Professional Documents
Culture Documents
Leh House JKL Bid
Leh House JKL Bid
2.2 Slope & Elevation Correction 422.6 SQM 365.40 127.89 493.29 208,464.35
This covers the supply of labor and equipment of cut
and fill of the lot for the sake of elevation and slope - -
correction.
2.3 Excavation 195 CU.M 682.50 682.50 133,087.50
This covers the supply of labor and equipment of all
necessary excavation to be for structural members of - -
main structure and site development.
2.4 Backfill and Compaction 128.3 SQM 550.00 550.00 70,565.00
This includes the supply of labor, materials, and
equipment for the area that backfilling and - -
compaction is necessary.
2.5 Gravel Bedding 57.8 CU.M 3,029.25 1,060.24 4,089.49 236,372.38
2.6 Soil Poisoning & Termites Treatment 486 SQM 375.00 187.50 562.50 273,375.00
2.7 Earth Hauling 1 LOT 251,160.00 87,906.00 339,066.00 339,066.00
This includes the supply of labor and equipment to haul
out the excavated earth and debris from construction - -
site.
2.8 Disposal of Construction Debris 1 LOT 105,978.60 37,092.51 143,071.11 143,071.11
2.9 Erecting Sign Post, Temporary Fence & etc. 1 LOT 130,500.00 45,675.00 176,175.00 176,175.00
2.10 Installation of Temporary Connection to Water & Power 1 LOT 61,250.00 - 61,250.00 61,250.00
2.11 Others - -
Sub-Total For Site Development 1,748,089.88
4.6 Vapor Barrier Installation 318 SQM 201.60 60.48 262.08 83,341.44
4.7 Steel Framing - -
4.7.1 Roof Trusses & Canopy Framing 10,120.1 KGS 158.55 63.42 221.97 2,246,358.60
4.7.2 Structural Framing 8,647.2 KGS 288.65 115.46 404.11 3,494,419.99
4.8 Masonry Works - -
This covers the supply of labor, materials, and
equipment to do the approved partitioning and
masonry walling of main structure that are based on - -
approved plans of the
Architect/Representative.
4.8.1 6" CHB 369.6 SQM 1,135.20 454.08 1,589.28 587,397.89
4.8.2 4" CHB 317.0 SQM 926.20 370.48 1,296.68 411,047.56
4.8.3 Plastering 1,373.2 SQM 553.30 221.32 774.62 1,063,708.18
4.9 Cementitious Waterproofing - -
This covers the supply of labor, materials, and
equipment of integral waterproofing such as Penetron
or alike that is approved by the - -
Architect/Representative and the Client for
the warranties.
4.9.1 Exterior Wall 339.7 SQM 819.00 327.60 1,146.60 389,500.02
4.9.2 Concrete Canopy 22.0 SQM 724.50 289.80 1,014.30 22,314.60
4.9.3 Balcony 15.5 SQM 724.50 289.80 1,014.30 15,721.65
4.9.4 T&B 18.0 SQM 656.25 262.50 918.75 16,537.50
4.10 Roofing and Canopy - -
4.10.1 350x347mm Flat Clay Roof Tile 1.0 LOT BY OTHERS -
4.10.2 10mm thk. Tempered-Laminated Glass 19.3 SQM 2,571.25 899.94 3,471.19 66,993.92
4.11 Door and Door Jambs Installation - -
4.11.1 Main Entrance 1.0 SETS OSM 4,817.40 4,817.40 4,817.40
4.11.2 Bedroom 1 1.0 SETS OSM 4,817.40 4,817.40 4,817.40
4.11.3 Bedroom 1 T&B 1.0 SETS OSM 4,817.40 4,817.40 4,817.40
4.11.4 Maid's Room 1.0 SETS OSM 4,817.40 4,817.40 4,817.40
4.11.5 Maid's Rm. T&B 2.0 SETS OSM 4,817.40 4,817.40 9,634.80
4.11.6 Wash Room 1.0 SETS OSM 4,817.40 4,817.40 4,817.40
4.11.7 Shower Room 1.0 SETS OSM 4,817.40 4,817.40 4,817.40
4.11.8 Powder Room 1.0 SETS OSM 4,817.40 4,817.40 4,817.40
4.11.9 Pantry 1.0 SETS OSM 4,817.40 4,817.40 4,817.40
4.11.10 Bedroom 2 2.0 SETS OSM 4,817.40 4,817.40 9,634.80
4.11.11 Master's Bedroom 3.0 SETS OSM 4,817.40 4,817.40 14,452.20
4.11.12 Master's Bedroom Storage 4.0 SETS OSM 4,817.40 4,817.40 19,269.60
4.11.13 Master's Bedroom Terrace 5.0 SETS OSM 4,817.40 4,817.40 24,087.00
4.12 Ceiling Works & Framing -
4.12.1 12mm THK MR Gypsum Board 137.4 SQM 1,141.80 456.72 1,598.52 219,636.65
4.12.2 12mm THK Ord. Gypsum Board 242.9 SQM 944.90 377.96 1,322.86 321,322.69
4.12.3 Ceiling Paint 399.3 SQM 695.20 278.08 973.28 388,630.70
4.12.4 Manhole/Access & Ventilation - -
4.13 Wall Finishes - -
4.13.1 Drywall + Painting 855.9 SQM 1,980.00 792.00 2,772.00 2,372,554.80
4.13.2 WF1- Exterior Wall Paint 456.6 SQM 762.30 304.92 1,067.22 487,292.65
4.13.3 WF2- Textured Stucco 35.2 SQM 997.50 399.00 1,396.50 49,156.80
4.13.4 WF4- Porcelaine Tile 35.1 SQM OSM 891.25 891.25 31,282.88
4.13.5 WF6- 200X200MM Glass Block 8.9 SQM OSM 2,117.50 2,117.50 18,845.75
4.14 Floor Finishes - -
4.14.1 Porcelaine Tiles 255.4 SQM OSM 747.50 747.50 190,911.50
4.14.2 Floor Vinyl 127.9 SQM OSM 690.00 690.00 88,251.00
4.14.3 Bathroom Tiles 31.3 SQM OSM 862.50 862.50 26,996.25
4.15 Steel Works + Coating and Protection -
4.15.1 Staircase Railings 1.0 LOT BY OTHERS -
4.15.2 Balcony Railings 1.0 LOT BY OTHERS -
4.15.3 Spiral Railings 1.0 LOT BY OTHERS -
4.15.4 Ramp Railing 1.0 LOT BY OTHERS -
4.16 Main Staircase - -
4.16.1 Staircase handrail incl. newel post 1.0 LOT BY OTHERS -
4.16.2 Staircase Steps/Run (solid wood) 1.0 LOT BY OTHERS -
4.16.3 Staircase Protection/Coating 1.0 LOT BY OTHERS -
4.17 Others - -
Sub-Total for Main Structure 16,975,165.08
5.0 Lap Pool, Pond and Lift
5.1 Excavation 123.8 CU.M 682.50 682.50 84,493.50
5.2 Backfill and Compaction 18.8 SQM 550.00 550.00 10,340.00
5.3 Gravel Bedding 8.1 CU.M 3,029.25 1,060.24 4,089.49 33,124.85
5.4 Earth Hauling 1.0 LOT 152,521.60 45,756.48 198,278.08 198,278.08
5.5 Reinforcement 6729.6 KGS 100.49 40.19 140.68 946,713.40
5.6 Formworks 123.0 SQM 958.65 383.46 1,342.11 165,079.53
5.7 Concreting 30.3 CU.M 6,105.75 2,442.30 8,548.05 259,005.92
5.8 Masonry Works -
5.8.1 6" CHB 19.2 SQM 1,135.20 454.08 1,589.28 30,514.18
5.8.3 Plastering 19.5 SQM 553.30 221.32 774.62 15,105.09
5.9 Waterproofing & Water Vapor Protection 96.6 SQM 724.50 289.80 1,014.30 97,981.38
5.10 Tiling -
5.10.1 Inside the pool 93.0 SQM OSM 862.50 862.50 80,212.50
5.10.2 Top of pool 18.5 SQM OSM 747.50 747.50 13,828.75
5.10.3 Side of pool incl. pond gutter 27.5 SQM OSM 862.50 862.50 23,718.75
5.10.4 wall feature 26.8 SQM BY OTHERS -
5.10 Mechanical works -
5.10.1 Water motor pump & other equipment for pool 1.0 LOT BY OTHERS -
5.10.2 Water motot pump & other equipment for pond 1.0 LOT BY OTHERS -
5.10.3 Lift Mechanism 1.0 LOT BY OTHERS -
5.11 Others -
Sub-Total For Lap Pool, Pond and Lift 1,958,395.92
6.0 Plumbing Works
6.1 Septic Tank
5.1.1 Excavation 9.45 CU.M - 682.50 682.50 6,449.63
5.1.2 Reinforcement 316 KGS 100.49 40.19 140.68 44,454.56
5.1.3 Formworks 9 SQM 958.65 383.46 1,342.11 12,078.99
5.1.4 Concreting: Site Mix 3 CU.M 6,105.75 2,442.30 8,548.05 25,644.15
5.1.5 6" CHB 9 SQM 1,135.20 454.08 1,589.28 14,303.52
5.1.6 Plastering 12 SQM 553.30 221.32 774.62 9,295.44
6.2 Roughing-ins - -
6.2.1 Sewer, Vent, and Storm Drainage Line - -
6.2.2 a. Pipe Laying & Fittings. Incl. culvert 743.2 LM 887.25 310.54 1,197.79 890,195.67
6.2.3 b. Catch Basin + Manhole 22.0 PCS 6,534.00 2,613.60 9,147.60 201,247.20
Consumables: Pipe Hanger, Bracket & Support 1.0 LOT 32,743.29 11,460.15 44,203.44 44,203.44
6.2.4 incl. solvent cement etc. - -
6.3 Waterline Distribution - -
6.3.1 Pipe Laying & Fittings (Phildex PPR) 159.1 LM 804.10 321.64 1,125.74 179,105.23
6.3.2 Valves 17.0 PCS 964.70 385.88 1,350.58 22,959.86
6.3.3 Consumables: Pipe Hanger, Bracket & Support
incl. teflon, nipple, elbows & etc.
1.0 LOT 6,061.95 2,121.68 8,183.64 8,183.64
7.2.1 Panel 'PP', 275AT, 1-Phase, 2P 240V, 60HZ 1 SET 78,487.50 23,546.25 102,033.75 102,033.75
7.2.2 Panel 'LP', 100AT, 1-Phase, 2P 240V, 60HZ 1 SET 46,718.75 14,015.63 60,734.38 60,734.38
7.2.3 Panel 'PBU', 125AT, 1-Phase, 2P 240V, 60HZ 1 SET 30,848.75 9,254.63 40,103.38 40,103.38
7.2.4 MCB 500AT, 1-Phase, 2P 240V, 60HZ 1 SET 25,530.00 7,659.00 33,189.00 33,189.00
7.2.5 ECB 2P-30AT, 14KAIC, 230V, 60HZ Nema 3R 13 SET 11,241.25 3,372.38 14,613.63 189,977.13
Enclosure
7.2.6 Consumables: Pipe hanger & support, Solvent 1 LOT 12,781.13 5,751.51 18,532.64 18,532.64
cement,Excavation
7.3 Chipping, Electrical Works
Tape etc. 555.6 LM 117.70 210.00 327.70 182,070.12
7.4 Concrete Restoration 66.7 SQM 1,620.30 695.99 2,316.29 154,496.71
7.5 Wires Pulling - -
7.5.1 2.0mm2 THHN 350.5 LM 48.00 19.20 67.20 23,553.60
7.5.2 3.5mm2 THHN 917.1 LM 75.00 30.00 105.00 96,295.50
7.5.3 5.5mm2 THHN 811.7 LM 108.00 43.20 151.20 122,729.04
7.5.4 8.0mm2 THHN 230.0 LM 250.00 100.00 350.00 80,500.00
7.5.5 14mm2 THHN 234.2 LM 316.00 126.40 442.40 103,610.08
7.5.6 22mm2 THHN 230.1 LM 432.00 172.80 604.80 139,164.48
7.5.7 30mm2 THHN 100.0 LM 985.00 394.00 1,379.00 137,900.00
7.5.8 38mm2 THHN 100.0 LM 1,300.00 520.00 1,820.00 182,000.00
7.5.9 125mm2 THHN 156.1 LM 1,458.00 583.20 2,041.20 318,631.32
7.5.10 150mm2 THHN 100.0 LM 2,398.00 959.20 3,357.20 335,720.00
7.5.11 Consumables: Electrical Tape, GI Wire etc. 1.0 LOT
entrance cap, rop, clamp etc 69,637.23 24,373.03 94,010.27 94,010.27
SUMMARY:
Total for General Requirements 1,778,166.70
Sub-Total for Site Development 1,748,089.88
Sub-Total for Perimeter Fence 2,067,454.92
Sub-Total for Main Structure 16,975,165.08
Sub-Total For Lap Pool, Pond and Lift 1,958,395.92
Total for Plumbing Works 2,399,042.67
Total for Electrical Works 3,079,693.11
Over-all Estimated Project Cost 30,006,008.28
Government Taxes, VAT (12%) 3,600,720.99
Contractor's Profit (10%) 3,000,600.83
Grand Total Amount 36,607,330.11