Concretecomputation

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 12

BILL OF QUANTITIES

ITEM ITEM DESCRIPTION UNIT QUANTITY

DIVISION 1 GENERAL REQUIREMENTS


1.0 Staff Salaries lot 1.00
2.0 Overhead Expenses lot 1.00
3.0 Temfacil lot 1.00
4.0 Bonds lot 1.00
Sub-total
TOTAL-DIVISION 1
DIVISION 2 SITE WORKS
1.0 Demolition Works lot
2.0 Clearing and Grubbing sq.m.
3.0 Batterboard Installation l.m. 50.00
4.0 Layouting grid line
5.0 Soil Poisoning sq.m. 150.00
a. Soil Poison lit 1050.00
6.0 Excavation cu.m. 102.218
7.0 Backfilling and Compaction cu.m. 73.34
8.0 Disposal cu.m. 28.88
Sub-total
TOTAL-DIVISION 2
DIVISION 3 CONCRETE
Wall Concrete Footings
WF
1.0 Gravel Bed Laying cu.m.
2.0 Reinforcement kgs.
a. GI Tie Wire # 16 kgs.
3.0 Concrete Pouring (one-bager) 3000 Psi cu.m. 38.856
a. Portland Cement (40 kg) bags 370
b. Sand cu.m. 19.428
c. Gravel 3/4" cu.m. 38.856
Sub-total
Column Footings
1.0 Gravel Bed Laying cu.m.
2.0 Reinforcement kgs.
a. GI Tie Wire # 16 kgs.
3.0 Concrete Pouring (one-bager) 3000 Psi cu.m. 34.7
a. Portland Cement (40 kg) bags 330
b. Sand cu.m. 17.35
c. Gravel 3/4" cu.m. 34.7
Sub-total
Footing Tie Beam
1.0 Gravel Bed Laying cu.m.
2.0 Reinforcement kgs.
a. GI Tie Wire # 16 kgs.
3.0 Concrete Pouring (one-bager) 3000 Psi cu.m. 6.1
a. Portland Cement (40 kg) bags 58
b. Sand cu.m. 3.05
c. Gravel 3/4" cu.m. 6.1
Sub-total
Slab on Fill (assumed 100 mm thick @ 500 m O.C.)
1.0 Gravel Bed Laying cu.m.
2.0 Reinforcement kgs.
a. GI Tie Wire # 16 kgs.
3.0 Formworks sq.m.
4.0 Concrete Pouring (one-bager) 3000 Psi (1000 mm tck) cu.m. 15
a. Portland Cement (40 kg) bags 143
b. Sand cu.m. 7.5
c. Gravel, G-1 cu.m. 15
5.0 Concrete Floor Finishing (staright to finish) sq.m. 150
Sub-total
Lintel Beams
1.0 Reinforcement kgs.
a. GI Tie Wire # 16 kgs.
2.0 Formworks sq.m.
3.0 Concrete Pouring (one-bager) 3000 Psi cu.m.
a. Portland Cement (40 kg) bags
b. Sand cu.m.
c. Gravel 3/4" cu.m.
Sub-total
Column
1.0 Reinforcement kgs.
a. GI Tie Wire # 16 kgs.
2.0 Formworks sq.m.
a. Plywood (12 mm thk 4' x 8') pcs
b. Wood Frame (2" x 2") bd. Ft.
c. Misc lot
3.0 Concrete Pouring (one-bager) 3000 Psi cu.m. 26.44
a. Portland Cement (40 kg) bags 252
b. Sand cu.m. 13.22
c. Gravel 3/4" cu.m. 26.44
4.0 Column Finishing sq.m.
Sub-total
Beams
1.0 Reinforcement kgs.
16 mm dia x 6 m pcs
a. GI Tie Wire # 16 kgs.
2.0 Formworks sq.m.
3.0 Concrete Pouring (one-bager) 3000 Psi cu.m. 10.83
a. Portland Cement (40 kg) bags 103
b. Sand cu.m. 5.415
c. Gravel 3/4" cu.m. 4.89
4.0 Beam Finishing sq.m. 10.83
Sub-total
Suspended Slab
1.0 Reinforcement kgs.
a. GI Tie Wire # 16 kgs.
2.0 Formworks sq.m.
3.0 Concrete Pouring (one-bager) 3000 Psi (1000 mm tck) cu.m. 21.83
a. Portland Cement (40 kg) bags 208
b. Sand cu.m. 10.915
c. Gravel, G-1 cu.m. 21.83
4.0 Concrete Floor Finishing (staright to finish) sq.m.
5.0 Slab Soffil Finishing? sq.m.
Sub-total
TOTAL-DIVISION 2
IES

MATERIALS LABOR
TOTAL
U/COST COST U/COST COST

included

22500.00
34793.985
24964.2026
9829.78242

102064.5
14188.4627
33704.4715

84430.5
12670.8785
30099.474

14839.3
2227.4455
5291.262

36586.55
5477.325
11723.85

64474.2
9654.6982
22934.5848
26352.55
3954.62865
4241.6838

53216.8
7971.33365
17062.1097
CONCRETE VOLUME FOR WALL AND COLUMN
DIMENSION
DESCRIPTION VOLUME QUANTITY TOTAL VOLUME
WIDTH HEIGHT LENGTH
CONCRETE VOLUME
WALL 2.00 4.20 3.00 25.2 1.00 25.2
2.00 4.20 2.00 16.8 1.00 16.8
2.00 4.20 2.50 21 1.00 21

F-01 FOR WALL 1.00 0.25 3.00 0.75 10.00 7.5


1.00 0.25 2.00 0.5 4.00 2
1.00 0.25 2.50 0.625 6.00 3.75

TOTAL 76.25

F-01 FOR COLUMN 1.00 0.25 1.00 0.25 21.00 5.25

C-01 0.25 7.70 0.25 0.48125 21.00 10.10625


TOTAL 15.35625

CONCRETE VOLUME FOR BEAMS


DIMENSION
DESCRIPTION VOLUME QUANTITY TOTAL VOLUME
WIDTH HEIGHT LENGTH
BEAM
GB-1 0.30 0.20 3.00 0.18 14.00 2.52
0.30 0.20 2.00 0.12 10.00 1.2
0.30 0.20 2.50 0.15 8.00 1.2
TOTAL 4.92

FB-1 0.30 0.20 3.00 0.18 16.00 2.88


0.30 0.20 2.00 0.12 9.00 1.08
0.30 0.20 2.50 0.15 10.00 1.5
TOTAL 5.46

BEAM TOTAL 10.38

CONCRETE VOLUME FOR SLAB


DIMENSION
DESCRIPTION VOLUME QUANTITY TOTAL VOLUME
WIDTH HEIGHT LENGTH
SLAB ON FILL 11.00 0.15 12.00 19.8 1.00 19.8

2ND FLOOR SLAB 11.00 0.15 12.00 19.80 1.00 19.8


TOTAL 39.6
CONCRETE
Wall Concrete Footings
WF
1.0 Gravel Bed Laying
2.0 Reinforcement
a. GI Tie Wire # 16
3.0 Concrete Pouring (one-bager) 3000 Psi
a. Portland Cement (40 kg)
b. Sand
c. Gravel 3/4"
Sub-total
Column Footings
1.0 Gravel Bed Laying
2.0 Reinforcement
a. GI Tie Wire # 16
3.0 Concrete Pouring (one-bager) 3000 Psi
a. Portland Cement (40 kg)
b. Sand
c. Gravel 3/4"
Sub-total
Ground Beams
1.0 Gravel Bed Laying
2.0 Reinforcement
a. GI Tie Wire # 16
3.0 Concrete Pouring (one-bager) 3000 Psi
a. Portland Cement (40 kg)
b. Sand
c. Gravel 3/4"
Sub-total
Slab on Fill (assumed 100 mm thick @ 500 m O.C.)
1.0 Gravel Bed Laying
2.0 Reinforcement
a. GI Tie Wire # 16
3.0 Formworks
4.0 Concrete Pouring (one-bager) 3000 Psi (1000 mm tck)
a. Portland Cement (40 kg)
b. Sand
c. Gravel, G-1
5.0 Concrete Floor Finishing (staright to finish)
Sub-total
Lintel Beams
1.0 Reinforcement
a. GI Tie Wire # 16
2.0 Formworks
3.0 Concrete Pouring (one-bager) 3000 Psi
a. Portland Cement (40 kg)
b. Sand
c. Gravel 3/4"
Sub-total
Column
1.0 Reinforcement
a. GI Tie Wire # 16
2.0 Formworks
a. Plywood (12 mm thk 4' x 8')
b. Wood Frame (2" x 2")
c. Misc
3.0 Concrete Pouring (one-bager) 3000 Psi
a. Portland Cement (40 kg)
b. Sand
c. Gravel 3/4"
4.0 Column Finishing
Sub-total
Floor Beams
1.0 Reinforcement
16 mm dia x 6 m
a. GI Tie Wire # 16
2.0 Formworks
3.0 Concrete Pouring (one-bager) 3000 Psi
a. Portland Cement (40 kg)
b. Sand
c. Gravel 3/4"
4.0 Beam Finishing
Sub-total
Suspended Slab
1.0 Reinforcement
a. GI Tie Wire # 16
2.0 Formworks
3.0 Concrete Pouring (one-bager) 3000 Psi (1000 mm tck)
a. Portland Cement (40 kg)
b. Sand
c. Gravel, G-1
4.0 Concrete Floor Finishing (staright to finish)
5.0 Slab Soffil Finishing?
Sub-total
TOTAL-CONCRETE
UNIT QUANTITY COST TOTAL

cu.m.
kgs.
kgs.
cu.m. 76.25
bags 687 189509
cu.m. 38.125 27843
cu.m. 76.25 66141

cu.m.
kgs.
kgs.
cu.m. 5.25
bags 48 12280.8
cu.m. 2.625 1917.06
cu.m. 5.25 4554

cu.m.
kgs.
kgs.
cu.m. 4.92
bags 45 11513
cu.m. 2.46 1796.56
cu.m. 4.92 4267.71

cu.m.
kgs.
kgs.
sq.m.
cu.m. 19.8
bags 179 45797
cu.m. 9.9 7230.07
cu.m. 19.8 15475
sq.m. 132
kgs.
kgs.
sq.m.
cu.m.
bags
cu.m.
cu.m.

kgs.
kgs.
sq.m.
pcs
bd. Ft.
lot
cu.m. 10.11
bags 91 23282
cu.m. 5.055 3691.72
cu.m. 10.11 8769.62
sq.m.

kgs.
pcs
kgs.
sq.m.
cu.m. 5.46
bags 50 12792.5
cu.m. 2.73 1993.75
cu.m. 5.46 4736.11
sq.m.

kgs.
kgs.
sq.m.
cu.m. 19.8
bags 179 45797
cu.m. 9.9 7230.07
cu.m. 19.8 15475
sq.m.
sq.m.

1764.975 512094