Ref: WIL/22-23/238 Date: 24.01.

2023

To
The Project Director
National Highways Authority of India
PIU Dausa
Rajasthan

Sub: Non-handing over of equipments in case of Titoli & Rabawata Fee Plaza

Ref: LOA No. NHAI/13013/547/CO/22-23/CB/Titoli & Rabawata FP/5378/


Dated 11.01.2023

Respected Sir,

In reference to above this is to inform you that we have started the collection of user
fees at Titoli & Rabawata toll plaza w.e.f. 17.01.2023. But we are not handed over the
equipments, furniture and administrative building by M/s Highway & Tandon
Tollways till date. This is causing the delay in full handover process as it has now
been more than a week since takeover of the toll plaza.

Your kind action in this regard will be highly appreciated.

Thanking you
Yours sincerely 

For Welcome Infratoll Limited

Authorized Signatory