Section Findings Observation Action Plan
Humidity Humidity deviation was
deviation on observed on 26/10/2022 on P10
temperature and P12 machine . Humidity deviation
and relative P17 on 25/10/2022 and P15 on should be escalate
humidity 30/10/2022 .Inspection remark with appropriate RC
PLANT A
monitoring was documented as and CAP to addres
record. satisfactory, without RCA and reoccurrence on
CAP. affected machines
Humidity deviation
should be escalated
with appropriate RCA
Process QC Supervisor closed
and CAP to address
reoccurrence on