Professional Documents
Culture Documents
ST.00.776.FCI.000 - Welded Steel Work
ST.00.776.FCI.000 - Welded Steel Work
Revision 0
© Copyright reserved - The reproduction, distribution and utilization of this document as well as the communication of its contents to
others without expressed authorization is prohibited. Offenders will be held liable for the payment of damages.
All rights reserved in the event of the grant of a patent, utility model or design.
2/28 - 21.09.2016
ST.00.776.FCI.000_Welded Steel Work
Table of Contents
1 GENERAL 5
1.1 Definitions 5
1.2 Scope 5
1.3 Sub-Contracting 5
1.4 Standards / technical codes 6
1.5 First specimen 7
1.6 Inspection 7
1.7 Copyright 8
5 WELDING 12
5.1 Standard quality requirements for fusion welding of metallic materials acc. to ISO 3834-3 12
5.2 Weld preparation 14
5.3 Joint preparation for site welds 14
5.4 Welding consumables 15
5.5 Works to be done after welding 16
5.5.1 Weld seam identification 16
5.5.2 Weld dressing 16
5.6 Weld inspection 17
5.6.1 Inspection methods for surface irregularities 17
5.6.2 Inspection methods for inner irregularities (non-destructive testing methods) 17
5.6.3 Scope of inspection 17
5.6.4 Acceptance criteria 18
5.6.5 Elimination of defects 18
3/28 - 21.09.2016
ST.00.776.FCI.000_Welded Steel Work
6.1 Pre-assembly 19
6.2 Test erection and inspection 19
6.3 Functional tests 19
10 DOCUMENTATION 26
10.1 General requirements 26
10.2 Form and number 26
10.3 Conformity declarations 26
10.4 Scope of documentation 27
4/28 - 21.09.2016
ST.00.776.FCI.000_Welded Steel Work
1 General
1.1 Definitions
“BUYER” Maerz Ofenbau AG and its subsidiaries
“MANUFACTURER” Recipient of purchase order or contract from BUYER
“P.O.” Purchase order or contract
“FCI” Fabrication and controlling instruction
“FIG” Fabrication and inspection guideline
“IRE” Inspection report
“ITP” Inspection and test plan
“COP” Controlling procedures
1.2 Scope
This Fabrication & Controlling Instruction (FCI) applies to the workshop manufacturing
and field installation of welded and bolted steel designs of MAERZ Ofenbau AG and its
subsidiaries for the MAERZ AG projects.
These FCI have to be observed by the MANAUFACTURER, if this document is
referenced in the P.O., Maerz standard and/or contract drawings such as .345.FCI,
.346.FCI, .347.FCI, .349.FCI, ST.00.772.FCI.000, ST.00.773.FCI.000,
ST.00.774.FCI.000, respective parts lists, or other documents, such as inspection report
(IRE) , inspection & test plans (ITP), controlling procedures (COP), or fabrication and
inspection guidelines (FIG).
If in for the P.O. relevant drawings, any manufacturing or inspection requirements
are described, they will overrule the requirements of the present document
ST.00.776.FCI.000 “Welded Steel Work”.
Depending on the application, additional specifications may have to be met, as detailed in
the relevant P.O. Should the additional specifications deviate from the requirements
specified herein, an agreement must be reached between BUYER and
MANUFACTURER regarding the procedures to be adopted.
If the MANUFACTURER has any reservations or doubts as to whether the quality
requirements in these instructions can be met due to reasons of manufacturing
technique, such reservations or doubts must be clarified with the BUYER in writing before
the order confirmation.
1.3 Sub-Contracting
Permission to sub-contract to a specific person or company has to be received from the
BUYER in writing. The same applies to further contracts the MANUFACTURER may
enter into. The MANUFACTURER is obligated to name his chosen sub-suppliers prior to
sub-contracting. The MANUFACTURER is obligated to hand out these instructions to his
sub-suppliers. Besides, in terms of welding related to sub-contracting, the rules in ISO
3834-3 subsection 6 must be taken into account.
5/28 - 21.09.2016
ST.00.776.FCI.000_Welded Steel Work
1.4 Standards / technical codes
The engineering standards and regulations stipulated in this document are of paramount
importance for the workshop manufacturing and field installation of all different kind of
Maerz kiln components.
The following table provides an overview of the different kind of kiln components and
respective technical codes to comply with:
Kiln component type Manufacturing Kiln destination / Technical codes to Implicated quality
country country of comply with in requirements for
operation terms of the factory and
manufacturing and quality assurance
testing principles
EN 1090-2
b). Pressure vessels Outside Europe Within Europe PED 2014/68/EU ISO 3834-3
3
(Legally specified area) EN 13445-4 (minimum
Within Europe Outside Europe requirement if EN
EN 13445-53 standards not
applicable)
Outside Europe Outside Europe In the absence of
contractual
agreement to the
contrary:
PED 2014/68/EU
EN 13445-43
EN 13445-53
c). Piping Outside Europe Within Europe PED 2014/68/EU ISO 3834-3
PED 2014/68/EU
EN 13480-4
EN 13480-5
d) Mechanical engineering Outside Europe Within Europe Maerz document: ISO 3834-3
components such as traps,
discharge, etc.
Within Europe Outside Europe
(Legally not specified area) .349.FCI
Outside Europe Outside Europe
6/28 - 21.09.2016
ST.00.776.FCI.000_Welded Steel Work
If there is a conflict between the requirements contained in the text of this document and
the applicable standards, in principle the more stringent requirement shall apply.
However, the manufacturer has the right to consult the BUYER, to find a mutually
agreeable solution.
Should no date of issue be mentioned, then the latest issue at time of order of the
relevant engineering standards, regulations and guidelines applies.
Provided it has been authorized by the BUYER in writing, national or international
standards, equivalent to those specified in this document, may be used.
This shall be considered on a case by case basis.
1.6 Inspection
The BUYER’s inspectors as well as any additional third party inspectors must be granted
access to the manufacture’s facilities at any time during normal working hours after prior
notification.
The BUYER reserves the right to witness manufacturing activities, trial assemblies and
final inspections. For welded joints, which are not accessible during final inspection,
interim inspections shall be scheduled. On this basis, the BUYER’s quality control
department must be notified in due time of the individual inspection stages.
Before start of production MANUFACTURER must submit to BUYER an inspection and
test plan (ITP) for all ordered Parts in accordance with PO, Into Inspection and testing
plan must be indicated Inspection steps such as:
- Steps before manufacturing of the steel parts
- Materials income control
- Steps during fabrication
- Steps during final inspection
- Documentation and record of the inspection according to chapter 10
- Pre-shipment inspection
The MANUFACTURER shall provide all the equipment, tools and qualified personnel
required for the inspections.
All inspection protocols shall include inspection reference drawings, relating the results of
the inspected items to a clearly marked position on the reference drawing.
Should the existence of defects be discovered during inspections, then all costs associate
with correcting the defects, shall be borne by the manufacturer.
7/28 - 21.09.2016
ST.00.776.FCI.000_Welded Steel Work
The manufactured parts and components are only then to be considered as accepted,
once the final acceptance after assembly and commissioning has taken place on the
construction site. Acceptance by the BUYER or his agents is not a substitute for internal
production control, nor does it release the MANUFACTURER and his sub-contractor from
his guarantee and liability commitments.
1.7 Copyright
Any print-out of these instructions is an uncontrolled copy. Without the prior consent of
BUYER, any utilization of the texts, even in extract form, contravenes copyright law and
makes the offender liable to prosecution. This also applies to reproduction, translations of
all kinds, scanning, microfilming and processing in electronic systems.
All results of the dimensional check (actual and specified data) must be entered by a
representative of the MANUFACTURER into a protocol.
The entries have to be confirmed by the stamp and signature of the representatives of
both the MANUFACTURER and the BUYER.
8/28 - 21.09.2016
ST.00.776.FCI.000_Welded Steel Work
2.2.1 Standard list of Maerz components considered as steel structures
2 2
# Component designation Component / drawing numbers EXC2 EXC3
4 Platforms 118 | 146 | 358 | 359 | 360 | 361 | 362 | 363 | 364 | X
365 | 366 | 367 | 368 | 370 | 373 | 374 | 375
9 Silo anchors, platforms and cladding 419 | 436 | 437 | 438 | 446 X
17 Shaft part I, II, III and IV 045 | 047 | 048 | 049 | 050 | 051 | 052 X1
1 As a general rule EXC2 applies, but in certain projects for the components 16 – 24 EXC3 may apply. The
manufacturer must clarify this eventuality with Maerz on time (e.g. during quotation phase).
2 The notion execution class (EXC) only applies for steel structures according to EN 1090-2. If other
national regulations apply, a different execution or weld quality classification system may apply.
9/28 - 21.09.2016
ST.00.776.FCI.000_Welded Steel Work
3 Specifications for the steel products used
3.1 Materials
Only materials of the quality specified in the drawings and parts lists may be used.
If a specified material is not available, then the MANUFACTURER shall propose to the
BUYER an equivalent alternative material. Such alternative material shall only be used
with the BUYER’s permission in writing. Plates and profiles must always be used in
maximum sizes and lengths.
If plates or profiles are not obtainable in the required dimensions or thicknesses, the
nearest adequate size is to be selected as an alternative. The BUYER shall be informed
in good time of any substitutions required in this way.
10/28 - 21.09.2016
ST.00.776.FCI.000_Welded Steel Work
4 Preparation of individual parts
4.2 Forming
Forming and aligning of the parts must be performed so that any constraints during
further processing are prevented. Structural members must be formed without twisting. All
formed or aligned parts must be completely free from cracks and surface damage after
the forming or aligning.
Any damage to the part surfaces by hammering etc. must be avoided. Any damage has
to be eliminated by grinding.
Cold forming is only permissible when the material is suitable for this procedure. All areas
concerned must be thoroughly visually examined for surface damage and cracks.
Aligning is not permissible in the temperature range between 200 and 300 °C (blue
brittleness).
11/28 - 21.09.2016
ST.00.776.FCI.000_Welded Steel Work
5 Welding
The MANUFACTURER shall develop a welding plan prior to execution of the work and
make it available to the BUYER upon request.
The arc may only be struck at points which are later fused again by welding.
For the welding of multiple layers, the surface of the preceding layers must be cleaned
from slag. Cracks, holes and areas with lack of fusion must not be welded over. Run-off
strips are preferably used at the weld ends. Open end craters must be avoided.
To ensure faultless weld joints, root passes should be gouged out and a cap pass should
be counter-welded. If welding is performed from one side only, the welding parameters
must be selected so that full penetration welding is ensured.
The welding parameters must be selected so that flush weld interfaces are obtained
avoiding detrimental undercuts.
If the lengths of intermittent fillet welds are not clearly dimensioned in the manufacturing
drawings, the following dimensions shall be applicable:
Length of fillet weld L ≥ 6 x a; L min = 30 mm; L max = 150 mm
If the welding instruction on the drawing refers to a bigger scope of inspection for
instance, than given in the document .349.FCI, then the welding instruction given in
the drawing is binding.
As shown in Fig. 1, ISO 3834-3 defines for all Maerz kiln components the quality
requirements for welding. Manufacturers including those who are not certified according
to ISO 3834-3 must be conscious about the following sections of this standard permitting
him to deliver the expected welding quality and the respective complete welding
documentation (see chapter 10).
12/28 - 21.09.2016
ST.00.776.FCI.000_Welded Steel Work
Subsection To review contents of ISO 3834-3 Extracts from ISO 3834-3
of ISO 3834-3before manufacturing
5.2 + 5.3 Review of requirements and technical Sections 5.2 and 5.3 of ISO 3834-3 to review!
review
6 Sub-contracting Section 6 of ISO 3834-3 to review!
7 Welding personal For all welders: Appropriate qualification according to ISO 9606-1 required.
Appropriate welding coordination personnel according to ISO 14731 at manufacturer’s disposal. Such persons having responsibility for quality
activities shall have sufficient authority to enable any necessary action to be taken. The tasks and responsibilities of such persons shall be
clearly defined.
(source: section 7 of ISO 3834-3)
8 Inspection and testing personnel Section 8 of ISO 3834-3 to review!
9 Equipment Section 9 of ISO 3834-3 to review!
10 Welding and related activities The manufacturer shall carry out adequate production planning
Welding-procedure specification (ISO 3834-3 | 10.2)
Imperative preparation and correct use in production of welding procedure specifications (WPS)
Qualification of the welding procedures (ISO 3834-3 | 10.3)
Prior to production, qualification of welding procedures according to ISO 15610, ISO 15611, ISO 15612, ISO 15613, or ISO 15614-1. If not
specified in the relevant technical code (e.g. EN 1090-2) or in our manufacturing order explicitly, procedure qualification can be achieved by
meeting any of these standards.
(source: section 10 of ISO 3834-3)
11 Storage and handling of welding Section 11 of ISO 3834-3 to review!
consumables
12 Storage of parent materials Section 12 of ISO 3834-3 to review!
13 Post-weld heat treatment Section 13 of ISO 3834-3 to review!
14 Inspection and testing Section 14 of ISO 3834-3 to review!
To check after welding whether compliant with relevant acceptance criteria
By visual inspection (VT) according to ISO 17637
By non-destructive testing according to ISO 17635 (general rules):
MT according to ISO 17638
PT according to ISO 3452-1
RT according to ISO 17636-1
UT according to ISO 17640 and ISO 22825
15 Non-conformance and corrective Section 15 of ISO 3834-3 to review!
actions
16 Calibration and validation of Section 16 of ISO 3834-3 to review!
measuring, inspection and testing
equipment
17 Identification and traceability Section 17 of ISO 3834-3 to review!
18 Quality records Section 18 of ISO 3834-3 to review!
Fig. 5 Quality requirements for fusion welding of metallic materials
13/28 - 21.09.2016
ST.00.776.FCI.000_Welded Steel Work
5.2 Weld preparation
The parts to be joined must be stored and held so that residual stress is minimized during
welding and the parts obtain the shape foreseen. If necessary, the parts to be welded
shall be positioned and aligned on the ground, on a layout pattern, to ensure that
dimensional deviations resulting from shrinkage do not accumulate.
The joint preparation must be in accordance with ISO 9692-1 (extract of standard: see
.349.FCI).
Cross joints are undesirable.
In concave fillets of rolled profiles manufactured from unskilled cast steels, weld seams in
longitudinal direction are not permissible.
If welding is to be performed in cold-formed areas including neighbouring areas up to a
width of 5 t, the limit values min. r/t according to the following table must be observed.
The values of the degree of deformation in above table don’t need to be observed if cold-
formed parts are subjected to normalising prior to welding.
The weld zones of the parts to be welded must be dry and free from scale, rust, oil and
other contaminations. A uniformly thin and firmly adhering rolling skin may be left.
Except in the case of over-weldable coatings (welding primer), all coatings on plates or
profiles in the heat-affected zone have to be removed. This includes areas which are
opposite the welding side of the sheet.
On galvanized structural members, the zinc layer in the heat-affected zone must also be
removed.
14/28 - 21.09.2016
ST.00.776.FCI.000_Welded Steel Work
5.4 Welding consumables
The type of welding consumables shall be appropriate to the welding process, as well as
the material(s) to be welded and must be documented in the welding procedure
specification (WPS). The following table (Fig. 7) provides an overview of the welding
consumables and respective product standards to be used (inspired by EN 1090-2 | 5.5).
The welding consumables must be free from damage, contamination and moisture. If
required, they must be dried according to the supplier’s instructions.
If no such instructions are given, basic electrodes shall be dried in an electrode quiver for
2-4 hours at a temperature between 300 and 400°C, and submerged-arc welding flux
shall be dried for 4 hours at a temperature between 350 and 400 °C.
15/28 - 21.09.2016
ST.00.776.FCI.000_Welded Steel Work
5.5 Works to be done after welding
Example:
16/28 - 21.09.2016
ST.00.776.FCI.000_Welded Steel Work
5.6 Weld inspection
Inspection rules for all different kind of products are defined in the respective technical
codes (see Fig. 1) and summarised in .349.FCI.
Ferritic steels VT
VT and MT
VT and PT
17/28 - 21.09.2016
ST.00.776.FCI.000_Welded Steel Work
5.6.4 Acceptance criteria
The acceptance criteria for weld inspection are defined in the respective technical codes
and standards (see Fig. 1) and cited in .349.FCI.
The following table provides a summary of the respective quality levels / limits for
imperfections according to ISO 5817 for weld irregularities, valid for VT and NDT.
Kiln component Technical codes to comply Quality levels / limits for
type with in terms of imperfections according to ISO
1
manufacturing and testing 5817
a) Steel structures EN 1090-2 EXC 2 C
(Legally specified EXC 3 B
area)
b) Pressure vessels PED 2014/68/EU
(Legally specified EN 13445-4
area) EN 13445-5 C
(instead of EN 13445 the AD
2000 Code is also admissible)
c) Piping PED 2014/68/EU Maerz gas pipes: B
(Legally specified EN 13480-4 branch welds < DN100
area) EN 13480-5 All other welds of C
process air and gas
pipes
d) Mechanical Maerz document:
engineering .349.FCI C
components such
as traps, discharge,
etc.
(Legally not
specified area)
Fig. 11 ISO 5817: Quality levels for imperfections
18/28 - 21.09.2016
ST.00.776.FCI.000_Welded Steel Work
6 Final fabrication steps: Inspection
6.1 Pre-assembly
Time needed for the assembly and erection at the construction site, should be kept as
short as possible. It is therefore advantageous, to fabricate all the parts needed, in the
largest possible format which can be transported, and handled at the construction site.
To ensure smooth and trouble-free assembly of the components on site, components
consisting of individual segments shall be completely pre-assembled for inspection at the
manufacturer’s workshop location.
The following conditions must be fulfilled:
- The pre-fabricated parts must have a coat of paint.
- All the assembly welding joints must be prepared in the workshop in order to permit
proper site welds.
19/28 - 21.09.2016
ST.00.776.FCI.000_Welded Steel Work
7 Preparation for Transport
7.3.1 Inspection
All weld seams of the lifting lugs must be inspected by
- 100% VT and
- 50% by either PT or MT.
20/28 - 21.09.2016
ST.00.776.FCI.000_Welded Steel Work
8 Protection against corrosion
Anti-corrosion coatings must not be applied before the work piece has been released by
the BUYER’s inspector respectively not before final inspection.
The BUYER reserves the right to inspect the coating material and the execution of the
protection measures against corrosion at any time either by sending one of his
representatives, a representative of the coating material manufacturer, or a respective
expert.
21/28 - 21.09.2016
ST.00.776.FCI.000_Welded Steel Work
8.5 Inspection of anti-corrosion protection
Verify the paint film is free of defects.
Verify that all masking tapes have been removed.
Verify that coating is cured as specified in the paint manufacturer’s application data. Cure
of catalysed materials may be determined by exposure to a suitable solvent as
recommended by the paint manufacturer.
Inspection and the reporting of the inspection results of the anti–corrosion coating shall
be in accordance with DIN EN ISO 12944-5 and -7.
The thickness of the individual layers, such as priming, intermediate and final coat, shall
be inspected by spot checking.
The nominal thickness of the entire paint system, as specified in Maerz standard
document .347.FCI, shall be inspected after the application and drying of all the individual
layers by measuring the dry film thickness (DFT) of the entire paint system.
The number of DFT measurements of the entire paint system shall be at least 5
2 2
measurements per 10 m or per individual piece of equipment of less than 10m surface
area and 2 for each piece of equipment at random location selected by BUYER’s
inspector.
Visual Inspection
- The paint surface must be free from unevenness.
- The paint surface shall be free of blisters, bubbles, craters, sags, runs, dry spray and
unnecessary brush marks.
DFT Measurements
- The arithmetic mean of all the individual DFTs shall be equal to or greater than the
nominal dry film thickness (NDFT)
- Individual DFTs shall be equal to or above the NDFT.
- Individual DFTs between 80% of the NDFT and the NDFT are acceptable provided
that the number of these measurements is less than 20% of all the individual
measurements taken.
- All individual DFTs shall be less than or equal to 130% of the NDFT.
22/28 - 21.09.2016
ST.00.776.FCI.000_Welded Steel Work
9 Fuel gas piping system
Fluid Pipe
Criteria
Group categories
PS > 0.5 bar and DN > 350 or
III
PS > 0.5 bar and DN > 100 and PS * DN > 3500
PS > 0.5 bar and 100 < DN ≤ 350 and PS * DN ≤ 3500 or
1
25 < DN ≤ 100 and PS * DN >1000 or II
25 < DN ≤ 350 and 1000 < PS * DN < 3500
PS > 0.5 bar and 25 < DN ≤ 100 and PS * DN ≤ 1000 I
Fig. 12 Pipe categories according to PED 2014/68/EU
9.3 Materials
The piping system must be made from seamless steel tubes for pressure purposes (tubes
acc. to EN 10216-2 made from P235GH – TC1/TC2). Pipes, elbows, T-pieces and fittings
with a DN < 500 must be seamless.
23/28 - 21.09.2016
ST.00.776.FCI.000_Welded Steel Work
9.3.2 Material inspection certificates
The MANUFACTURER shall provide material inspection certificates for each single part
of the gas piping system (item no. on BUYER’s drawings/parts lists) as specified in DIN
EN 764-5.
The drawing and item numbers shown on BUYER’s drawings must be handwritten on
each sheet of the certificates, to enable back tracking. Sheets without item numbers will
be rejected.
24/28 - 21.09.2016
ST.00.776.FCI.000_Welded Steel Work
9.5 Marking and documentation of the installed gas piping
system
9.5.2 Marking
In order to clearly identify the pre-fabricated piping elements, they must be marked.
The marking can be by painting, stamping or by attaching a label.
The marking must remain visible for the duration of the installation of the piping system.
For clear identification of an installed pipeline or parts thereof it must be clearly marked,
by either painting, stamping or by attaching a permanent label. Based on the marking it
must be possible to identify to which piping system the pipeline belongs.
Pipelines belonging to categories I to III (according to PED) must have an unmistakable
marking directly on the pipeline or by an attached label. The marking must reference a
document containing information for operation, maintenance and required regular
inspections. The required information is specified in DIN EN 13480-4: section 11.2.
9.5.3 Documentation
At the end of manufacturing and installation of the piping system the MANUFACTURER
shall provide documentation for his scope of delivery, as required by
DIN EN 13480-5: 2012, section 9.5.
II E1
I A
After successful completion of the factory acceptance test and compilation of the
documentation and issuing all required material inspection certificates, the
MANUFACTURER shall issue a manufacturer’s declaration of conformity with the PED
and all applicable standards.
25/28 - 21.09.2016
ST.00.776.FCI.000_Welded Steel Work
10 Documentation
26/28 - 21.09.2016
ST.00.776.FCI.000_Welded Steel Work
10.4 Scope of documentation
The following QA/QC documents shall be issued for all manufactured components in
accordance with the stated standards, the requirements given in the individual sections of
this document, as well as with in 3.1.1 listed Maerz standards.
Material inspection certificates as required by EN 10204 shall be submitted to the
BUYER’s inspector prior to final inspection.
The inspection documents must be clearly marked, permitting the allocation of the
materials to the respective drawings and items on the drawing.
Item QA / QC document
No.
1 Record of requirement / technical review
2 Material inspection documents
Documents to provide acc. to
27/28 - 21.09.2016
ST.00.776.FCI.000_Welded Steel Work
11 Packing and transport
The BUYER’s packing instructions shall be observed.
Welded steel components must be secured with suitable means that deformation and
other damage during storage, loading and transport is excluded.
Tagging and packing of the products to be shipped must be in accordance with the
following Maerz documents:
ST.00.772.FCI.000 “Tagging of material”
ST.00.773.FCI.000 “Packing and Marking”
ST.00.774.FCI.000 “Packing list”
28/28 - 21.09.2016
ST.00.776.FCI.000_Welded Steel Work