan pada
Gambar 11.11.
Material Release—Rope
In managing plant operations, raw material should not be released earlier than the scheduled TOC raw
material release date. Releasing the raw material on these dates will minimize the WIP inventory and
reduce the choice of orders to be run on the nonbottleneck operations.
Memanfaatkan Drum
Dalam menjadwalkan drum, permintaan produk dapat melebihi kapasitas yang tersedia di drum. Dalam
hal ini mungkin perlu mengambil langkah-langkah untuk menambah kapasitas drum. Ini mungkin
melibatkan pembongkaran beberapa pesanan yang dijadwalkan pada drum ke mesin lain yang tidak
membosankan, atau mengalihdayakan pekerjaan ini ke pemasok. Pilihan lain akan termasuk mengerjakan
drum melalui makan siang dan istirahat, menambah waktu lembur, dan meningkatkan ukuran batch di
drum untuk meminimalkan waktu pemasangan. Namun, ukuran kumpulan tidak boleh ditingkatkan jika
ini akan menyebabkan penundaan tanggal pengiriman yang dijadwalkan untuk pesanan pelanggan. Ini
adalah contoh yang baik tentang seberapa banyak pemisahan dapat digunakan. Dengan membagi bets
menjadi apa yang melayani pelanggan dan apa yang masuk ke dalam inventori, pemanfaatan kendala
keseluruhan (penjualan throughput) dimaksimalkan.
Mengangkat Drum
Ini benar-benar langkah perencanaan. Setelah lantai toko berjalan dengan lancar, pertimbangan harus
diberikan dalam proses perencanaan untuk meningkatkan kapasitas drum. Jika kapasitas ditingkatkan
pada kendala, adalah mungkin bagi organisasi untuk menumbuhkan bisnis.
TOC Contributions
Now we can identify clearly one of TOC’s primary contributions.When finite scheduling through
bottleneck resources is complete, the result is a doable master production schedule.
For this reason, TOC is sometimes considered to be a “front-end” system (i.e., a master production
scheduling technique).We see it less as an MPS technique than an enhancement to the
MPS.TOCconceivably can take any MPSas input and determine the extent to which it is doable.
This means TOC makes an explicit computer-based analysis of the feedback from engine (and back end)
to the front end—an important enhancement to MRP systems. It means a valid MPS is generated—one
the firm has a strong chance of achieving—that is based on the capacity parameters used in the
scheduling.
A secondary contribution at this stage comes from the way TOC schedules the nonbottleneck resources.
The easiest way to see this is to assume (as is often the case in practice) there are no bottlenecks. In that
case, TOC schedules are based on MRP logic. The difference is that TOC in this case will change batch
sizes (reducing them) to the point where some resources almost become bottlenecks. The result is less
WIP, reduced lead time, greater material velocity, and a move toward “zero inventory” manufacturing.
TOC does much of this by overlapping schedules, using unequal batch sizes for transferring and
processing.
TOC’s third important contribution is to virtually eliminate the fundamental issue of conflicting priorities
betweenMRPand finite scheduling. Since only a small fraction of the work centers are scheduled finitely,
job priority conflicts largely disappear. Moreover, computational time required to do finite scheduling
should be dramatically cut by dealing onlywith a subset of orders andwork centers/resources.
In operation as a shop-floor control technique, TOC has a few other differences from usual practice. A
fundamental tenet in TOC is that an hour lost in a bottleneck resource is an hour lost to the entire
factory’s output, while an hour lost in a nonbottleneck resource has no real cost. This means capacity
utilization of bottleneck resources is important. TOC increases utilization by using WIP buffers in front of
bottlenecks, and where output from a bottleneck joins with some other parts. TOC also runs large batch
sizes at bottleneck operations, thereby reducing relative time spent in setup downtime.
In practice, the variable lot size issue has two major implications. First, lead times should be shorter:
smaller batches will move faster through nonbottleneck work centers. Second (and less felicitous),
procedures have to be developed to split/join batches as they go through production.
Kontribusi TOC
Sekarang kita dapat mengidentifikasi dengan jelas salah satu kontribusi utama TOC. Ketika penjadwalan
yang terbatas melalui sumber daya bottleneck selesai, hasilnya adalah jadwal induk produksi yang bisa
dilakukan.
Untuk alasan ini, TOC kadang-kadang dianggap sebagai sistem "front-end" (yaitu, teknik penjadwalan
produksi utama). Kita melihatnya kurang sebagai teknik MPS daripada peningkatan MPS. sejauh mana
hal itu bisa dilakukan.
Ini berarti TOC membuat analisis berbasis komputer yang eksplisit tentang umpan balik dari engine (dan
ujung belakang) ke ujung depan — peningkatan penting bagi sistem MRP. Ini berarti MPS yang valid
dihasilkan — yang memiliki peluang kuat untuk dicapai — yang didasarkan pada parameter kapasitas
yang digunakan dalam penjadwalan.
Kontribusi sekunder pada tahap ini berasal dari cara TOC menjadwalkan sumber daya nonbottleneck.
Cara termudah untuk melihat ini adalah dengan berasumsi (seperti yang sering terjadi dalam praktik)
tidak ada hambatan. Dalam hal ini, jadwal TOC didasarkan pada logika MRP. Perbedaannya adalah
bahwa TOC dalam hal ini akan mengubah ukuran batch (menguranginya) ke titik di mana beberapa
sumber daya hampir menjadi hambatan. Hasilnya adalah kurang WIP, mengurangi lead time, kecepatan
material yang lebih besar, dan bergerak menuju manufaktur "nol inventaris". TOC melakukan banyak hal
dengan tumpang tindih jadwal, menggunakan ukuran batch yang tidak sama untuk mentransfer dan
memproses.
Selain itu, waktu komputasi yang diperlukan untuk melakukan penjadwalan yang terbatas harus dikurangi
secara dramatis dengan hanya berurusan dengan subset pesanan dan pusat kerja / sumber daya.
Dalam operasi sebagai teknik kontrol lantai toko, TOC memiliki beberapa perbedaan lain dari praktik
biasa. Prinsip mendasar dalam TOC adalah bahwa satu jam hilang dalam sumber daya bottleneck adalah
satu jam hilang dari output seluruh pabrik, sementara satu jam hilang dalam sumber daya nonbottleneck
tidak memiliki biaya nyata. Ini berarti pemanfaatan kapasitas sumber daya bottleneck penting. TOC
meningkatkan pemanfaatan dengan menggunakan buffer WIP di depan bottleneck, dan di mana output
dari bottleneck bergabung dengan beberapa bagian lainnya. TOC juga menjalankan ukuran batch besar
pada operasi bottleneck, sehingga mengurangi waktu relatif yang dihabiskan dalam downtime pengaturan.
Dalam praktiknya, masalah ukuran lot variabel memiliki dua implikasi besar. Pertama, waktu tunggu
harus lebih pendek: batch yang lebih kecil akan bergerak lebih cepat melalui pusat kerja nonbottleneck.
Kedua (dan kurang tepat), prosedur harus dikembangkan untuk membelah / bergabung dalam batch saat
mereka melalui produksi.
Implementation Issues
A major paradigm shift is required in order to obtain the benefits of TOC scheduling. Management needs
to recognize that the plant culture needs to change from one of keeping people busy and equipment fully
loaded to one of maximizing throughput at the critical resources—the bottleneck. This means that under
TOC, as with JIT, it’s quite all right to not work if there’s no work to do at nonbottleneck resources. In
fact, working (by the usual definition) in this situation will cause problems. If people at the nonbottleneck
work on orders that are not needed to maximize flow through the bottleneck work centers, the net result
of their work will be to simply increase WIP and cause confusion for scheduling at other work
centers.Understanding the basic concepts is critical in obtaining the benefits of TOC scheduling.
TOC presents further difficulties in implementation. Companies also need sound basic systems,
education, top-management support, and a willingness to unlearn some ingrained habits. One firm we
know of has been working for several years to implement finite scheduling, without great success,
because it has strong pressures to fully utilize all direct labor-hours. In this case, the fundamental
principles of TOC have not been accepted.
Masalah Implementasi
Diperlukan pergeseran paradigma besar untuk mendapatkan manfaat dari penjadwalan TOC. Manajemen
perlu menyadari bahwa budaya pabrik perlu berubah dari yang membuat orang sibuk dan peralatan
dimuat penuh ke salah satu memaksimalkan throughput pada sumber daya kritis — hambatan. Ini berarti
bahwa di bawah TOC, seperti halnya JIT, tidak apa-apa untuk tidak bekerja jika tidak ada pekerjaan di
sumber daya nonbottleneck. Bahkan, bekerja (menurut definisi biasa) dalam situasi ini akan
menyebabkan masalah. Jika orang-orang di nonbottleneck mengerjakan pesanan yang tidak diperlukan
untuk memaksimalkan aliran melalui pusat kerja bottleneck, hasil bersih dari pekerjaan mereka adalah
dengan hanya meningkatkan WIP dan menyebabkan kebingungan untuk penjadwalan di pusat-pusat kerja
lain. Memahami konsep dasar sangat penting dalam mendapatkan manfaat dari penjadwalan TOC.
TOC menyajikan kesulitan lebih lanjut dalam implementasi. Perusahaan juga membutuhkan sistem dasar
yang sehat, pendidikan, dukungan manajemen puncak, dan kemauan untuk melepaskan beberapa
kebiasaan yang sudah tertanam. Satu perusahaan yang kami tahu telah bekerja selama beberapa tahun
untuk menerapkan penjadwalan yang terbatas, tanpa keberhasilan besar, karena perusahaan itu memiliki
tekanan kuat untuk sepenuhnya memanfaatkan semua jam kerja langsung. Dalam hal ini, prinsip-prinsip
dasar TOC belum diterima.