Analysis - 2022-23

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 117

Page 1 of 117(Ana. Int.

Sl.no Description of Items Unit Quantity Rate Amount


1 FALSE CEILING- Suspended ceiling (Singe layer) Gyp. Board.
Data taken for 100 sqm

A. Framing
i G.I. Angle (25x10x0.55mm) 18 nos 25x10x0.55mmx64.0 mtr 58.86

ii G.I. Perimeter 30x27x20x0.55mm 11 nos 30x27x0.55mmx40.0 mtr 112.32

iii G.I. intermediate (45x15x15x0.9mm) 23 nos 45x15x0.9mmx84.0mtr 185.12

iv G.I. Ceiling section (51.5x26x10.5x0.55) 63 nos 51.5x26x10.5x0.55mmx230.0 mtr 185.12

v Rawl plug (64Nos.) 2 pkt 295.00

vi Sofit Cleat(64nos) 2 pkt 100.00

vii connecting clip (184nos) 2 pkt 330.00

viii Other misclaneous hard ware @ 5%


B. Boarding
i Gyp. Board 12mm thk. 46 nos (11219x1829mm) 388.00

ii 25mm Drywall Screw (2800nos) 2 pkt 218.40

iii Joint paper(146rmt) 2 roll 90.00

iv Jointing compound 55 kg 23.50


Page 2 of 117(Ana. Int.)

Add waste @ 5%
Add transportation @ 3%

Add labour charges 100 sqm 200.00

Overhead charges @ 7.5%


Contractor profit @ 7.5%

Add labour cess 1%

Cost of 100 sqm


Cost of 1 sqm
Add putty cost of 1 sqm
Add primer cost of 1 sqm
Add painting cost of 1 sqm

Cost of 1 sqm
Say

2 WOODEN CEILLING.
Data taken for 1 sqm

i. Framing
Vertical frame (sal wood) 2 nos 50x25x1000mm
Horizontal frame (sal wood) 2 nos 50x25x1000mm

Total frame used in cum


4x1mtrx.05mtrx.025 mtr cum 0.005 37552.00

ii. 12mm marine ply 1.00 sqm 807.00

iii. 1.0mm thick laminate 1.00 sqm 361.46

iv. Add for adhesive, nail, screws @ 5%


v. Add waste @ 5%
vi. Add transportation @ 3%

Add labour charges @ 10%

Overhead charges @ 7.5%


Contractor profit @ 7.5%

Add labour cess 1%

Cost of 1 sqm
Say

10.i WOODEN PANELLING.(Laminate with frame)


Page 3 of 117(Ana. Int.)

Data taken for 1 sqm


i. Framing

Vertical frame 50.8x25.4x1.34mm. Th. Al. rectangular 2 nos 1.00


section.

Horizontal frame 50.8x25.4x1.34mm. Th. Al. 2 nos 1.00


rectangular section.
Total frame used
kg/mtr
4 mtr 0.651 2.604 258.00

ii. 12mm fire retardant ply 1 sqm 947.00

iii. 1.0mm thick laminate 1 sqm 361.00

iv. Add for Adhesive, nail, Screws @ 5%


v. Add waste @ 5%
vi Add transportation @ 2.5%

vii. Add labour charges @ 5%

viii. Over head charges @ 7.5%


ix Contractor's profit @ 7.5%

x Add labour cess 1%

Cost of 1 sqm
Say

6 STORAGE UNIT WITH LAMINATE.


Data taken for 10' X4' = 70Sqft

12 mm thick marine ply


i. vertical members 5.00 sft 1'-6"x4'-0" 30.00
horizontal shelf & bottom 3.00 sft 10'-0"x1'-6" 45.00
door shutter and back support 2.00 sft 10'-0"x4'-0" 80.00
155.00 75.00

ii 19mm thk. marine ply on top. 1.00 sft 10'-0"x1'-6" 15.00 98.00

iii. teak wood Leaping( all around the door shutter rft 88.00 12.00
iv. polishing rft 88.00 20.00

v 1.0mm thick laminate to all visible surface


Top outside 1 Sqft 10'-0"x1'-6" 15.00
2 sides 2.00 sft 1'-6"x4'-0" 12.00
front and back 2.00 sft 10'-0"x4'-0" 80.00
107.00 33.59
vi. 0.5 mm thick laminate to inside surface
2 sides 8.00 sft 4'-0"x1'-6" 48.00
front and back 2.00 sft 10'-0"x4'-0" 80.00
horizontal shelf top and bottom 5.00 sft 10'-0"x1'-6" 75.00
203.00 22.00
vii Enamel paint to bottom and inside top 1.00 sft 10'-0"x1'-6" 15.00 65.00
Page 4 of 117(Ana. Int.)

viii. Add for Adhesive, nail, Screws, hinges @ 5 %


ix. Add waste @ 5%
x. Add transportation @ 3%
xii. Add labour charges @ 20%

xiii. Overhead charges @ 7.5%


xiv. Contractor profit @ 7.5%

xv Add labour cess 1%


Cost of 40 sqft
Cost of 1 sqft
Cost of 1 sqm
Say
Page 5 of 117(Ana. Int.)

1059.48

1235.52

4257.76

11662.56

590.00

200.00

660.00
---------------
19665.32
983.27

17848.00

436.80

180.00

1292.50
---------------
40405.89
Page 6 of 117(Ana. Int.)

2020.29
1212.18
---------------
43638.36
20000.00
---------------
63638.36
4772.88
4772.88
---------------
73184.11
731.84
---------------
73915.95
739.16
74.30
40.60
60.50
---------------
914.56
914.60

187.76

807.00

361.46
------------------
1356.22
67.81
67.81
40.69
------------------
1532.53
153.25
------------------
1685.78
126.43
126.43
------------------
1938.65
19.39
------------------
1958.04
1958.00
Page 7 of 117(Ana. Int.)

671.83

947.00

361.00
------------------
1979.83
98.99
98.99
49.50
------------------
2227.31
111.37
------------------
2338.68
175.40
175.40
------------------
2689.48
26.89
------------------
2716.37
2716.40

11625.00

1470.00

1056.00
1760.00

3594.13

4466.00
975.00
--------------
Page 8 of 117(Ana. Int.)

24946.13
1247.31
1247.31
748.38
4989.23
---------------
33178.35
2488.38
2488.38
38155.11
381.55
38536.66
963.42
10366.36
10366.40
LEAD STATEMENT

Total of
Sl. Name of the Lead in Basic Cost Cost of
Name of the materials. Unit Royalty Carriage
No. quarry Kms. of Material carriage
and Royalty

1 R.R Stone Granite Broken Lanjiberna 1 Cum. 57.00 212.23 589.21 130.00 719.21
2 40mm Size C.B. metal (Granite) Lanjiberna 1 Cum. 57.00 704.76 589.21 130.00 719.21
3 25mm Size C.B. metal Lanjiberna 1 Cum. 57.00 750.48 589.21 130.00 719.21
4 20mm size Granite C.B. chips Lanjiberna 1 Cum 57.00 1028.57 589.21 130.00 719.21
5 12mm Size C.B. chips (Granite) Lanjiberna 1 Cum. 57.00 1045.71 589.21 130.00 719.21
6 10mm Size C.B. chips Lanjiberna 1 Cum. 57.00 1090.48 589.21 130.00 719.21
7 6.7 mm Size C.B. metal (Granite) Lanjiberna 1 Cum. 57.00 728.57 589.21 130.00 719.21
8 4.70 mm Size C.B. metal (Granite) Lanjiberna 1 Cum. 57.00 664.76 589.21 130.00 719.21
9 Moorum Local Quarry 1 Cum. 5.00 44.76 149.67 35.00 184.67
10 Sand (for road filling) IB river 1 Cum. 5.00 43.81 149.67 35.00 184.67
11 Sand (for motar) IB river 1 Cum 5.00 50.48 149.67 35.00 184.67
12 C.B. Brick (23 x 11 x 8) Cm Karamdihi 1000 Nos 10.00 2480.85 466.15 87.50 553.65
221.46 /400Nos
13 Fly ash Brick (23 x 11 x 8) Cm Local 1000 Nos 0.00 3506.38 386.910 21.25 408.16
163.26 /400Nos
14 Cement Sundargarh 1 Qntl At site 517.42 5.50 5.50
15 Steel Rourkela 1M.T. 0.00 76532.48 0.00
0.00 /Qntl
16 Wooden centering materials Sundargarh 1 Cum 5.00 129.376 129.38
17 Humepipe 600 mm Class NP3 Sambalpur Per trip 95.00 16975.00 4584.87 4584.87
18 Clay Local area 1 Cum 5.00 51.43 149.67 35.00 184.67
19 Vitrified tile (Printed) Sundargarh 1 Sqm 5.00 562.99 5.37 5.37
20 Vitrified tile (Plain) Sundargarh 1 Sqm 5.00 522.05 5.37 5.37
21 Marble tile Sundargarh 1 Sqm 5.00 582.68 5.37 5.37
22 Granite tile Sundargarh 1 Sqm 5.00 1645.67 5.37 5.37
23 Ceramic Wall tile Sundargarh 1 Sqm 5.00 299.21 5.37 5.37
24 Ceramic floor tile Sundargarh 1 Sqm 5.00 334.65 5.37 5.37
25 Chequred Tile Sundargarh 1 Sqm 5.00 170.87 5.37 5.37
26 Kota Stone Sundargarh 1 Sqm 5.00 313.39 5.37 5.37
27 Koddapa Stone Sundargarh 1 Sqm 5.00 277.95 5.37 5.37
28 Industrial Vitrified tile Sundargarh 1 Sqm 5.00 472.44 5.37 5.37
29 Bitumen Sambalpur 1M.T. 83.00 29340.00 762.74 762.74
30 Angle Sambalpur 1M.T. 83.00 762.74 762.74
76.27 /Qntl
31 Nuria Tile Local 1000 No 5.00 579.53 203.00 203.00
32 Sheet Jharsuguda 1 Sqm 32.00 383.93
33 Paver Block Jharsuguda 30.00 510.00 10.87 77.88 88.75
34 K.B. Brick (25 x 11 x 8) Cm 1000 Nos 15.00 3500.43 545.39 87.50 632.89
221.51 /350Nos
35 Clay Local 1 Cum 5.00 51.43 149.67 35.00 184.67

Certified that the lead provided above are correct and minimum to the best of my knowledge and belief.

Assistant Engineer Assistant Executive Engineer #REF!


Building (R&B) Section Sundargarh (R&B) Sub-Division #REF!
ANALYSIS OF RATES
Sl. No. Description Qnty. Unit Rate Amount
1 Earth work in excavation of foundation in hard soil or gravelly soil including
dressing and leveling the bed and disposal of the excavated materials with
mechanical means within 5.00km. initial leads and lifts as per direction of
E.I.C.
(A.R.-2006, Page No - 2, Item No. - 2(a))
Data for 100 Cums.
(i) a) Labour
Mulia 21.50 Each 333.00 7159.50
Woman mulia 21.50 Each 333.00 7159.50
Over Head Charge 7.5 % = 1073.93
Contractor's Profit 7.5 % = 1073.93
Total= 16466.86
Rate for 1.00 Cum= 164.67
Add 20 % toward foundation works 32.93
96.0000 Total = Rs. 197.60
Add 1% Labour cess = 1.98
Total = Rs 199.58
Say Rs. 199.60 per Cum.
Add for Cost of disposal of excavated earth by mechanical means = 149.67

Total = Rs 347.27
Add 1% Labour cess = 3.47
Total = Rs 350.74
Say Rs. 350.70 Per Cum
2nd depth of 1.5m –1½ times initial rate + 1½ times lift 247.01
49.40
296.41
Add 1% Labour cess = 2.96
Total = Rs 299.37
Say Rs. 299.40 Per Cum
3rd depth of 1.5m –2 times initial rate + 2½ times lift 329.34
65.86
395.20
Add 1% Labour cess = 3.95
Total = Rs 399.15
Say Rs. 399.20 Per Cum

4th depth of 1.5m –2½ times initial rate + 3½ times liftt 411.67
82.33
494.00
Add 1% Labour cess = 4.94
Total = Rs 498.94
Say Rs. 498.90 Per Cum
For Back Filling
1/3 of Earth work rate 66.53
Per Cum

Basic rate 199.60


2/3 of basic rate 132.93

6 Excavation of foundation in hard rock(granite) removed by chiselling


including dressing and levelling the bed not exceeding 1.5mtr in depth and
depositing the soil within 590mtr lead and as per specification approved by
the Deptt. (per 1cum.)
Man mulia (nos.) 5.68 Each 333.00 1891.44
Over head charges @ 7.5% 7.5% 141.86
Contractor Profit @ 7.5% 7.5% 141.86
2175.16
Sl. No. Description Qnty. Unit Rate Amount
Add Cess 1% 1% 21.75
2196.91
Cum or say 2196.90
2 Supplying & filling foundation and plinth with sand well watered and
rammed including cost, cost of all labour, carriage, royalty, taxes, T&P etc
complete.
(A.R.-2006, Page No - 8, Item No. - 15)
Data for 100 Cums.
a) Labour
Mulia 12.36 Each 333.00 4115.88
b) Materials
Sand 100.00 Cum. 43.81 4381.00
Total = 8496.88
Over Head Charge 7.5 % = 637.27
Contractor's Profit 7.5 % = 637.27
Total = 9771.42
c) Carriage and royalty of materials
Sand 100.00 Cum. 184.67 18467.00
Total = 28238.42
Rate for 1.00 Cum= 282.38
Add 1% Labour cess = 2.82
Total = Rs 285.20
Say Rs. 285.20 Per Cum
3 Cement Concrete (1:4:8) using 40mm size hard granite metal approved
quality from approved quarry including hoisting laying using concrete
mixture and vibrators including cost, carriage, royalty, cost of labour T.&P.
etc complete and as directed by E.I.C.

(A.R.-2006, Page No - 43, Item No. - 4)


a) Materials
40mm size Granite C.B. metal 0.96 Cum. 704.76 676.56
Sand 0.48 Cum. 50.48 24.23
Cement 1.72 Qntl 517.42 889.96
Total = 1590.75
b) Labour
Mason Second Class 0.18 Each 423.00 76.14
Mulia 2.50 Each 333.00 832.50
Woman mulia 1.40 Each 333.00 466.20
Total = 1374.84
Over Head Charge 7.5 % = 222.41
Contractor's Profit 7.5 % = 222.41
e) Cost of Carriage and Royalty of Materials
40mm size Granite C.B. metal 0.96 Cum. 719.21 690.44
Sand 0.48 Cum. 184.67 88.64
Cement 1.72 Qntl 5.50 9.46
Total= 788.54
Total =(a+b+c+d+e) = Rs. 4198.95
Add 1% Labour cess = 41.98
Total = Rs 4240.93
Say Rs. 4240.90 Per Cum
3 Cement Concrete (1:3:6) using 40mm size hard granite C.B. metal
approved quality from approved quarry including hoisting laying using
concrete mixture and vibrators including cost, carriage, royalty, cost of all
labour T.&P. etc complete and as directed by E.I.C.

(A.R.-2006, Page No - 43, Item No. - 3)


a) Materials
40mm size Granite C.B. metal 0.96 Cum. 704.76 676.56
Sand 0.48 Cum. 50.48 24.23
Sl. No. Description Qnty. Unit Rate Amount
Cement 2.29 Qntl 517.42 1184.89
Total = 1885.68
b) Labour
Mason Second Class 0.18 Each 423.00 76.14
Mulia 3.90 Each 333.00 1298.70
Total = 1374.84
Over Head Charge 7.5 % = 244.53
Contractor's Profit 7.5 % = 244.53
e) Cost of Carriage and Royalty of Materials
40mm size Granite C.B. metal 0.96 Cum. 719.21 690.44
Sand 0.48 Cum. 184.67 88.64
Cement 2.29 Qntl 5.50 12.59
Total= 791.67
Total =(a+b+c+d) = Rs. 4541.25
Add 1% Labour cess = 45.41
Total = Rs 4586.66
Say Rs. 4586.70 Per Cum
below ground level beyond 1.5m and upto 4.5m depth
(i) Basic rate of C.C. (1:3:6) 4541.25
(ii) 15% extra on labour below ground level beyond 1.5m and upto 4.5m depth 206.22
add 15per cent extra labour over and above
(iii) Over Head Charge 7.5 % = 15.46
Contractor's Profit 7.5 % = 15.46
4778.39
Add 1% Labour cess = 47.78
Total = Rs 4826.17
Say Rs. 4826.20 per Cum
3 C.C. (1:2:4) with 12mm and down grade C.B. chips approved quality from
approved quarry including hoisting, laying hire charges of concrete mixture,
vibrator, watering, curing and including cost, carriage, royalty, cost of all
labour T.&P. etc complete and as directed by E.I.C.

(A.R.-2006, Page No - 49, Item No. - 7)


Data for 1 Cum.
a) Materials
12mm size Granite C.B. chips 0.90 Cum. 1045.71 941.13
Sand 0.45 Cum. 50.48 22.71
Cement 3.23 Qntl 517.42 1671.26
Total = 2635.10
b) Labour
Mason Second Class 0.68 Each 423.00 287.64
Man mulia for mixing stone, sand and cement 1.40 Each 333.00 466.20
and getting water
Man mulia 1.80 Each 333.00 599.40
Woman mulia 1.40 Each 333.00 466.20
Total = 1819.44
Over Head Charge 7.5 % = 334.09
Contractor's Profit 7.5 % = 334.09
e) Cost of Carriage and Royalty of Materials
12mm size Granite C.B. chips 0.90 Cum. 719.21 647.28
Sand 0.45 Cum. 184.67 83.10
Cement 3.23 Qntl 5.50 17.76
Total= 748.14
Total =(a+b+c+d+e) = Rs. 5870.86
Add 1% Labour cess = 58.70
Total = Rs 5929.56
Say Rs. 5929.60 Per Cum
First floor
(i) Basic rate of C.C. (1:2:4) 5870.86
Sl. No. Description Qnty. Unit Rate Amount
(ii) 15% extra on labour 272.91
(iii) Over Head Charge 7.5 % = 20.46
Contractor's Profit 7.5 % = 20.46
6184.69
Add 1% Labour cess = 61.84
Total = Rs 6246.53
Say Rs. 6246.50 per Cum
2nd floor
(i) Basic rate of C.C. (1:2:4) (First floor) 6184.69
(ii) 15% extra on labour 313.84
(iii) Over Head Charge 7.5 % = 23.53
Contractor's Profit 7.5 % = 23.53
6545.59
Add 1% Labour cess = 65.45
Total = Rs 6611.04
Say Rs. 6611.00 per Cum
6 C.C. (1:1½:3) with 12mm and down grade C.B. chips including hoisting,
laying hire charges of concrete mixture, vibrator, watering, curing and cost
of all materials and labour, T&P centering shuttering etc complete (using
Concret Mixture)
(A.R.-2006, Page No - 49, Item No. - 2)
Data for 1 Cum.
a) Materials
12mm size Granite C.B. chips 0.90 Cum. 1045.71 941.13
Sand 0.45 Cum. 50.48 22.71
Cement 4.29 Qntl 517.42 2219.73
Total = 3183.57
b) Labour
Mason Second Class 0.68 Each 423.00 287.64
Man mulia 1.80 Each 333.00 599.40
Woman mulia 1.40 Each 333.00 466.20
Total = 1353.24
c) Machinery
Concrete mixture 0.40 Hour 153.91 61.56
Generator 33 KVA 0.40 Hour 208.70 83.48
Total = 145.04
Over Head Charge 7.5 % = 351.13
Contractor's Profit 7.5 % = 351.13
f) Cost of Carriage and Royalty of Materials
12mm size Granite C.B. chips 0.90 Cum. 719.21 647.28
Sand 0.45 Cum. 184.67 83.10
Cement 4.29 Qntl 5.50 23.59
Total= 753.97
Total =(a+b+c+d+e) = Rs. 6138.08
Add 1% Labour cess = 61.38
Total = Rs 6199.46
Say Rs. 6199.50 Per Cum
First floor
(i) Basic rate of C.C. (1:1½:3) 6138.08
(ii) 15% extra on labour 202.98
(iii) Over Head Charge 7.5 % = 15.22
Contractor's Profit 7.5 % = 15.22
6371.50
Add 1% Labour cess = 63.71
Total = Rs 6435.21
Say Rs. 6435.20 per Cum
2nd floor
(i) Basic rate of C.C. (1:1½:3) (First floor) 6371.50
(ii) 15% extra on labour 233.42
Sl. No. Description Qnty. Unit Rate Amount
(iii) Over Head Charge 7.5 % = 17.50
Contractor's Profit 7.5 % = 17.50
6639.92
Add 1% Labour cess = 66.39
Total = Rs 6706.31
Say Rs. 6706.30 per Cum
4 M-15 with 20mm and down grade C.B. chips including hoisting, laying hire
charges of concrete mixture, vibrator, watering, curing and cost of all
materials and labour, T&P centering shuttering etc complete but cost
excluding of ment complete.
(A.R.-2006, Page No - 49, Item No. - 3)
Data for 1 Cum.
a) Materials
20mm size Granite C.B. chips 0.54 Cum. 1028.57 555.42
10mm size Granite C.B. chips 0.36 Cum. 1090.48 392.57
Sand 0.45 Cum. 50.48 22.71
Cement 2.80 Qntl 517.42 1448.77
Total = 2419.47
b) Labour
Mate 0.06 Each 373.00 22.38
Mason 2nd Class 0.10 Each 423.00 42.30
Mulia 1.33 Each 333.00 442.89
Total = 507.57
c) Machinery
Concrete mixture 0.40 Hour 153.91 61.56
Generator 0.40 Hour 208.70 83.48
Total = 145.04
Over Head Charge 7.5 % = 230.40
Contractor's Profit 7.5 % = 230.40
e) Cost of Carriage and Royalty of Materials
20mm size Granite C.B. chips 0.54 Cum. 719.21 388.37
12mm size Granite C.B. chips 0.36 Cum. 719.21 258.91
Sand 0.45 Cum. 184.67 83.10
Cement 2.80 Qntl 5.50 15.40
Total= 745.78
Total =(a+b+c+d+e) = Rs. 4278.66
Add 1% Labour cess = 42.78
Total = Rs 4321.44
Say Rs. 4321.40 Per Cum
First floor
(i) Basic rate of M-15 4278.66
(ii) 15% extra on labour 76.13
(iii) Over Head Charge 7.5 % = 5.70
Contractor's Profit 7.5 % = 5.70
4366.19
Add 1% Labour cess = 43.66
Total = Rs 4409.85
Say Rs. 4409.90 per Cum
2nd floor
(i) Basic rate of M-15 (First floor) 4366.19
(ii) 15% extra on labour 87.55
(iii) Over Head Charge 7.5 % = 6.56
Contractor's Profit 7.5 % = 6.56
4466.86
Add 1% Labour cess = 44.66
Total = Rs 4511.52
Say Rs. 4511.50 per Cum
Sl. No. Description Qnty. Unit Rate Amount
4 R.C.C. M-20 grade with 20mm and down grade C.B. chips of approved
quality from approved quarry including hoisting, laying hire charges of
concrete mixture, vibrator, watering, curing and cost of all materials and
labour, T&P centering shuttering etc complete but excluding cost of
reinforcement complete.

(A.R.-2006, Page No - 50, Item No. - 4)


Data for 15 Cums.
a) Materials
20mm size Granite C.B. metal 8.10 Cum. 1028.57 8331.41
10mm size Granite C.B. chips 5.40 Cum. 1090.48 5888.59
Sand 6.75 Cum. 50.48 340.74
Cement 52.10 Qntl 517.42 26957.58
Total = 41518.32
b) Labour
Mate 0.86 Each 373.00 320.78
Mason Second Class 1.50 Each 423.00 634.50
Mulia 20.00 Each 333.00 6660.00
Total = 7615.28
c) Machinery
Cement Mixture 6.00 Hour 153.91 923.46
Generator 6.00 Hour 208.70 1252.20
Total = 2175.66
Over Head Charge 7.5 % = 3848.19
Contractor's Profit 7.5 % = 3848.19
f) Cost of Carriage and Royalty of Materials
20mm size Granite C.B. metal 8.10 Cum. 719.21 5825.60
10mm size Granite C.B. chips 5.40 Cum. 719.21 3883.73
Sand 6.75 Cum. 184.67 1246.52
Cement 52.10 Qntl 5.50 286.55
Total= 11242.40
Total =(a+b+c+d+e+f) = Rs. 70248.04
= Rs. 4683.20
Add 1% Labour cess = 46.83
Total = Rs 4730.03
Say Rs. 4730.00 Per Cum
First floor
(i) Basic rate = 4683.20
(ii) Add 15 % extra Labour = 76.15
Over Head Charge 7.5 % = = 5.71
Contractor's Profit 7.5 % = = 5.71
Total = 4770.77
Add 1% Labour cess = 47.70
Total = Rs 4818.47
Say Rs. 4818.50 per Cum
2nd floor
(i) Basic rate 4770.77
(ii) 15% extra on labour 87.57
(iii) Over Head Charge 7.5 % = 6.56
Contractor's Profit 7.5 % = = 6.56
4871.46
Add 1% Labour cess = 48.71
Total = Rs 4920.17
Say Rs. 4920.20 per Cum
Rigid smooth centering shuttering for R.C.C.work including all cost etc
complete
(A) Plinth Band, Column Footing
Data for 10.00Sqms.
a) Materials
25mm. Non sal plank 0.267 One Cum 16172.61 4318.08
Sl. No. Description Qnty. Unit Rate Amount
80mm.dia non sal bullah for strutting 12.600 R.M. 39.83 501.85
Carriage of wood 0.3284 One Cum 129.38 42.48
4862.41
For one time use cost 486.24
b) Labour
Carpenter Second Class 0.50 Each 423.00 211.50
Semi skilled Mulia 0.50 Each 373.00 186.50
Total = 398.00
Over Head Charge 7.5 % = 66.31
Contractor's Profit 7.5 % = 66.31
Total= 1016.86
For 1.00Sqm=Total/10.00 101.68
per Sqm.
First floor
(i) Basic rate = 101.68
(ii) Add 20 % extra = 20.33
Total = 122.01
per Sqm.
2nd floor
(i) Basic rate = 122.01
(ii) Add 20 % extra = 24.40
Total = 146.41
per Sqm.
(B) Lintel band
Data for 7.8 sqm.
a) Materials
Plank 38mm 0.413 One cum 16172.61 6679.28
120mm dia Non-sal bullah 21.00 R.M. 59.75 1254.75
Carriage of wood 0.689 One Cum 129.38 89.14
8023.17
For one time use cost 802.31
b) Labour
Carpenter Second Class 1.25 Each 423.00 528.75
Semi skilled Mulia 1.25 Each 373.00 466.25
Total = 995.00
Over Head Charge 7.5 % = 134.79
Contractor's Profit 7.5 % = 134.79
Total= 2066.89
For 1.00Sqm=Total/7.8 264.98
per Sqm.
First floor
(i) Basic rate = 264.98
(ii) Add 20 % extra = 52.99
Total = 317.97
per Sqm.
2nd floor
(i) Basic rate = 317.97
(ii) Add 20 % extra = 63.59
Total = 381.56
per Sqm.
(C) Roof Slab, Shelves and Chajja
Data for 9 sqm.
a) Materials
Non sal wood scantling 0.112 One Cum 16172.61 1811.33
Plank 38mm 0.34 One cum 16172.61 5498.68
120mm dia sal bullah 56.00 R.M. 80.50 4508.00
Carriage of wood 1.142 One Cum 129.38 147.74
11965.75
For one time use cost 1196.57
Sl. No. Description Qnty. Unit Rate Amount
b) Labour
Carpenter Second Class 2.75 Each 423.00 1163.25
Semi skilled Mulia 2.75 Each 373.00 1025.75
Total = 2189.00
Over Head Charge 7.5 % = 253.91
Contractor's Profit 7.5 % = 253.91
Total= 3893.39
For 1.00Sqm=Total/9.00 432.59
per Sqm.
First floor
(i) Basic rate = 432.59
(ii) Add 20 % extra = 86.51
Total = 519.10
per Sqm.
2nd floor
(i) Basic rate = 519.10
(ii) Add 20 % extra = 103.82
Total = 622.92
per Sqm.
(D) Beams, Column
Data for 4.2 Sqm
a) Materials
38mm.Sal planks 0.218 One Cum 16172.61 3525.62
120mm dia salbullah 15.20 R.M. 80.50 1223.60
80mm dia sal bullah for bracing 8.00 R.M. 80.50 644.00
Carriage of wood 0.456 One Cum 129.38 58.99
5452.21
For one time use cost 545.22
b) Labour
Carpenter Second Class 2.75 Each 423.00 1163.25
Semi skilled Mulia 2.75 Each 373.00 1025.75
Total= 2189.00
Over Head Charge 7.5 % = 205.06
Contractor's Profit 7.5 % = 205.06
Total= 3144.34
Rate for 1.00Sqm=Total/4.2 748.65
per Sqm.
First floor
(i) Basic rate = 748.65
(ii) Add 20 % extra = 149.73
Total = 898.38
per Sqm.
2nd floor
(i) Basic rate = 898.38
(ii) Add 20 % extra = 179.67
Total = 1078.05
per Sqm.
(E)Staircase
Data for 5.00 Sqms.
a) Materials
38mm.Non-Sal planks 0.228 One Cum 16172.61 3687.35
Non-Sal wood scantling 0.039 One Cum 16172.61 630.73
120mm dia non-sal bullah 6.50 R.M. 59.75 388.37
Carriage of wood 0.35 One Cum 129.38 45.28
4751.73
For one time use cost 475.17
b) Labour
Carpenter Second Class 2.75 Each 423.00 1163.25
Semi skilled Mulia 2.75 Each 373.00 1025.75
Sl. No. Description Qnty. Unit Rate Amount
Total= 2189.00
Over Head Charge 7.5 % = 199.81
Contractor's Profit 7.5 % = 199.81
Total= 3063.79
Rate for 1.00Sqm=Total/5.00 612.75
per Sqm.
First floor
(i) Basic rate = 612.75
(ii) Add 20 % extra = 122.55
Total = 735.30
per Sqm.
2nd floor
(i) Basic rate = 735.30
(ii) Add 20 % extra = 147.06
Total = 882.36
per Sqm.
(F) RCC wall and Fins
Data for 23.90 Sqm
38mm.Non-Sal planks 0.954 One Cum 16172.61 15428.66
Non-Sal wood scantling 0.269 One Cum 16172.61 4350.43
125mm dia non-sal bullah 100.80 R.M. 59.75 6022.80
Carriage of wood 2.461 One Cum 129.38 318.39
26120.28
For one time use cost 2612.02
b) Labour
Carpenter Second Class 13.50 Each 423.00 5710.50
Semi skilled Mulia 13.50 Each 373.00 5035.50
Total= 10746.00
Over Head Charge 7.5 % = 1001.85
Contractor's Profit 7.5 % = 1001.85
Total= 15361.72
Rate for 1.00Sqm=Total/23.90 642.74
per Sqm.
First floor
(i) Basic rate = 642.74
(ii) Add 20 % extra = 128.54
Total = 771.28
per Sqm.
2nd floor
(i) Basic rate = 771.28
(ii) Add 20 % extra = 154.25
Total = 925.53
per Sqm.
Finished Rate
(A) Drain base
Rate as per (Basic Rate of RCCM-20) 4683.20
Add for centering and shuttering 1.50 One Sqm 101.68 152.52
Total= 4835.72
Add 1% Labour cess = 48.35
Total = Rs 4884.07
Say Rs. 4884.10 per Cum
(B) Plinth band (Grade beam)
Rate as per (Basic Rate of RCCM-20) 4683.20
Add for centering and shuttering 5.00 One Sqm 101.68 508.40
Total= 5191.60
Add 1% Labour cess = 51.91
Total = Rs 5243.51
Say Rs. 5243.50 per Cum
First floor
Sl. No. Description Qnty. Unit Rate Amount
(i) Basic rate 4770.77
(ii) Add for centering and shuttering = 5.00 Sqm 122.01 610.05
Total = 5380.82
Add 1% Labour cess = 53.80
Total = Rs 5434.62
Say Rs. 5434.60 per Sqm.
2nd floor
(i) Basic rate 4871.46
(ii) Add for centering and shuttering = 5.00 Sqm 146.41 732.05
Total = 5603.51
Add 1% Labour cess = 56.03
Total = Rs 5659.54
Say Rs. 5659.50 per Sqm.
(C) Roof Slab
Rate as per (Basic Rate of RCCM-20) 4683.20
Add for centering and shuttering 10.00 One Sqm 432.59 4325.90
Total= 9009.10
Add 1% Labour cess = 90.09
Total = Rs 9099.19
Say Rs. 9099.20 per Cum
First floor
(i) Basic rate 4770.77
(ii) Add for centering and shuttering = 10.00 Sqm 519.10 5191.00
Total = 9961.77
Add 1% Labour cess = 99.61
Total = Rs 10061.38
Say Rs. 10061.40 per Cum
2nd floor
(i) Basic rate 4871.46
(ii) Add for centering and shuttering = 10.00 Sqm 622.92 6229.20
Total = 11100.66
Add 1% Labour cess = 111.00
Total = Rs 11211.66
Say Rs. 11211.70 per Sqm.
(D) Lintel band
Rate as per (Basic Rate of RCCM-20) 4683.20
Add for centering and shuttering 14.00 One Sqm 264.98 3709.72
Total= 8392.92
Add 1% Labour cess = 83.92
Total = Rs 8476.84
Say Rs. 8476.80 per Cum
First floor
(i) Basic rate 4770.77
(ii) Add for centering and shuttering = 14.00 Sqm 317.97 4451.58
Total = 9222.35
Add 1% Labour cess = 92.22
Total = Rs 9314.57
Say Rs. 9314.60 per Sqm.
2nd floor
(i) Basic rate 4871.46
(ii) Add for centering and shuttering = 14.00 Sqm 381.56 5341.84
Total = 10213.30
Add 1% Labour cess = 102.13
Total = Rs 10315.43
Say Rs. 10315.40 per Sqm.
(E) Chajja
Rate as per (Basic Rate of RCCM-20) (for 6.50Cm average thick) 0.065 x 4683.20 304.40
Add for centering and shuttering 1.10 One Sqm 432.59 475.84
Total= 780.24
Sl. No. Description Qnty. Unit Rate Amount
Add 1% Labour cess = 7.80
Total = Rs 788.04
Say Rs. 788.00 per Sqm.
First floor
Rate as per (Basic Rate of RCCM-20) (for 6.50Cm average thick) 0.065 x 4770.77 310.10
Add for centering and shuttering 1.10 One Sqm 519.10 571.01
Total= 881.11
Add 1% Labour cess = 8.81
Total = Rs 889.92
Say Rs. 889.90 per Sqm.
2nd floor
Rate as per (Basic Rate of RCCM-20) (for 6.50Cm average thick) 0.065 x 4871.46 316.64
Add for centering and shuttering 1.10 One Sqm 622.92 685.21
Total= 1001.85
Add 1% Labour cess = 10.01
Total = Rs 1011.86
Say Rs. 1011.90 per Sqm.
(F) Fins
Rate as per (Basic Rate of RCCM-20) (for 7.5Cm average thick) 0.075 x 4683.20 351.24
Add for centering and shuttering 2.00 One Sqm 642.74 1285.48
Total= 1636.72
Add 1% Labour cess = 16.36
Total = Rs 1653.08
Say Rs. 1653.10 per Sqm.
First floor
Rate as per (Basic Rate of RCCM-20) (for 7.5Cm average thick) 0.075 x 4770.77 357.80
Add for centering and shuttering 2.00 One Sqm 771.28 1542.56
Total= 1900.36
Add 1% Labour cess = 19.00
Total = Rs 1919.36
Say Rs. 1919.40 per Sqm.
2nd floor
Rate as per (Basic Rate of RCCM-20) (for 7.5Cm average thick) 0.075 x 4871.46 365.35
Add for centering and shuttering 2.00 One Sqm 925.53 1851.06
Total= 2216.41
Add 1% Labour cess = 22.16
Total = Rs 2238.57
Say Rs. 2238.60 per Sqm.
(G) Column in Superstrecture, Beam
Rate as per (Basic Rate of RCCM-20) 4683.20
Add for centering and shuttering 10.00 One Sqm 748.65 7486.50
Total= 12169.70
Add 1% Labour cess = 121.69
Total = Rs 12291.39
Say Rs. 12291.40 per Cum
First floor
(i) Basic rate 4770.77
(ii) Add for centering and shuttering = 10.00 Sqm 898.38 8983.80
Total = 13754.57
Add 1% Labour cess = 137.54
Total = Rs 13892.11
Say Rs. 13892.10 per Sqm.
2nd floor
(i) Basic rate 4871.46
(ii) Add for centering and shuttering = 10.00 Sqm 1078.05 10780.50
Total = 15651.96
Add 1% Labour cess = 156.51
Total = Rs 15808.47
Say Rs. 15808.50 per Sqm.
Sl. No. Description Qnty. Unit Rate Amount
(H) Staircase
Rate as per (Basic Rate of RCCM-20) 4683.20
Add for centering and shuttering 9.00 One Sqm 612.75 5514.75
Total= 10197.95
Add 1% Labour cess = 101.97
Total = Rs 10299.92
Say Rs. 10299.90 per Cum
First floor
(i) Basic rate 4770.77
(ii) Add for centering and shuttering = 9.00 Sqm 735.30 6617.70
Total = 11388.47
Add 1% Labour cess = 113.88
Total = Rs 11502.35
Say Rs. 11502.40 per Sqm.
2nd floor
(i) Basic rate 4871.46
(ii) Add for centering and shuttering = 9.00 Sqm 882.36 7941.24
Total = 12812.70
Add 1% Labour cess = 128.12
Total = Rs 12940.82
Say Rs. 12940.80 per Sqm.
(I) RCC Selves Thickness (37.50mm)
Rate as per (Basic Rate of RCCM-20) 0.0375 x 4683.20 175.62
Add for centering and shuttering 1.10 One Sqm 432.59 475.84
Total= 651.46
Add 1% Labour cess = 6.51
Total = Rs 657.97
Say Rs. 658.00 per Sqm.
First floor
Rate as per (Basic Rate of RCCM-20) 0.0375 Sqm 4770.77 178.90
Add for centering and shuttering 1.10 Sqm 519.10 571.01
Total = 749.91
Add 1% Labour cess = 7.49
Total = Rs 757.40
Say Rs. 757.40 per Sqm.
2nd floor
Rate as per (Basic Rate of RCCM-20) 0.0375 Sqm 4871.46 182.67
Add for centering and shuttering 1.10 Sqm 622.92 685.21
Total = 867.88
Add 1% Labour cess = 8.67
Total = Rs 876.55
Say Rs. 876.60 per Sqm.
(J) RCC Wall
Rate as per (Basic Rate of RCCM-20) 4683.20
Add for centering and shuttering 7.00 One Sqm 642.74 4499.18
Total= 9182.38
Add 1% Labour cess = 91.82
Total = Rs 9274.20
Say Rs. 9274.20 per Cum
First floor
(i) Basic rate 4770.77
(ii) Add for centering and shuttering = 7.00 Sqm 771.28 5398.96
Total = 10169.73
Add 1% Labour cess = 101.69
Total = Rs 10271.42
Say Rs. 10271.40 per Sqm.
2nd floor
(i) Basic rate 4871.46
(ii) Add for centering and shuttering = 7.00 Sqm 925.53 6478.71
Sl. No. Description Qnty. Unit Rate Amount
Total = 11350.17
Add 1% Labour cess = 113.50
Total = Rs 11463.67
Say Rs. 11463.70 per Sqm.
(H) Precast slab
Rate as per (Basic Rate of RCCM-20) 4683.20
Add for centering and shuttering 5.00 One Sqm 101.68 508.40
Total= 5191.60
Add 1% Labour cess = 51.91
Total = Rs 5243.51
Say Rs. 5243.50 per Cum
First floor
Rate as per (Basic Rate of RCCM-20) 4770.77
Add for centering and shuttering 5.00 One Sqm 122.01 610.05
Total= 5380.82
Add 1% Labour cess = 53.80
Total = Rs 5434.62
Say Rs. 5434.60 per Cum
2nd floor
Rate as per (Basic Rate of RCCM-20) 4871.46
Add for centering and shuttering 5.00 One Sqm 146.41 732.05
Total= 5603.51
Add 1% Labour cess = 56.03
Total = Rs 5659.54
Say Rs. 5659.50 per Cum
9 C.C. M-25 grade with 20mm and down grade b.h. granite C.B. chips of
approved quality from approved quarry including watering, curing, cost,
carriage, royalty & taxes of all materials and labour, T&P etc complete.

Data for 15 cum


a) Material
20 mm size chips 8.10 Cum 1028.57 8331.41
10mm size chips 5.40 Cum 1090.48 5888.59
coarse sand (screened and washed) 6.75 Cum 50.48 340.74
Cement 60.50 Qntl 517.42 31303.91
Total = 45864.65
b) Labour
Mate 0.86 No 373.00 320.78
Mason 2nd class 1.50 No 423.00 634.50
Man Mulia 20.00 No 333.00 6660.00
Total = 7615.28
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) 6.00 Hour 153.91 923.46
Generator 33 KVA 6.00 Hour 208.70 1252.20
Total = 2175.66
Over Head Charge 7.5 % = 4174.16
Contractor's Profit 7.5 % = 4174.16
f) Cost of Carriage and Royalty of Materials
20mm size Granite C.B. metal 8.10 Cum. 719.21 5825.60
10mm size Granite C.B. chips 5.40 Cum. 719.21 3883.73
Sand 6.75 Cum. 184.67 1246.52
Cement 60.50 Qntl 5.50 332.75
Total= 11288.61
Total =(a+b+c+d+e+f) = Rs. 75292.52
= Rs. 5019.50
Add 1% Labour cess = 50.19
Total = Rs 5069.69
Say 5069.70 Per Cum
First floor
Sl. No. Description Qnty. Unit Rate Amount
(i) Basic rate = 5019.50
(ii) Add 15 % extra Labour = 76.15
Over Head Charge 7.5 % = = 5.71
Contractor's Profit 7.5 % = = 5.71
Total = 5107.07
Add 1% Labour cess = 51.07
Total = Rs 5158.14
Say Rs. 5158.10 per Cum
2nd floor
(i) Basic rate 5107.07
(ii) 15% extra on labour 87.57
(iii) Over Head Charge 7.5 % = 6.56
Contractor's Profit 7.5 % = 6.56
5207.76
Add 1% Labour cess = 52.07
Total = Rs 5259.83
Say Rs. 5259.80 per Cum
11 Brick work with C.B. bricks 23cm x 11cm x 8cm size having crushing
strength not less than 75Kg/cm2 with dimensional tolerance ±8 percent in
cement mortar (1:6) in Foundation and Plinth including watering, curing,
cost, carriage, royalty and taxes of all materials, cost of all labour, T&P etc
complete as per the direction of E.I.C.

Ref :-A/R - 2006 ,P-71, Item No - 3


Data for 1 Cum.
a) Materials
C.B. Brick 23cm × 11cm x 8cm 400.00 One cum 2.481 992.40
:400Nos. for Each.
Sand 0.28 One cum 50.48 14.13
Cement 0.672 One Qntl. 517.42 347.70
Total = 1354.23
b) Labour
Mason Special 0.35 Each 483.00 169.05
Mason Second class 1.05 Each 423.00 444.15
Man mulia 1.41 Each 333.00 469.53
Women mulia 1.41 Each 333.00 469.53
Man mulia for preparing mortar etc. 0.14 Each 333.00 46.62
Total = 1598.88
Over Head Charge 7.5 % = 221.48
Contractor's Profit 7.5 % = 221.48
e) Cost of Carriage and Royalty of the materials
C.B. Brick 23cm × 12cm x 8cm 1.00 One cum 221.46 221.46
Sand 0.28 One cum 184.67 51.70
Cement 0.672 One Qntl. 5.50 3.69
Total = 276.85
Total (a+b+c+d+e)= 3672.92
Add 1% Labour cess = 36.72
Total = 3709.64
Say Rs. 3709.60 per Cum
Add for Super-structure = 33.00
Total = 3705.92
Add 1% Labour cess = 37.05
Total = 3742.97
Say Rs. 3743.00 per Cum
Below ground level beyond 1.5m. and upto 4.5m. Depth
(i) Basic rate of C.B. brick 3672.92
(ii) 15% extra on labour 239.83
(iii) Over Head Charge 7.5 % = 17.98
Contractor's Profit 7.5 % = 17.98
Sl. No. Description Qnty. Unit Rate Amount
3948.71
Add 1% Labour cess = 39.48
Total = 3988.19
Say Rs. 3988.20 per Cum
(B) First floor
(i) Basic rate = 3705.92
(ii) Add 15 % extra Labour = 239.83
Over Head Charge 7.5 % = = 17.98
Contractor's Profit 7.5 % = 17.98
Total = 3981.71
Add 1% Labour cess = 39.81
Total = 4021.52
Say Rs. 4021.50 per Cum
(C) 2nd floor
(i) Basic rate = 3981.71
(ii) Add 15 % extra Labour = 275.80
Over Head Charge 7.5 % = = 20.68
Contractor's Profit 7.5 % = 20.68
Total = 4298.87
Add 1% Labour cess = 42.98
Total = 4341.85
Say Rs. 4341.90 per Cum
(D) 3rd floor
(i) Basic rate = 4298.87
(ii) Add 15 % extra Labour = 317.17
Over Head Charge 7.5 % = = 23.78
Contractor's Profit 7.5 % = 23.78
Total = 4663.60
Add 1% Labour cess = 46.63
Total = 4710.23
Say Rs. 4710.20 per Cum
5 Brick work with Fly ash bricks 23cm x 11cm x 8cm size having crushing
strength not less than 75Kg/cm2 with dimensional tolerance ±8 percent in
cement mortar (1:6) in Foundation and Plinth including watering, curing,
cost, carriage, royalty and taxes of all materials, cost of all labour, T&P etc
complete as per the direction of E.I.C.

4 Brick work with Fly ash bricks 23cm x 11cm x 8cm size having crushing
strength not less than 75Kg/cm2 with dimensional tolerance ±8 percent in
cement mortar (1:6) in Superstructure including watering, curing, cost,
carriage, royalty and taxes of all materials, cost of all labour, T&P etc
complete as per the direction of E.I.C.

Ref :-A/R - 2006 ,P-71, Item No - 3


Data for 1 Cum.
a) Materials
Fly ash Brick 23cm × 11cm x 8cm 400.00 One cum 3.50600 1402.40
:400Nos. for Each.
Sand 0.28 One cum 50.48 14.13
Cement 0.672 One Qntl. 517.42 347.70
Total = 1764.23
b) Labour
Mason Special 0.35 Each 483.00 169.05
Mason Second class 1.05 Each 423.00 444.15
Man mulia 1.41 Each 333.00 469.53
Women mulia 1.41 Each 333.00 469.53
Man mulia for preparing mortar etc. 0.14 Each 333.00 46.62
Total = 1598.88
Over Head Charge 7.5 % = 252.23
Sl. No. Description Qnty. Unit Rate Amount
Contractor's Profit 7.5 % = 252.23
e) Cost of Carriage and Royalty of the materials
Fly ash Brick 23cm × 11cm x 8cm 1.00 One cum 163.26 163.26
Sand 0.28 One cum 184.67 51.70
Cement 0.672 One Qntl. 5.50 3.69
Total = 218.65
Total (a+b+c+d+e)= 4086.22
Add 1% Labour cess = 40.86
Total = 4127.08
Say Rs. 4127.10 per Cum
Add for Super-structure = 33.00
Total = 4119.22
Add 1% Labour cess = 41.19
Total = 4160.41
Say Rs. 4160.40 per Cum
Below ground level beyond 1.5m. and upto 4.5m. Depth
(i) Basic rate of C.B. brick 4086.22
(ii) 15% extra on labour 239.83
(iii) Over Head Charge 7.5 % = 17.98
Contractor's Profit 7.5 % = 17.98
4362.01
Add 1% Labour cess = 43.62
Total = 4405.63
Say Rs. 4405.60 per Cum
(B) First floor
(i) Basic rate = 4119.22
(ii) Add 15 % extra Labour = 239.83
Over Head Charge 7.5 % = = 17.98
Contractor's Profit 7.5 % = 17.98
Total = 4395.01
Add 1% Labour cess = 43.95
Total = 4438.96
Say Rs. 4439.00 per Cum
(C) 2nd floor
(i) Basic rate = 4395.01
(ii) Add 15 % extra Labour = 275.80
Over Head Charge 7.5 % = = 20.68
Contractor's Profit 7.5 % = 20.68
Total = 4712.17
Add 1% Labour cess = 47.12
Total = 4759.29
Say Rs. 4759.30 per Cum
(D) 3rd floor
(i) Basic rate = 4712.17
(ii) Add 15 % extra Labour = 317.17
Over Head Charge 7.5 % = = 23.78
Contractor's Profit 7.5 % = 23.78
Total = 5076.90
Add 1% Labour cess = 50.76
Total = 5127.66
Say Rs. 5127.70 per Cum
12 Brick work with Fly ash bricks 23cm x 11cm x 8cm size having crushing
strength not less than 75Kg/cm2 with dimensional tolerance ±8 percent in
cement mortar (1:4) in Foundation and Plinth including watering curing,
cost of carriage, royalty and taxes of all materials, cost of all labour, T&P
etc complete as per the direction of Engg-in -charge.

Ref :-A/R - 2006 ,P-71, Item No - 2


Data for 1 Cum.
Sl. No. Description Qnty. Unit Rate Amount
a) Materials
Fly ash Brick 23cm × 11cm x 8cm 400.00 One cum 3.510 1404.00
:400Nos. for Each.
Sand 0.28 One cum 50.48 14.13
Cement 1.00 One Qntl. 517.42 517.42
Total = 1935.55
b) Labour
Mason Special 0.35 Each 483.00 169.05
Mason Second class 1.05 Each 423.00 444.15
Man mulia 1.41 Each 333.00 469.53
Women mulia 1.41 Each 333.00 469.53
Man mulia for preparing mortar etc. 0.14 Each 333.00 46.62
Total = 1598.88
Over Head Charge 7.5 % = 265.08
Contractor's Profit 7.5 % = 265.08
d) Cost of Carriage and Royalty of the materials
Fly ash Brick 23cm × 11cm x 8cm 1.00 One cum 163.26 163.26
Sand 0.28 One cum 184.67 51.71
Cement 1.00 One Qntl. 5.50 5.50
Total = 220.47
Total (a+b+c+d+e)= 4285.06
Add 1% Labour cess = 42.85
Total = 4327.91
Say Rs. 4327.90 per Cum
Add for Super-structure = 33.00
Total = 4318.06
Add 1% Labour cess = 43.18
Total = 4361.24
Say Rs. 4361.20 per Cum
(B) First floor
(i) Basic rate = 4318.06
(ii) Add 15 % extra Labour = 239.83
Over Head Charge 7.5 % = = 17.98
Contractor's Profit 7.5 % = 17.98
Total = 4593.85
Add 1% Labour cess = 45.93
Total = 4639.78
Say Rs. 4639.80 per Cum
(C) 2nd floor
(i) Basic rate = 4593.85
(ii) Add 15 % extra Labour = 275.80
Over Head Charge 7.5 % = = 20.68
Contractor's Profit 7.5 % = 20.68
Total = 4911.01
Add 1% Labour cess = 49.11
Total = 4960.12
Say Rs. 4960.10 per Cum
Brick work with C.B. bricks 25cm x 12cm x 8cm/23cm x 11cm x 8cm size
having crushing strength not less than 35Kg/cm2 with dimensional
tolerance ±8 percent in cement mortar (1:6) in Foundation & Plinth
including all cost etc. complete but excluding cost of bricks.

Ref :-A/R - 2006 ,P-71, Item No - 3


Data for 1 Cum.
a) Materials
Sand 0.28 One cum 50.48 14.13
Cement 0.672 One Qntl. 517.42 347.70
Total = 361.83
b) Labour
Sl. No. Description Qnty. Unit Rate Amount
Mason Special 0.35 Each 483.00 169.05
Mason Second class 1.05 Each 423.00 444.15
Man mulia 1.41 Each 333.00 469.53
Women mulia 1.41 Each 333.00 469.53
Man mulia for preparing mortar etc. 0.14 Each 333.00 46.62
Total = 1598.88
Over Head Charge 7.5 % = 147.05
Contractor's Profit 7.5 % = 147.05
d) Cost of Carriage and Royalty of the materials
Sand 0.28 One cum 184.67 51.70
Cement 0.672 One Qntl. 5.50 3.69
Total = 55.39
Total (a+b+c+d)= 2310.20
Add 1% Labour cess = 23.10
Total = 2333.30
Say Rs. 2333.30 per Cum
Add for Super-structure = 33.00
Total = 2343.20
Add 1% Labour cess = 23.43
Total = 2366.63
Say Rs. 2366.60 per Cum
(B) First floor
(i) Basic rate = 2343.20
(ii) Add 15 % extra Labour = 239.83
Over Head Charge 7.5 % = = 17.98
Contractor's Profit 7.5 % = 17.98
Total = 2618.99
Add 1% Labour cess = 26.18
Total = 2645.17
Say Rs. 2645.20 per Cum
(C) 2nd floor
(i) Basic rate = 2618.99
(ii) Add 15 % extra Labour = 275.80
Over Head Charge 7.5 % = = 20.68
Contractor's Profit 7.5 % = 20.68
Total = 2936.15
Add 1% Labour cess = 29.36
Total = 2965.51
Say Rs. 2965.50 per Cum
14 Brick work with C.B. bricks 25cm x 12cm x 8cm size having crushing
strength not less than 35Kg/cm2 with dimensional tolerance ±8 percent in
clay in foundation and plinth including cost, carrige, royalty etc. complete.

Ref:- A/R - 2006 Item No. 6 Page No. 72


a) Material
C.B. Brick 25cm × 12cm x 8cm 350.00 One cum 2.481 868.35
:350Nos. for Each.
Clay mortar 0.32 One cum 51.43 16.45
Total = 884.80
b) Labour
Mason 2nd class 1.05 No. Each 423.00 444.15
Man mulia 1.05 No. Each 333.00 349.65
women mulia 1.05 No. Each 333.00 349.65
Total = 1143.45
Over Head Charge 7.5 % = 152.11
Contractor's Profit 7.5 % = 152.11
e) Cost of Carriage and Royalty of Materials
C.B. Brick 25cm × 12cm x 8cm 1.00 One cum #NAME? #NAME?
Sl. No. Description Qnty. Unit Rate Amount
Clay 0.32 One cum 184.67 59.09
Total = #NAME?
Total (a+b+c+d+e)= #NAME?
Add 1% Labour cess = #NAME?
Total = #NAME?
Say Rs. #NAME? per Cum
Add for Super-structure = 33.00
Total = #NAME?
Add 1% Labour cess = #NAME?
Total = #NAME?
Say Rs. #NAME? per Cum
14 Brick work with K.B. bricks 25cm x 12cm x 8cm size having crushing
strength not less than 35Kg/cm2 with dimensional tolerance ±8 percent in
clay in foundation and plinth including cost, carrige, royalty etc. complete.

Ref:- A/R - 2006 Item No. 6 Page No. 72


a) Material
K.B. Brick 25cm × 12cm x 8cm 350.00 One cum 3.500 1225.00
:350Nos. for Each.
Clay mortar 0.32 One cum 51.43 16.45
Total = 1241.45
b) Labour
Mason 2nd class 1.05 No. Each 423.00 444.15
Man mulia 1.05 No. Each 333.00 349.65
women mulia 1.05 No. Each 333.00 349.65
Total = 1143.45
Over Head Charge 7.5 % = 178.86
Contractor's Profit 7.5 % = 178.86
e) Cost of Carriage and Royalty of Materials
K.B. Brick 25cm × 12cm x 8cm 1.00 One cum 221.51 221.51
Clay 0.32 One cum 184.67 59.09
Total = 280.60
Total (a+b+c+d+e)= 3023.22
Add 1% Labour cess = 30.23
Total = 3053.45
Say Rs. 3053.50 per Cum
Add for Super-structure = 33.00
Total = 3056.22
Add 1% Labour cess = 30.56
Total = 3086.78
Say Rs. 3086.80 per Cum
15 Random Rubble H.G. stone Masonry in cement mortar (1:6) in foundation
and plinth including watering, curing, cost, carriage, royalty and taxes of all
materials, cost of all labour, T&P etc complete as per the direction of E.I.C.

Ref :-A/R - 2006 ,P-75, Item No - 3


Data for 1 Cum.
a) Materials
Rough stone granite quarried including bond stones. 1.00 One Cum 212.23 212.23
Sand 0.34 One Cum 50.48 17.16
Cement 0.8151 One Qntl. 517.42 421.74
Total = 651.13
b) Labour
Man mulia for preparing mortar etc. 0.35 Each 333.00 116.55
Mason Special 0.35 Each 483.00 169.05
Mason Second class 1.41 Each 423.00 596.43
Women mulia 1.41 Each 333.00 469.53
Man mulia 1.41 Each 333.00 469.53
Sl. No. Description Qnty. Unit Rate Amount
Total = 1821.09
Over Head Charge 7.5 % = 185.41
Contractor's Profit 7.5 % = 185.41
d) Cost of Carriage and Royalty of the materials
Rough stone granite quarried including bond stones. 1.00 One Cum 719.21 719.21
Sand 0.34 One Cum 184.67 62.78
Cement 0.8151 One Qntl. 5.50 4.48
Total = 786.47
Total (a+b+c+d)= 3629.51
Add 1 % Labour Cess = 36.29
Total= 3665.80
Say Rs. 3665.80 per Cum.
Add for Super-structure = 41.90
Total = 3671.41
Add 1 % Labour Cess = 36.71
Total= 3708.12
Say Rs. 3708.10 per Cum
6 Providing M.S. reinforcement for R.C.C. work including cutting, bending,
binding and tying the grills and placing in position including cost of binding
wire 18 to 20 gauge and cost and carriage of steel. etc. complete.

(A.R.-2006, Page No - 52, Item No. - 9)


a) Materials
Cost of rods including 5 % overlapping and wastage 1.05 M.T. 0.00
Binding wire 8.00 Kg. 67.23 537.84
Total = 537.84
b) Labour
Mate 0.44 Each 373.00 164.12
Black smith special 3.00 Each 483.00 1449.00
Mulia 8.00 Each 333.00 2664.00
Total = 4277.12
Over Head Charge 7.5 % = 361.12
Contractor's Profit 7.5 % = 361.12
e) Cost of Carriage and Royalty of Materials
Rods 1.05 M.T. 0.00 0.00
Total= 0.00
Total =(a+b+c+d+e) = Rs. 5537.20
Total= 553.72
Add 1% Labour cess = 5.53
Total = 559.25
Say Rs. 559.30 per Qntl
(B) First floor
(i) Basic rate = 553.72
(ii) Add 5 % extra Labour = 21.38
Over Head Charge 7.5 % = 1.60
Contractor's Profit 7.5 % = 1.60
Total = 578.30
Add 1% Labour cess = 5.78
Total = 584.08
Say Rs. 584.10 per Qntl
(C) 2nd floor
(i) Basic rate = 578.30
(ii) Add 5 % extra Labour = 22.44
Over Head Charge 7.5 % = 1.68
Contractor's Profit 7.5 % = 1.68
Total = 604.10
Add 1% Labour cess = 6.04
Total = 610.14
Say Rs. 610.10 per Qntl
Sl. No. Description Qnty. Unit Rate Amount
5 12mm thick C.P. in C.M.(1:6) over brick masonary to the smooth surface
including watering, curing, cost, carriage, royalty and taxes of all materials,
cost of all labour, T&P etc complete as per the direction of E.I.C.

Ref :-A/R - 2006 ,P- 103, Item No - 4


a) Materials
Sand 0.015 One Cum 50.48 0.75
Cement 0.0358 One Qntl. 517.42 18.52
Total = 19.27
b) Labour
Man mulia 0.02 Each 333.00 6.66
Mason Second class 0.14 Each 423.00 59.22
Man mulia 0.05 Each 333.00 16.65
Women mulia 0.05 Each 333.00 16.65
Total = 99.18
Over Head Charge 7.5 % = 8.88
Contractor's Profit 7.5 % = 8.88
e) Cost of Carriage and Royalty of Materials
Sand 0.015 One Cum 184.67 2.77
Cement 0.0358 One Qntl. 5.50 0.19
Total = 2.96
Total (a+b+c+d+e) = 139.17
Add 1% Labour cess = 1.39
Total = 140.56
Say Rs. 140.60 per Sqm.
First floor
(i) Basic rate 139.17
(ii) 5% extra on labour 4.95
(iii) Over Head Charge 7.5 % = 0.37
Contractor's Profit 7.5 % = 0.37
144.86
Add 1% Labour cess = 1.44
Total = 146.30
Say Rs. 146.30 per Cum
2nd floor
(i) Basic rate 144.86
(ii) 5% extra on labour 5.19
(iii) Over Head Charge 7.5 % = 0.38
Contractor's Profit 7.5 % = 0.38
150.81
Add 1% Labour cess = 1.50
Total = 152.31
Say Rs. 152.30 per Cum
6 16mm thick C.P. in C.M.(1:6) over brick masonary to the rough surface
including watering, curing cost, carriage, royalty, and taxes of all materials,
cost of all labour, T&P etc complete as per the direction of E.I.C.

Ref :-A/R - 2006 ,P- 105, Item No - 14


a) Materials
Sand 0.018 One Cum 50.48 0.90
Cement 0.043 One Qntl. 517.42 22.24
Total = 23.14
b) Labour
Man mulia 0.02 Each 333.00 6.66
Mason Second class 0.16 Each 423.00 67.68
Man mulia 0.11 Each 333.00 36.63
Women mulia 0.11 Each 333.00 36.63
Total = 147.60
Over Head Charge 7.5 % = 12.80
Sl. No. Description Qnty. Unit Rate Amount
Contractor's Profit 7.5 % = 12.80
e) Cost of Carriage and Royalty of Materials
Sand 0.018 One Cum 184.67 3.32
Cement 0.043 One Qntl. 5.50 0.23
Total = 3.55
Total (a+b+c+d+e) = 199.89
Add 1% Labour cess = 1.99
Total = 201.88
Say Rs. 201.90 per Sqm.
First floor
(i) Basic rate 199.89
(ii) 3% extra on labour 4.42
(iii) Over Head Charge 7.5 % = 0.33
Contractor's Profit 7.5 % = 0.33
204.97
Add 1% Labour cess = 2.04
Total = 207.01
Say Rs. 207.00 per Sqm.
2nd floor
(i) Basic rate 204.97
(ii) 3% extra on labour 4.55
(iii) Over Head Charge 7.5 % = 0.34
Contractor's Profit 7.5 % = 0.34
210.20
Add 1% Labour cess = 2.10
Total = 212.30
Say Rs. 212.30 per Sqm.
19 12 mm thick C.P. in C.M.(1:4) over brick masonary to the smooth surface
including curing cost of carriage, royalty, and taxes of all materials, cost of
all labour, T&P etc complete as per the direction of Engg-in -charge.

Ref :-A/R - 2006 ,P- 106, Item No - 16


a) Materials
Sand 0.015 One Cum 50.48 0.75
Cement 0.0543 One Qntl. 517.42 28.09
Total = 28.84
b) Labour
Man mulia 0.12 Each 333.00 39.96
Mason Second class 0.14 Each 423.00 59.22
Total = 99.18
Over Head Charge 7.5 % = 9.60
Contractor's Profit 7.5 % = 9.60
e) Cost of Carriage and Royalty of Materials
Sand 0.015 One Cum 184.67 2.77
Cement 0.0543 One Qntl. 5.50 0.29
Total = 3.06
Total (a+b+c+d+e) = 150.28
Add 1% Labour cess = 1.50
Total = 151.78
Say Rs. 151.80 per Sqm.
First floor
(i) Basic rate 150.28
(ii) 3% extra on labour 2.97
(iii) Over Head Charge 7.5 % = 0.22
Contractor's Profit 7.5 % = 0.22
153.69
Add 1% Labour cess = 1.53
Total = 155.22
Say Rs. 155.20 per Sqm
Sl. No. Description Qnty. Unit Rate Amount
2nd floor
(i) Basic rate 153.69
(ii) 3% extra on labour 3.05
(iii) Over Head Charge 7.5 % = 0.22
Contractor's Profit 7.5 % = 0.22
157.18
Add 1% Labour cess = 1.57
Total = 158.75
Say Rs. 158.80 per Sqm.
8 20mm thick C.P. in C.M.(1:6) over brick masonary to the rough surface
including watering, curing cost, carriage, royalty, and taxes of all materials,
cost of all labour, T&P etc complete as per the direction of E.I.C.

Ref :-A/R - 2006 ,P- 103, Item No - 8


a) Materials
Sand 0.021 One Cum 50.48 1.06
Cement 0.057 One Qntl. 517.42 29.49
Total = 30.55
b) Labour
Man mulia 0.02 Each 333.00 6.66
Mason Second class 0.16 Each 423.00 67.68
Man mulia 0.11 Each 333.00 36.63
Women mulia 0.11 Each 333.00 36.63
Total = 147.60
Over Head Charge 7.5 % = 13.36
Contractor's Profit 7.5 % = 13.36
e) Cost of Carriage and Royalty of Materials
Sand 0.021 One Cum 184.67 3.87
Cement 0.057 One Qntl. 5.50 0.31
Total = 4.18
Total (a+b+c+d+e) = 209.05
Add 1% Labour cess = 2.09
Total = 211.14
Say Rs. 211.10 per Sqm.
First floor
(i) Basic rate 209.05
(ii) 3% extra on labour 4.42
(iii) Over Head Charge 7.5 % = 0.33
Contractor's Profit 7.5 % = 0.33
214.13
Add 1% Labour cess = 2.14
Total = 216.27
Say Rs. 216.30 per Sqm.
2nd floor
(i) Basic rate 214.13
(ii) 3% extra on labour 4.55
(iii) Over Head Charge 7.5 % = 0.34
Contractor's Profit 7.5 % = 0.34
219.36
Add 1% Labour cess = 2.19
Total = 221.55
Say Rs. 221.60 per Sqm.
20 12mm thick C.P. in C.M.(1:4) over brick masonary to the smooth surface
with neat cement punning including watering curing, cost, carriage, royalty,
and taxes of all materials, cost of all labour, T&P etc complete as per the
direction of Engg-in -charge.
Ref :-A/R - 2006 ,P- 103, Item No - 6
a) Materials
Sand 0.015 One Cum 50.48 0.75
Sl. No. Description Qnty. Unit Rate Amount
Cement 0.0644 One Qntl. 517.42 33.32
Total = 34.07
b) Labour
Man mulia 0.11 Each 333.00 36.63
Mason Second class 0.15 Each 423.00 63.45
Total = 100.08
Over Head Charge 7.5 % = 10.06
Contractor's Profit 7.5 % = 10.06
d) Cost of Carriage and Royality of Materials
Sand 0.015 One Cum 184.67 2.77
Cement 0.0644 One Qntl. 5.50 0.35
Total = 3.12
Total (a+b+c+d+e) = 157.39
Add 1% Labour cess = 1.57
Total = 158.96
Say Rs. 159.00 per Sqm
(B) First floor
(i) Basic rate = 157.39
(ii) Add 3 % extra Labour = 3.00
(iii) Over Head Charge 7.5 % = 0.22
Contractor's Profit 7.5 % = 0.22
Total = 160.83
Add 1% Labour cess = 1.60
Total = 162.43
Say Rs. 162.40 per Sqm
2nd floor
(i) Basic rate 160.83
(ii) 3% extra on labour 3.09
(iii) Over Head Charge 7.5 % = 0.23
Contractor's Profit 7.5 % = 0.23
164.38
Add 1% Labour cess = 1.64
Total = 166.02
Say Rs. 166.00 per Sqm.
9 6 mm thick cement plaster (1:4) to RCC surfaces finished smooth including
closed deep chiping and slury treatment , watering, curing cost, carriage,
royalty, and taxes of all materials, cost of all labour, T&P etc complete as
per the direction of E.I.C.
Per 1 Sqm
a) Materials
Sand(Screened & Washed) 0.0075 Cum. 50.48 0.37
Cement 0.0372 Qntl 517.42 19.24
Total 19.61
b) Labour
Mulia 0.120 Each 333.00 39.96
Mason Second class 0.140 Each 423.00 59.22
Labour for closed deep chipping & cleaning (Man Mulia) 0.050 Nos Each 333.00 16.65
Total = 115.83
Over Head Charge 7.5 % = 10.15
Contractor's Profit 7.5 % = 10.15
d) Cost of Carriage and Royality of Materials
Sand 0.0075 One Cum 184.67 1.38
Cement 0.0372 One Qntl. 5.50 0.20
Total = 1.58
Total (a+b+c+d+e) = 157.32
Add 1% Labour cess = 1.57
Total = 158.89
Say Rs. 158.90 per Sqm.
(B) First floor
Sl. No. Description Qnty. Unit Rate Amount
(i) Basic rate = 157.32
(ii) Add 3 % extra Labour = 3.47
(iii) Over Head Charge 7.5 % = 0.26
Contractor's Profit 7.5 % = 0.26
Total = 161.31
Add 1% Labour cess = 1.61
Total = 162.92
Say Rs. 162.90 per Sqm
2nd floor
(i) Basic rate 161.31
(ii) 3% extra on labour 3.57
(iii) Over Head Charge 7.5 % = 0.26
Contractor's Profit 7.5 % = 0.26
165.40
Add 1% Labour cess = 1.65
Total = 167.05
Say Rs. 167.10 per Sqm.
107 20 mm thick C.P. in C.M.(1:4) over concrete surface to the smooth surface
including curing cost of carriage, royalty, and taxes of all materials, cost of
all labour, T&P etc complete as per the direction of Engg-in -charge.

(A.R.-2006, Page No - 106, Item No. - 17)


a) Materials
Sand (Screened and washed) 0.021 Cum 50.48 1.06
Cement 0.0744 Qntl 517.42 38.49
Total = 39.55
b) Labour
Man mulia for mixing sand and cement in small quantities and watering 0.02 No 333.00 6.66

Mason 0.16 No 423.00 67.68


Man mulia 0.11 No 333.00 36.63
Women mulia 0.11 No 333.00 36.63
Total = 147.60
Over Head Charge 7.5 % = 14.03
Contractor's Profit 7.5 % = 14.03
Total (a+b+c) = 215.21
d) Cost carriage royalty
Sand (Screened and washed) 0.021 Cum 184.67 3.87
Cement 0.0744 Qntl 5.50 0.40
Total = 4.27
Total (a+b+c+d) = 219.48
Add 1 % Labour Cess = 2.19
Total= 221.67
Say Rs. 221.70 per Sqm.
22 Labour charges for fitting glass strips in joints of marble chips flooring / A.S.
flooring including cost of glass strips, cost of all materials, labour etc
complete.
(A.R.-2006, Page No - 89, Item No. - 15)
Data for 10.00 mtrs.
a) Labour
Mason Second class 0.25 Each 423.00 105.75
Mulia 0.25 Each 333.00 83.25
Total = 189.00
Over Head Charge 7.5 % = 14.17
Contractor's Profit 7.5 % = 14.17
Total = 217.34
d) Materials For 1 Rm. = 21.73
Glass strips 5 mm (Plain) 0.100 Rmt 443.40 44.34
Total= 66.07
Sl. No. Description Qnty. Unit Rate Amount
Add 1% Labour cess = 0.66
Total = 66.73
Say Rs. 66.70 per Rmt
23 Labour charges for fitting 4mm thick ply wood in joints of concrete road
including cost of ply wood, cost of all labour etc complete.
(A.R.-2006, Page No - 89, Item No. - 15)
Data for 10.00 mtrs.
a) Labour
Mason Second class 0.25 Each 423.00 105.75
Mulia 0.25 Each 333.00 83.25
Total = 189.00
Over Head Charge 7.5 % = 14.17
Contractor's Profit 7.5 % = 14.17
Total = 217.34
d) Materials For 1 Rm. = 21.73
Play wood (4mm thick) 0.050 Rmt 293.62 14.68
Total= 36.41
Add 1% Labour cess = 0.36
Total = 36.77
Say Rs. 36.80 per Rmt
24 10cm thick C.B. bricks khoa well water and rammed to recive A.S. flooring
including water, curing, cost, carriage, royalty & taxes of all materials,
labour, T&P etc. complete.
Ref :-A/R - 2006 ,P-86, Item No - 9
Data for 1 Sqm.
a) Materials
C.B. Brick khoa 0.14 One cum 228.09 31.93
Total = 31.93
b) Labour
Mason Second class 0.05 Each 423.00 21.15
Man mulia 0.38 Each 333.00 126.54
Total = 147.69
Over Head Charge 7.5 % = 13.47
Contractor's Profit 7.5 % = 13.47
d) Cost of Carriage and Royalty of the materials
C.B. Brick khoa 0.14 One cum 228.67 32.01
Total = 32.01
Total (a+b+c+d)= 238.57
Add 1% Labour cess = 2.38
Total = 240.95
Say Rs. 241.00 per Sqm.
6 2.5cm thick A.S. flooring with cement concrete (1:2:4) using 12mm size
C.B. chips including curing, cost, carriage, royalty and taxes of all
materials, cost of all labour, T&P etc complete as per the direction of E.I.C.

(A.R.-2006, Page No - 84, Item No. - 2)


a) Materials
12mm size Granite C.B. metal 0.023 Cum. 1045.71 24.05
Sand 0.012 Cum. 50.48 0.60
Cement 0.0858 Qntl 517.42 44.39
Total = 69.04
b) Labour
Man mulia for mixing chips cement and sand in small quantity and watering 0.03 Each 333.00 9.99

Mason Special 0.13 Each 483.00 62.79


Mulia 0.22 Each 333.00 73.26
Mulia 0.11 Each 333.00 36.63
Total = 182.67
Over Head Charge 7.5 % = 18.87
Sl. No. Description Qnty. Unit Rate Amount
Contractor's Profit 7.5 % = 18.87
d) Cost of Carriage and Royalty of Materials
12mm size Granite C.B. metal 0.023 Cum. 719.21 16.54
Sand 0.012 Cum. 184.67 2.21
Cement 0.0858 Qntl 5.50 0.47
Total= 19.22
Total =(a+b+c+d) = Rs. 308.67
Add 1% Labour cess = 3.08
Total = 311.75
Say Rs. 311.80 per Sqm
1st floor:-
Basic Rate: = 308.67
(ii) Add 5 % extra labour 9.13
Over Head Charge 7.5 % = 0.68
Contractor's Profit 7.5 % = 0.68
Total= 319.16
Add 1% Labour cess = 3.19
Total = 322.35
Say Rs. 322.40 per Sqm.
2nd floor:-
Basic Rate: = 319.16
(ii) Add 5 % extra labour 9.58
Over Head Charge 7.5 % = 0.71
Contractor's Profit 7.5 % = 0.71
Total= 330.16
Add 1% Labour cess = 3.30
Total = 333.46
Say Rs. 333.50 per Sqm.
8 2.5cm thick grading concrete (1:2:2) on roof slab with 6mm size hard
crusher broken granite chips on new work including watering curing cost of
all materials, water-proofing compounds, T.& P. required for the works etc
complete.
(A.R.-2006, Page No - 47, Item No. - 17)
a) Materials
6mm size Granite C.B. metal 0.0169 Cum. 728.57 12.31
Sand 0.0169 Cum. 50.48 0.85
Cement 0.1208 Qntl 517.42 62.50
Water proofing compounds 0.2416 Kg. 30.00 7.24
Total = 82.90
b) Labour
Man mulia for mixing chips cement and sand in small quantity and watering 0.03 Each 333.00 9.99

Mason Special 0.10 Each 483.00 48.30


Mulia 0.33 Each 333.00 109.89
Total = 168.18
Over Head Charge 7.5 % = 18.83
Contractor's Profit 7.5 % = 18.83
d) Cost of Carriage and Royalty of Materials
6mm size Granite C.B. metal 0.0169 Cum. 719.21 12.15
Sand 0.0169 Cum. 184.67 3.12
Cement 0.1208 Qntl 5.50 0.66
Total= 15.93
Total =(a+b+c+d+e) = Rs. 304.67
Add 1% Labour cess = 3.04
Total = Rs 307.71
Say Rs. 307.70 per Sqm.
1st floor:-
Basic Rate: = 304.67
(ii) Add 15 % extra labour 25.22
Sl. No. Description Qnty. Unit Rate Amount
Over Head Charge 7.5 % = 1.89
Contractor's Profit 7.5 % = 1.89
Total= 333.67
Add 1% Labour cess = 3.33
Total = 337.00
Say Rs. 337.00 per Sqm.
2nd floor:-
Basic Rate: = 333.67
(ii) Add 15 % extra labour 29.00
Over Head Charge 7.5 % = 2.17
Contractor's Profit 7.5 % = 2.17
Total= 367.01
Add 1% Labour cess = 3.67
Total = 370.68
Say Rs. 370.70 per Sqm.
7 4cm thick grading concrete (1:2:4) on roof slab with 12mm & down graded
size hard crusher broken granite chips on old work including watering
curing cost of all materials, water-proofing compounds, wire mesh T.& P.
required for the works etc complete.

(A.R.-2006, Page No - 48, Item No. - 18)


a) Materials
12mm size Granite C.B. metal 0.018 Cum. 1045.71 18.82
4.7mm size Granite C.B. metal 0.018 Cum. 664.76 11.96
Sand 0.018 Cum. 50.48 0.90
Cement 0.1287 Qntl 517.42 66.59
Water proofing compounds 0.2574 Kg. 30.00 7.72
Chicken wire mesh 1.05 Sqm 32.50 34.12
Total = 140.11
b) Labour
Man mulia for mixing chips cement and sand in small quantity and watering 0.528 Each 333.00 175.82

Mason Special 0.165 Each 483.00 79.69


Mulia 0.48 Each 333.00 159.84
Total = 415.35
Over Head Charge 7.5 % = 41.65
Contractor's Profit 7.5 % = 41.65
e) Cost of Carriage and Royalty of Materials
12mm size Granite C.B. metal 0.018 Cum. 719.21 12.94
4.7mm size Granite C.B. metal 0.018 Cum. 719.21 12.94
Sand 0.018 Cum. 184.67 3.32
Cement 0.1287 Qntl 5.50 0.70
Total= 29.90
Total =(a+b+c+d+e) = Rs. 668.66
Add 1% Labour cess = 6.68
Total = Rs 675.34
Say Rs. 675.30 per Sqm.
1st floor:-
Basic Rate: = 668.66
(ii) Add 15 % extra labour 62.30
Over Head Charge 7.5 % = 4.67
Contractor's Profit 7.5 % = 4.67
Total= 740.30
Add 1% Labour cess = 7.40
Total = Rs 747.70
Say Rs. 747.70 per Sqm.
2nd floor:-
Basic Rate: = 740.30
(ii) Add 15 % extra labour 71.64
Sl. No. Description Qnty. Unit Rate Amount
Over Head Charge 7.5 % = 5.37
Contractor's Profit 7.5 % = 5.37
Total= 822.68
Add 1% Labour cess = 8.22
Total = 830.90
Say Rs. 830.90 per Sqm.
10 2.5 cm. Damp proof course with C.C. (1:2:4) using 12mm. Size hard broken
granite Chips of approved quality from approved quarry including watering,
curing, cost, carraige, royalty & taxes of all materials, cost of all labour,
T&P etc. complete.
A/R - 2006 Page No. - 91 Item - 20
Data for 1 Sqm
a) Material
12mm. Size granite chips 0.023 Cum. 1045.71 24.05
Sand 0.012 Cum. 50.48 0.60
Cement 0.0754 Qntl 517.42 39.01
Total = 63.66
b) Labour
Man Mulia 0.36 Each 333.00 119.88
Mason special 0.1030 Each 483.00 49.74
Total = 169.62
Over Head Charge 7.5 % = 17.49
Contractor's Profit 7.5 % = 17.49
d) Cost of Carriage and Royalty of the materials
12mm. Size granite chips 0.023 Cum. 719.21 16.54
Sand 0.012 One cum 184.67 2.21
Cement 0.0754 One Qntl. 5.50 0.41
Total = 19.16
Total (a+b+c+d)= 287.42
Add 1% Labour cess = 2.87
Total = Rs 290.29
Say Rs. 290.30 per Sqm.
6 Priming 1 coat with wall primer water bond cement primer including all
labour, materials, T&P etc. complete.
Ref :-A/R - 2006 ,P - 93, Item No- 1
Data for 9.3 Sqm.
a) Labour
Painter Special 0.50 Each 483.00 241.50
Man mulia for preparation of surface. 0.50 Each 333.00 166.50
Total= 408.00
Over Head Charge 7.5 % = 30.60
Contractor's Profit 7.5 % = 30.60
Total= 469.20
For 1 Sqm= 469.20 9.30 50.45
Add cost of wall primer = (0.840 x 118.11)/10 = 9.92
Total= 60.37
Add 1% Labour cess = 0.60
Total = 60.97
Say Rs. 61.00 per Sqm.
1st floor:-
Basic Rate: = 60.37
(ii) Add 5 % extra labour 2.19
Over Head Charge 7.5 % = 0.16
Contractor's Profit 7.5 % = 0.16
Total= 62.88
Add 1% Labour cess = 0.62
Total = 63.50
Say Rs. 63.50 per Sqm.
2nd floor:-
Sl. No. Description Qnty. Unit Rate Amount
Basic Rate: = 62.88
(ii) Add 5 % extra labour 2.30
Over Head Charge 7.5 % = 0.17
Contractor's Profit 7.5 % = 0.17
Total= 65.52
Add 1% Labour cess = 0.65
Total = 66.17
Say Rs. 66.20 per Sqm.
3rd floor:-
Basic Rate: = 65.52
(ii) Add 5 % extra labour 2.41
Over Head Charge 7.5 % = 0.18
Contractor's Profit 7.5 % = 0.18
Total= 68.29
Add 1% Labour cess = 0.68
Total = 68.97
Say Rs. 69.00 per Sqm.
4th floor:-
Basic Rate: = 68.29
(ii) Add 5 % extra labour 2.53
Over Head Charge 7.5 % = 0.18
Contractor's Profit 7.5 % = 0.18
Total= 71.18
Add 1% Labour cess = 0.71
Total = 71.89
Say Rs. 71.90 per Sqm.
7 Painting 2 coats with any approved paint in iron works including sand
papering, polishing surfaces, cost of paints, cost of all labour, T&P, etc
complete in all floors as per direction of E.I.C.
Ref :-A/R - 2006 ,P - 93, Item No-3
Data for 9.30 Sqm.
a) Labour
Painter Special 1.25 Each 483.00 603.75
Man mulia 1.00 Each 333.00 333.00
Man mulia for preparation of surface. 0.10 Each 333.00 33.30
Total= 970.05
Over Head Charge 7.5 % = 72.75
Contractor's Profit 7.5 % = 72.75
Total= 1115.55
For 1 Sqm= 1115.55 9.30 119.95
Add cost of Enamel paint =1.25 x 151.97/10= 18.99
Total= 138.94
Add 1% Labour cess = 1.38
Total = 140.32
Say Rs. 140.30 per Sqm
1st floor:-
Basic Rate: = 138.94
(ii) Add 3 % extra labour 3.12
Over Head Charge 7.5 % = 0.23
Contractor's Profit 7.5 % = 0.23
Total= 142.52
Add 1% Labour cess = 1.42
Total = 143.94
Say Rs. 143.90 per Sqm
2nd floor:-
Basic Rate: = 142.52
(ii) Add 3 % extra labour 3.21
Over Head Charge 7.5 % = 0.24
Contractor's Profit 7.5 % = 0.24
Sl. No. Description Qnty. Unit Rate Amount
Total= 146.21
Add 1% Labour cess = 1.46
Total = 147.67
Say Rs. 147.70 per Sqm
29 Painting 1 coat with any approved paint in iron works including sand
papering, polishing surfaces, cost of paints, cost of all labour, T&P, etc
complete in all floors as per direction of E.I.C.
Ref :-A/R - 2006 ,P - 93, Item No-2
Data for 9.30 Sqm.
a) Labour
Painter Special 0.75 Each 483.00 362.25
Man mulia 0.75 Each 333.00 249.75
Man mulia for preparation of surface. 0.07 Each 333.00 23.31
Total= 635.31
Over Head Charge 7.5 % = 47.64
Contractor's Profit 7.5 % = 47.64
Total= 730.59
For 1 Sqm= 730.59 9.30 78.55
Add cost of Enamel paint =0.75 x 151.97/10= 11.39
Total= 89.94
Add 1% Labour cess = 0.89
Total = 90.83
Say Rs. 90.80 per Sqm
1st floor:-
Basic Rate: = 89.94
(ii) Add 3 % extra labour 2.04
Over Head Charge 7.5 % = 0.15
Contractor's Profit 7.5 % = 0.15
Total= 92.28
Add 1% Labour cess = 0.92
Total = 93.20
Say Rs. 93.20 per Sqm
2nd floor:-
Basic Rate: = 92.28
(ii) Add 3 % extra labour 2.10
Over Head Charge 7.5 % = 0.15
Contractor's Profit 7.5 % = 0.15
Total= 94.68
Add 1% Labour cess = 0.94
Total = 95.62
Say Rs. 95.60 per Sqm
8 Wall painting 2 coats with plastic emulsion paint of approved shade on new
work to give an even shade including cost of paint etc complete.

Ref :-A/R - 2006 ,P - 99, Item No-20


Data for 10 Sqm.
a) Labour
Painter Special 0.54 Each 483.00 260.82
Man mulia 0.54 Each 333.00 179.82
Man mulia for preparation of surface. 0.10 Each 333.00 33.30
Total= 473.94
Over Head Charge 7.5 % = 35.54
Contractor's Profit 7.5 % = 35.54
Total= 545.02
For 1 Sqm= 545.02 10.00 54.50
Add cost of plastic emulsion paint =1.25 x 196.06/10= 24.50
Total= 79.00
Add 1% Labour cess = 0.79
Total = 79.79
Sl. No. Description Qnty. Unit Rate Amount
Say Rs. 79.80 per Sqm
1st floor:-
Basic Rate: = 79.00
(ii) Add 3 % extra labour 1.42
Over Head Charge 7.5 % = 0.10
Contractor's Profit 7.5 % = 0.10
Total= 80.62
Add 1% Labour cess = 0.80
Total = 81.42
Say Rs. 81.40 per Sqm
2nd floor:-
Basic Rate: = 80.62
(ii) Add 3 % extra labour 1.46
Over Head Charge 7.5 % = 0.10
Contractor's Profit 7.5 % = 0.10
Total= 82.28
Add 1% Labour cess = 0.82
Total = 83.10
Say Rs. 83.10 per Sqm
3rd floor:-
Basic Rate: = 82.28
(ii) Add 3 % extra labour 1.50
Over Head Charge 7.5 % = 0.11
Contractor's Profit 7.5 % = 0.11
Total= 84.00
Add 1% Labour cess = 0.84
Total = 84.84
Say Rs. 84.80 per Sqm
4th floor:-
Basic Rate: = 84.00
(ii) Add 3 % extra labour 1.55
Over Head Charge 7.5 % = 0.11
Contractor's Profit 7.5 % = 0.11
Total= 85.77
Add 1% Labour cess = 0.85
Total = 86.62
Say Rs. 86.60 per Sqm
31 Finishing walls with water proofing cement paint of approved shade on new
work 1 coat to give an even shade including curing, cost of cement paint,
cost of all labour, over in all floors as per the direction of Engineer - in -
charge.T&P, etc complete
Ref :-A/R - 2006 ,P - 98, Item No-17
Data for 10 Sqm.
a) Labour
Painter Special 0.15 Each 483.00 72.45
Man mulia 0.22 Each 333.00 73.26
Total= 145.71
Over Head Charge 7.5 % = 10.92
Contractor's Profit 7.5 % = 10.92
Total= 167.55
For 1 Sqm= 167.55 10.00 16.75
Add cost of Cement paint =1.66 x 36.22/10= 6.01
Total= 22.76
Add 1% Labour cess = 0.22
Total = 22.98
Say Rs. 23.00 per Sqm.
Sl. No. Description Qnty. Unit Rate Amount
13 Finishing walls with water proofing cement paint of approved shade on new
work 2 coats to give an even shade including curing cost of cement paint,
cost of all labour, in all floors as per the direction of E.I.C..T&P, etc
complete.
Ref :-A/R - 2006 ,P - 98, Item No-18
Data for 10 Sqm.
a) Labour
Painter Special 0.22 Each 483.00 106.26
Man mulia 0.22 Each 333.00 73.26
Man mulia for preparation of surface. 0.10 Each 333.00 33.30
Total= 212.82
Over Head Charge 7.5 % = 15.96
Contractor's Profit 7.5 % = 15.96
Total= 244.74
For 1 Sqm= 244.74 10.00 24.47
Add cost of Cement paint =2.5 x 36.22/10= 9.05
Total= 33.52
Add 1% Labour cess = 0.33
Total = 33.85
Say Rs. 33.90 per Sqm
1st floor:-
Basic Rate: = 33.52
(ii) Add 5 % extra labour 1.06
Over Head Charge 7.5 % = 0.07
Contractor's Profit 7.5 % = 0.07
Total= 34.72
Add 1% Labour cess = 0.34
Total = 35.06
Say Rs. 35.10 per Sqm
2nd floor:-
Basic Rate: = 34.72
(ii) Add 5 % extra labour 1.11
Over Head Charge 7.5 % = 0.08
Contractor's Profit 7.5 % = 0.08
Total= 35.99
Add 1% Labour cess = 0.35
Total = 36.34
Say Rs. 36.30 per Sqm
33 Cement washing two coats including curing cost of all labours and cost of
all materials etc complete as per the direction of Engineer - in - charge.

Ref :-A/R - 2006 ,P - 113, Item No-41


Data for 93 Sqm.
a) Materials
Cement 1.5015 Qntl 517.42 776.90
Total= 776.90
b) Labour
Painter Second class 1.00 Each 423.00 423.00
Man mulia 0.75 Each 333.00 249.75
Man mulia for preparation of surface. 0.88 Each 333.00 293.04
Total= 965.79
Over Head Charge 7.5 % = 130.70
Contractor's Profit 7.5 % = 130.70
d) Cost of Carriage and Royality of Materials
Cement 1.5015 Qntl 5.50 8.25
Total= 2012.34
For 1 Sqm= 2012.34 93.00 21.63
Add 1% Labour cess = 0.21
Total = 21.84
Sl. No. Description Qnty. Unit Rate Amount
Say Rs. 21.80 per Sqm.
34 Priming 1 coat with wood primer including all labour, materials, T&P etc.
complete.
Ref :-A/R - 2006 ,P - 93, Item No- 1
Data for 9.3 Sqm.
a) Labour
Painter Special 0.50 Each 483.00 241.50
Man mulia for preparation of surface. 0.50 Each 333.00 166.50
Total= 408.00
Over Head Charge 7.5 % = 30.60
Contractor's Profit 7.5 % = 30.60
Total= 469.20
For 1 Sqm= 469.20 9.30 50.45
Add cost of primer = 0.75 x 112.60/10= 8.44
Total= 58.89
Add 1% Labour cess = 0.58
Total = 59.47
Say Rs. 59.50 per Sqm.
First foor:-
Basic Rate: = 58.89
(ii) Add 3 % extra labour 1.31
Over Head Charge 7.5 % = 0.09
Contractor's Profit 7.5 % = 0.09
Total= 60.38
Add 1% Labour cess = 0.60
Total = 60.98
Say Rs. 61.00 per Sqm.
9 Priming 1 coat with primer red oxcide primer including all labour, materials,
T&P etc. complete.
Ref :-A/R - 2006 ,P - 93, Item No- 1
Data for 9.3 Sqm.
a) Labour
Painter Special 0.50 Each 483.00 241.50
Man mulia for preparation of surface. 0.50 Each 333.00 166.50
Total= 408.00
Over Head Charge 7.5 % = 30.60
Contractor's Profit 7.5 % = 30.60
Total= 469.20
For 1 Sqm= 469.20 9.30 50.45
Add cost of primer = 0.54 x 97.64/10= 5.27
Total= 55.72
Add 1% Labour cess = 0.55
Total = 56.27
Say Rs. 56.30 per Sqm.
First foor:-
Basic Rate: = 55.72
(ii) Add 3 % extra labour 1.31
Over Head Charge 7.5 % = 0.09
Contractor's Profit 7.5 % = 0.09
Total= 57.21
Add 1% Labour cess = 0.57
Total = 57.78
Say Rs. 57.80 per Sqm.
35 Distempering 1 coat to walls with distemper of approved shade on old work
to give an even shade including cost of distemper and labour, T & P. etc
complete.
Ref :-A/R - 2006 ,P - 99, Item No-21
Data for 10 Sqm.
a) Labour
Sl. No. Description Qnty. Unit Rate Amount
Painter Special 0.33 Each 483.00 159.39
Man mulia 0.40 Each 333.00 133.20
Total= 292.59
Over Head Charge 7.5 % = 21.94
Contractor's Profit 7.5 % = 21.94
Total= 336.47
For 1 Sqm= 336.47 10.00 33.64
Add cost of distemper =1.66 x 51.97/10= 8.62
Total= 42.26
Add 1% Labour cess = 0.42
Total = 42.68
Say Rs. 42.70 per Sqm.
5 Distempering 2 coats to walls with distemper of approved shade on new
work to give an even shade including cost of distemper and labour, T & P.
etc complete.
Ref :-A/R - 2006 ,P - 99, Item No-22
Data for 10 Sqm.
a) Labour
Painter Special 0.52 Each 483.00 251.16
Man mulia 0.52 Each 333.00 173.16
Man mulia for preparation of surface. 0.10 Each 333.00 33.30
Total= 457.62
Over Head Charge 7.5 % = 34.32
Contractor's Profit 7.5 % = 34.32
Total= 526.26
For 1 Sqm= 526.26 10.00 52.62
Add cost of distemper =2.5 x 51.97/10= 12.99
Total= 65.61
Add 1% Labour cess = 0.65
Total = 66.26
Say Rs. 66.30 per Sqm
(B) First floor
(i) Basic rate = 65.61
(ii) Add 3 % extra Labour = 1.37
Over Head Charge 7.5 % = = 0.10
Contractor's Profit 7.5 % = 0.10
Total = 67.18
Add 1% Labour cess = 0.67
Total = 67.85
Say Rs. 67.90 per Sqm.
(C) 2nd floor
(i) Basic rate = 67.18
(ii) Add 3 % extra Labour = 1.41
Over Head Charge 7.5 % = = 0.10
Contractor's Profit 7.5 % = 0.10
Total = 68.79
Add 1% Labour cess = 0.68
Total = 69.47
Say Rs. 69.50 per Sqm.
(C) 3rd floor
(i) Basic rate = 68.79
(ii) Add 3 % extra Labour = 1.45
Over Head Charge 7.5 % = = 0.10
Contractor's Profit 7.5 % = 0.10
Total = 70.44
Add 1% Labour cess = 0.70
Total = 71.14
Say Rs. 71.10 per Sqm.
(C) 4th floor
Sl. No. Description Qnty. Unit Rate Amount
(i) Basic rate = 70.44
(ii) Add 3 % extra Labour = 1.49
Over Head Charge 7.5 % = = 0.10
Contractor's Profit 7.5 % = 0.10
Total = 72.13
Add 1% Labour cess = 0.72
Total = 72.85
Say Rs. 72.90 per Sqm.
37 White washing 3 coats with stone lime including all costs complete.
Ref :-A/R - 2006 ,P - 111, Item No-35
Data for 93 Sqm.
a) Materials
Stone lime unslaked 0.0425 Cum. 1500.00 63.75
Total= 63.75
b) Labour
Painter Second class 1.50 Each 423.00 634.50
Man mulia 1.00 Each 333.00 333.00
Total= 967.50
Over Head Charge 7.5 % = 77.34
Contractor's Profit 7.5 % = 77.34
Total= 1122.18
For 1 Sqm= 1122.18 93.00 12.06
Add 1% Labour cess = 0.12
Total = 12.18
Say Rs. 12.20 per Sqm.
38 White washing 2 coats with stone lime including all costs complete.
Ref :-A/R - 2006 ,P - 111, Item No-33
Data for 93 Sqm.
a) Materials
Stone lime unslaked 0.032 Cum. 1500.00 48.00
Total= 48.00
b) Labour
Painter Second class 1.00 Each 423.00 423.00
Man mulia 0.75 Each 333.00 249.75
Total= 672.75
Over Head Charge 7.5 % = 54.05
Contractor's Profit 7.5 % = 54.05
Total= 828.85
For 1 Sqm= 828.85 93.00 8.91
Add 1% Labour cess = 0.08
Total = 8.99
Say Rs. 9.00 per Sqm.
38 White washing 1 coats with stone lime including all costs complete.
Ref :-A/R - 2006 ,P - 111, Item No-33
Data for 93 Sqm.
a) Materials
Stone lime unslaked 0.021 Cum. 1500.00 31.50
Total= 31.50
b) Labour
Painter Second class 0.75 Each 423.00 317.25
Man mulia 0.50 Each 333.00 166.50
Total= 483.75
Over Head Charge 7.5 % = 38.64
Contractor's Profit 7.5 % = 38.64
Total= 592.53
For 1 Sqm= 592.53 93.00 6.37
Add 1% Labour cess = 0.06
Total = 6.43
Say Rs. 6.40 per Sqm.
Sl. No. Description Qnty. Unit Rate Amount
39 Colour washing two coats with stone lime and colouring materials
Ref :-A/R - 2006 ,P - 112, Item No-39
Data for 93 Sqm.
a) Materials
Stone lime un-slacked 0.0425 Cum. 1500.00 63.75
Total= 63.75
b) Labour
Painter Second class 1.50 Each 423.00 634.50
Man mulia 1.00 Each 333.00 333.00
Total= 967.50
Over Head Charge 7.5 % = 77.34
Contractor's Profit 7.5 % = 77.34
Total= 1185.93
For 1 Sqm= 1185.93 93.00 12.75
Add 1% Labour cess = 0.12
Total = 12.87
Say Rs. 12.90 per Sqm.
3 White washing 3 coats with shell lime including all costs of all materials,
labour, T&P etc. complete.
Ref :-A/R - 2006 ,P - 111, Item No-34
Data for 93 Sqm.
a) Materials
Shell lime unslaked 23.32 1 kg 18.10 422.09
Total= 422.09
b) Labour
Painter Second class 1.50 Each 423.00 634.50
Man mulia 1.00 Each 333.00 333.00
Total= 967.50
Over Head Charge 7.5 % = 104.21
Contractor's Profit 7.5 % = 104.21
Total= 1598.01
For 1 Sqm= 1598.01 93.00 17.18
Add 1% Labour cess = 0.17
Total = Rs 17.35
Say Rs. 17.40 Per Sqm
41 White washing 2 coats with shell lime including cost of all material, cost of
all labour, T&P. etc. complete.
Ref :-A/R - 2006 ,P - 110, Item No-32
Data for 93 Sqm.
a) Materials
Shell lime unslaked 18.66 1 kg 18.10 337.74
Total= 337.74
b) Labour
Painter Second class 1.00 Each 423.00 423.00
Man mulia 0.75 Each 333.00 249.75
Total= 672.75
Over Head Charge 7.5 % = 75.78
Contractor's Profit 7.5 % = 75.78
Total= 1162.05
For 1 Sqm= 1162.05 93.00 12.49
Add 1 % Labour cess = 0.12
Total= 12.61
Say Rs. 12.60 Per Sqm
41 White washing 1 coats with shell lime including cost of all material, cost of
all labour, T&P. etc. complete.
Ref :-A/R - 2006 ,P - 110, Item No-30
Data for 93 Sqm.
a) Materials
Shell lime unslaked 11.80 1 kg 18.10 213.58
Sl. No. Description Qnty. Unit Rate Amount
Total= 213.58
b) Labour
Painter Second class 0.75 Each 423.00 317.25
Man mulia 0.50 Each 333.00 166.50
Total= 483.75
Over Head Charge 7.5 % = 52.29
Contractor's Profit 7.5 % = 52.29
Total= 801.91
For 1 Sqm= 801.91 93.00 8.62
Add 1 % Labour cess = 0.08
Total= 8.70
Say Rs. 8.70 Per Sqm
42 Colour washing two coats with shell lime and colouring materials
Ref :-A/R - 2006 ,P - 112, Item No-38
Data for 93 Sqm.
a) Materials
Shell lime un-slacked 18.66 kg 18.10 337.74
Total= 337.74
b) Labour
Painter Second class 1.00 Each 423.00 423.00
Man mulia 0.75 Each 333.00 249.75
Total= 672.75
Over Head Charge 7.5 % = 75.78
Contractor's Profit 7.5 % = 75.78
Add extra for labour and colouring materials L.S. 25.00
Total= 1187.05
For 1 Sqm= 1187.05 93.00 12.76
Add 1 % Labour cess = 0.12
Total= 12.88
Say Rs. 12.90 Per Sqm
10 Finishing to the exposed surfaces of wall with weather coat of any
approved shade on new work 2 coats to give an even shade including
cost of weather coat all cost of all labours and T&P etc. complete .

(A.R.-2006, Page No - 99, Item No. - 20)


Unit:- 10 Sqm, Data for 10.00 Sqms.
a) Labour
Painter Special 0.54 Each 483.00 260.82
Man Mulia 0.54 Each 333.00 179.82
Women Mulia 0.10 Each 333.00 33.30
Total = 473.94
Over Head Charge 7.5 % = 35.54
Contractor's Profit 7.5 % = 35.54
Total (a+b+c)= 545.02
Rate per Sqm = 54.50
Add cost of Weather coat 0.125 Ltr 151.18 18.89
T= 73.39
Add 1% Labour cess = 0.73
Total = Rs 74.12
Say Rs. 74.10 per Sqm.
(B) First floor
(i) Basic rate = 73.39
(ii) Add 5 % extra Labour = 2.36
Over Head Charge 7.5 % = = 0.17
Contractor's Profit 7.5 % = 0.17
Total = 76.09
Add 1% Labour cess = 0.76
Total = Rs 76.85
Say Rs. 76.90 per Sqm.
Sl. No. Description Qnty. Unit Rate Amount
(C) 2nd floor
(i) Basic rate = 76.09
(ii) Add 5 % extra Labour = 2.48
Over Head Charge 7.5 % = = 0.18
Contractor's Profit 7.5 % = 0.18
Total = 78.93
Add 1% Labour cess = 0.78
Total = Rs 79.71
Say Rs. 79.70 per Sqm.
(C) 3rd floor
(i) Basic rate = 78.93
(ii) Add 5 % extra Labour = 2.60
Over Head Charge 7.5 % = = 0.19
Contractor's Profit 7.5 % = 0.19
Total = 81.91
Add 1% Labour cess = 0.81
Total = Rs 82.72
Say Rs. 82.70 per Sqm.
44 Finishing to the exposed surfaces of wall with weather coat of any
approved shade on old work 1 coat to give an even shade including cost
of weather coat all cost of all labours and T&P etc. complete .

(A.R.-2006, Page No - 99, Item No. -19)


Unit:- 10 Sqm, Data for 10.00 Sqms.
a) Labour
Painter Special 0.36 Each 483.00 173.88
Man Mulia 0.36 Each 333.00 119.88
Women Mulia 0.07 Each 333.00 23.31
Total = 317.07
Over Head Charge 7.5 % = 23.78
Contractor's Profit 7.5 % = 23.78
Total (a+b+c)= 364.63
Rate per Sqm = 36.46
Add cost of Weather coat 0.075 Ltr 151.18 11.33
T= 47.79
Add 1% Labour cess = 0.47
Total = Rs 48.26
Say Rs. 48.30 per Sqm.
(B) First floor
(i) Basic rate = 47.79
(ii) Add 5 % extra Labour = 1.58
Over Head Charge 7.5 % = = 0.11
Contractor's Profit 7.5 % = 0.11
Total = 49.59
Add 1% Labour cess = 0.49
Total = Rs 50.08
Say Rs. 50.10 per Sqm.
(C) 2nd floor
(i) Basic rate = 49.59
(ii) Add 5 % extra Labour = 1.66
Over Head Charge 7.5 % = = 0.12
Contractor's Profit 7.5 % = 0.12
Total = 51.49
Add 1% Labour cess = 0.51
Total = Rs 52.00
Say Rs. 52.00 per Sqm.
French polishing to wood work 2 coats with priming including cost of all
materials labour T&P etc. complete.
A/R - 2006, P-96, Item - 11
Sl. No. Description Qnty. Unit Rate Amount
Per 1 Sqm
Data for 9.30 Sqm.
a) Labour
Painter Special 1.00 each 483.00 483.00
Man Mulia 1.00 each 333.00 333.00
Man Mulia for perparation of surface 0.10 each 333.00 33.30
849.30
For 1 Sqm= 849.30 9.30 91.32
Over Head Charge 7.5 % = 6.84
Contractor's Profit 7.5 % = 6.84
Add cost of French Polish =1.25 x 128.35/10= 16.04
Total = Rs 121.04
Total (a+b+c)= 121.04
Add 1% Labour cess = 1.21
Total = Rs 122.25
Say Rs. 122.30 per Sqm.
46 Wall painting 2 coats with any approved paint on new work to give an even
shade including cost of all matirials, labour, T&P etc. complete.

Ref :-S/R - 2006 ,P - 112, Item No-7


Data for 1 Sqm.
(i) In All Floors
Ref :-S/R - 2006 ,P - 112, Item No-7 4.62
Add cost of enamel paint =1.25 x 151.97/10= 18.99
Total= 23.61
Add 1% Labour cess = 0.23
Total = Rs 23.84
Say Rs. 23.80 per Sqm.
11 Finishing surface of walls with Cement based wall putty & making smooth
to recive painting including cost of scaffolding etc. with cost of all materials,
labour T&P etc. complete.
Ref:- A/R-2006, Item No -2 Page-236
Data for 10 Sqm
(a)Labour
Painter Second Class 0.50 Nos 423.00 211.50
Man Mulia 0.50 Nos 333.00 166.50
Mulia for preparation of surface 0.07 Nos 333.00 23.31
Add cost of Putty 8.00 Kg 30.00 240.00
Total= 641.31
Over Head Charge 7.5 % = 48.09
Contractor's Profit 7.5 % = 48.09
Total(a+b)= 737.49
Rate for 1 Sqm = 73.74
Add 1% Labour cess = 0.73
Total= 74.47
Say Rs. 74.50 per Sqm
1st floor:-
Basic Rate: = 73.74
(ii) Add 3 % extra labour 1.20
Over Head Charge 7.5 % = 0.09
Contractor's Profit 7.5 % = 0.09
Total= 75.12
Add 1% Labour cess = 0.75
Total= 75.87
Say Rs. 75.90 per Sqm.
2nd floor:-
Basic Rate: = 75.12
(ii) Add 3 % extra labour 1.24
Over Head Charge 7.5 % = 0.09
Sl. No. Description Qnty. Unit Rate Amount
Contractor's Profit 7.5 % = 0.09
Total= 76.54
Add 1% Labour cess = 0.76
Total= 77.30
Say Rs. 77.30 per Sqm.
48 Finishing plastered surface of wall surface with plaster of paris & making
smooth to recive painting including cost of scaffolding etc. with cost of all
materials, labour T&P etc. complete.
Ref:- A/R-2006, Item No -23 Page-100
Data for 10 Sqm
(a)Labour
Painter Second Class 0.50 Nos 423.00 211.50
Man Mulia 0.50 Nos 333.00 166.50
Mulia for preparation of surface 0.07 Nos 333.00 23.31
Total= 401.31
Over Head Charge 7.5 % = 30.09
Contractor's Profit 7.5 % = 30.09
Total(a+b+c)= 461.49
Rate for 1 Sqm = 46.14
Add cost of Plaster of paris 3.00 Kg 9.45 28.35
74.49
Add 1% Labour cess = 0.74
Total= 75.23
Say Rs. 75.20 per Sqm
49 Fixing Kota stone (up to 0.10 Sqms) in floors treads or steps and landing
on 20 mm thick bed of cement mortar 1:4 (1cement : 4 sand) jointed with
neat cement slury mixed with pigment to match the shades of the tiles
including rubbing and polishing complete including cost of kota stone.

(A.R.-2006, Page No - 89, Item No. - 16)


Data for 10 Sqms.
a) Materials
Cost of tile 10.000 Sqm 313.39 3133.90
Sand 0.21 Cum. 50.48 10.60
Cement 0.744 Qntl 517.42 384.96
Cement for slurry 0.33 Qntl 517.42 170.74
White Cement 0.076 Qntl 1413.39 107.41
Total = 3807.61
b) Labour
Mason Special 2.16 Each 483.00 1043.28
Semi-skilled mulia or rubbing 5.50 Each 373.00 2051.50
Mulia 2.16 Each 333.00 719.28
Total = 3814.06
Over Head Charge 7.5 % = 571.62
Contractor's Profit 7.5 % = 571.62
e) Cost of Carriage and Royality of Materials
Tile 10.00 Sqm 5.37 53.73
Sand 0.21 Cum. 184.67 38.78
Cement 0.744 Qntl 5.50 4.09
Cement for slurry 0.33 Qntl 5.50 1.81
White Cement 0.076 Qntl 5.50 0.41
Total= 98.82
Total =(a+b+c+d+e) = Rs. 8863.73
For 1 Sqm = Rs. 886.37
Add for wax polishing = 8.50
Total= 894.87
Add 1 % Labour Cess = 8.94
Total= 903.81
Say Rs. 903.80 per Sqm.
Sl. No. Description Qnty. Unit Rate Amount
1st floor:-
Basic Rate: = 894.87
(ii) Add 5 % extra labour 19.07
Over Head Charge 7.5 % = 1.43
Contractor's Profit 7.5 % = 1.43
Total= 916.80
Add 1% Labour cess = 9.16
Total = Rs 925.96
Say Rs. 926.00 per Sqm.
2nd floor:-
Basic Rate: = 916.80
(ii) Add 5 % extra labour 20.02
Over Head Charge 7.5 % = 1.50
Contractor's Profit 7.5 % = 1.50
Total= 939.82
Add 1% Labour cess = 9.39
Total = Rs 949.21
Say Rs. 949.20 per Sqm.
50 Fixing Kota stone (up to 0.10 Sqms) in dados skirting and risers of steps on
12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with
pigments to match the shade of the tiles including rubbing and polishing
complete including all costs complete
(A.R.-2006, Page No - 90, Item No. - 17)
Data for 10 Sqms.
a) Materials
Sand 0.15 Cum. 50.48 7.57
Cement 0.715 Qntl 517.42 369.95
Cement for slurry 0.66 Qntl 517.42 341.49
Kota tiles 10.00 Sqm 313.39 3133.90
Total = 3852.91
b) Labour
Mason Special 3.25 Each 483.00 1569.75
Semi-skilled mulia or rubbing 7.60 Each 373.00 2834.80
Mulia 3.25 Each 333.00 1082.25
Total = 5486.80
Over Head Charge 7.5 % = 700.47
Contractor's Profit 7.5 % = 700.47
e) Cost of Carriage and Royality of Materials
Sand 0.15 Cum. 184.67 27.70
Cement 0.715 Qntl 5.50 3.93
Cement for slurry 0.66 Qntl 5.50 3.63
Kota tiles 10.00 Sqm 5.37 53.73
Total= 88.99
Total =(a+b+c+d+e) = Rs. 10829.64
For 1 Sqm = Rs. 1082.96
Add for wax polishing = 8.50
Total = 1091.46
Add 1% Labour cess = 10.91
Total = Rs 1102.37
Say Rs. 1102.40 per Sqm.
1st floor:-
Basic Rate: = 1091.46
(ii) Add 5 % extra labour 27.43
Over Head Charge 7.5 % = 2.05
Contractor's Profit 7.5 % = 2.05
Total= 1122.99
Add 1% Labour cess = 11.22
Total = Rs 1134.21
Say Rs. 1134.20 per Sqm.
Sl. No. Description Qnty. Unit Rate Amount
2nd floor:-
Basic Rate: = 1122.99
(ii) Add 5 % extra labour 28.80
Over Head Charge 7.5 % = 2.16
Contractor's Profit 7.5 % = 2.16
Total= 1156.11
Add 1% Labour cess = 11.56
Total = Rs 1167.67
Say Rs. 1167.70 per Sqm.
16 Fixing glazzed tiles (30cmx30cm / 40cm x 40cm special plain/printed series
ceramic tiles of premium grade having thickness 7 mm to 8mm confirming
to IS 13755) in floors treads or steps and landing on 20 mm thick bed of
cement mortar 1:4 (1cement : 4sand) jointed with neat cement slury mixed
with pigment to match the shades of the tiles including cost of tiles.

(A.R.-2006, Page No - 89, Item No. - 16 & S/R - 2012, Chapter XIX , Item N
1 (B))
Data for 10 Sqms.
a) Materials
Cost of tile 10.000 Sqm 334.65 3346.50
Sand 0.21 Cum. 50.48 10.60
Cement 0.744 Qntl 517.42 384.96
Cement for slurry 0.33 Qntl 517.42 170.74
White Cement 0.076 Qntl 1413.39 107.41
Total = 4020.21
b) Labour
Mason Special 2.16 Each 483.00 1043.28
Mulia 2.16 Each 333.00 719.28
Total = 1762.56
Over Head Charge 7.5 % = 433.70
Contractor's Profit 7.5 % = 433.70
d) Cost of Carriage and Royality of Materials
Tile 10.00 Sqm 5.37 53.73
Sand 0.21 Cum. 184.67 38.78
Cement 0.744 Qntl 5.50 4.09
Cement for slurry 0.33 Qntl 5.50 1.81
White Cement 0.076 Qntl 5.50 0.41
Total= 98.82
Total =(a+b+c+d) = Rs. 6748.99
For 1 Sqm = Rs. 674.89
Add 1 % Labour Cess = 6.74
Total= 681.63
Say Rs. 681.60 per Sqm.
1st floor:-
Basic Rate: = 674.89
(ii) Add 5 % extra labour 8.81
Over Head Charge 7.5 % = 0.66
Contractor's Profit 7.5 % = 0.66
Total= 685.02
Add 1% Labour cess = 6.85
Total = Rs 691.87
Say Rs. 691.90 per Sqm.
2nd floor:-
Basic Rate: = 685.02
(ii) Add 5 % extra labour 9.25
Over Head Charge 7.5 % = 0.69
Contractor's Profit 7.5 % = 0.69
Total= 695.65
Add 1% Labour cess = 6.95
Sl. No. Description Qnty. Unit Rate Amount
Total = Rs 702.60
Say Rs. 702.60 per Sqm.
10 Fixing glazzed tiles (20cmx30cm / 20cm x 20cm special plain/printed series
ceramic wall tiles of premium grade having thickness 6.5mm to 6.7mm
confirming to IS 13753) in dados skirting and risers of steps on 12mm thick
cement plaster (1:3) jointed with neat cement slurry mixed with pigments to
match the shades of the tiles including cost of tiles.

(A.R.-2006, Page No - 90, Item No. - 17)


Data for 10 Sqms.
a) Materials
Sand 0.15 Cum. 50.48 7.57
Cement 0.715 Qntl 517.42 369.95
Cement for slurry 0.66 Qntl 517.42 341.49
Glazed tiles 10.00 Sqm 299.21 2992.10
Total = 3711.11

b) Labour
Mason Special 3.25 Each 483.00 1569.75
Mulia 3.25 Each 333.00 1082.25
Total = 2652.00
Over Head Charge 7.5 % = 477.23
Contractor's Profit 7.5 % = 477.23
d) Cost of Carriage and Royality of Materials
Sand 0.15 Cum. 184.67 27.70
Cement 0.715 Qntl 5.50 3.93
Cement for slurry 0.66 Qntl 5.50 3.63
Glazed tiles 10.00 Sqm 5.37 53.73
Total= 88.99
Total =(a+b+c+d) = Rs. 7406.56
For 1 Sqm = Rs. 740.65
Add 1% Labour cess = 7.40
Total = Rs 748.05
Say Rs. 748.10 per Sqm.
1st floor:-
Basic Rate: = 740.65
(ii) Add 5 % extra labour 13.26
Over Head Charge 7.5 % = 0.99
Contractor's Profit 7.5 % = 0.99
Total= 755.89
Add 1% Labour cess = 7.55
Total = Rs 763.44
Say Rs. 763.40 per Sqm.
2nd floor:-
Basic Rate: = 755.89
(ii) Add 5 % extra labour 13.92
Over Head Charge 7.5 % = 1.04
Contractor's Profit 7.5 % = 1.04
Total= 771.89
Add 1% Labour cess = 7.71
Total = Rs 779.60
Say Rs. 779.60 per Sqm.
11 Fixing Marble (above 0.40 sqm) in floors treads or steps and landing on
20mm thick bed of cement mortar 1:4 (1cement : 4sand) jointed with neat
cement slury mixed with pigment to match the shades of the tiles including
rubbing and polishing complete including cost, carriage, royalty & taxes of
all material, cost of all labour T&P etc. complete.

(A.R.-2006, Page No - 89, Item No. - 16)


Sl. No. Description Qnty. Unit Rate Amount
Data for 10 Sqms.
a) Materials
Cost of tile 10.000 Sqm 582.68 5826.80
Sand 0.21 Cum. 50.48 10.60
Cement 0.744 Qntl 517.42 384.96
Cement for slurry 0.33 Qntl 517.42 170.74
White Cement 0.076 Qntl 1413.39 107.41
Total = 6500.51
b) Labour
Mason Special 2.16 Each 483.00 1043.28
Semi-skilled mulia or rubbing 5.50 Each 373.00 2051.50
Mulia 2.16 Each 333.00 719.28
Total = 3814.06
Over Head Charge 7.5 % = 773.59
Contractor's Profit 7.5 % = 773.59
d) Cost of Carriage and Royality of Materials
Tile 10.00 Sqm 5.37 53.73
Sand 0.21 Cum. 184.67 38.78
Cement 0.744 Qntl 5.50 4.09
Cement for slurry 0.33 Qntl 5.50 1.81
White Cement 0.076 Qntl 5.50 0.41
Total= 98.82
Total =(a+b+c+d) = Rs. 11960.57
For 1 Sqm = Rs. 1196.05
Add for wax polishing = 8.50
Total= 1204.55
Add 1 % Labour Cess = 12.04
Total= 1216.59
Say Rs. 1216.60 per Sqm.
1st floor:-
Basic Rate: = 1204.55
(ii) Add 5 % extra labour 19.07
Over Head Charge 7.5 % = 1.43
Contractor's Profit 7.5 % = 1.43
Total= 1226.48
Add 1% Labour cess = 12.26
Total = Rs 1238.74
Say Rs. 1238.70 per Sqm.
2nd floor:-
Basic Rate: = 1226.48
(ii) Add 5 % extra labour 20.02
Over Head Charge 7.5 % = 1.50
Contractor's Profit 7.5 % = 1.50
Total= 1249.50
Add 1% Labour cess = 12.49
Total = Rs 1261.99
Say Rs. 1262.00 per Sqm.
54 Fixing Marble in (up to 0.10 sqm) dados skirting and risers of steps on
12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with
pigments to match the shade of the tiles including rubbing and polishing
complete including all costs complete
(A.R.-2006, Page No - 90, Item No. - 17)
Data for 10 Sqms.
a) Materials
Sand 0.15 Cum. 50.48 7.57
Cement 0.715 Qntl 517.42 369.95
Cement for slurry 0.66 Qntl 517.42 341.49
Marble tiles 10.00 Sqm 582.68 5826.80
Total = 6545.81
Sl. No. Description Qnty. Unit Rate Amount
b) Labour
Mason Special 3.25 Each 483.00 1569.75
Semi-skilled mulia for rubbing 7.60 Each 373.00 2834.80
Mulia 3.25 Each 333.00 1082.25
Total = 5486.80
Over Head Charge 7.5 % = 902.44
Contractor's Profit 7.5 % = 902.44
d) Cost of Carriage and Royality of Materials
Sand 0.15 Cum. 184.67 27.70
Cement 0.715 Qntl 5.50 3.93
Cement for slurry 0.66 Qntl 5.50 3.63
Marble tiles 10.00 Sqm 5.37 53.73
Total= 88.99
Total =(a+b+c+d) = Rs. 13926.48
Or for 1 Sqm = Rs. 1392.64
Add for wax polishing = 8.50
T= 1401.14
Add 1% Labour cess = 14.01
Total = Rs 1415.15
Say Rs. 1415.20 per Sqm.
1st floor:-
Basic Rate: = 1401.14
(ii) Add 5 % extra labour 27.43
Over Head Charge 7.5 % = 2.05
Contractor's Profit 7.5 % = 2.05
Total= 1432.67
Add 1% Labour cess = 14.32
Total = Rs 1446.99
Say Rs. 1447.00 per Sqm.
1st floor:-
Basic Rate: = 1432.67
(ii) Add 5 % extra labour 28.80
Over Head Charge 7.5 % = 2.16
Contractor's Profit 7.5 % = 2.16
Total= 1465.79
Add 1% Labour cess = 14.65
Total = Rs 1480.44
Say Rs. 1480.40 per Sqm.
6 Fixing Vitrified tiles (size 600mmx600mm) (Plain) in dados skirting and
risers of steps on 12mm thick cement plaster (1:3) jointed with neat cement
slurry mixed with pigments to match the shade of the tiles including cost,
carriage, cost of all labour etc. complete.
(A.R.-2006, Page No - 90, Item No. - 17)
Data for 10 Sqms.
a) Materials
Sand 0.15 Cum. 50.48 7.57
Cement 0.715 Qntl 517.42 369.95
Cement for slurry 0.66 Qntl 517.42 341.49
Vetrified tiles 10.00 Sqm 522.05 5220.50
Total = 5939.51
b) Labour
Mason Special 3.25 Each 483.00 1569.75
Mulia 3.25 Each 333.00 1082.25
Total = 2652.00
Over Head Charge 7.5 % = 644.36
Contractor's Profit 7.5 % = 644.36
d) Cost of Carriage and Royality of Materials
Sand 0.15 Cum. 184.67 27.70
Cement 0.715 Qntl 5.50 3.93
Sl. No. Description Qnty. Unit Rate Amount
Cement for slurry 0.66 Qntl 5.50 3.63
Vetrified tiles 10.00 Sqm 5.37 53.73
Total= 88.99
Total =(a+b+c+d+e) = Rs. 9969.22
For 1 Sqm = Rs. 996.92
Add 1% Labour cess = 9.96
Total = Rs 1006.88
Say Rs. 1006.90 per Sqm.
1st floor:-
Basic Rate: = 996.92
Add 5 % extra labour 13.26
Over Head Charge 7.5 % = 0.99
Contractor's Profit 7.5 % = 0.99
Total= 1012.16
Add 1% Labour cess = 10.12
Total = Rs 1022.28
Say Rs. 1022.30 per Sqm.
2nd floor:-
Basic Rate: = 1012.16
Add 5 % extra labour 13.92
Over Head Charge 7.5 % = 1.04
Contractor's Profit 7.5 % = 1.04
Total= 1028.16
Add 1% Labour cess = 10.28
Total = Rs 1038.44
Say Rs. 1038.40 per Sqm.
10 Supplying, fitting and fixing vitrified tile (Plain) in floors of size 600mm x
600mm of approved make conformaing to IS : 13755 laid on 20 mm thick
cement mortar (1:4) (1 cement :4 course sand) and filling joints with white
cement of approved quality including cost of all materials, labour T&P etc.
required for the work all complete as per direction of E.I.C. (For New work
only)

(A.R.-2006, P - 235, Item No. - 1 & P - 89 Item - 16


Data for 10 Sqms.
a) Materials
Cost of tile 10.000 Sqm 522.05 5220.50
Sand 0.21 Cum. 50.48 10.60
Cement 0.744 Qntl 517.42 384.96
Cement for slurry 0.33 Qntl 517.42 170.74
White Cement 0.076 Qntl 1413.39 107.41
Total = 5894.21
b) Labour
Mason Special 2.16 Each 483.00 1043.28
Mulia 2.16 Each 333.00 719.28
Total = 1762.56
Over Head Charge 7.5 % = 574.25
Contractor's Profit 7.5 % = 574.25
e) Cost of Carriage and Royality of Materials
Tile 10.00 Sqm 5.37 53.73
Sand 0.21 Cum. 184.67 38.78
Cement 0.744 Qntl 5.50 4.09
Cement for slurry 0.33 Qntl 5.50 1.81
White Cement 0.076 Qntl 5.50 0.41
Total= 98.82
Total =(a+b+c+d+e) = Rs. 8904.09
For 1 Sqm = Rs. 890.40
Add 1 % Labour Cess = 8.90
Total= 899.30
Say Rs. 899.30 per Sqm.
Sl. No. Description Qnty. Unit Rate Amount
1st floor:-
Basic Rate: = 890.40
(ii) Add 5 % extra labour 8.81
Over Head Charge 7.5 % = 0.66
Contractor's Profit 7.5 % = 0.66
Total= 900.53
Add 1 % Labour Cess = 9.00
Total= 909.53
Say Rs. 909.50 per Sqm.
2nd floor:-
Basic Rate: = 900.53
(ii) Add 5 % extra labour 9.25
Over Head Charge 7.5 % = 0.69
Contractor's Profit 7.5 % = 0.69
Total= 911.16
Add 1% Labour cess = 9.11
Total = Rs 920.27
Say Rs. 920.30 per Sqm.
58 Fixing Chequred tiles in floors treads or steps and on 20mm thick bed of
cement mortar 1:4 (1cement : 4 sand) jointed with neat cement slury mixed
with pigment to match the shades of the tiles including cost, carriage,
royalty & taxes of all materials, cost of all labours T&P etc complete.

Derived from (A.R.-2006, Page No - 89, Item No. - 16)


Data for 10 Sqms.
a) Materials
Chequed tiles 10.00 Sqm 170.87 1708.70
Sand 0.21 Cum 50.48 10.60
Cement 0.744 Qntl 517.42 384.96
Cement for slurry 0.33 Qntl 517.42 170.74
Total = 2275.00
b) Labour
Mason Special 2.16 Each 483.00 1043.28
Mulia 2.16 Each 333.00 719.28
Total = 1762.56
Over Head Charge 7.5 % = 302.81
Contractor's Profit 7.5 % = 302.81
d) Cost of Carriage and Royality of Materials
Chequed tiles 10.00 Sqm 5.37 53.73
Sand 0.21 Cum 184.67 38.78
Cement 0.744 Qntl 5.50 4.09
Cement for slurry 0.33 Qntl 5.50 1.81
Total= 98.41
Total =(a+b+c+d+e) = Rs. 4741.59
For 1 Sqm = Rs. 474.15
Add 1% Labour cess = 4.74
Total = Rs 478.89
Say Rs. 478.90 per Sqm.
1st floor:-
Basic Rate: = 474.15
Add 5 % extra labour 8.81
Over Head Charge 7.5 % = 0.66
Contractor's Profit 7.5 % = 0.66
Total= 484.28
Add 1% Labour cess = 4.84
Total = Rs 489.12
Say Rs. 489.10 per Sqm.
2nd floor:-
Basic Rate: = 484.28
Sl. No. Description Qnty. Unit Rate Amount
Add 5 % extra labour 9.25
Over Head Charge 7.5 % = 0.69
Contractor's Profit 7.5 % = 0.69
Total= 494.91
Add 1% Labour cess = 4.94
Total = Rs 499.85
Say Rs. 499.90 per Sqm.
13 Fixing Vitrified Industrial tiles in floors treads or steps and on 20mm thick
bed of cement mortar 1:4 (1cement : 4 sand) jointed with neat cement slury
mixed with pigment to match the shades of the tiles including cost,
carriage, royalty & taxes of all materials, cost of all labours T&P etc
complete.

Derived from (A.R.-2006, Page No - 89, Item No. - 16)


Data for 10 Sqms.
a) Materials
Industrial floor tiles 10.00 Sqm 472.44 4724.40
Sand 0.21 Cum 50.48 10.60
Cement 0.744 Qntl 517.42 384.96
Cement for slurry 0.33 Qntl 517.42 170.74
White Cement 0.076 Qntl 1413.39 107.41
Total = 5398.11
b) Labour
Mason Special 2.16 Each 483.00 1043.28
Mulia 2.16 Each 333.00 719.28
Total = 1762.56
Over Head Charge 7.5 % = 537.05
Contractor's Profit 7.5 % = 537.05
e) Cost of Carriage and Royality of Materials
Industrial floor tiles 10.00 Sqm 5.37 53.73
Sand 0.21 Cum 184.67 38.78
Cement 0.744 Qntl 5.50 4.09
Cement for slurry 0.33 Qntl 5.50 1.81
White Cement 0.076 Qntl 5.50 0.41
Total= 98.82
Total =(a+b+c+d+e) = Rs. 8333.59
For 1 Sqm = Rs. 833.35
Add 1% Labour cess = 8.33
Total = Rs 841.68
Say Rs. 841.70 per Sqm.
1st floor:-
Basic Rate: = 833.35
Add 5 % extra labour 8.81
Over Head Charge 7.5 % = 0.66
Contractor's Profit 7.5 % = 0.66
Total= 843.48
Add 1% Labour cess = 8.43
Total = Rs 851.91
Say Rs. 851.90 per Sqm.
2nd floor:-
Basic Rate: = 843.48
Add 5 % extra labour 9.26
Over Head Charge 7.5 % = 0.69
Contractor's Profit 7.5 % = 0.69
Total= 854.12
Add 1% Labour cess = 8.54
Total = Rs 862.66
Say Rs. 862.70 per Sqm.
Sl. No. Description Qnty. Unit Rate Amount
6 Fixing Vitrified industrial tiles (size 600mmx600mm) (Plain) in dados
skirting and risers of steps on 12mm thick cement plaster (1:3) jointed with
neat cement slurry mixed with pigments to match the shade of the tiles
including cost, carriage, cost of all labour etc. complete.

(A.R.-2006, Page No - 90, Item No. - 17)


Data for 10 Sqms.
a) Materials
Sand 0.15 Cum. 50.48 7.57
Cement 0.715 Qntl 517.42 369.95
Cement for slurry 0.66 Qntl 517.42 341.49
Industrial floor tiles 10.00 Sqm 472.44 4724.40
Total = 5443.41
b) Labour
Mason Special 3.25 Each 483.00 1569.75
Mulia 3.25 Each 333.00 1082.25
Total = 2652.00
Over Head Charge 7.5 % = 607.15
Contractor's Profit 7.5 % = 607.15
d) Cost of Carriage and Royality of Materials
Sand 0.15 Cum. 184.67 27.70
Cement 0.715 Qntl 5.50 3.93
Cement for slurry 0.66 Qntl 5.50 3.63
Industrial Vetrified tiles 10.00 Sqm 5.37 53.73
Total= 88.99
Total =(a+b+c+d+e) = Rs. 9398.70
For 1 Sqm = Rs. 939.87
Add 1% Labour cess = 9.39
Total = Rs 949.26
Say Rs. 949.30 per Sqm.
1st floor:-
Basic Rate: = 939.87
Add 5 % extra labour 13.26
Over Head Charge 7.5 % = 0.99
Contractor's Profit 7.5 % = 0.99
Total= 955.11
Add 1% Labour cess = 9.55
Total = Rs 964.66
Say Rs. 964.70 per Sqm.
2nd floor:-
Basic Rate: = 955.11
Add 5 % extra labour 13.93
Over Head Charge 7.5 % = 1.04
Contractor's Profit 7.5 % = 1.04
Total= 971.12
Add 1% Labour cess = 9.71
Total = Rs 980.83
Say Rs. 980.80 per Sqm.
12 Dismantling brick or stone masonary in cement mortar under 3.00m height
including all costs complete. Stacking the useful materials for reuse and
removing the debris 50 mtr lead.
Ref :-A/R - 2006 ,P - 214, Item No-03
Data for 2.83Cums.
(a) Labour
Man mulias 4.00 Each 333.00 1332.00
Woman mulias 4.50 Each 333.00 1498.50
Total 2830.50
Over Head Charge 7.5 % = 212.28
Contractor's Profit 7.5 % = 212.28
Sl. No. Description Qnty. Unit Rate Amount
Total = 3255.06
per Cum= 1150.19
Add 1% Labour cess = 11.50
Total = Rs 1161.69
Say Rs. 1161.70 per Cum
a First floor
Basic rate = 1150.19
Add 5 % extra Labour = 50.00
Over Head Charge 7.5 % = = 3.75
Contractor's Profit 7.5 % = 3.75
Total = 1207.69
Add 1% Labour cess = 12.07
Total = 1219.76
Say Rs. 1219.80 per Cum
b 2nd floor
(i) Basic rate = 1207.69
(ii) Add 5 % extra Labour = 52.50
Over Head Charge 7.5 % = = 3.93
Contractor's Profit 7.5 % = 3.93
Total = 1268.05
Add 1% Labour cess = 12.68
Total = 1280.73
Say Rs. 1280.70 per Cum
61 Dismantling brick or stone masonary in cement mortar above 3.00m height
including all costs complete. Stacking the useful materials for reuse and
removing the debris 50 mtr lead.
Ref :-A/R - 2006 ,P - 215, Item No-05
Data for 2.83Cums.
(a) Labour
Man mulias 4.50 Each 333.00 1498.50
Woman mulias 4.50 Each 333.00 1498.50
Total 2997.00
Over Head Charge 7.5 % = 224.77
Contractor's Profit 7.5 % = 224.77
Total = 3446.54
per Cum= 1217.85
Add 1% Labour cess = 12.17
Total = Rs 1230.02
Say Rs. 1230.00 per Cum
a First floor
Basic rate = 1217.85
Add 5 % extra Labour = 52.95
Over Head Charge 7.5 % = = 3.97
Contractor's Profit 7.5 % = 3.97
Total = 1278.74
Add 1% Labour cess = 12.78
Total = 1291.52
Say Rs. 1291.50 per Cum
b 2nd floor
(i) Basic rate = 1278.74
(ii) Add 5 % extra Labour = 55.59
Over Head Charge 7.5 % = = 4.16
Contractor's Profit 7.5 % = 4.16
Total = 1342.65
Add 1% Labour cess = 13.42
Total = 1356.07
Say Rs. 1356.10 per Cum
Sl. No. Description Qnty. Unit Rate Amount
62 Dismantling and removing 2.5 cm. thick artificial stone flooring including
stacking the useful materials for reuse and removing the debris within 50m
lead
Ref :-A/R - 2006 ,P - 217, Item No-12
Data for 9.30 Sqm.
Man mulias 0.75 Each 333.00 249.75
Woman mulias 1.25 Each 333.00 416.25
Over Head Charge 7.5 % = 49.95
Contractor's Profit 7.5 % = 49.95
Total = 765.90
per Sqm= 82.35
Add 1% Labour cess = 0.82
Total = Rs 83.17
Say Rs. 83.20 per Sqm.
a First floor
Basic rate = 82.35
Add 5 % extra Labour = 3.58
Over Head Charge 7.5 % = = 0.26
Contractor's Profit 7.5 % = 0.26
Total = 86.45
Add 1% Labour cess = 0.86
Total = 87.31
Say Rs. 87.30 per Cum
b 2nd floor
(i) Basic rate = 86.45
(ii) Add 5 % extra Labour = 3.75
Over Head Charge 7.5 % = = 0.28
Contractor's Profit 7.5 % = 0.28
Total = 90.76
Add 1% Labour cess = 0.90
Total = 91.66
Say Rs. 91.70 per Cum
63 Dismantling and removing doors, windows and ventilators including
removal of frame, hinges, fastening and stacking the same for reuse and
removing the debris within 50m lead
Ref :-A/R - 2006 ,P - 219, Item No-18
Data for 2.60 Sqm.
Carpenter Second Class 0.50 Each 423.00 211.50
Man mulias 0.60 Each 333.00 199.80
Woman mulias 1.00 Each 333.00 333.00
Over Head Charge 7.5 % = 55.82
Contractor's Profit 7.5 % = 55.82
Total = 855.94
Rate per Sqm = 329.20
Add 1% Labour cess = 3.29
Total = Rs 332.49
Say Rs. 332.50 per Sqm.
(B) First floor
(i) Basic rate = 329.20
(ii) Add 5 % extra Labour = 14.31
Over Head Charge 7.5 % = = 1.07
Contractor's Profit 7.5 % = 1.07
Total = 345.65
Add 1% Labour cess = 3.45
Total = Rs 349.10
Say Rs. 349.10 per Sqm.
(B) 2nd floor
(i) Basic rate = 345.65
(ii) Add 5 % extra Labour = 15.02
Sl. No. Description Qnty. Unit Rate Amount
Over Head Charge 7.5 % = = 1.12
Contractor's Profit 7.5 % = 1.12
Total = 361.79
Add 1% Labour cess = 3.61
Total = Rs 365.40
Say Rs. 365.40 per Sqm.
11 Providing, fitting , fixing A.C. Sheet in roof including fixing of ridges wind
ties etc. complete but including cost of fitting including drilling holes in wind
ties
Ref :-A/R - 2006, P - 126, Item No-33
Data for 9.3Sqm.
a) Labour
Carpenter Second Class 1.00 Each 483.00 483.00
Man mulia 3.00 Each 333.00 999.00
Over Head Charge 7.5 % = 111.15
Contractor's Profit 7.5 % = 111.15
Total= 1704.30
For 1 Sqm= 1704.30 9.30 183.25
per Sqm.
C) Materials
Cost of A.C. Sheet 1.10 Sqm 157.48 173.22
Nuts and Bolt 0.03 Kgs. 60.63 1.81
L/J hooks 0.132 Kgs. 56.17 7.41
Total= 182.44
Grand total = 365.69
Add 1% Labour cess = 3.65
Total = Rs 369.34
Say Rs. 369.30 per Sqm.
12 Providing, fitting , fixing G.C.I. Sheet in roof including fixing of ridges wind
ties etc. complete but including cost of fitting including drilling holes in wind
ties
Ref :-A/R - 2006, P - 126, Item No-33
Data for 9.3Sqm.
a) Labour
Carpenter special class 0.50 Each 483.00 241.50
Fitter Special 1.00 Each 483.00 483.00
Man mulia 2.00 Each 333.00 666.00
Over Head Charge 7.5 % = 104.28
Contractor's Profit 7.5 % = 104.28
Total= 1599.06
For 1 Sqm= 1599.06 9.30 171.94
per Sqm.
d) Materials
Cost of G.C.I Sheet(0.30mm) thick 1.10 Sqm 238.30 262.13
Nuts and Bolt 0.030 Kgs. 60.63 1.81
L/J hooks 0.132 Kgs. 56.17 7.41
Total= 271.35
Total (a+b+c+d)= 443.29
Add 1% Contingency = 4.43
Total= 447.72
Say Rs. 447.70 per Sqm.
d) Materials
Cost of G.C.I Sheet(0.40mm) thick 1.10 Sqm 246.81 271.49
Nuts and Bolt 0.030 Kgs. 60.63 1.81
L/J hooks 0.132 Kgs. 56.17 7.41
Total= 280.71
Total= 452.65
Add 1% Labour cess = 4.52
Total= 457.17
Sl. No. Description Qnty. Unit Rate Amount
Say Rs. 457.20 per Sqm.
66 20cm to 25cm. Single Nuria Tiles roofing with cement mortar (1:6) borders
23cm×5cm at 1.8 meters intervals complete.
Ref :-A/R - 2006, P - 115, Item No-1
Data for 9.30Sqm.
a) Materials
Nuria tiles 20cm to 25 cm long 1000.00 Nos 0.580 580.00
Cement 0.53 Qntls 517.42 274.23
Sand 0.19 Cum. 50.48 9.59
Total= 863.82
b) Labour
Gharami 2.00 Each 373.00 746.00
Mason 0.25 Each 423.00 105.75
Man mulia 0.50 Each 333.00 166.50
Total= 1018.25
Over Head Charge 7.5 % = 141.15
Contractor's Profit 7.5 % = 141.15
d) Carriage & royalty
Nuria tiles 20 mm to 25 mm 1000.00 Nos. 203.00 253.75
per 800 Nos
Cement 0.53 Qntls 5.50 2.91
Sand 0.19 Cum. 184.67 35.08
Total= 291.74
Total (a+b+c+d)= 2456.11
For 1 Sqm= 2456.11 9.30 264.09
Add 1% Labour cess = 2.64
Total= 266.73
Say Rs. 266.70 per Sqm.
67 20cm to 25cm. Long Double Nuria Tiles roofing with cement mortar(1:6)
borders 23cm×5cm at 1.80 meters intervals complete per 1 sqm

Ref :-A/R - 2006, P - 115, Item No-3


Data for 9.30Sqm.
a) Materials
Nuria tiles 20cm to 25 cm long 2000.00 Nos 0.580 1160.00
Cement 0.53 Qntls 517.42 274.23
Sand 0.19 Cum. 50.48 9.59
Total= 1443.82
b) Labour
Gharami 3.00 Each 373.00 1119.00
Mason 0.25 Each 423.00 105.75
Man mulia 0.50 Each 333.00 166.50
Total= 1391.25
Over Head Charge 7.5 % = 212.63
Contractor's Profit 7.5 % = 212.63
d) Carriage & royalty
Nuria tiles 20 mm to 25 mm 2000.00 Nos. 203.00 507.50
per 800 Nos
Cement 0.53 Qntls 5.50 2.91
Sand 0.19 Cum. 184.67 35.08
Total= 545.49
Total (a+b+c)= 3805.82
For 1 Sqm= 3805.82 9.30 409.22
Add 1% Labour cess = 4.09
Total= 413.31
Say Rs. 413.30 per Sqm.
68 Shifting or relaying Nuria tiles in single Nuria tiles roof (labour only) (in all
floor)
Ref :-A/R - 2006, P - 114, Item No-1
Sl. No. Description Qnty. Unit Rate Amount
Data for 9.30Sqm.
a) Labour
Gharami 1.00 Each 373.00 373.00
Man mulia 0.50 Each 333.00 166.50
Over Head Charge 7.5 % = 40.46
Contractor's Profit 7.5 % = 40.46
Total= 620.42
For 1 Sqm= 620.42 9.30 66.71
Add 1 % Labour Cess = 0.66
Total= 67.37
Say Rs. 67.40 per Sqm.
69 Double under reamed pile foundation with R.C.C. M - 20 using 12mm size
black hard granite (crusher broken)stone chips including cost of boreholes
but excluding cost of M.S. rod/Tor steel and labour chrages for cutting,
bending and binding of steel.
Ref :-A/R - 2006 ,P - 211, Item No-2
a) 375mm dia 6.00mtrs long
Data for 1 pile
Excavation of bore hole (assuming two pits can 2.00 Each 483.00 966.00
be constructed per day) Boring Mistry(Special)
Winch operator 0.50 Each 483.00 241.50
Hire & running charges of tripod 0.50 Each 450.00 225.00
Bentonite power 2.50 Each Bag 145.00 362.50
Over Head Charge 7.5 % = 134.62
Contractor's Profit 7.5 % = 134.62
Total = 2064.24
Exacvation of Bore Hole (take 90%) = 1857.81
Volume of Concrete = (3.14)/4x(0.30)² x 6 +4.13x(0.30)³
(Rate same as Item No. No. 4 of RCC) 0.5350 Cum. 4683.20 2505.51
Add- Cost of 10% extra cement 0.1729 Qntl 517.42 89.46
Total = 4452.78
per Pile
13 Clearing and grubbing road land including prooting rank vegetation, grass,
bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps
of trees cut earlier and disposal of un-serviceable materials and stacking of
serviceable material to be used or auctioned, up to a lead of 1000 metres
including removal and disposal of top organic soil not exceeding 150 mm in
thickness.

(A.R.-2006, Page No - 196, Item No. - 3)


Data for 1 Hectare = 2.47103 Acer
In area of light jungle
a) Labour
Mate 6.00 Each 373.00 2238.00
Mulia 150.00 Each 333.00 49950.00
Total = 52188.00
b) Machineries
Tractor - trolly 1.00 Hour 200.87 200.87
Total = 200.87
Over Head Charge 7.5 % = 3929.17
Contractor's Profit 7.5 % = 3929.17
Total= 60247.21
For 1 Sqm = Rs. 6.02
Total = Rs 6.02
Add 1 % Labour Cess = 0.06
Total= 6.08
Say Rs. 6.10 per Sqm.
Sl. No. Description Qnty. Unit Rate Amount
71 Dismantling pan or single Nuria or Mangalore tileroofing (Tiles only)
including stacking the useful materials for reuse and removing the debris
within 50m. Lead
Ref :-A/R - 2006, P-216, Item No - 7
Unit:- 1 Sqm, Data for 9.30 Sqms.
a) Labour
Man mulia 1.00 Each 333.00 333.00
Women mulia 1.75 Each 333.00 582.75
Total = 915.75
Over Head Charge 7.5 % = 68.68
Contractor's Profit 7.5 % = 68.68
Total = 1053.11
Rate per 1 Sqm 113.23
Total = Rs 113.23
Add 1 % Labour Cess = 1.13
Total= 114.36
Say Rs. 114.40 per Sqm.
71 Dismantling flat & pan tiled roofing (Tiles only) including stacking the useful
materials for reuse and removing the debris within 50m. Lead

Ref :-A/R - 2006, P-216, Item No - 7


Unit:- 1 Sqm, Data for 9.30 Sqms.
a) Labour
Man mulia 1.25 Each 333.00 416.25
Women mulia 4.00 Each 333.00 1332.00
Total = 1748.25
Over Head Charge 7.5 % = 131.11
Contractor's Profit 7.5 % = 131.11
Total = 2010.47
Rate per 1 Sqm 216.17
Total = Rs 216.17
Add 1 % Labour Cess = 2.16
Total= 218.33
Say Rs. 218.30 per Sqm.
72 Dismantling G.C.I. or A.C. sheet roofing after carefully removing the bolts
and nuts including stacking of the materials for reuse and removing the
debris within 50m lead
Ref :-A/R - 2006, P-218, Item No - 18
Unit:- 1 Sqm, Data for 9.30 Sqms.
a) Labour
Fitter 0.25 Each 423.00 105.75
Man mulia 0.50 Each 333.00 166.50
Women mulia 1.00 Each 333.00 333.00
Total = 605.25
Over Head Charge 7.5 % = 45.39
Contractor's Profit 7.5 % = 45.39
Total (a+b+c)= 696.03
Rate for 1 Sqm = 74.84
Add 1% Labour cess = 0.74
Total = Rs 75.58
Say Rs. 75.60 per Sqm.
a First floor
(i) Basic rate = 74.84
(ii) Add 5 % extra Labour = 3.25
Over Head Charge 7.5 % = = 0.24
Contractor's Profit 7.5 % = 0.24
Total = 78.57
Add 1% Labour cess = 0.78
Total = 79.35
Sl. No. Description Qnty. Unit Rate Amount
Say Rs. 79.40 per Sqm.
b 2nd floor
(i) Basic rate = 78.57
(ii) Add 5 % extra Labour = 3.41
Over Head Charge 7.5 % = = 0.25
Contractor's Profit 7.5 % = 0.25
Total = 82.48
Add 1% Labour cess = 0.82
Total = 83.30
Say Rs. 83.30 per Sqm.
73 Dismantling double Nuria tileroofing (Tiles only) including stacking the
useful materials for reuse and removing the debris within 50m. Lead

Ref :-A/R - 2006, P-216, Item No - 16


Unit:- 1 Sqm, Data for 9.30 Sqms.
a) Labour
Man mulia 1.25 Each 333.00 416.25
Women mulia 3.00 Each 333.00 999.00
Total = 1415.25
Over Head Charge 7.5 % = 106.14
Contractor's Profit 7.5 % = 106.14
Total = 1627.53
Total (a+b+c)= 175.00
Add 1% Labour cess = 1.75
Total = 176.75
Say Rs. 176.80 per Sqm.
(B) First floor
(i) Basic rate = 175.00
(ii) Add 5 % extra Labour = 7.60
Over Head Charge 7.5 % = = 0.57
Contractor's Profit 7.5 % = 0.57
Total = 183.74
Add 1% Labour cess = 1.83
Total = 185.57
Say Rs. 185.60 per Sqm.
(C) 2nd floor
(i) Basic rate = 183.74
(ii) Add 5 % extra Labour = 7.98
Over Head Charge 7.5 % = = 0.59
Contractor's Profit 7.5 % = 0.59
Total = 192.90
Add 1% Labour cess = 1.92
Total = 194.82
Say Rs. 194.80 per Sqm.
74 Dismantling reapers under tiled roof (pan, flat or nuria tiles) after careful
removal of nails including stacking the useful materials for reuse and
removing the debris within 50m. lead
Ref :-A/R - 2006, P-216, Item No - 8
Unit:- 1 Sqm, Data for 9.30 Sqms.
a) Labour
Carenter(2nd Class) 0.33 Each 423.00 139.59
Women mulia 1.25 Each 333.00 416.25
Total = 555.84
Over Head Charge 7.5 % = 41.68
Contractor's Profit 7.5 % = 41.68
Total = 639.20
Rate for 1 Sqm = 68.73
Add 1% Labour cess = 0.68
Total = 69.41
Sl. No. Description Qnty. Unit Rate Amount
Say Rs. 69.40 per Sqm.
75 Dismantling wrought and framed timber in roof frame work of roofs after
careful removal of nail, bolts etc. and stacking of the materials for reuse
and removing the debris within 50m lead
Ref :-A/R - 2006, P-219, Item No - 17
Unit:- 1 Cum, Data for 0.0283 Cums.
a) Labour
Carpenter (2nd class) 0.03 Nos Each 423.00 12.69
Man Mulia 0.04 Nos Each 333.00 13.32
T= 26.01
Over Head Charge 7.5 % = 1.95
Contractor's Profit 7.5 % = 1.95
Total (a+b+c) = 29.91
Rate per 1 cum = 1056.89
Add 1% Labour cess = 10.56
Total = Rs 1067.45
Say Rs. 1067.50 per Cum
14 Removing old lime or cement plaster from walls including raking out joints
12 mm deep and removing the debris within 50m lead
Ref :-A/R - 2006, P-218, Item No - 13
Unit:- 1 Sqm, Data for 9.30 Sqms.
a) Labour
Mulia 1.00 Each 333.00 333.00
Total = 333.00
Over Head Charge 7.5 % = 24.97
Contractor's Profit 7.5 % = 24.97
Total (a+b+c)= 382.94
Rate per Sqm= 41.17
Add 1% Labour cess = 0.41
Total = Rs 41.58
Say Rs. 41.60 Per Sqm
1st floor:-
(i) Basic Rate:- 41.17
(ii) 5% Extra on Labour:- 1.79
Over Head Charge 7.5 % = 0.13
Contractor's Profit 7.5 % = 0.13
43.22
Add 1% Labour cess = 0.43
Total = Rs 43.65
Say Rs. 43.70 Per Sqm
2nd floor:-
(i) Basic Rate:- 43.22
(ii) 5% Extra on Labour:- 1.87
Over Head Charge 7.5 % = 0.14
Contractor's Profit 7.5 % = 0.14
45.37
Add 1% Labour cess = 0.45
Total = Rs 45.82
Say Rs. 45.80 Per Sqm
77 Dismantling terraced roof (Madras or Orissa) including stacking the useful
materials for reuse and removing the debris within 50m lead
Ref :-A/R - 2006, P-218, Item No - 15
Unit:- 1 Sqm, Data for 9.30 Sqms.
a) Labour
Man mulia 2.35 Each 333.00 782.55
Woman mulia 4.00 Each 333.00 1332.00
Total = 2114.55
Over Head Charge 7.5 % = 158.59
Contractor's Profit 7.5 % = 158.59
Sl. No. Description Qnty. Unit Rate Amount
Total (a+b+c)= 2431.73
Rate per Sqm = 261.47
Add 1% Labour cess = 2.61
Total = Rs 264.08
Say Rs. 264.10 Per Sqm
1st floor:-
(i) Basic Rate:- 261.47
(ii) 5% Extra on Labour:- 11.36
Over Head Charge 7.5 % = 0.85
Contractor's Profit 7.5 % = 0.85
274.53
Add 1% Labour cess = 2.74
Total = Rs 277.27
Say Rs. 277.30 Per Sqm
2nd floor:-
(i) Basic Rate:- 274.53
(ii) 5% Extra on Labour:- 11.92
Over Head Charge 7.5 % = 0.89
Contractor's Profit 7.5 % = 0.89
288.23
Add 1% Labour cess = 2.88
Total = Rs 291.11
Say Rs. 291.10 Per Sqm
78 Dismantling and removing R.C.C. columns beams slab staircase landing
lintels including stacking the useful materials for reuse and removing the
debris within 50m lead
Ref :-A/R - 2006, P-221, Item No - 24
Unit:- 1 Cum
a) Labour
Semi Skilled mulia 1.50 Each 373.00 559.50
Man mulia 1.50 Each 333.00 499.50
Total = 1059.00
Over Head Charge 7.5 % = 79.42
Contractor's Profit 7.5 % = 79.42
Total (a+b+c)= 1217.84
Add 1% Labour cess = 12.17
Total = Rs 1230.01
Say Rs. 1230.00 Per Cum
79 Providing and laying 0.600m dia NP 3 H.P. including all cost complete as
per direction of Engineer-in-charge.
Data for 1 Mtr.
a) Materials
Cost of 0.600m dia H.P. 1.00 Mtrs 1358.00 1358.00
Total = 1358.00
b) Labour
As per S.R. -2006 Page -125 Item - 20 - (f) 1.00 Mtr 28.10 28.10
c) Cost of Carriage of H.P.
5 Nos of 0.600m dia H.P. to be carriaed by Truck in 1 trips (Lead = 90 Km
from Sambalpur)
Hume pipe
1 No. of Hume pipe = 2.50 Mtr.
5 No. of Hume pipe = 5 x 2.50 Mtr. = 12.50 Mtr.
Total carriage of 12.50 Mtr H.P = Rs. 3682/- =
For 1.00m length of H.P. = 3682.00/12.50 = Rs. 294.56 per Rmt 1.00 Mtr 294.56 294.56
Total = 1680.66
Add 1% Labour cess = 16.81
Total = 1697.47
Say Rs. 1697.50 Per Rmt
Sl. No. Description Qnty. Unit Rate Amount
80 Providing weep holes on R.C.C. abutment, wing walls, return wall with
80mm dia A.C. pipe extended through the full width of the structure with
slope of 1:20 towards drainage face complete as per drawing and directed
by Engg-in-charge.
(A.R.-2006, Page No - 264, Item No. - 7)
Data for 30.00 mtrs.
a) Materials
A.C.pipe (including wastage @ 5 per cent ) 31.50 Mtr. 60.00 1890.00
M.S.Clamp 30.00 Each 10.00 300.00
Coal tar for A.C. pipe 10.00 Each 6.00 60.00
Cement mortar (1:3) 0.05 Cum. 665.90 33.29
Total = 2283.29
b) Labour
Mate 0.03 Each 373.00 11.19
Mason Second Class 0.50 Each 423.00 211.50
Mulia 0.25 Each 333.00 83.25
Total = 305.94
Over Head Charge 7.5 % = 194.19
Over Head Charge 7.5 % = 194.19
Total =(a+b+c) = Rs. 2977.61
99.25
Add 1% Labour cess = 0.99
Total = 100.24
Or say 100.20 per Rm.
80 Providing weep holes on brick wall, concrete wall with 60mm dia P.V.C.
pipe extended through the full width of the structure with slope of 1:20
towards drainage face complete as per drawing and directed by Engg-in-
charge.
(A.R.-2006, Page No - 264, Item No. - 7)
Data for 30.00 mtrs.
a) Materials
A.C.pipe (including wastage @ 5 per cent ) 31.50 Mtr. 60.00 1890.00
Total = 1890.00
b) Labour
Mate 0.03 Each 373.00 11.19
Mason Second Class 0.50 Each 423.00 211.50
Mulia 0.25 Each 333.00 83.25
Total = 305.94
Over Head Charge 7.5 % = 164.69
Contractor's Profit 7.5 % = 164.69
Total =(a+b+c) = Rs. 2525.32
84.17
Add 1% Labour cess = 0.84
Total = 85.01
Or say 85.00 per Rm.
81 Providing, fitting, fixing of false celling made out of gypsum board of any
make with aluminum anodised T-Section No 3215 with 2'-0" centre to
centre, L-Section no 1705 upto 15 micron on 4 walls tobe fixed by means
of steel screws and pvc plug and the aluminium grid of 2'-0" x 2'-0" with
Gypsum board suspended from celling including cost of all materials, cost
of all labour T&P etc. complete

Ref :- A/R - 2006, P-237, Item No - 3


data for 14'-6" x 14'-6"=210.25 Sft or 19.53 Sqm
(a) Material
Aluminium anodised T-section No-3215 = 16 x 4.41 = 70.56 M @ 18.20
0.258Kg/m =
Perimeter Angle section No-1785 = 17.64m @ 0.233 Kg/m = 4.11
Total = 22.31 Kgs
Wastage 5% = 1.12
Sl. No. Description Qnty. Unit Rate Amount
23.43 Kgs 224.68 5264.25
PVC Rawl plug 42.00 Nos 7.00 294.00
9" connecting hooks with nuts & washer 42.00 Nos 5.50 231.00
G.I. wire 2.00 Kgs 51.06 102.12
12 thick gypsum 20.59 Sqm 135.94 2799.00
65mm PVC Plug 50.00 Nos 0.60 30.00
Screw 50mm x 8mm 50.00 Nos 0.63 31.50
Hire charges of drill machine 1.50 Day 100.00 150.00
Total= 8901.87

(b)Labour
Carpenter 1st Class 5.00 483.00 2415.00
Muila 5.00 333.00 1665.00
Total= 4080.00
Over Head Charge 7.5 % = 973.64
Contractor's Profit 7.5 % = 973.64
Total(a+b+c+d)= 14929.15
Rate per Sqm = 764.42
Add 1% Labour cess = 7.64
Total = Rs 772.06
Say Rs. 772.10 per Sqm.
15 Finishing wall surface with Acrylic wall putty (water based) of approved
make and finished smooth & even surface to receive painting including cost
of scaffolding etc. with cost of all materials, labour T&P etc. complete.

Ref :-A/R - 2006, P-236, Item No - 2


Data for 10 Sqm
(a) Materials
Synthetic Putty 8.00 Kgs. 50.68 405.44
Total = 405.44
(b) Labour
Painter 2nd class 0.50 Nos 423.00 211.50
Mulia 0.57 Nos 333.00 189.81
Total = 401.31
Over Head Charge 7.5 % = 60.50
Contractor's Profit 7.5 % = 60.50
Total (a+b+c+d)= 927.75
Rate per Sqm = 92.77
Add 1% Labour cess = 0.92
Total = Rs 93.69
Say Rs. 93.70 per Sqm.
(B) First floor
(i) Basic rate = 92.77
(ii) Add 3 % extra Labour = 1.20
Over Head Charge 7.5 % = = 0.09
Contractor's Profit 7.5 % = 0.09
Total = 94.15
Add 1% Labour cess = 0.94
Total = Rs 95.09
Say Rs. 95.10 per Sqm.
(C) 2nd floor
(i) Basic rate = 94.15
(ii) Add 3 % extra Labour = 1.23
Over Head Charge 7.5 % = = 0.09
Contractor's Profit 7.5 % = 0.09
Total = 95.56
Add 1% Labour cess = 0.95
Total = Rs 96.51
Say Rs. 96.50 per Sqm.
Sl. No. Description Qnty. Unit Rate Amount
1 Providing and laying water proofs with polymeric bituminous membrane
(plastic felt) of 2.25Kg./Sqm and 2.00mm thickness consisting of layers
having centre core of 20 micros thermoplastic high molecular high density
polythyne H.M.H.D.P.E. film of grade 2504 including priming the surface
with bituminous primer @ 0.30 Kg./Sqm. providing a coat of hot blown
bitumen of 1.32kg. /Sqm applying and laying plastic felt membrane with
10c.m. overlap adhered to blown bitumen of 85/25 or 90/15 grade and
covered with a layer of hot blown bitumen @ 1.20Kg./Sqm. etc complete.

A/R - 2006/ P-238 Item No - 5


Data for 1 Sqm
a) Materials
2mm plastic felt 1.00 Sqm 84.00 84.00
Bitumen (Rate 01-12-2014) 2.70 Kg 29.34 79.21
Fule/firewod 0.0015 M.T. 4300.00 6.45
169.66
b) Labour
Semi skilled labour 0.025 Each 373.00 9.32
High skilled labour 0.100 Each 483.00 48.30
Skilled labour 0.028 Each 423.00 11.84
Total = 69.46
Over Head Charge 7.5 % = 17.93
Contractor's Profit 7.5 % = 17.93
d) Carraige and Royalty of Materials
Bitumen 2.70 Kg 0.760 2.05
Total = 2.05
Total = Rs. 277.03
Add 1% Labour cess = 2.77
Total = Rs 279.80
Say Rs. 279.80 per Sqm.
85 Providing and laying water proofs with polymeric bituminous membrane
(plastic felt) of 2.25Kg./Sqm and 1.50mm thickness consisting of layers
having centre core of 20 micros thermoplastic high molecular high density
polythyne H.M.H.D.P.E. film of grade 2504 including priming the surface
with bituminous primer @ 0.30 Kg./Sqm. providing a coat of hot blown
bitumen of 1.32kg. /Sqm applying and laying plastic felt membrane with
10c.m. overlap adhered to blown bitumen of 85/25 or 90/15 grade and
covered with a layer of hot blown bitumen @ 1.20Kg./Sqm. etc complete.

A/R - 2006/ P-238 Item No - 5


Data for 1 Sqm
a) Materials
1.5mm plastic felt 1.00 Sqm 72.00 72.00
Bitumen 2.70 Kg 29.34 79.21
Fule 0.0015 M.T. 4300.00 6.45
157.66
b) Labour
Semi skilled labour 0.025 Each 373.00 9.32
High skilled labour 0.100 Each 483.00 48.30
Skilled labour 0.028 Each 423.00 11.84
Total = 69.46
Over Head Charge 7.5 % = 17.03
Contractor's Profit 7.5 % = 17.03
d) Carraige and Royalty of Materials
Bitumen 2.70 Kg 0.760 2.05
Total = 2.05
Total = Rs. 246.20
Add 1% Labour cess = 2.46
Total = Rs 248.66
Sl. No. Description Qnty. Unit Rate Amount
Say Rs. 248.70 per Sqm.
120 Fixing granite tile (Above 0.40 Sqm) (20mm thick) in floors treads or steps
and landing on 20mm thick bed of cement mortar 1:4 (1cement : 4sand)
jointed with neat cement slury mixed with pigment to match the shades of
the tiles including rubbing and polishing complete including cost, carriage,
royalty & taxes of all material, cost of all labour T&P etc. complete.

(A.R.-2006, Page No - 89, Item No. - 16)


Data for 10 Sqms.
a) Materials
Cost of tile 10.000 Sqm 1645.67 16456.70
Sand 0.21 Cum. 50.48 10.60
Cement 0.744 Qntl 517.42 384.96
Cement for slurry 0.33 Qntl 517.42 170.74
White Cement 0.076 Qntl 1413.39 107.41
Total = 17130.41
b) Labour
Mason Special 2.16 Each 483.00 1043.28
Mulia 2.16 Each 333.00 719.28
Total = 1762.56
Over Head Charge 7.5 % = 1416.97
Contractor's Profit 7.5 % = 1416.97
d) Cost of Carriage and Royality of Materials
Tile 10.00 Sqm 5.37 53.73
Sand 0.21 Cum. 184.67 38.78
Cement 0.744 Qntl 5.50 4.09
Cement for slurry 0.33 Qntl 5.50 1.81
White Cement 0.076 Qntl 5.50 0.41
Total= 98.82
Total =(a+b+c+d) = Rs. 21825.73
For 1 Sqm = Rs. 2182.57
Add 1 % Labour Cess = 21.82
Total= 2204.39
Say Rs. 2204.40 per Sqm.
1st floor:-
Basic Rate: = 2182.57
(ii) Add 5 % extra labour 8.81
Over Head Charge 7.5 % = 0.66
Contractor's Profit 7.5 % = 0.66
Total= 2192.70
Add 1% Labour cess = 21.92
Total = Rs 2214.62
Say Rs. 2214.60 per Sqm.
2nd floor:-
Basic Rate: = 2192.70
(ii) Add 5 % extra labour 9.25
Over Head Charge 7.5 % = 0.69
Contractor's Profit 7.5 % = 0.69
Total= 2203.33
Add 1% Labour cess = 22.03
Total = Rs 2225.36
Say Rs. 2225.40 per Sqm.
86 Fixing granite tile (Above 0.40 Sqm) (20mm thick) dados skirting and risers
of steps on 12mm thick cement plaster (1:3) jointed with neat cement slurry
mixed with pigments to match the shade of the tiles including rubbing and
polishing complete including cost of material, labour, T&P etc. complete

(A.R.-2006, Page No - 90, Item No. - 17)


Data for 10 Sqms.
Sl. No. Description Qnty. Unit Rate Amount
a) Materials
Sand 0.15 Cum. 50.48 7.57
Cement 0.715 Qntl 517.42 369.95
Cement for slurry 0.66 Qntl 517.42 341.49
Granite tiles 10.00 Sqm 1645.67 16456.70
Total = 17175.71
b) Labour
Mason Special 3.25 Each 483.00 1569.75
Mulia 3.25 Each 333.00 1082.25
Total = 2652.00
Over Head Charge 7.5 % = 1487.07
Contractor's Profit 7.5 % = 1487.07
d) Cost of Carriage and Royality of Materials
Sand 0.15 Cum. 184.67 27.70
Cement 1.375 Qntl 5.50 7.56
Granite tiles 10.00 Sqm 5.37 53.73
Total= 88.99
Total =(a+b+c+d) = Rs. 22890.84
For 1 Sqm = Rs. 2289.08
Add 1% Labour cess = 22.89
Total = Rs 2311.97
Say Rs. 2312.00 per Sqm.
1st floor:-
Basic Rate: = 2289.08
Add 5 % extra labour 13.26
Over Head Charge 7.5 % = 0.99
Contractor's Profit 7.5 % = 0.99
Total= 2304.32
Add 1% Labour cess = 23.04
Total = Rs 2327.36
Say Rs. 2327.40 per Sqm.
2nd floor:-
Basic Rate: = 2304.32
Add 5 % extra labour 13.92
Over Head Charge 7.5 % = 1.04
Contractor's Profit 7.5 % = 1.04
Total= 2320.32
Add 1% Labour cess = 23.20
Total = Rs 2343.52
Say Rs. 2343.50 per Sqm.
87 R.C.C. (1:1½:3) with 12mm and down grade C.B. chips including hoisting,
laying hire charges of concrete mixture, vibrator, watering, curing and cost
of all materials and labour, T&P centering shuttering etc complete but
excluding cost of ment complete.
(To be used in minor work)
(A.R.-2006, Page No - 49, Item No. - 2)
Data for 1 Cum.
a) Materials
12mm size Granite C.B. chips 0.90 Cum. 1045.71 941.13
Sand 0.45 Cum. 184.67 83.10
Cement 4.29 Qntl 517.42 2219.73
Total = 3243.96
b) Labour
Mason Second Class 0.68 Each 423.00 287.64
Labour 4.60 Each 333.00 1531.80
Total = 1819.44
Over Head Charge 7.5 % = 379.75
Contractor's Profit 7.5 % = 379.75
d) Cost of Carriage and Royalty of Materials
Sl. No. Description Qnty. Unit Rate Amount
12mm size Granite C.B. chips 0.90 Cum. 719.21 647.28
Sand 0.45 Cum. 184.67 83.10
Cement 4.29 Qntl 5.50 23.59
Total= 753.97
Total =(a+b+c+d) = Rs. 6576.87
Add 1% Labour cess = 65.76
Total = Rs 6642.63
Say Rs. 6642.60 Per Cum
89 Scraping old paint with scrapers, sand papering and washing with soap
water or soda including scaffolding charges up to 5mtr height.

S/R - 2006 Page 112/ Item No. (h) 8


Say Rs. 3.37 per Sqm.
Add 1% Labour cess = 0.03
Total = Rs 3.40
Say Rs. 3.40 per Sqm.
16 Hoisting joists and trusses and placing in position including cost, carriage,
royalty and taxes of all materials, cost of all labour, T&P etc complete as
per the direction of E.I.C.
A/R - 2006 Page No. - 224 Item - 1
Data for 0.508 Qntl.
Sambalpur Exfactory Rate
a) Angle 0.508
Wastage 10 % = 0.0508
Total = 0.5588 MT 54319.00 3035.35
Total = 3035.35
a) Labour
Single Mulia for conveying joist from outside to the buildings 0.25 Each 373.00 93.25
Sangi Mulia for fitting joists up top of the walls with ropes etc. 0.75 Each 373.00 279.75
Man Mulia for placing joists in position 0.17 Each 333.00 56.61
Total = 429.61
Over Head Charge 7.5 % = 259.87
Contractor Profit 7.5 % = 259.87
Total (a+b+c) = 3984.70
Rate per 1 Qntl = 7843.90
d) Carriage 1.10 Qntl 76.27 83.90
Total = Rs 7927.80
Add 1 % Labour cess = 79.28
Total = Rs 8007.08
Say Rs. 8007.10 per Qntl
92 Taking out the door or window shutter and reflexing them after necessary
repair including screw as may be required
(a) Door
(As per S/R - 2006, Page No. - 105 Item No. 12 (a)) 51.63
Add 1% Labour cess = 0.51
Total = Rs 52.14
Say Rs. 52.10 per Each
(b) Window
(As per S/R - 2006, Page No. - 105 Item No. 12 (b)) 31.44
Add 1% Labour cess = 0.31
Total = Rs 31.75
Say Rs. 31.80 per Each
94 Rubbing old marble tile flooring and dados skirting including wax polishing
to give granolithic finish including cost of all materials, cost of all labour
T&P, etc. complete.
S/R - 2006 Page-110/Item (e) 3 Rs. 52.88
Add 1% Labour cess = 0.52
Total = 53.40
Say Rs. 53.40 per Sqm.
Sl. No. Description Qnty. Unit Rate Amount
95 Removing old grading plaster from roof slab, cleaning the surface, lowering
and removing the debris within 50m lead.
S/R - 2006 Page - 220 Item No. 21
per 1 sqm
Data for 9.30 sqm
a) Labour
Man Mulia 1.40 Nos 333.00 466.20
Woman Mulia 0.15 Nos 333.00 49.95
T= 516.15
Over Head Charge 7.5 % = 38.71
Contractor's Profit 7.5 % = 38.71
Total (a+b+c) = 593.57
Rate per 1 sqm = 63.82
Add 1 % Labour Cess = 0.63
Total= 64.45
Say Rs. 64.50 per Sqm
96 Removing old tarfelt from roof slab, cleaning the surface, lowering and
removing the debris within 50m lead
S/R - 2006 Page - 221 Item No. 22
per 1 sqm
Data for 9.30 sqm
a) Labour
Man Mulia 1.75 Nos 333.00 582.75
Over Head Charge 7.5 % = 43.70
Contractor's Profit 7.5 % = 43.70
Total (a+b+c) = 670.15
Rate per 1 sqm = 72.05
Add 1 % Labour Cess = 0.72
Total= 72.77
Say Rs. 72.80 per Sqm
1st floor:-
(i) Basic Rate:- 72.05
(ii) 5% Extra on Labour:- 3.13
Over Head Charge 7.5 % = 0.23
Contractor's Profit 7.5 % = 0.23
75.64
Add 1 % Labour Cess = 0.75
Total= 76.39
Say Rs. 76.40 Per Sqm
97 Dismantling and removing R.C.C. Chajja, Selves, fins and parapet
including stacking the useful materials for reuse and removing the debris
within 50m lead
S/R - 2006 Page - 222 Item No. 25
per 1 sqm
Data for 9.30 sqm
a) Labour
Man Mulia 3.50 Nos 333.00 1165.50
Over Head Charge 7.5 % = 87.41
Contractor's Profit 7.5 % = 87.41
Total (a+b+c) = 1340.32
Rate per 1 sqm = 144.12
Add 1 % Labour Cess = 1.44
Total= 145.56
Say Rs. 145.60 per Sqm
1st floor:-
(i) Basic Rate:- 144.12
(ii) 5% Extra on Labour:- 6.26
Over Head Charge 7.5 % = 0.46
Contractor's Profit 7.5 % = 0.46
Sl. No. Description Qnty. Unit Rate Amount
151.30
Add 1 % Labour Cess = 1.51
Total= 152.81
Say Rs. 152.80 Per Sqm
2nd floor:-
(i) Basic Rate:- 151.30
(ii) 5% Extra on Labour:- 6.57
Over Head Charge 7.5 % = 0.49
Contractor's Profit 7.5 % = 0.49
158.85
Add 1 % Labour Cess = 1.58
Total= 160.43
Say Rs. 160.40 Per Sqm
17 Providing fitting and fixing up partition walling OEL aluminum anodized
section No.9210 and 9207 as single groove and double groove respectively
as horizontal and vertical member and OEL section 4660 as Tapered clip
for fixing up 12mm thick pre laminated board (Nova pan Make) and jointing
angle No. 1855 but excluding cost of glass and pre laminated boardetc
complete

A/R - 2006, Page No. - 239 Item No. - 6


Data for 6'-10" x 7'-06" = 51.22Sft or 4.76 Sqm 24.39 Kg
a) Materials
External Frame
Al. Section No 9210, Vertical =2.08 Horizontal = 2.286 = 4.37m total length 11.97 Kg
8.74m 8.74 m @ 1.37Kg/M =
Internal Frame:
Al. Section No 9207 Vertical & Horizontal (2.08+2.286) = 4.37 m @ 6.21
1.42Kg/M =
Tappered Clip Sec. No 4660 34.94m@0.169Kg/M= 5.90
Al. angle Sec. No 1855 12 nos. = 0.60m @ 0.518Kg/M= 0.31
T= 24.39 Kg
Wastage 5% = 1.22 Kg
Total = 25.61 Kg 224.68 5754.05
T Rubber beads 34.94 Mtr 10.00 349.40
PVC Rawl plug 40.00 Nos. 7.00 280.00
3"Screws 10.00 Nos. 2.00 20.00
Screws 50 mm x 8mm 30.00 Nos. 0.63 18.90
Hire charges of drills machine 2.00 Day 100.00 200.00
T= 6622.35
b) Labour
Carpenter 1st class 1.50 Nos. 483.00 724.50
Fitter 2nd Class 1.50 Nos. 423.00 634.50
Helper to Carpainter 3.30 Nos. 373.00 1230.90
Mulia 3.30 Nos. 333.00 1098.90
T= 3688.80
Over Head Charge 7.5 % = 773.33
Contractor's Profit 7.5 % = 773.33
Total (a+b+c+d) = 11857.81
Rate per kg = 486.17
Add 1 % Labour Cess = 4.86
Total= 491.03
Say ` 491.00 per Kg
14 Supplying of M.S. Door, Window with grills, Grills, collapsible gates made
out of M.S. Angle frame, M.S. Flat, Sheet etc of approved section &
design, electrically welded properly with all necessary locking arrengement,
and 1 coat red oxide primer including cost of all materials, labour T&P,
carriage of materials to site etc. complete.

Double Leafs Door Rs. 69.50 Kg


Sl. No. Description Qnty. Unit Rate Amount
Add 1% Labour cess = 0.69
Total = 70.19
Say ` 70.20 per Kg
Single Leaf Door Rs. 76.00 Kg
Add 1% Labour cess = 0.76
Total = 76.76
Say ` 76.80 per Kg
Double Leafs Window Rs. 67.30 Kg
Add 1% Labour cess = 0.67
Total = 67.97
Say ` 68.00 per Kg
Single Leaf Window Rs. 72.00 Kg
Add 1% Labour cess = 0.72
Total = 72.72
Say ` 72.70 per Kg
Grill window Rs. 57.00 Kg
Add 1% Labour cess = 0.57
Total = 57.57
Say ` 57.60 per Kg
Rolling Shutter Rs. 67.00 Kg
Add 1% Labour cess = 0.67
Total = 67.67
Say ` 67.70 per Kg
15 Labour charges for fitting, fixing M.S. gates (M.S. Door, Window with grills, Rs. 67.40 Sqm
Grills, collapsible gates) as per approved design including cost of all labour,
T&P etc. complete.
Add 1% Labour cess = 0.67
Total = 68.07
Say ` 68.10 per Sqm
23 Supplying fitting fixing of P.V.C. door of approved quality including cost of Rs. 170.00 Sft
all materials labour T&P etc complete.
Add 1% Labour cess = 1.70
Total = 171.70
Say ` 171.70 per Sft
102 Shifting or relaying Nuria tiles in Double Nuria tiles roof (labour only)

Ref :-A/R - 2006, P - 114, Item No-1


Data for 9.30Sqm.
a) Labour
Gharami 2.00 Each 373.00 746.00
Man mulia 0.75 Each 333.00 249.75
Over Head Charge 7.5 % = 74.68
Contractor's Profit 7.5 % = 74.68
Total= 1145.11
For 1 Sqm= 1145.11 9.30 123.13
Add 1 % Labour Cess = 1.23
Total= 124.36
Say Rs. 124.40 per Sqm.
103 Wall painting 1 coat with plastic emulsion paint of approved shade on old
work to give an even shade exculding cost of paint.
Per 1 Sqm.
Data for 10 Sqm.
a) Labour
Painter or polisher (special) 0.36 Nos each 483.00 173.88
Man Mulia 0.36 Nos each 333.00 119.88
Man Mulia for preparation of 0.07 Nos each 333.00 23.31
Total= 317.07
Over Head Charge 7.5 % = 23.78
Contractor's Profit 7.5 % = 23.78
Sl. No. Description Qnty. Unit Rate Amount
Total (a+b+c)= 364.63
Rate per 1 Sqm. = 9.53
Add cost of plastic emulsion paint = 0.75 x 196.06/10= 14.70
Total= 24.23
Add 1 % Labour Cess = 0.24
Total= 24.47
Say Rs. 24.50 per Sqm.
8 Providing, fitting, fixing of celling made out of Decco ceiling tile of any make
with aluminum anodised T-Section No 3215 with 2'-0" centre to centre, L-
Section no 1705 upto 15 micron on 4 walls tobe fixed by means of steel
screws and pvc plug and the aluminium grid of 2'-0" x 2'-0" suspended from
celling etc. complete.

Ref :- A/R - 2006, P-237, Item No - 3


data for 14'-6" x 14'-6"=210.25 Sft or 19.53 Sqm
(a) Material
Aluminium anodised T-section No-3215 = 16 x 4.41 = 70.56 M @ 18.20
0.258Kg/m =
Perimeter Angle section No-1785 = 17.64m @ 0.233 Kg/m = 4.11
Total = 22.31 Kgs
Wastage 5% = 1.12
23.43 Kgs 224.68 5264.25
PVC Rawl plug 42.00 Nos 7.00 294.00
9" connecting hooks with nuts & washer 42.00 Nos 5.50 231.00
G.I. Wire 2.00 Kgs 51.06 102.12
Decco tile 20.59 Sqm 190.00 3912.10
65mm PVC Plug 50.00 Nos 0.60 30.00
Screw 50mm x 8mm 50.00 Nos 0.63 31.50
Hire charges of drill machine 1.50 Day 100.00 150.00
Total= 10014.97

(b)Labour
Carpenter 1st Class 5.00 Each 483.00 2415.00
Muila 5.00 Each 333.00 1665.00
Total= 4080.00
Over Head Charge 7.5 % = 1057.12
Contractor's Profit 7.5 % = 1057.12
Total(a+b+c+d)= 16209.21
Rate per Sqm = 829.96
Add 1 % Labour Cess = 8.29
Total= 838.25
Say Rs. 838.30 per Sqm.
18 Disposal of the excavated materials from work site with mechanical means = 149.67 Cum
within 5.00km. initial leads as per direction of E.I.C.
Add 1% Labour cess = 1.49
Total = Rs 151.16
Say Rs. 151.20 per Cum
Colour washing two coats with shell lime and colouring materials
Ref :-A/R - 2006 ,P - 112, Item No-39
Data for 93 Sqm.
a) Materials
Shell lime un-slacked 18.66 Cum. 16.00 298.56
Total= 298.56
b) Labour
Painter Second class 1.50 Each 423.00 634.50
Man mulia 0.75 Each 333.00 249.75
Total= 884.25
Over Head Charge 7.5 % = 88.71
Contractor's Profit 7.5 % = 88.71
Total= 1360.23
Sl. No. Description Qnty. Unit Rate Amount
For 1 Sqm= 1360.23 93.00 14.63
Add 1 % Labour Cess = 0.14
Total= 14.77
Say Rs. 14.80 per Sqm.
108 Dismantling and removing old tiled flooring including removing the base
coarse and stacking the useful materials for reuse and removing the debris
within 50m lead
(A/R-2006, Page No.- 223, Item No.-28)
per 1 sqm
Data for 9.30 sqm
a) Labour
Man Mulia 1.00 Each 333.00 333.00
Woman Mulia 1.50 Each 333.00 499.50
832.50
Over Head Charge 7.5 % = 62.43
Contractor's Profit 7.5 % = 62.43
Total (a+b+c) = 957.36
Rate for 1 Sqm = 102.94
Add 1 % Labour Cess = 1.02
Total= 103.96
Say Rs. 104.00 per Sqm.
1st floor:-
Basic Rate: = 102.94
(ii) Add 3 % extra labour 2.68
Over Head Charge 7.5 % = 0.20
Contractor's Profit 7.5 % = 0.20
Total= 106.02
Add 1 % Labour Cess = 1.06
Total= 107.08
Say Rs. 107.10 per Sqm.
109 Cement Mortar 1:3 (1 cement : 3 sand)
Unit = 1 cum (Ref:- A/R - 2006 P -264 Item No.6)
Taking output = 1 cum
a) Materials
Cement 0.51 MT 517.42 263.88
Sand 1.05 Cum 50.48 53.00
b) Labour
Mate 0.04 Each 333.00 13.32
Mazdoor 0.90 Each 373.00 335.70
Total = 665.90
per Cum
110 Providing & Labour for spreading moorum & consolidation with H.R.R.
including , cost, carriage, royalty & taxes of all material etc. complete.

(A.R. - 2006, Page No - 142 Item No. - 7)


Unit = Cum, Taking out-put = 2.83 Cums.
(a) Labour
Man Mulia 1.50 Each 333.00 499.50
Woman Mulia 1.50 Each 333.00 499.50
Total = 999.00
Over Head Charge 7.5 % = 74.92
(b) Contractor profit 7.5% of (a)= 74.92
Total = 1148.84
Rate per Cum = 405.95
(d) Materials Cost , Carriage & Royalty
Moorum 1.28 Cum 229.43 293.67
Total (a+b+c+d) = 699.62
Add 1% Labour cess = 6.99
Total = 706.61
Sl. No. Description Qnty. Unit Rate Amount
Or say = 706.60 Per Cum
110 Providing & Labour for spreading moorum including , cost, carriage,
royalty & taxes of all material etc. complete.
(A.R. - 2006, Page No - 142 Item No. - 7)
Unit = Cum, Taking out-put = 2.83 Cums.
(a) Labour
Man Mulia 1.50 Each 333.00 499.50
Woman Mulia 1.50 Each 333.00 499.50
Total = 999.00
Over Head Charge 7.5 % = 74.92
(b) Contractor profit 7.5% of (a)= 74.92
Total = 1148.84
Rate per Cum = 405.95
(d) Materials Cost , Carriage & Royalty
Moorum 1.00 Cum 229.43 229.43
Total (a+b+c+d) = 635.38
Add 1% Labour cess = 6.35
Total = 641.73
Or say = 641.70 Per Cum
Dismantling and removing cement concrete including stacking the useful
materials for reuse and removing the debris within 50m lead
per 1 cum
Ref:- A/R - 2006, P- 221, Item No. 23
a) Labour
Man Mulia 1.50 Each 333.00 499.50
Woman Mulia 0.10 Each 333.00 33.30
Total = 532.80
Over Head Charge 7.5 % = 39.96
Contractor's Profit 7.5 % = 39.96
Total = 612.72
Add 1% Labour cess = 6.12
Total= 618.84
Say Rs. 618.80 Per Cum
Dismantling brick or stone masonry in clay under 3m. height including
stacking the useful materials for reuse and removing the debris within 50m.
Lead
Data for 2.83 cum
Ref:- A/R - 2006, P- 214, Item No. 1
a) Labour
Man Mulia 1.25 Each 333.00 416.25
Woman Mulia 3.50 Each 333.00 1165.50
Total = 1581.75
Over Head Charge 7.5 % = 118.63
Contractor's Profit 7.5 % = 118.63
Total = 1819.01
Rate for 1 Cum = 642.75
Add 1% Labour cess = 6.42
Total= 649.17
Or say = 649.20 Per Cum
111 Dismantling brick or stone masonry in clay above 3m. height including
stacking the useful materials for reuse and removing the debris within 50m.
Lead
Data for 2.83 cum
Ref:- A/R - 2006, P- 214, Item No. 2
a) Labour
Man Mulia 1.50 Each 333.00 499.50
Woman Mulia 3.50 Each 333.00 1165.50
Total = 1665.00
Over Head Charge 7.5 % = 124.87
Sl. No. Description Qnty. Unit Rate Amount
Contractor's Profit 7.5 % = 124.87
Total = 1914.74
Rate for 1 Cum = 676.58
Add 1% Labour cess = 6.76
Total= 683.34
Or say = 683.30 Per Cum
112 Dressed seasoned sal wood (50mm. to 150mm. & above 2.75m. long.)
work framed and fixed (wrought and put up) in trusses, purlins, frames of
doors, windows, ventilators and beams
(A.R.-2006, Page No - 132, Item No. - 2)
Data for 0.028 cum.
a) Material
Sal wood scantling sawn 0.028 Cum 28907.05 809.39
(Rate based on forest corporation rates)
b) Labour
Carpenter special 0.50 Nos 483.00 241.50
Man mulia 0.50 Nos 333.00 166.50
Total = 408.00
Total (a+b) = 1217.39
Over Head Charge 7.5 % = 91.30
Contractor's Profit 7.5 % = 91.30
Total (a+b+c) = 1399.99
Rate per 1 cum = 49999.64
Add 1% Labour cess = 499.99
Total= 50499.63
Or say = 50499.60 Per Cum
113 Construction of embankment with approved material obtained from borrow
pits with all lead and lifts ,transporting to site by mechanical means with a
lead of 5 Kms ,spreading,grading to required slope and compacting to meet
requirement of table 300 - 2 and clause 305 of MoSRT & H (4th revision ).

Ref: -A/R -2006, P-157, Item No.- 35


Taking out put 100 cum
a ) Labour
Mate 0.04 No 373.00 14.92
Mulia unskilled 1.00 No 333.00 333.00
Total= 347.92
b) Machinery
Hydraulic excavator @ 60 cum/h 1.67 Hour 730.43 1219.81
Tipper 10 t capacity (160T x 5Km= 800t.km) 800.00 t.km 2.17 1736.00
Loading and unloading @ 10% 173.60
Dozer 80 HP @ 200 cum/hour 0.50 Hour 1592.17 796.08
Motor Grader @ 100 cum / hour 1.00 Hour 772.50 772.50
Water tanker 6KL Capacity 4.00 Hour 506.09 2024.36
Vibratory roller 8-10 t copacity 1.00 Hour 864.35 864.35
Total= 7586.70

c) Material
Cost of water 24.00 KL 10.00 240.00
Compensation of earth taken from private land 100.00 Cum 0.00 0.00
Total= 240.00
Over Head Charge 7.5 % = 613.09
Contractor's Profit 7.5 % = 613.09
e ) royalty
Earth 100.00 Cum 35.00 3500.00
Cost for 100 cum Total= 12900.80
Rate per cum 129.00
Add 1% Labour cess = 1.29
Total= 130.29
Sl. No. Description Qnty. Unit Rate Amount
Or say = 130.30 Per Cum
Labour for laying sub-base in layers not exceeding 100mm watering and
compacting to the required density in O.M.C with PRR but excluding cost
and conveyance of sub base materials
Unit = Cum
Taking output = 2.83 cum
a ) Labour
Man Mulia for removing from stacks spreading and rolling 1.00 No 333.00 333.00
Women Mulia for watering & conveyance, etc. 1.50 No 333.00 499.50
Total= 832.50
b) Machinery
Add hire and running charges of PRR for consolidation considering 0.05327 Hour 294.78 15.70
425Cum of out turn with PRR per day (8 hours) = 2.83 x 8 x 269.00 /425

Over Head Charge 7.5 % = 63.61


Contractor's Profit 7.5 % = 63.61
975.42
Per 1 Cum = 344.67
(e) Cost,Carriage & Royalty:-
Moorum 1.28 Cum 229.43 293.67
Total= 638.34
Add 1% Labour cess = 6.38
Total= 644.72
Or say = 644.70 Per Cum
Non-sal wood reapers fixed on rafters with reaper nails at 10cm centres
including coaltaring the top of the reapers for receiving pan tiled roof

Data 9.30 Sqm


A/R - 2006/ P-127 Item No - 38
Material
Non Sal wood reapers 5cm × 2.5cm 99.06m or 0.1238 0.1238 Sqm 10130.29 1254.12
5cm long french reapers nails 1.36 Kg 40.00 54.40
Total = 1308.52
b) Labour
Carpenter (2nd class) 0.88 Nos 423.00 372.24
Women mulia 1.00 No 333.00 333.00
Total = 705.24
Over Head Charge 7.5 % = 151.03
Contractor's Profit 7.5 % = 151.03
Total (a+b+c) = 2315.82
Rate for 1 Sqm = 249.01
Add 1% Labour cess = 2.49
Total= 251.50
Or say = 251.50 Per Sqm
Mud walling per 1cum clay mortar (paddle, clay mixed with sand in
suitable proportion)
Ref :-A/R - 2006 , Page 74, Item No. 10
Data for 1 Cum
Material:-
Clay 1.00 Cum. 51.43 51.43
Labour
Man Mulia 1.4100 Each 333.00 469.53
Women mulia 0.7100 Each 333.00 236.43
Over Head Charge 7.5 % = 3.85
Contractor's Profit 7.5 % = 3.85
Total (a+b+c) = 765.09
Add 1% Labour cess = 7.65
Total= 772.74
Say Rs. 772.70 per Sqm.
Sl. No. Description Qnty. Unit Rate Amount
117 Labour for replacing Frosting glass-panes including cutting to size with
cost of nails and putty.
S/R-2006 Page-104 Item -(b) 1 Rs. 50.00
Add Cost of Glass 5 mm Foster 1.00 Sqm 470.64 470.64
Total = Rs 520.64
Add 1% Labour cess = 5.20
Total= 525.84
Say Rs. 525.80 per Sqm.
118 Dressed seasoned Non-sal wood (50mm. to 150mm. & above 2.75m.
long.) work framed and fixed (wrought and put up) in trusses, purlins,
frames of doors, windows, ventilators and beams
(A.R.-2006, Page No - 132, Item No. - 2)
Data for 0.028 cum.
a) Material
Non-Sal wood scantling sawn 0.028 Cum 16172.61 452.83
(Rate based on forest corporation rates)
b) Labour
Carpenter special 0.50 Nos 483.00 241.50
Man mulia 0.50 Nos 333.00 166.50
Total = 408.00
Total (a+b) = 860.83
Over Head Charge 7.5 % = 64.56
Contractor Profit 7.5 % = 64.56
Total (a+b+c) = 989.95
Rate per 1 cum = 35355.35
Add 1 % Labour cess = 353.55
Total = 35708.90
Say Rs. 35708.90 per Cum
119 Closed deep chipping and cleaning to A.S. flooring/C.C. surface for
receiving cement plaster and concrete.
(This item Derive from A/R -2006, Page 66 Item No. 14)
Data for 10 sqm
a) Labour
Man mulia 0.50 Each 333.00 166.50
Over Head Charge 7.5 % = 12.48
Contractor's Profit 7.5 % = 12.48
Total = 191.46
Rate for 1 Sqm = 19.14
Add 1 % Labour cess = 0.19
Total = 19.33
Say Rs. 19.30 per Sqm.
1st floor:-
Basic Rate: = 19.14
Add 5 % extra labour 0.83
Over Head Charge 7.5 % = 0.06
Contractor's Profit 7.5 % = 0.06
Total= 20.09
Add 1% Labour cess = 0.20
Total = Rs 20.29
Say Rs. 20.30 per Sqm.
2nd floor:-
Basic Rate: = 20.09
Add 5 % extra labour 0.87
Over Head Charge 7.5 % = 0.06
Contractor's Profit 7.5 % = 0.06
Total= 21.08
Add 1% Labour cess = 0.21
Total = Rs 21.29
Say Rs. 21.30 per Sqm.
Sl. No. Description Qnty. Unit Rate Amount
2 Supplying, fitting & fixing of PPGL sheet (Pre-painted Galvanized sheet) of
0.50 mm thick in roof with fitting & fixing of wind ties including cost, carriage
& taxes of all materials cost of all labour for fixing and cost of fitting
materials & drilling holes in wind ties etc. complete.

Executive Engineer approved rate Say Rs. 597.00 per Sqm.


Deduct 18% for GST 505.93
Say Rs. 505.90 per Sqm.
Flank dressing to proper camber including cost of all labour as direction of
EIC etc complete
Unit = 100 Sqm.
Taking output = 9.3 sqm
Ref: A/R 2006, Page No. 141, Item No. 4
a) Labour
Man Mulia 0.1200 Nos. 333.00 39.96
Over Head Charge 7.5 % = 2.99
Contractor's Profit 7.5 % = 2.99
Total (a+b+c) = 45.94
Rate per 100 Sqm = (a+b+c) x 100 / 9.3= 493.97
Add 1 % Labour Cess = 4.93
Total= 498.90
Say Rs. 498.90 per 100 Sqm.
16 Providing fitting, fixing of Aluminium door with anodized Al. door section of
9202 as verticalmember, 9201 as top member and 9200 as bottom and
middle member with frame section as 9221by means of tapered clip No.
4660 and the frame to be completed by means of jointing angle No. 1855
including all cost of labour, T&P, hire charges of drilling machine, labour
charges etc. complete. excluding cost of laminated board.

(A.R.-2006, Page No - 243, Item No. - 10


Data for 3'-0" x 6'-6" = 19.50 Sft or 1.81 Sqm or 23.76 Kg
(i) a)Materials
Al. Section No 9210 (Choukat Section) 5.33m @ 1.377Kg/M =
Al. Section No 9202 3.96 m @ 1.201Kg/M = 4.76 Kgs.
Al. Section No 9201 0.90 m @ 1.298Kg/M = 3.59 Kgs.
Al. Section No 9200 1.82 m @ 1.974Kg/M = 1.17 Kgs.
Al. Section No 4660 15.24 m @ 0.169Kg/M = 2.58 Kgs.
Al. Ang. Sec. No 1855 2.44 m @ 0.518Kg/M = 0.22 Kgs.
11.46
Total = 23.78 Kgs.
Westage 5 % = 1.19 Kgs.
Total = 24.95 Kgs. 224.68 5605.76
4" Al. Hinges. 4.00 Each 39.00 156.00
U rubber beading 18.29 Rm 15.00 274.35
Door Stopper 1.00 Each 25.00 25.00
Handle 2 Nos. 2.00 Each 62.50 125.00
6 Level mortice lock 1.00 Each 400.00 400.00
Hire charges of drilling machine 1.50 One Day 100.00 150.00
Aluminium Screws adaessive L.S. 50.00 50.00
Total = 6786.11
b) Labour
Carpenter 1st class:- 0.42 Each 483.00 202.86
Fitter (2nd class) 1.50 Each 423.00 634.50
Helper to Carpenter 1.20 Each 373.00 447.60
Mulia 1.50 Each 333.00 499.50
Total = 1784.46
Over Head Charge 7.5 % = 642.79
Contractor's Profit 7.5 % = 642.79
Total (a+b+c+d)= 9856.15
Sl. No. Description Qnty. Unit Rate Amount
Rate for 1.00 Sqm= Total = Rs. 414.82
Add 1% Labour cess = 4.14
Total = 418.96
Say Rs. 419.00 per Kg
123 Providing fitting, fixing of Aluminium door with anodized Al. door section of
9202 as verticalmember, 9201 as top member and 9200 as bottom and
middle member with frame section as 9221by means of tapered clip No.
4660 and the frame to be completed by means of jointing angle No. 1855
including all cost of labour, T&P, hire charges of drilling machine, labour
charges etc. complete. excluding cost of laminated board

(A.R.-2006, Page No - 243, Item No. - 10)


Data for 3'-06" x 6'-8" = 23.31 Sft or 2.16 Sqm or 27.13 Kg
(i) a)Materials
Vertical Section No 9202 4.06m @ 1.201Kg/M = 4.88
Middle and bottom portion:- Al. Section No. 9200= 2.14 M @ 1.97 Kg/M = 4.22 Kgs.

Top Al. Section No. 9201 = 2.13 M @ 1.298 Kg/M = 2.76 Kgs.
Tapper Clip Al. Section No. 4660 @ 0.169 Kg/M = 2.81 Kgs.
Al. Angle Section 1855 = 0.42m @ 0.518 Kg/M = 0.22 Kgs.
Al Frame Section No. 9221= 6.2 M @ 1.975 Kg/M = 12.25 Kgs.
Total = 27.13 Kgs.
Westage 5 % = 1.36 Kgs.
Total = 28.49 Kgs. 224.68 6401.13
4" Anodised Al. Hinges. 4.00 Each 39.00 156.00
U rubber beading 18.29 Rm 15.00 274.35
Door Stopper 1.00 Each 25.00 25.00
Handle 2 Nos. 2.00 Each 62.50 125.00
6 Level mortice lock 1.00 Each 400.00 400.00
Hire charges of drilling machine 1.50 One Day 100.00 150.00
Aluminium Screws adaessive L.S. 50.00 50.00
Total = 7581.48
b) Labour
Carpenter 1st class:- 0.42 Each 483.00 202.86
Fitter (2nd class) 1.68 Each 423.00 710.64
Helper to Carpenter 2.30 Each 373.00 857.90
Mulia 3.00 Each 333.00 999.00
Total = 2770.40
Total (a+b) = 10351.88
Over Head Charge 7.5 % = 776.39
Contractor's Profit 7.5 % = 776.39
Total (a+b+c)= 11904.66
Rate for 1.00 Kg= 438.80
Add 1% Labour cess = 4.38
Total = 443.18
Say Rs. 443.20 per Kg
17 Providing and fitting of glass pane (5 mm thick plain Glass) for windows,
door and ventilators including cost of all materials, labour T&P etc.
complete. (Measurement to be taken as per actual)

Material
5 mm Plain Glass 1.00 Sqm
Westage 5 % = 0.05 Sqm
1.05 Sqm 443.40 465.57
Total = Rs 465.57
Add 1% Labour cess = 4.65
Total = Rs 470.22
Say Rs. 470.20 per Sqm
Sl. No. Description Qnty. Unit Rate Amount
27 Providing and fitting of glass pane (5 mm thick black Glass) for windows,
door and ventilators including cost of all materials, labour T&P etc.
complete. (Measurement to be taken as per actual)

Material
5 mm Black Glass 1.00 Sqm
Westage 5 % = 0.05 Sqm
1.05 Sqm 539.57 566.54
Total = Rs 566.54
Add 1% Labour cess = 5.66
Total = Rs 572.20
Say Rs. 572.20 per Sqm
19 Providing and fitting of (12 mm thick) Pre-laminated Board Standard Type
(ISI) in Alluminioum frame of doors, windows & ventilatos etc. including
cost of all materials, labour T&P etc. complete. (Measurement to be taken
as per actual)
Material
12 mm thick Pre-laminated Board Standard Type (ISI) 1.00 Sqm
Westage 5 % = 0.05 Sqm
1.05 Sqm 582.98 612.12
Total = Rs 612.12
Add 1% Labour cess = 6.12
Total = Rs 618.24
Say Rs. 618.20 per Sqm
20 Supplying, fitting and fixing of stainless steel of 304 grade in hand railing
using 50 mm dia of 2 mm thick circular pipe with Balustrade of size 32 mm
x 32mm x 2mm @ 0.90 mtr C/C and stainless aquare pipe bracing of size
case as per approved design and specification, buffing, polishing etc. with
the cost, conveyance taxses of all material, cost of all labour etc. complete
in all respect. (in all floor)

Data for 3.26 Rmt


a) Materials
Railing 50 mm outer dia of 2 mm thick 3.26 rmt @ 3.50 Kg/Rmt 11.41 Kgs. 187.69 2141.54
Balustrade of size 32mm x 32mm x 2mm (4x 0.90m = 3.60 mtr @ 1.70 6.12 Kgs. 200.48 1226.93
Kg/Rmt) =
Stainless steel square pipe bracing of size 32 mm x 32mm x 2mm in 3 row 16.63 Kgs. 200.48 3333.98
(3x3.26m = 9.78mtr @ 1.70 Kg/Rmt)
Fabrication 34.16 Kgs. 10.00 341.60
Bulfing, Polishing etc. 2 % = 134.04
Total = 7178.09
b) Labour
High Skilled Labour 0.89 Each 483.00 429.87
Semi Skilled Labour 0.89 Each 373.00 331.97
Total = 761.84
Total (a+b) = 7939.93
Over Head Charge 7.5 % = 595.49
Contractor's Profit 7.5 % = 595.49
Total (a+b+c+d) = 9130.91
Rate for 1 Kg = 267.29
Add 1% Labour cess = 2.67
Total = Rs 269.96
Say Rs. 270.00 per Kg
19 Supplying, fitting, fixing up window (sliding type) made up aluminum
Section 9778 as windows frame, section No. 4095, 4096 and 9777, 3994
as shutter frame with rubber beading including locking arrangement
including all fitting including cost of materials all taxes labour, T&P etc.
complete as per direction of Engineer-in-charge. excluding cost of glass.
Sl. No. Description Qnty. Unit Rate Amount
(A.R.-2006, Page No - 240, Item No. - 7)
Data for 4'-0" x 4'-0" = 16.00 Sft or 1.49 Sqm or 7.28 Kg
(i) a)Materials
Al. Section bottom frame No. 4095= 1.20 m @ 0.875Kg/M = 1.050 Kgs.
Top & Side frame Sec.No 4096 = 3.60 m @ 0.747Kg/M = 2.689 Kgs.
Inter Lock Sec.No 9778 2.44 m @ 0.906Kg/M = 1.460 Kgs.
Vertical Shutter section No. 3994 = 2.44 m @ 0.379Kg/M = 0.910 Kgs.
Horizontal Shutter Section 9777 = 2.44 m @ 0.587Kg/M = 1.174 Kgs.
Total = 7.283 Kgs.
Westage 5 % = 0.36 Kgs.
Say Total = 7.65 Kgs. 224.68 1718.80
PVC plug 8.00 Each 1.50 12.00
Al. Screws of diff. Sizes L.S. 30.00 30.00
U rubber beading 9.75 Rm 11.72 114.27
Window Pile 7.50 Mtr 7.81 58.57
Al wheel runner 8.00 Each 19.53 156.24
Handle with lock . 2.00 Each 31.25 62.50
Hire charges of drilling machine 1.00 One Day 100.00 100.00
Total = 2252.38
b) Labour
Carpenter 1st class:- 0.50 Each 483.00 241.50
Fitter (2nd class) 0.50 Each 423.00 211.50
Helper to Carpenter 1.50 Each 373.00 559.50
Mulia 1.50 Each 333.00 499.50
Total= 1512.00
Total (a+b) = 3764.38
Over Head Charge 7.5 % = 282.32
Contractor's Profit 7.5 % = 282.32
Total= 4329.02
Rate for 1.00 Kg= Total = Rs. 594.64
Add 1% Labour cess = 5.94
Total = 600.58
Say Rs. 600.60 per Kg
7 Supplying, fitting fixing fully glazzed alumimium framed openable windows
using 15 micron anodized aluminum section, 4124 as a shutter section
frame with tappered clip of section 4125, aluminum angle, rubber breading,
friction stay and handle etc execluding cost of glass.

Ref: Revised in CSR- 2012


Data: 1 x 6'-00" x 4'-00" = 24.00 Sft or 2.23 Sqm = 10.54 Kg
a) Materials
Outer Al. Section No. 2082 = 6.09 M @ 0.554 Kg/m = 3.37 Kgs.
Mullion Sec. No. 9139 = 2.40 M @ 0.810 Kg/M = 1.98 Kgs.
Shutter Sec. No. 4124 = 10.97 M @ 0.493 Kg/M = 3.00 Kgs.
Tappered clip Al. Sec. No. 4125 = 10.97 M @ 0.183 Kg/M = 2.01 Kgs.
Al. angle Section No. 1772 = 0.28 M @ 0.64 Kg/M = 0.18 Kgs.
Total = 10.54 Kgs.
Wastage 5 % = 0.53 Kgs.
Total = 11.07 Each Kg 224.68 2487.20
U rubber beading 10.97 Each Rmt 15.00 164.55
Handle 2 Nos. 21.00 42.00
Friction stay 4 Nos. 122.00 488.00
PVC Screws of drills machine 15 Nos. 7.00 105.00
Al. Screws of diff. Sizes L.S. 50.00
Hire charges of drilling machine 1 per day 100.00 100.00
Total= 3436.75
b) Labour
Carpenter 1st class:- 0.60 Each 483.00 289.80
Fitter (2nd class) 1.62 Each 423.00 685.26
Sl. No. Description Qnty. Unit Rate Amount
Helper to Carpenter 2.40 Each 373.00 895.20
Mulia 3.00 Each 333.00 999.00
Total= 2869.26
Total (a+b) = 6306.01
c) Over Head Charge 7.5 % = 472.95
Contractor's Profit 7.5 % = 472.95
Total= 7251.91
Rate for 1.00 Kg= Total = Rs. 688.03
Add 1% Labour cess = 6.88
Total = 694.91
Say Rs. 694.90 per Kg
Dismantling and removing marble chips flooring including stacking the
useful materials for reuse and removing the debris within 50m lead

Per 1 Sqm
Data for 9.30 Sqm
a) Labour
Man Mulia 0.85 Nos. 333.00 283.05
Women Mulia 1.40 Nos. 333.00 466.20
Over Head Charge 7.5 % = 56.19
Contractor's Profit 7.5 % = 56.19
Total (a+b+c) = 861.63
Rate for 1 Sqm = 92.64
Add 1% Labour cess = 0.92
Total = Rs 93.56
Say Rs. 93.60 per Sqm
Dismantling and removing marbel chips dados & skirting from walls
including rackingout joints 12mm. Deep stacking the useful materials for
reuse and removing the debris within 50m lead
Per 1 Sqm
Data for 9.30 Sqm
a) Labour
Man Mulia 1.10 Nos. 333.00 366.30
Over Head Charge 7.5 % = 36.63
Contractor's Profit 7.5 % = 7.32
Total (a+b+c) = 410.25
Rate for 1 Sqm = 44.11
Add 1% Labour cess = 0.44
Total = Rs 44.55
Say Rs. 44.60 per Sqm
Dismantling and removing 2.5 cm thick grading concrete from roof slab
cleaning the surface lowering and removing the debris within 50m lead

Ref: AR- 2006, Page No. 220, Item No. 20


Per 1 Sqm
Data for 9.30 Sqm
a) Labour
Man Mulia 0.75 Nos. 333.00 249.75
Women Mulia 1.25 Nos. 333.00 416.25
Woman Mulia for lifting the debries 0.25 Nos. 333.00 83.25
Total = 749.25
Over Head Charge 7.5 % = 56.19
Contractor's Profit 7.5 % = 56.19
Total = 861.63
Rate for 1 Sqm = 92.64
Add 1% Labour cess = 0.92
Total = Rs 93.56
Say Rs. 93.60 per Sqm
1st floor:-
Sl. No. Description Qnty. Unit Rate Amount
Basic Rate: = 92.64
(ii) Add 5 % extra labour 3.74
Over Head Charge 7.5 % = 0.28
Contractor's Profit 7.5 % = 0.28
Total= 96.94
Add 1% Labour cess = 0.96
Total = Rs 97.90
Say Rs. 97.90 per Sqm.
2nd floor:-
Basic Rate: = 96.94
(ii) Add 5 % extra labour 3.92
Over Head Charge 7.5 % = 0.29
Contractor's Profit 7.5 % = 0.29
Total= 101.44
Add 1% Labour cess = 1.01
Total = Rs 102.45
Say Rs. 102.50 per Sqm.
128 Fixing koddapa stone (above 0.40 Sqms) in dados skirting and risers of
steps on 12mm thick cement plaster (1:3) jointed with neat cement slurry
mixed with pigments to match the shade of the tiles including rubbing and
polishing complete including all costs complete

(A.R.-2006, Page No - 90, Item No. - 17)


Data for 10 Sqms.
a) Materials
Sand 0.15 Cum. 50.48 7.57
Cement 0.715 Qntl 517.42 369.95
Cement for slurry 0.66 Qntl 517.42 341.49
koddapa stone 10.00 Sqm 277.95 2779.50
Total = 3498.51
b) Labour
Mason Special 3.25 Each 483.00 1569.75
Semi-skilled mulia or rubbing 7.60 Each 373.00 2834.80
Mulia 3.25 Each 333.00 1082.25
Total = 5486.80
Over Head Charge 7.5 % = 673.89
Contractor's Profit 7.5 % = 673.89
d) Cost of Carriage and Royality of Materials
Sand 0.15 Cum. 35.00 5.25
Cement 0.715 Qntl 5.50 3.93
Cement for slurry 0.66 Qntl 5.50 3.63
koddapa stone 10.00 Sqm 5.37 53.73
Total= 66.54
Total =(a+b+c+d) = Rs. 10399.63
For 1 Sqm = Rs. 1039.96
Add for wax polishing = 8.50
Total = 1048.46
Add 1% Labour cess = 10.48
Total = Rs 1058.94
Say Rs. 1058.90 per Sqm.
32mm thick piasal wood or local teak wood fully glazed shutters complete
with iron fitting and wooden hinged cleats etc., fitted and fixed in position
including all labour, but excluding the cost of glass panes and iron fittings

(A.R.-2006, Page No - 133, Item No. - 4)


Per 1Sqm
Data for a door 1.08m × 2.15 sqm.
a) Material
Area of shutters 0.94 × 2.0m = 1.88sqm
Sl. No. Description Qnty. Unit Rate Amount
Piasal wood planks for shutters 0.0454 Cum 45200.00 2053.88
b) Labour
Labour for making shutters
(i) Carpenter special 1.5000 Nos 483.00 724.50
(ii) Helper 1.8800 Nos 373.00 701.24

Wooden hinged cleats 2.00 Nos 12.50 25.00


Labour for fixing shutters Carpenter 2nd class 1.00 Nos 423.00 423.00
Man mulia 1.00 Nos 333.00 333.00
Total = 4260.62
Over Head Charge 7.5 % = 319.54
Contractor's Profit 7.5 % = 319.54
Total = 4899.70
Rate per 1 Sqm = 2606.22
Add 1% Labour cess = 26.06
Total = Rs 2632.28
Say Rs. 2632.30 per Sqm.
Brick work with C.B. bricks 23cm x 11cm x 8cm size having crushing
strength not less than 35Kg/cm2 with dimensional tolerance ±8 percent in
cement mortar (1:6) in Foundation & Plinth including cost of labour, &
royalty etc. complete but excluding cost of bricks. & carriage

Ref :-A/R - 2006 ,P-71, Item No - 3


Data for 1 Cum.
a) Materials
Sand 0.28 One cum 50.48 14.13
Cement 0.672 One Qntl. 517.42 347.70
Total = 361.83
b) Labour
Mason Special 0.35 Each 483.00 169.05
Mason Second class 1.05 Each 423.00 444.15
Man mulia 1.41 Each 333.00 469.53
Women mulia 1.41 Each 333.00 469.53
Man mulia for preparing mortar etc. 0.14 Each 333.00 46.62
Total = 1598.88
Over Head Charge 7.5 % = 147.05
Contractor's Profit 7.5 % = 147.05
d) Cost of Carriage and Royalty of the materials
Brick (Only Royalty) 1.00 One cum 87.50 87.50
Sand 0.28 One cum 184.67 51.70
Cement 0.672 One Qntl. 5.50 3.69
Total = 142.89
Total (a+b+c+d)= 2397.70
Add 1% Labour cess = 23.97
Total = 2421.67
Say Rs. 2421.70 per Cum
Add for Super-structure = 33.00
Total = 2430.70
Add 1% Labour cess = 24.30
Total = 2455.00
Say Rs. 2455.00 per Cum
(B) First floor
(i) Basic rate = 2430.70
(ii) Add 15 % extra Labour = 239.83
Over Head Charge 7.5 % = = 17.98
Contractor's Profit 7.5 % = 17.98
Total = 2706.49
Add 1% Labour cess = 27.06
Total = 2733.55
Sl. No. Description Qnty. Unit Rate Amount
Say Rs. 2733.60 per Cum
(C) 2nd floor
(i) Basic rate = 2706.49
(ii) Add 15 % extra Labour = 275.80
Over Head Charge 7.5 % = = 20.68
Contractor's Profit 7.5 % = 20.68
Total = 3023.65
Add 1% Labour cess = 30.23
Total = 3053.88
Say Rs. 3053.90 per Cum
49 Fixing Koddpa stone (up to 0.40 Sqms) in floors treads or steps and
landing on 20 mm thick bed of cement mortar 1:4 (1cement : 4 sand)
jointed with neat cement slury mixed with pigment to match the shades of
the tiles including rubbing and polishing complete including cost of kota
stone.
(A.R.-2006, Page No - 89, Item No. - 16)
Data for 10 Sqms.
a) Materials
Cost of tile 10.000 Sqm 277.95 2779.50
Sand 0.21 Cum. 50.48 10.60
Cement 0.744 Qntl 517.42 384.96
Cement for slurry 0.33 Qntl 517.42 170.74
White Cement 0.076 Qntl 1750.00 133.00
Total = 3478.80
b) Labour
Mason Special 2.16 Each 483.00 1043.28
Semi-skilled mulia or rubbing 5.50 Each 373.00 2051.50
Mulia 2.16 Each 333.00 719.28
Total = 3814.06
Over Head Charge 7.5 % = 546.96
Contractor's Profit 7.5 % = 546.96
e) Cost of Carriage and Royality of Materials
Tile 10.00 Sqm 5.37 53.73
Sand 0.21 Cum. 35.00 7.35
Cement 0.744 Qntl 5.50 4.09
Cement for slurry 0.33 Qntl 5.50 1.81
White Cement 0.076 Qntl 5.50 0.41
Total= 67.39
Total =(a+b+c+d+e) = Rs. 8454.17
For 1 Sqm = Rs. 845.41
Add for wax polishing = 8.50
Total= 853.91
Add 1 % Labour Cess = 8.53
Total= 862.44
Say Rs. 862.40 per Sqm.
1st floor:-
Basic Rate: = 853.91
(ii) Add 5 % extra labour 19.07
Over Head Charge 7.5 % = 1.43
Contractor's Profit 7.5 % = 1.43
Total= 875.84
Add 1% Labour cess = 8.75
Total = Rs 884.59
Say Rs. 884.60 per Sqm.
2nd floor:-
Basic Rate: = 875.84
(ii) Add 5 % extra labour 20.02
Over Head Charge 7.5 % = 1.50
Contractor's Profit 7.5 % = 1.50
Sl. No. Description Qnty. Unit Rate Amount
Total= 898.86
Add 1% Labour cess = 8.98
Total = Rs 907.84
Say Rs. 907.80 per Sqm.
Dismantling and removing old tiled cladding from walls including racking
out joints 12mm deep stacking the useful materials for reuse and removing
the debris within 50m lead
Ref :-A/R - 2006 ,P-223, Item No - 29
Data for 9.30 sqm
a) Labour
Man Mulia 1.30 Nos 333.00 432.90
#REF! 432.90
Over Head Charge 7.5 % = 32.46
Contractor's Profit 7.5 % = 32.46
#REF! 497.82
Rate per 1 Sqm = 53.52
Add 1% Labour cess = 0.53
Total = 54.05
Say Rs. 54.10 per Sqm.
12 Brick work with C.B. bricks 23cm x 11cm x 8cm size having crushing
strength not less than 35Kg/cm2 with dimensional tolerance ±8 percent in
cement mortar (1:4) in Foundation and Plinth including watering curing,
cost of carriage, royalty and taxes of all materials, cost of all labour, T&P
etc complete but excluding cost of brick as per the direction of Engg-in -
charge.

Ref :-A/R - 2006 ,P-71, Item No - 2


Data for 1 Cum.
a) Materials
Sand 0.28 One cum 50.48 14.13
Cement 1.00 One Qntl. 517.42 517.42
0.00 531.55
b) Labour
Mason Special 0.35 Each 483.00 169.05
Mason Second class 1.05 Each 423.00 444.15
Man mulia 1.41 Each 333.00 469.53
Women mulia 1.41 Each 333.00 469.53
Man mulia for preparing mortar etc. 0.14 Each 333.00 46.62
1598.88
Over Head Charge 7.5 % = 159.78
Contractor's Profit 7.5 % = 159.78
d) Cost of Carriage and Royalty of the materials
Sand 0.28 One cum 184.67 51.70
Cement 1.00 One Qntl. 5.50 5.50
Total = 57.20
Total (a+b+c+d+e)= 2507.19
Add 1% Labour cess = 25.07
Total = 2532.26
Say Rs. 2532.30 per Cum
Add for Super-structure = 33.00
Total = 2540.19
Add 1% Labour cess = 25.40
Total = 2565.59
Say Rs. 2565.60 per Cum
(B) First floor
(i) Basic rate = 2540.19
(ii) Add 15 % extra Labour = 2.11
Over Head Charge 7.5 % = = 0.15
Contractor's Profit 7.5 % = 0.15
Total = 2542.60
Sl. No. Description Qnty. Unit Rate Amount
Add 1% Labour cess = 25.42
Total = 2568.02
Say Rs. 2568.00 per Cum
(C) 2nd floor
(i) Basic rate = 2542.60
(ii) Add 15 % extra Labour = 2.42
Over Head Charge 7.5 % = = 0.18
Contractor's Profit 7.5 % = 0.18
Total = 2545.38
Add 1% Labour cess = 25.45
Total = 2570.83
Say Rs. 2570.80 per Cum
21 Supplying, fitting fixing fully glazzed alumimium framed fixed using 15
micron anodized aluminum section, 4124 as a shutter section frame with
tappered clip of section 4125, aluminum angle, rubber breading, etc

Ref: Revised in CSR- 2012 (Derive from openable window items)


Data: 1 x 6'-00" x 4'-00" = 24.00 Sft or 2.23 Sqm = 10.54 Kg
a) Materials
Outer Al. Section No. 2082 = 6.09 M @ 0.554 Kg/m = 3.37 Kgs.
Mullion Sec. No. 9139 = 2.40 M @ 0.810 Kg/M = 1.98 Kgs.
Shutter Sec. No. 4124 = 10.97 M @ 0.493 Kg/M = 3.00 Kgs.
Tappered clip Al. Sec. No. 4125 = 10.97 M @ 0.183 Kg/M = 2.01 Kgs.
Al. angle Section No. 1772 = 0.28 M @ 0.64 Kg/M = 0.18 Kgs.
Total = 10.54 Kgs.
Wastage 5 % = 0.53 Kgs.
Total = 11.07 Each Kg 224.68 2487.20
U rubber beading 10.97 Each Rmt 15.00 164.55
PVC Screws of drills machine 15 Nos. 7.00 105.00
Al. Screws of diff. Sizes L.S. 50.00
Hire charges of drilling machine 1 per day 100.00 100.00
Total= 2906.75
b) Labour
Carpenter 1st class:- 0.60 Each 483.00 289.80
Fitter (2nd class) 1.62 Each 423.00 685.26
Helper to Carpenter 2.40 Each 373.00 895.20
Mulia 3.00 Each 333.00 999.00
Total= 2869.26
Total (a+b) = 5776.01
c) Over Head Charge 7.5 % = 433.20
Contractor's Profit 7.5 % = 433.20
Total= 6642.41
Rate for 1.00 Kg= Total = Rs. 630.20
Add 1% Labour cess = 6.30
Total = 636.50
Say Rs. 636.50 per Kg
Mud and cowdung leaping per 1Sqm
Ref: A/R- 2006, P-113, I.N.: 42
Data for 9.3 Sqm
a) Labour
Woman mulia 0.3300 Nos 333.00 109.89
Over Head Charge 7.5 % = 8.24
Contractor's Profit 7.5 % = 8.24
Total = 126.37
Rate for 1 sqm = 13.58
Add 1% Labour cess = 0.13
Total = 13.71
Say Rs. 13.70 per Sqm
Sl. No. Description Qnty. Unit Rate Amount
1 Supplying fitting and fixing of flush door made out of 25 mm thich BWR ply
wood including cost of all materials, cost of all fittings (hinges, tower bolt,
aldrop, hadle, screw etc.) and cost of all labour, all taxes and T&P etc.
complete.
(Derived from A.R.-2006, Page No - 243, Item No. - 10
Data for 3'-0" x 6'-6" = 19.50 Sft or 1.81 Sqm
(i) a)Materials
25 mm Ply wood 1.81 Sqm
Wastage 10% 0.18 Sqm
Total = 1.99 Sqm 1317.45 2621.72
4" Al. Hinges. 4.00 Each 39.00 156.00
Door Stopper 1.00 Each 25.00 25.00
Handle 2 Nos. 2.00 Each 62.50 125.00
6 Level mortice lock 1.00 Each 400.00 400.00
Hire charges of drilling machine 1.50 One Day 100.00 150.00
Aluminium Screws & adaessive L.S. 50.00 50.00
Add for Sun mica (2 x 1.81) = 3.62 Sqm 672.50 2434.45
Total = 5962.17
b) Labour
Carpenter 1st class:- 0.42 Each 483.00 202.86
Fitter (2nd class) 1.50 Each 423.00 634.50
Helper to Carpenter 1.20 Each 373.00 447.60
Mulia 1.50 Each 333.00 499.50
Total = 1784.46
Over Head Charge 7.5 % = 580.99
Contractor's Profit 7.5 % = 580.99
Total (a+b+c+d)= 8908.61
Rate for 1.00 Sqm= Total = Rs. 4921.88
Add 1% Labour cess = 49.21
Total = 4971.09
Say Rs. 4971.10 per Sqm
1 Providing fitting and fixing of wall panelling made out of BWR Ply wood
(ISI) of 25mm thick ply with decorative laminate (Sunmica) one side
including, jointing and finishing to a flush finish bonded with adhesives,
anti-termite treatment (Terminator) etc. complete as per direction of
Engineer - in - Charge.

Data for 70.00 sft of 6.50 Sqm


a) Materials
(i) 25mm thick (DWR) ply wood
4 x 2' 06" x 7' 00" = 70.000 Sft
4 x 2 x 2' 06" x 0' 02" = 3.200 Sft
Total = 73.200 Sft
Add 10 % Wastage 7.320 Sft
Total = 80.520 Sft
Or 7.480 Sqm 1317.45 9854.52
(ii) 1mm thick Sun Mica (One Side)
Area = 7.480 Sqm 545.00 4076.60
(iii) Fevicol 73.200 Sft
@ 27.00 Sft/ Kg = 2.710 Kg 230.00 623.30
(iv) Nail & Screw LS 50.00
(vi Abrotape 2.000 Roll 36.70 73.40
(vi) Hire and Running Charges of Drill machine 1.000 Day 100.00 100.00
(vii) Beat (Base of Panneling) (4 x 2' 06") = 10.000 Rft 8.00 80.00
(viii) Anti termite Liquid (4 x 2' 06" x 7' 00" x 2 side) = 140.00 Sft 140.000 Sft
Panneling area = (23.10 Sft x 2 side) =46.20 Sft 46.200 Sft
Total = 186.200 Sft
Or 17.30 Sqm @ 0.084 Ltr/Sqm = 1.450 Ltr 600.00 870.00
MDF Board 4.860 Sft 300.00 1458.00
Total (a) = 17185.82
Sl. No. Description Qnty. Unit Rate Amount
b. Add 35% of Material cost as per prevailing market rate 6015.04
Total = 23200.86
b) Labour
Carpenter, 1st Class 2.000 No 483.00 966.00
Fitter, 2nd Class 2.000 No 423.00 846.00
Helper 2.000 No 373.00 746.00
Mulia 2.000 No 333.00 666.00
Total = 3224.00
c) Over Head Charge 7.5 % on (a+b) = 1981.86
d) Contractor's Profit 7.5 % on (a+b) = 1981.86
Total (a+b+c+d+e) = 30388.58
Rate per 1 Sqm = 4675.16
Add 1% Labour cess = 46.75
Total = 4721.91
Say Rs. 4721.90 per Sqm.
22 Providing fitting and fixing of wall panelling made out of BWR Ply wood
(ISI) of 25mm thick ply as base layer and 19 mm thick ply as top layer with
decorative laminate (Sunmica) one side including, jointing and finishing to a
flush finish bonded with adhesives, anti-termite treatment (Terminator) etc.
complete as per direction of Engineer - in - Charge.

Data for 70.00 sft of 6.50 Sqm


a) Materials
(i) 25mm thick (DWR) ply wood (1st layer)
4 x 2' 06" x 7' 00" x 2 = 140.000 Sft
4 x 2 x 2' 06" x 0' 06" = 10.000 Sft
Total = 150.000 Sft
Add 10 % Wastage 15.000 Sft
Total = 165.000 Sft
Or 15.330 Sqm 1317.45 20196.50
(i) 19mm thick (DWR) ply wood (2nd ayer)
4 x 2' 06" x 7' 00" x 2 = 70.000 Sft
4 x 2 x 2' 06" x 0' 02" = 3.200 Sft
Total = 73.200 Sft
Add 10 % Wastage 7.320 Sft
Total = 80.520 Sft
Or 7.480 Sqm 919.15 6875.24
(ii) 1mm thick Sun Mica (One Side)
Area = 15.330 Sqm 545.00 8354.85
(iii) Fevicol 73.200 Sft
@ 27.00 Sft/ Kg = 2.710 Kg 230.00 623.30
(iv) Nail & Screw LS 50.00
(vi Abrotape 2.000 Roll 36.70 73.40
(vi) Hire and Running Charges of Drill machine 1.000 Day 100.00 100.00
(vii) Beat (Base of Panneling) (4 x 2' 06") = 10.000 Rft 8.00 80.00
(viii) Anti termite Liquid (4 x 2' 06" x 7' 00" x 2 side) = 140.00 Sft 140.000 Sft
Panneling area = (23.10 Sft x 2 side) =46.20 Sft 46.200 Sft
Total = 186.200 Sft
Or 17.30 Sqm @ 0.084 Ltr/Sqm = 1.450 Ltr 600.00 870.00
MDF Board 9.960 Sft 500.00 4980.00
Total (a) = 42203.29

Total = 42203.29
b) Labour
Carpenter, 1st Class 2.000 No 483.00 966.00
Fitter, 2nd Class 1.000 No 423.00 423.00
Helper 1.000 No 373.00 373.00
Mulia 1.000 No 333.00 333.00
Total = 2095.00
Sl. No. Description Qnty. Unit Rate Amount
c) Over Head Charge 7.5 % on (a+b) = 3322.37
d) Contractor's Profit 7.5 % on (a+b) = 3322.37
Total (a+b+c+d+e) = 50943.03
Rate per 1 Sqm = 7837.38
Add 1% Labour cess = 78.37
Total = 7915.75
Say Rs. 7915.80 per Sqm.
23 Providing & fixing of cup board consisting of BWR Ply wood (ISI) with
decorative Laminated both sides including all types of fittings such as
handle, lock chain, magnet channel, screws, bolt & nuts etc and jointing,
finishing to a flush finish bonded with adhesive etc complete as per
direction of the department

Data for 1 x 6' 00" x 4' 00" (1' 08" B) =24.00 Sft or 2.23 Sqm
(a) Materials - (i) 19 mm thick Ply wood
vertical:- 2 x 6' 00" x 4' 00" = 48.000
Side Vertical 2 x 2' 08" x 6' 00" = 31.920
stand 1 x 4' 00" x 0' 06" = 2.000
Rack = 3 x 1' 05" x 4' 00" = 18.000
Horizontal 2 x 1' 08" x 4' 00" = 13.280
Total = 113.200 Sft
Add 10 % Wastage = 11.320 Sft
Total = 124.520 Sft
Or say = 11.570 Sqm 919.15 10634.56
(ii) 12 mm thick ply wood;
Rack = 2 x 1' 05" x 4' 00" = 12.000
Side Vertical 2 x 1' 08" x 6' 00" = 19.920
Total = 31.920 Sft
Add 10 % Wastage = 3.190 Sft
Total = 35.110 Sft
Or say = 3.260 Sqm 663.83 2164.08
(iii) 16 mm thick block board (ISI)
Door 2 x 2' 00" x 4' 00" = 16.000
Add 10 % Wastage = 1.600 Sft
Total = 17.600 Sft
Or say = 1.630 Sqm 781.28 1273.48
(iv) Sunmica)
Qnty same as (i) = 11.570
Qnty same as (ii) = 3.260
Qnty same as (iii) = 1.630
16.460
Add 10 % Wastage = 1.640 Sqm
Total = 18.100 Sqm 600.00 10860.00
(v) Fevicol
Qnty same as Sun mica area 150.64 Sft @ 27.00 Kg/Sft 5.570 Kg 230.00 1281.10
(vii) Nail & Screw L.S. 50
(vi) Abrotape 2.000 Roll 36.70 73.40
(vii) Handle 2.000 Nos 156.00 312.00
(viii) Lock: 1.000 Nos 133.00 133.00
(ix) Magnet 1.000 Nos 30.00 30.00
(xi) Auto Hinges 2.000 Nos 52.00 104.00
(Xii) Cable Magnet 2.000 Nos 30.00 60.00
(xiv) Anti termite Liquid @ 0.084 Ltr/Sqm = 1.520 Ltr 600.00 912.00
(vii) Hire and Running Charges of Drill machine 1.000 Day 100.00 100.00
Total (a) = 27987.62
b) Labour
Carpenter, 1st Class 2.000 No 483.00 966.00
Fitter, 2nd Class 2.000 No 423.00 846.00
Helper 1.000 No 373.00 373.00
Mulia 2.000 No 333.00 666.00
Sl. No. Description Qnty. Unit Rate Amount
Total = 2851.00
c) Over Head Charge 7.5 % = 2312.89
d) Contractor's Profit 7.5 % = 2312.89
Total (a+b+c+d+e) = 35464.40
Rate per 1 Sqm = 15903.31
Add 1% Labour cess = 159.03
Total = 16062.34
Say Rs. 16062.30 per Sqm.
1 Providing and fitting of zinc coated wire mesh) for windows, door and
ventilators including cost of all materials, labour T&P etc. complete.
(Measurement to be taken as per actual)
Material
Wire Mesh 1.00 Sqm
Westage 10 % = 0.10 Sqm
1.10 Sqm 300.00 330.00
Total = Rs 330.00
Add 1% Labour cess = 3.30
Total = Rs 333.30
Say Rs. 333.30 per Sqm
3 R.C.C. M-30 grade with 20mm and down grade C.B. chips of approved
quality from approved quarry by Batching Plant, Transit Mixture and
Concrete pump including hoisting, charges of watering, curing and cost of
all materials and labour, T&P centering shuttering etc complete but
excluding cost of reinforcement complete.

Data Book Page No. 478


Data for 120 Cums.
a) Materials
20mm size Granite C.B. metal 64.80 Cum. 1028.57 66651.33
10mm size Granite C.B. chips 43.20 Cum. 1090.48 47108.73
Sand 54.60 Cum. 50.48 2756.20
Cement 48.79 Mt 5174.20 252449.21
Admixture @ 0.4 per cent of cement 0.2000 Mt 1000.00 200.00
Total = 369165.47
b) Labour
Mate 0.88 Each 373.00 328.24
Mason 3.00 Each 483.00 1449.00
Mulia 19.00 Each 333.00 6327.00
Total = 8104.24
c) Machinery
Batching plant (assuming output 20 cum/hr) 6.0000 hour 1043.4800 6260.88
Generator 100 KVA 6.0000 hour 391.3000 2347.80
Front End Loader 6.0000 hour 452.1700 2713.02
Transit Mixer (capacity 4.0 cum) Lead upto 1 km 15.0000 hour 521.7400 7826.10
Lead beyond 1 km, L=7 300.0000 t.km 2.5000 5250.00
Concrete Pump 6.0000 hour 143.4800 860.88
Total = 25258.68
Over Head Charge 7.5 % = 30189.62
Contractor's Profit 7.5 % = 30189.62
f) Cost of Carriage and Royalty of Materials
20mm size Granite C.B. metal 64.80 Cum. 719.21 46604.80
10mm size Granite C.B. chips 43.20 Cum. 719.21 31069.87
Sand 54.60 Cum. 184.67 10082.98
Cement 48.79 Mt 55.00 2683.45
Admixture @ 0.4 per cent of cement 0.2000 Mt 0.2200 0.04
Total= 90441.14
Total =(a+b+c+d+e+f) = Rs. 553348.77
= Rs. 4611.23
Add 1% Labour cess = 46.11
Sl. No. Description Qnty. Unit Rate Amount
Total = Rs 4657.34
Say Rs. 4657.30 Per Cum
24 Providing, fitting and fixing 80 mm thick factory made cement concrete
interlocking (Uni shape) standard paver block of M-15 grade and approved
make variety colour and size made by block making machine with strong
vibratory compaction of approved design

Data for 10 Sqms.


a) Materials
Cost of tile 10.000 Sqm 510.00 5100.00
Sand for spreading laid after paver block 0.10 Cum. 43.81 4.38
Total = 5104.38
b) Labour
Mason Special 0.30 Each 483.00 144.90
Mulia 0.30 Each 333.00 99.90
Total = 244.80
Over Head Charge 7.5 % = 401.18
Contractor's Profit 7.5 % = 401.18
e) Cost of Carriage and Royality of Materials
Tile 10.00 Sqm 88.75 887.50
Sand 0.10 Cum. 184.67 18.46
Total= 905.96
Total =(a+b+c+d+e) = Rs. 7057.50
For 1 Sqm = Rs. 705.75
Total= 705.75
Add 1 % Labour Cess = 7.05
Total= 712.80
Say Rs. 712.80 per Sqm.

25 Providing and fixing internal wall panels on Light gauge steel frame work
with 12.5mm thick gypsum plaster board conforming IS 2095:2011 fixed on
cement board as per standard sizes fixed with self-drilling / taping screws /
fasteners @ 60cm c/c of approved make, Screws shall be of counter sunk
rib head of 1.60mm to 4 mm thick or 8 to 10 gauge of length varying from
25 to 45 mm. Proper taping and jointing to be done using fiber mesh tape
and epoxy and acrylic based jointing compound for seamless finish.(cost of
frame work to be paid for separately

Cement Fiber Board 6 mm thick as per IS 14862:2000 of type B (High


pressure Steam Cured)
Details of cost for 10 Sqm Material
6 mm thick fibre cement board 10 sqm +1 sqm (Add for wastage 11.0000 Sqm 570.00 6270.00
@10%)=11.00 sqm
MS screws of gauge 10, length 25 mm for fixing cement fibre board to C 40.0000 Each 0.36 14.40
section Tapping and finishing Cement board joints
Filling the Grove of 2 mm to 3 mm between 6 mm and 10 mm thick cement 10.0000 Sqm 92.85 928.50
bonded particle boards.
Total = 7212.90
LABOUR
Sl. No. Description Qnty. Unit Rate Amount
For cutting and fixing of Cement & gypsum board Carpenter 2nd class 1.1100 No 423.00 469.53

Welder 3.3300 No 423.00 1408.59


Total = 1878.12
Over Head Charge 7.5 % = 681.83
Contractor's Profit 7.5 % = 681.83
Total = 10454.68
Rate for 1 Sqm 1045.47
Add 1 % Labour Cess = 10.45
Total= 1055.92
Say Rs. 1055.90 per Sqm.
26 Providing, fitting, fixing of Aluminium frame only with aluminum anodised T-
Section No 3215 with 2'-0" centre to centre, L-Section no 1705 upto 15
micron on 4 walls tobe fixed by means of steel screws and pvc plug and the
aluminium grid of 2'-0" x 2'-0" excluding board suspended from celling
including cost of all materials, cost of all labour T&P etc. complete

Ref :- A/R - 2006, P-237, Item No - 3


data for 14'-6" x 14'-6"=210.25 Sft or 19.53 Sqm
(a) Material
Aluminium anodised T-section No-3215 = 16 x 4.41 = 70.56 M @ 18.20
0.258Kg/m =
Perimeter Angle section No-1785 = 17.64m @ 0.233 Kg/m = 4.11
Total = 22.31 Kgs
Wastage 5% = 1.12
23.43 Kgs 224.68 5264.25
PVC Rawl plug 42.00 Nos 7.00 294.00
9" connecting hooks with nuts & washer 42.00 Nos 5.50 231.00
G.I. wire 2.00 Kgs 51.06 102.12
65mm PVC Plug 50.00 Nos 0.60 30.00
Screw 50mm x 8mm 50.00 Nos 0.64 32.00
Hire charges of drill machine 1.50 Day 100.00 150.00
Total= 6103.37

(b)Labour
Carpenter 1st Class 5.00 483.00 2415.00
Muila 5.00 333.00 1665.00
Total= 4080.00
Over Head Charge 7.5 % = 763.75
Contractor's Profit 7.5 % = 763.75
Total(a+b+c+d)= 11710.87
Rate per Sqm = 599.63
Add 1% Labour cess = 5.99
Total = Rs 605.62
Say Rs. 605.60 per Sqm.
27 Providing corrugated G.S. sheet roofing including vertical / curved surface
fixed with polymer coated J or L hooks, bolts and nuts 8 mm diameter with
bitumen and G.I. limpet washers or with G.I. limpet washers filled with white
leadin roof including fixing of ridges wind ties etc. complete but including
cost of fitting including drilling holes in wind ties.

Derived from Ref :-A/R - 2006, P - 126, Item No-33


Data for 9.3Sqm.
a) Labour
Carpenter special class 0.50 Each 476.00 238.00
Fitter Special 1.00 Each 476.00 476.00
Man mulia 2.00 Each 326.00 652.00
Over Head Charge 7.5 % = 102.45
Contractor's Profit 7.5 % = 102.45
Sl. No. Description Qnty. Unit Rate Amount
Total= 1570.90
For 1 Sqm= 1570.90 9.30 168.91
per Sqm.
d) Materials
Cost of Galvanised steel corrugated sheets (Zinc Coated) (0.40mm) thick 1.20 Sqm 505.00 606.00
= 1 Sqm + 20% Wastage =
Nuts and Bolt 0.030 Kgs. 60.63 1.81
L/J hooks 0.132 Kgs. 56.17 7.41
UPVC Pipe 0.30 mtr per Sqm (IS 4980/2000) (Class - 4) (EPM Rate) 0.300 Rmt 300.02 90.00

Designer Border made of MDF Material @ 60% for 1 Sqm area =60% x 1 0.600 Sqm 281.80 169.08
sqm =
Gable Top @ 8 Sqm per 1 No. =1/8 = 0.125 no 0.125 No 600.00 75.00
Total= 949.30
Total= 1118.21
Add 1% Labour cess = 11.18
Total= 1129.39
Say Rs. 1129.40 per Sqm.
Sl. No. Description Qnty. Unit Rate Amount
28 Providing and fixing 35 mm thick Single Leaf Flush Door shutters
conforming to IS : 2202 (Part I) decorative type, core of block board
construction with frame of 1st class hard wood and well matched teak 3 ply
veneering with vertical grains or cross bands and face veneers on both
faces of shutters inclussive of 4 Nos of Stainless steel Butt Hinges (100mm
x60mm x2.5mm), 40mm stainless steel screws, 1 No T72V door closer
(CE certified) (40 - 80Kg)( Godrej - 3495), 200 mm Door Handle set with
Lock Body 1CK ( Godrej - 8313), 1 no Door Stopper , 1 No of tower Bolt
SS 10 X 300 mm(Godrej 3264),and 1 No of PVC Buffer with SS Screw
etc,teak wood lipping around the edges & paste with 1.5mm thick laminate
on both side of the flush door , etc. including the cost of all materials,
hardware fittings, cost of all labour, conveyance, loading, unloading, T&P,
etc, complete as per the direction of Engineer-in-Charge.

Total= 3964.80
per Sqm.

Assistant Engineer Assistant Executive Engineer


Building (R&B) Section Sundargarh (R&B) Sub-Division

#REF!
#REF!
Labour Chat
Sl. No. Labour Category Labour Cost
1 Mulia 333.00 7 340.00
2 Semi skilled 373.00 7 380.00
3 Skilled (2nd class) 423.00 7 430.00
4 Highly Skilled 483.00 7 490.00
BASIC RATE OF MATERIALS (PRE GST RATES) PRE GST RATES (POST GST RATES)
Total pre
Excise
Sl. No. Name of items Unit Sundargarh VAT % GST Tax Sundargarh
Duty %
in %
1 2 3 10 17 18 19 26
1 Well burnt clamp burnt bricks (25 1000 3215.00 5.00 12.50 17.50 2736.17
Cm. x 12Cm. x 8Cm.) having Nos
crushing strength not less than 35
Kg./Cm2 with dimensional
tolerance ± 8
percent.

2 Well burnt clamp burnt bricks (23 1000 2915.00 5.00 12.50 17.50 2480.85
Cm. x 11Cm. x 8Cm.) having Nos
crushing strength not less than 35
Kg./Cm2 with dimensional
tolerance ± 8
percent.

3 K.B. bricks (25 Cm x 12Cm x 1000 4113.00 5.00 12.50 17.50 3500.43
8Cm) having crushing strength not Nos
less than 75 Kg./Cm2 with
dimensional tolerance ± 8
percent.
4 K.B. bricks (23 Cm. x 11Cm. x 1000 3700.00 5.00 12.50 17.50 3148.94
8Cm.) having crushing strength not Nos
less than 75 Kg./Cm2 with
dimensional tolerance ± 8 percent.

5 Fly ash bricks of 25 Cm. x 12 1000 4550.00 5.00 12.50 17.50 3872.34
Cm. x 8 Cm. size having Nos
crushing strength not less than
75 Kg./Cm2 with dimensional
tolerance ± 2 %
6 Fly ash bricks of 23 Cm. x 11 1000 4120.00 5.00 12.50 17.50 3506.38
Cm. x 8 Cm. size having Nos
crushing strength not less than
75 Kg./Cm2 with dimensional
tolerance ± 2 %
7 Fly ash blocks of 30 Cm. x 20 Each 16.00 5.00 12.50 17.50 13.62
Cm. x 15 Cm. size having crushing
strength not less than
75 Kg./Cm2 with dimensional
tolerance ± 2 %
8 Cement concrete solid Block
machine mixed and Hydraulic
compressed having crushing
strength not less than
75kg/cm2
a. 400mm x 200mm x 200mm size Each 30.00 14.50 12.50 27.00 23.62
b. 400mm x 150mm x 200mm size Each 22.00 14.50 12.50 27.00 17.32
c. 400mm x 100mm x 150mm size Each 17.00 14.50 12.50 27.00 13.39
d. 300mm x 200mm x 150mm size Each 19.00 14.50 12.50 27.00 14.96
e. 300mm x 150mm x 150mm size Each 16.00 14.50 12.50 27.00 12.60
f. 300mm x 100mm x 150mm size Each 12.00 14.50 12.50 27.00 9.45
9 Cement concrete Hollow Blocks
machine mixed and Hydraulic
compressed having crushing
strength not less than
70kg/cm2
a. 400mm x 200mm x 200mm size Each 25.00 14.50 12.50 27.00 19.69
b. 400mm x 150mm x 200mm size Each 20.00 14.50 12.50 27.00 15.75
c. 400mm x 100mm x 200mm size Each 14.00 14.50 12.50 27.00 11.02
d. 300mm x 200mm x 150mm size Each 14.00 14.50 12.50 27.00 11.02
e. 300mm x 150mm x 150mm size Each 14.00 14.50 12.50 27.00 11.02
f. 300mm x 100mm x 150mm size Each 12.00 14.50 12.50 27.00 9.45
10 K.B. bricks Khoa 4 Cm.size 1 Cum 343.00 5.00 12.50 17.50 291.91
11 Clamp burnt brick Khoa 4 cm. 1 Cum 268.00 5.00 12.50 17.50 228.09
size.
12 Surki of clamp burnt bricks. 1 Cum 425.00 5.00 12.50 17.50 361.70
13 Surki of Kiln burnt bricks. 1 Cum 470.00 5.00 12.50 17.50 400.00
14 Screen washed gravel for 1 Cum 128.00 5.00 0.00 5.00 121.90
concrete (12mm. to 20mm.)
15 Gravel or moorum 1 Cum 47.00 5.00 0.00 5.00 44.76
16 Stone screened Dust passing 1 Cum 84.00 5.00 0.00 5.00 80.00
through 2.36 mm sieve and
retained on 0.075 mm sieve
17 River single or Bajri (12mm. to 1 Cum 98.00 5.00 0.00 5.00 93.33
20mm.)
18 Screened and washed sharp 1 Cum 53.00 5.00 0.00 5.00 50.48
sand for mortar
19 Sand for filling and road 1 Cum 46.00 5.00 0.00 5.00 43.81
blinding
20 Clay mortar for masonry work 1 Cum 54.00 5.00 0.00 5.00 51.43
with admixture of sand.
21 Stone lime unslaked. 1 Kg. 17.00 5.00 0.00 5.00 16.19
22 Ghooting lime unslaked. 1 Kg. 21.00 5.00 0.00 5.00 20.00
23 Shell lime unslaked. 1 Kg. 19.00 5.00 0.00 5.00 18.10
24 a) Granite broken stone of size not 1 Cum. 243.00 14.50 0.00 14.50 212.23
less than 0.0025 Cum.
Stacked
b) Granite stone of size not less 1 Cum. 220.00 14.50 0.00 14.50 192.14
than 0.0025 Cum. picked up.
25 Stone other than granite quarried, 1 Cum. 198.00 5.00 0.00 5.00 188.57
broken and staked
0.0015 Cum to 0.003 Cum
26 Stone other than granite picked up 1 Cum. 172.00 5.00 0.00 5.00 163.81
and staked 0.0015 Cum. to
0.003 Cum
27 Stone other than granite quarried, 1 Cum. 180.00 5.00 0.00 5.00 171.43
broken and staked
above 0.003 Cum
28 Stone other than granite picked up, 1 Cum. 175.00 5.00 0.00 5.00 166.67
broken and staked above
0.003 Cum
29 Granite Stone broken metal
63mm. size Passing through
90mm. Sieve and retained on
53 mm sieve.
a) Crusher broken. 1 Cum. 655.00 5.00 0.00 5.00 623.81
b) Hand broken. 1 Cum. 505.00 5.00 0.00 5.00 480.95
30 Granite Stone broken metal
45mm. size (Passing through
53mm sieve & retained on
26.5mm sieve)
a) Crusher broken. 1 Cum. 683.00 5.00 0.00 5.00 650.48
b) Hand broken. 1 Cum. 533.00 5.00 0.00 5.00 507.62
31 Granite Stone broken metal
40mm. size
a) Crusher broken. 1 Cum. 740.00 5.00 0.00 5.00 704.76
b) Hand broken. 1 Cum. 595.00 5.00 0.00 5.00 566.67
32 Granite Stone broken metal
26.5mm. size (Passing through
45mm sieve & retained on
22.4mm sieve)
a) Crusher broken. 1 Cum. 760.00 5.00 0.00 5.00 723.81
b) Hand broken. 1 Cum. 605.00 5.00 0.00 5.00 576.19
33 Granite Stone broken metal
25mm. size (Passing through
40mm sieve & retained on
20mm sieve)
a) Crusher broken. 1 Cum. 788.00 5.00 0.00 5.00 750.48
b) Hand broken. 1 Cum. 640.00 5.00 0.00 5.00 609.52
34 Granite Stone broken metal
22.4mm. size (Passing through
26.5mm sieve & retained on
11.2mm sieve)
a) Crusher broken. 1 Cum. 800.00 5.00 0.00 5.00 761.90
b) Hand broken. 1 Cum. 640.00 5.00 0.00 5.00 609.52
35 Granite Stone broken chips
20mm. size (Minimum 65% by Wt.
Passing through 19mm sieve &
retained on 13.2mm sieve but
whole should pass through 26.5mm
sieve)

a) Crusher broken. 1 Cum. 1080.00 5.00 0.00 5.00 1028.57


b) Hand broken. 1 Cum. 883.00 5.00 0.00 5.00 840.95
36 Granite Stone broken chips
13.2mm. Size (Passing through
22.4mm sieve & retained on
11.2mm sieve)
a) Crusher broken. 1 Cum. 1088.00 5.00 0.00 5.00 1036.19
b) Hand broken. 1 Cum. 888.00 5.00 0.00 5.00 845.71
37 Granite Stone broken chips
12mm. size (Minimum 65% by Wt.
Passing through 13.2mm sieve &
retained on 9.50mm sieve but
whole should pass through 19mm
sieve)

a) Crusher broken. 1 Cum. 1098.00 5.00 0.00 5.00 1045.71


b) Hand broken. 1 Cum. 900.00 5.00 0.00 5.00 857.14
38 Granite Stone broken chips 0.00
11.2mm. size (Passing through
13.2mm sieve & retained on
5.6mm sieve)
a) Crusher broken. 1 Cum. 1133.00 5.00 0.00 5.00 1079.05
b) Hand broken. 1 Cum. 913.00 5.00 0.00 5.00 869.52
39 Granite Stone broken chips
10mm. size (Minimum 65% by Wt.
Passing through 9.5mm sieve &
retained on 6.3mm sieve but whole
should pass through 13.2mm sieve)

a) Crusher broken. 1 Cum. 1145.00 5.00 0.00 5.00 1090.48


b) Hand broken. 1 Cum. 913.00 5.00 0.00 5.00 869.52
(A) Granite Stone broken chips 1 Cum. 765.00 5.00 0.00 5.00 728.57
6.7mm size (Passing through
11.2mm sieve & retained on
2.8mm sieve)
(B) Granite Stone screening 1 Cum. 675.00 5.00 0.00 5.00 642.86
(Passing through 2.36mm sieve
& retained on 180 micron sieve)
40 Granite stone broken chips of 1 Cum. 698.00 5.00 0.00 5.00 664.76
4.7 mm size passing through
6.7 mm sieve (crusher broken.)
and retained on 2.36 mm sieve.
41 Stone other than granite 1 Cum. 260.00 5.00 0.00 5.00 247.62
broken to 5cm. size.
42 Stone other than granite 1 Cum. 273.00 5.00 0.00 5.00 260.00
broken to 4 cm. size.
43 Stone other than granite 1 Cum. 300.00 5.00 0.00 5.00 285.71
broken to 2 cm. size.
44 Stone other than granite 1 Cum. 310.00 5.00 0.00 5.00 295.24
broken to 1cm. size.
45 Stone boulder 15cm. & above size 1 Cum. 133.00 5.00 0.00 5.00 126.67
granite picked up and
nullah boulders.
46 Soiling stone boulder 15Cm. & 1 Cum. 148.00 5.00 0.00 5.00 140.95
above size picked up nullah
boulders broken.
47 Stone boulder 15cm. & above size 1 Cum. 121.00 5.00 0.00 5.00 115.24
other than granite or laterite picked
up and nullah
boulders.
48 Soiling stone boulder 15Cm. & 1 Cum. 133.00 5.00 0.00 5.00 126.67
above size other than granite or
laterite picked up nullah
boulders broken.
49 Soling stone boulders 10 Cm. size 1 Cum. 123.00 5.00 0.00 5.00 117.14
picked up other than
granite.
50 Hard broken soling stone other than 1 Cum. 195.00 5.00 0.00 5.00 185.71
granite (40mm. to 90mm.)
51 I.R.C. Grade I (90mm-45 mm.) 1 Cum. 602.00 5.00 0.00 5.00 573.33
52 I.R.C. Grade II (63mm. to 1 Cum. 668.00 5.00 0.00 5.00 636.19
45mm.)
53 I.R.C.Grade III (53mm. to 1 Cum. 713.00 5.00 0.00 5.00 679.05
22.4mm.)
54 Laterite soling stone 23Cm. size 1 Cum. 99.00 5.00 0.00 5.00 94.29
55 Laterite Stone rough dressed 1 Cum. 530.00 5.00 0.00 5.00 504.76
56 Bamboo mat or talai. 1 Sqm. 123.00 14.50 6.00 20.50 102.07
57 Bamboo 1ST class 7Cm. to Each 138.00 14.50 6.00 20.50 114.52
10Cm. dia & above 6m. long.
58 a) Belongi Bomboo 2.51 Cm. to Each 26.00 14.50 6.00 20.50 21.58
4Cm. dia & above 5m. long.
b) Belongi Bomboo above 4Cm. dia Each 38.00 14.50 6.00 20.50 31.54
& up to 7Cm. dia & above
5m. long.
59 Sal bullahs 75mm. to 120mm. mean 1Mtr 97.00 14.50 6.00 20.50 80.50
dia up to 5.5m. long.
60 Sal bullahs 150mm. to 200mm. 1Mtr 103.00 14.50 6.00 20.50 85.48
mean dia up to 5.5m. long.
61 Sal bullahs above 200mm. & up to 1Cum. 8943.00 14.50 6.00 20.50 7421.58
250mm. mean dia & up to
2.75m. long.
62 Sal bullahs above 200mm. & up to 1Cum. 10110.00 14.50 6.00 20.50 8390.04
250mm. mean dia above
2.75m. long & up to 4.75m.
long.
63 Sal bullahs above 200mm. & up to 1Cum. 11655.00 14.50 6.00 20.50 9672.20
250mm. mean dia above
4.75m. long
64 Sal bullahs above 250mm. & up to 1Cum. 13079.00 14.50 6.00 20.50 10853.94
380mm. mean dia & up to
2.75m. long
65 Sal bullahs above 250mm. & up to 1Cum. 16058.00 14.50 6.00 20.50 13326.14
380mm. mean dia & above
2.75m. long up to 4.75m. long
66 Sal bullahs above 250mm. & up to 1Cum. 18135.00 14.50 6.00 20.50 15049.79
380mm. mean dia & above
4.75m. long.
67 Non-sal bullahs 75mm. mean 1Mtr. 48.00 14.50 6.00 20.50 39.83
dia of any length.
68 Non-sal bullahs 100mm. mean 1Mtr. 58.00 14.50 6.00 20.50 48.13
dia of any length.
69 Non-sal bullahs 125mm. mean 1Mtr. 72.00 14.50 6.00 20.50 59.75
dia of any length.
70 Non-Sal bullahs 150mm. to 1Mtr. 88.00 14.50 6.00 20.50 73.03
200mm. mean dia of any length.
71 Non-Sal bullahs above 200mm. 1Cum. 5895.00 14.50 6.00 20.50 4892.12
& up to 250mm. mean dia up to
2.5m. long.
72 Non-Sal bullahs above 200mm. 1Cum. 6460.00 14.50 6.00 20.50 5361.00
& up to 250mm. mean dia above
2.5m. long.
73 Seasoned rough dressed sawn Sal 1Cum. 35225.00 14.50 6.00 20.50 29232.37
wood having minimum dimension
50mm. to 150mm. & up to 2.75m.
long.
74 Seasoned rough dressed sawn Sal 1Cum. 37880.00 14.50 6.00 20.50 31435.68
wood having minimum dimension
50mm. to 150mm. & above 2.75m.
long.
75 Seasoned Sal wood beam of cross 1Cum. 38331.00 14.50 6.00 20.50 31809.96
sectional area not less than
150Sq.cm. & least lateral dimension
100mm. & above
2.75m. long.
76 Seasoned Sal wood planks not 1Cum. 34833.00 14.50 6.00 20.50 28907.05
more than 75mm. thick & not less
than 200mm. width.
77 Seasoned Piasal wood planks 1Cum. 54466.00 14.50 6.00 20.50 45200.00
for shutters.
78 Seasoned Teak wood planks for 1Cum. 73871.00 14.50 6.00 20.50 61303.73
shutters.
79 Non Sal wood scantling & 1Cum. 19488.00 14.50 6.00 20.50 16172.61
plants(Tentera, Kasi, Gamhari,
Kuruma)
80 Non-Sal reapers. 1Cum. 12207.00 14.50 6.00 20.50 10130.29
81 Fire wood 1Qntl 430.00 0.00 0.00 0.00 430.00
82 1St class Raniganj or Mangalore 100 548.00 14.50 12.50 27.00 431.50
pattern tiles. Nos.
83 Ridges of Raniganj or 100 1440.00 14.50 12.50 27.00 1133.86
Mangalore parttern tiles. Nos.
84 Flat tiles(14Cm. x14 Cm.x 1Cm. 1000 297.00 14.50 12.50 27.00 233.86
) Nos.
85 Flat tiles (15Cm x15Cmx 1.2 1000 329.00 14.50 12.50 27.00 259.06
Cm ) Nos.
86 Flat tiles (30Cm. x 15 Cm.x 2.5 1000 1307.00 14.50 12.50 27.00 1029.13
Cm. ) Nos.
87 Flat tiles (30Cm. x 30 Cm.x 2.5 1000 1539.00 14.50 12.50 27.00 1211.81
Cm. ) Nos.
88 Pan tiles 1000 312.00 14.50 12.50 27.00 245.67
Nos.
89 Nuria tiles(20Cm. to 25Cm.) 1000 736.00 14.50 12.50 27.00 579.53
Nos.
90 Nuria tiles(25Cm. to 30Cm.) 1000 889.00 14.50 12.50 27.00 700.00
Nos.
91 Ridge tiles 1000 1010.00 14.50 12.50 27.00 795.28
Nos.
92 Marble Tiles of minimum 16
mm thick, dunguri Variety.
(a) Up to 0.10 Sqm. 1 Sqm. 544.00 14.50 12.50 27.00 428.35
(b) Above 0.10 Sqm. to 0.40 1 Sqm. 658.00 14.50 12.50 27.00 518.11
Sqm.
( c) Above 0.4 Sqm. to 1.00 1 Sqm. 740.00 14.50 12.50 27.00 582.68
Sqm.
93 Kota Tiles of minimum 16 mm
thick
(a) Up to 0.10 Sqm. 1 Sqm. 398.00 14.50 12.50 27.00 313.39
(b) Above 0.10 Sqm. 1 Sqm. 485.00 14.50 12.50 27.00 381.89
94 Khandolites (Up to 0.06 Sqm.) 1 Sqm. 308.00 14.50 12.50 27.00 242.52
95 Granite Tiles
(a) Up to 0.10 Sqm. (10mm 1 Sqm. 1163.00 14.50 12.50 27.00 915.75
thick)
b) Above 0.10 Sqm 0.00
(i)Above 0.10 Sqm & up to 0.4 1 Sqm. 1323.00 14.50 12.50 27.00 1041.73
sqm (10mm. thick)
ii) Above 0.40 sqm. (20mm 1 Sqm. 2090.00 14.50 12.50 27.00 1645.67
thick)
96 Kodappa Tiles of 10 mm thick
(a) Above 0.1 Sqm & Up to 1 Sqm. 300.00 14.50 12.50 27.00 236.22
0.40 Sqm.
(b) Above 0.40 Sqm. 1 Sqm. 353.00 14.50 12.50 27.00 277.95
97 Dholpuri Stone Tiles. 1 Sqm. 399.00 14.50 12.50 27.00 314.17
98 Tiles up to-
(a) 20cmx30cm / 20cm x 20cm 1 Sqm. 380.00 14.50 12.50 27.00 299.21
special plain /printed series ceramic
wall tiles of premium grade having
thickness 6.5mm to 6.7mm
confirming to IS
13753

(b) 30cm x 30cm / 40cm x 1 Sqm. 425.00 14.50 12.50 27.00 334.65
40cm special plain / printed series
ceramic floor tiles of premium grade
having thickness 7mm to 8mm
confirming to IS 13755

(c) Polished Vitrified floor tiles of


premium grade having thickness 8
mm to 10mm confirming to IS
15622:2006 (Group-B la) of
following sizes.
(I) Vitrified Tile 600mmx600mm 1 Sqm. 663.00 14.50 12.50 27.00 522.05
Plain (Ivory)
(II) Vitrified Tile 1 Sqm. 715.00 14.50 12.50 27.00 562.99
600mmx600mm Coloured / Printed
series(Homogeneous)
(d) Vitrified industrial floor Tile of 1 Sqm. 600.00 14.50 12.50 27.00 472.44
premium grade having thickness
8mm to 10mm confirming to IS
4457 of size
300mmx300mm
99 Chequred Tiles. 1 Sqm. 217.00 14.50 12.50 27.00 170.87
100 Terrazo Tiles. 0.00
(a) With grey cement. 1 Sqm. 245.00 14.50 12.50 27.00 192.91
(b) With white cement 1 Sqm. 293.00 14.50 12.50 27.00 230.71
101 Red oxide Primer 1 Litre 124.00 14.50 12.50 27.00 97.64
102 Wood Primer 1 Litre 143.00 14.50 12.50 27.00 112.60
103 Wood Shine Paint 1 Litre 155.00 14.50 12.50 27.00 122.05
104 Plastic Emulsion paint 1 Litre 249.00 14.50 12.50 27.00 196.06
105 Enamel paint 1 Litre 193.00 14.50 12.50 27.00 151.97
106 Distemper 1 Kg. 66.00 14.50 12.50 27.00 51.97
107 Cement paint 1 Kg. 46.00 14.50 12.50 27.00 36.22
108 Red oxide powder 1 Kg. 113.00 14.50 12.50 27.00 88.98
109 French polish 1 Litre 163.00 14.50 12.50 27.00 128.35
110 Varnish 1 Litre 158.00 14.50 12.50 27.00 124.41
111 Plaster of paris 1 Kg. 12.00 14.50 12.50 27.00 9.45
112 Coal Tar 1 Kg. 44.00 5.00 12.50 17.50 37.45
113 G.C.I. Sheet
a) 0.30mm thick 1 Sqm. 280.00 5.00 12.50 17.50 238.30
b) 0.40mm thick 1 Sqm. 290.00 5.00 12.50 17.50 246.81
114 A.C. Sheet 1 Sqm. 200.00 14.50 12.50 27.00 157.48
115 A.C. ridges 1 pair 180.00 14.50 12.50 27.00 141.73
116 6mm. Thick Plain A.C. Sheet 1 Sqm 230.00 14.50 12.50 27.00 181.10
117 Tar Paper 1 Sqm 17.00 5.00 12.50 17.50 14.47
118 Putty (Wood) 1 Kg. 28.00 14.50 12.50 27.00 22.05
119 Putty (Iron) 1 Kg. 99.00 14.50 12.50 27.00 77.95
120 Wire Nails 1 Kg. 60.00 5.00 12.50 17.50 51.06
121 M.S. Angle 1 Qntl. Rate as fixed by Rate as fixed by
122 M.S. Channel 1 Qntl. SAIL SAIL
123 Bolt, Nut & Washers 1 Kg. 77.00 14.50 12.50 27.00 60.63
124 Holding down bolts minimum 1 Kg. 74.00 14.50 12.50 27.00 58.27
60 Cm. long with 15Cm. x 15
Cm. x 6mm. size washer plate
125 Binding Wire. 1 Kg. 79.00 5.00 12.50 17.50 67.23
126 Coir String 1 Kg. 44.00 0.00 6.00 6.00 41.51
127 Empty Cement bags (HDPE) by lot 100 nos 370.00 5.00 18.00 23.00 300.81
.a) & not shorted out
b) Empty Cement gunny bags by 100 nos 370.00 5.00 18.00 23.00 300.81
lot & not shorted out
c) Empty Bitumen Drum Each 132.00 5.00 18.00 23.00 107.32
d) Empty Bitumen Emulsion Drum Each 253.00 5.00 18.00 23.00 205.69
128 Straw in Bundle 100 nos 275.00 5.00 18.00 23.00 223.58
129 Marble Chips. 1qntl 600.00 14.50 0.00 14.50 524.02
130 Marble Powder 1qntl 348.00 14.50 0.00 14.50 303.93
131 Cement
a) 33 Grade 1qntl Average factory Average factory
b) 43 Grade price of three price of three
c) 53 Grade manufacturers of manufactures of
132 White Cement. 1qntl cement inside
1795.00 14.50 12.50 27.00 cement iside the
1413.39
133 Steel
a) Mild Steel 1qntl Rate as fixed by Rate as fixed by
b) HYSD (FE-415) /(FE500) 1qntl SAIL SAIL
134 “Z” type Steel Sheet Piles . 1qntl 5300.00 5.00 12.50 17.50 4510.64
135 Bentonite powder 1qntl 290.00 14.50 14.50 253.28
Oxidized mild steel fittings
(I.S.I.)
136 Butt hinges (I.S.I.)
a) 50x37x1.50mm Each 6.00 14.50 12.50 27.00 4.72
b) 75x47x0.70mm Each 8.00 14.50 12.50 27.00 6.30
c) 100x58x1.90mm Each 14.00 14.50 12.50 27.00 11.02
d) 125x65x2.12mm Each 22.00 14.50 12.50 27.00 17.32
137 M.S. aldrop (I.S.I.) 0.00
a) 250x16mm Each 90.00 14.50 12.50 27.00 70.87
b) 300x16mm Each 97.00 14.50 12.50 27.00 76.38
138 M.S. handle (I.S.I.)
a) 100mm Each 14.00 14.50 12.50 27.00 11.02
b) 125mm Each 16.00 14.50 12.50 27.00 12.60
c) 150mm Each 20.00 14.50 12.50 27.00 15.75
139 M.S. tower bolt (I.S.I.)
a) 100x10mm Each 17.00 14.50 12.50 27.00 13.39
b) 150x10mm Each 26.00 14.50 12.50 27.00 20.47
c) 200x10mm Each 34.00 14.50 12.50 27.00 26.77
140 M/S. Screw (I.S.I.)
a) 12x3mm 100 pcs 29.00 14.50 12.50 27.00 22.83
b) 12x4mm 100 pcs 33.00 14.50 12.50 27.00 25.98
c) 20x4mm 100 pcs 37.00 14.50 12.50 27.00 29.13
d) 20x5mm 100 pcs 39.00 14.50 12.50 27.00 30.71
e) 25x4mm 100 pcs 40.00 14.50 12.50 27.00 31.50
f) 25x5mm 100 pcs 46.00 14.50 12.50 27.00 36.22
g) 30x4mm 100 pcs 48.00 14.50 12.50 27.00 37.80
h) 30x5mm 100 pcs 50.00 14.50 12.50 27.00 39.37
i) 30x6mm 100 pcs 55.00 14.50 12.50 27.00 43.31
j) 35x6mm 100 pcs 57.00 14.50 12.50 27.00 44.88
k) 35x7mm 100 pcs 61.00 14.50 12.50 27.00 48.03
l) 35x8mm 100 pcs 68.00 14.50 12.50 27.00 53.54
m) 50x7mm 100 pcs 77.00 14.50 12.50 27.00 60.63
n) 50x8mm 100 pcs 81.00 14.50 12.50 27.00 63.78
141 Steel window stay bar (I.S.I.)
a) 200mm Each 25.00 14.50 12.50 27.00 19.69
b) 250mm Each 30.00 14.50 12.50 27.00 23.62
c) 300mm Each 36.00 14.50 12.50 27.00 28.35
142 Steel window handle including
Nut, bolt & washer (I.S.I.)
a) 100mm Each 20.00 14.50 12.50 27.00 15.75
b) 150mm Each 26.00 14.50 12.50 27.00 20.47
143 Welded mesh 0.00
a) 25mmx25mmx11 gauge Sqm 183.00 5.00 12.50 17.50 155.74
b) 25mmx25mmx13 gauge Sqm 168.00 5.00 12.50 17.50 142.98
c) 50mmx25mmx11 gauge Sqm 168.00 5.00 12.50 17.50 142.98
d) 50mmx25mmx13 gauge Sqm 155.00 5.00 12.50 17.50 131.91
144 G.I. “L” & “J” hook Kg 66.00 5.00 12.50 17.50 56.17
145 W.I. clamp Kg 75.00 14.50 12.50 27.00 59.06
Aluminium fittings (I.S.I.)
146 Butt hinges (I.S.I.)
a) 125mmx75mmx4mm Each 65.00 14.50 12.50 27.00 51.18
b) 125mmx63mmx4mm Each 54.00 14.50 12.50 27.00 42.52
c) 100mmx75mmx4mm Each 51.00 14.50 12.50 27.00 40.16
d) 100mmx63mmx4mm Each 49.00 14.50 12.50 27.00 38.58
e) 75mmx63mmx4mm Each 33.00 14.50 12.50 27.00 25.98
f) 50mmx35mmx3.2mm Each 13.00 14.50 12.50 27.00 10.24
147 Aluminium handle (I.S.I.)
a) 150mm with 175mm x 40mm Each 28.00 14.50 12.50 27.00 22.05
flat
b) 125mm with 175mm x 40mm Each 28.00 14.50 12.50 27.00 22.05
flat
c) 100mm with 150mm x 33m flat Each 27.00 14.50 12.50 27.00 21.26
d) 75mm with 118mm x 33mm Each 26.00 14.50 12.50 27.00 20.47
flat
148 Aluminium tower bolt (Barrel
type) (I.S.I.)
a) 300mm x10mm Each 65.00 14.50 12.50 27.00 51.18
b) 250mm 10mm Each 60.00 14.50 12.50 27.00 47.24
c) 200mm x 10mm Each 55.00 14.50 12.50 27.00 43.31
d) 150mm x 10mm Each 46.00 14.50 12.50 27.00 36.22
e) 100mm x 10mm Each 37.00 14.50 12.50 27.00 29.13
149 Sliding door bolt (Aldrop)
(I.S.I.)
a) 300mm x 16mm Each 214.00 14.50 12.50 27.00 168.50
b) 250mm x 16mm Each 200.00 14.50 12.50 27.00 157.48
150 Brass fittings( I.S.I. ) Butt hinges
(light/Ordinary) (I.S.I.)
a 125mm x 70mm x 4mm Each 65.00 5.00 12.50 17.50 55.32
b 100mm x 70mm x 4mm Each 49.00 5.00 12.50 17.50 41.70
c 75mm x 40mm x 2.5mm Each 36.00 5.00 12.50 17.50 30.64
d 50mm x 40mm x 2.5mm Each 18.00 5.00 12.50 17.50 15.32
151 Brass But hinges (Heavy type)
(I.S.I.)
a 125mm x 85mm x 5.5mm (0.07 Each 200.00 5.00 12.50 17.50 170.21
kg )
b 100mmx85mm5.5mm Each 183.00 5.00 12.50 17.50 155.74
(0.056Kg)
c 75mmx65mmx4mm (.02 kg ) Each 77.00 5.00 12.50 17.50 65.53
152 Brass tower bolt (Barrel type)
(I.S.I.)
a 250mm x 10-mm Each 203.00 5.00 12.50 17.50 172.77
b 200mm x 10mm Each 165.00 5.00 12.50 17.50 140.43
c 150mm x 10mm Each 125.00 5.00 12.50 17.50 106.38
d 100mm x 10mm Each 94.00 5.00 12.50 17.50 80.00
153 Brass Screws (I.S.I.)
a 50mm 100 Nos 170.00 5.00 12.50 17.50 144.68

b 40mm 100 Nos 155.00 5.00 12.50 17.50 131.91

c 30mm 100 Nos 135.00 5.00 12.50 17.50 114.89

d 25mm 100 Nos 120.00 5.00 12.50 17.50 102.13

e 20mm 100 Nos 89.00 5.00 12.50 17.50 75.74


154 Chromium plated fittings
(Brass) (I.S.I.)Handle (I.S.I)
a. 125mm with 175 x 32mm plate Each 145.00 5.00 12.50 17.50 123.40
b. 100mm with 150 x 25mm plate Each 122.00 5.00 12.50 17.50 103.83
c. 75mm with 125 x 25mm plate Each 105.00 5.00 12.50 17.50 89.36
155 Wall cement primer (I.S.I.)
a) Oil bound 1 ltr 113.00 14.50 12.50 27.00 88.98
b) Water bound 1 ltr 150.00 14.50 12.50 27.00 118.11
156 Aluminium paint (I.S.I.) 1 ltr 162.00 14.50 12.50 27.00 127.56
157 Weather Coat (I.S.I.) 1 ltr 192.00 14.50 12.50 27.00 151.18
158 Adhesive (I.S.I.) 1 Kg 215.00 14.50 12.50 27.00 169.29
159 Bitumenous expansion joint
board (I.S.I.)
a. 12mm thick Sqm 695.00 5.00 14.00 19.00 584.03
b. 16mm thick Sqm 970.00 5.00 14.00 19.00 815.13
c. 25mm thick Sqm 1255.00 5.00 14.00 19.00 1054.62
160 Barbed wire (I.S.I.) Kg 65.00 5.00 12.50 17.50 55.32
161 Glass plain (I.S.I.)
a 3mm Sqm 350.00 5.00 12.50 17.50 297.87
b 4mm Sqm 400.00 5.00 12.50 17.50 340.43
c 5mm Sqm 521.00 5.00 12.50 17.50 443.40
d 6mm Sqm 600.00 5.00 12.50 17.50 510.64
e 8mm Sqm 913.00 5.00 12.50 17.50 777.02
f 10mm Sqm 1158.00 5.00 12.50 17.50 985.53
g 12mm Sqm 1351.00 5.00 12.50 17.50 1149.79
162 Glass pin headed (I.S.I.)
a 4mm Sqm 305.00 5.00 12.50 17.50 259.57
b 5mm Sqm 389.00 5.00 12.50 17.50 331.06
163 Black glass (I.S.I.)
a 4mm Sqm 528.00 5.00 12.50 17.50 449.36
b 5mm Sqm 634.00 5.00 12.50 17.50 539.57
c 6mm Sqm 773.00 5.00 12.50 17.50 657.87
d 8mm Sqm 1202.00 5.00 12.50 17.50 1022.98
e 12mm Sqm 1930.00 5.00 12.50 17.50 1642.55
164 Frosted glass (I.S.I.)
a 4mm Sqm 520.00 5.00 12.50 17.50 442.55
b 5mm Sqm 553.00 5.00 12.50 17.50 470.64
165 Wire glass – 6 mm (I.S.I.) Sqm 645.00 5.00 12.50 17.50 548.94
166 Sun-control film (I.S.I.)
a. Reflective Sqm 568.00 5.00 12.50 17.50 483.40
b. Non-reflective Sqm 405.00 5.00 12.50 17.50 344.68
167 Prelaminated particle board
(standard type) (I.S.I.)
a. 9mm Sqm 603.00 5.00 12.50 17.50 513.19
b. 12mm Sqm 685.00 5.00 12.50 17.50 582.98
c. 18mm Sqm 755.00 5.00 12.50 17.50 642.55
d. 25mm Sqm 895.00 5.00 12.50 17.50 761.70
168 BWR ply wood (I.S.I.)
a 3mm Sqm 297.00 5.00 12.50 17.50 252.77
b 4mm Sqm 345.00 5.00 12.50 17.50 293.62
c 6mm Sqm 480.00 5.00 12.50 17.50 408.51
d 9mm Sqm 598.00 5.00 12.50 17.50 508.94
e 12mm Sqm 780.00 5.00 12.50 17.50 663.83
f 16mm Sqm 918.00 5.00 12.50 17.50 781.28
g 19mm Sqm 1080.00 5.00 12.50 17.50 919.15
h 25mm Sqm 1548.00 5.00 12.50 17.50 1317.45
169 BWR Block Board (I.S.I.)
a 16mm Sqm 810.00 5.00 12.50 17.50 689.36
b 19mm Sqm 915.00 5.00 12.50 17.50 778.72
c 25mm Sqm 1048.00 5.00 12.50 17.50 891.91
d 32mm Sqm 1292.00 5.00 12.50 17.50 1099.57
170 Vinyl Flooring (I.S.I.)
(A) Homogeneous Range (I.S.I.)
i) PVC (MF) Classic roll- 1.00mm Sqm 303.00 14.50 12.50 27.00 238.58
thick
ii) PVC (MF) classic tile- 1.00mm Sqm 350.00 14.50 12.50 27.00 275.59
thick
iii) PVC (MF) impress roll-1.50mm Sqm 400.00 14.50 12.50 27.00 314.96
thick
iv) PVC (MF) impress tile-1.50mm Sqm 478.00 14.50 12.50 27.00 376.38
thick
v) PVC (MF) super roll-2.00mm Sqm 529.00 14.50 12.50 27.00 416.54
thick
vi) PVC (MF) super tile -2.00mm Sqm 608.00 14.50 12.50 27.00 478.74
thick
(B) Heterogeneous Range (I.S.I.)
i) PVC (MF) Hetro roll- 2.00mm Sqm 548.00 14.50 12.50 27.00 431.50
thick
ii) PVC (MF) hetro tile- 2.00mm Sqm 623.00 14.50 12.50 27.00 490.55
thick
171 Aluminium extruded section Kg 264.00 5.00 12.50 17.50 224.68
172 Roll formed sections made of pre-
painted steel ( base steel as per IS-
513 of 0.6 mm thick "D" quality,
galvanised as per IS-
277 with zinc of 120 gm / sq.
mtr)

a) Outer frames Po-527 Mtr 335.00 5.00 12.50 17.50 285.11


b) Intermediate mullion Po-528 Mtr 370.00 5.00 12.50 17.50 314.89
c) Shutter frame Po-153 Mtr 278.00 5.00 12.50 17.50 236.60
d) Fixed beeding Po-179 Mtr 147.00 5.00 12.50 17.50 125.11
e) Sliding shutter Po-254 Mtr 176.00 5.00 12.50 17.50 149.79
f) Outer frames(side / top) Po- Mtr 210.00 5.00 12.50 17.50 178.72
255
g) Outer frames(bottom) Po- Mtr 145.00 5.00 12.50 17.50 123.40
256
h) Sliding track (SS) Po-257 Mtr 538.00 5.00 12.50 17.50 457.87
i) Sashbar Po-101 Mtr 512.00 5.00 12.50 17.50 435.74
j) Sashbar at shutter Po-107 Mtr 283.00 5.00 12.50 17.50 240.85
k) Louvered horizontal (Top / Mtr 148.00 5.00 12.50 17.50 125.96
bottom) Po-193 A
l) 33 x 57 Box Section Mtr 335.00 5.00 12.50 17.50 285.11
m)100x50mm Box Section Mtr 508.00 5.00 12.50 17.50 432.34
n)Small Z Section Mtr 250.00 5.00 12.50 17.50 212.77
o) Extended Z Section Mtr 334.00 5.00 12.50 17.50 284.26
p) Cover Profile Mtr 120.00 5.00 12.50 17.50 102.13
Acessories
a) sliding outer frame Each 265.00 5.00 12.50 17.50 225.53
assembly / pc
b) sliding shutter /pc Each 328.00 5.00 12.50 17.50 279.15
c) Sashbar Each 18.00 5.00 12.50 17.50 15.32
d) wall fixing with polymide anchor Each 29.00 5.00 12.50 17.50 24.68
at every 600mm c/c of
outer frame
e) Outer frame corner Each 43.00 5.00 12.50 17.50 36.60
f) Top hung shutter / pc Each 357.00 5.00 12.50 17.50 303.83
g) Fixed mullion Each 54.00 5.00 12.50 17.50 45.96
h) Fixed glazing Each 110.00 5.00 12.50 17.50 93.62
i) Louvered blade Each 29.00 5.00 12.50 17.50 24.68
j) Side hung door / pc Each 408.00 5.00 12.50 17.50 347.23
k) Door lock / pc Each 360.00 5.00 12.50 17.50 306.38
l) Swing door shutter /pc Each 200.00 5.00 12.50 17.50 170.21
m) Floor Spring (Godrej Make) Each 3125.00 5.00 12.50 17.50 2659.57
Gasket
a) For Shutter Po-153 Mtr 39.00 5.00 12.50 17.50 33.19
b) For beading Po-179 Mtr 53.00 5.00 12.50 17.50 45.11
c) For Sashbar Po-101 Mtr 112.00 5.00 12.50 17.50 95.32
173 Rate of 60 micron powder coating Kg of 29.00 14.50 12.50 27.00 22.83
(including labour charges and Alumini
material for powder coating) for um
aluminium
section.
174 12.5 mm thick gypsum board of One 385.00 14.50 12.50 27.00 303.15
size 6' x 4' Piece
New Item
175 Waste Plastic duly cleaned and Per Kg Not available 30.00
shredded conforming to the size
passing 2.36mm sieve and retained
on 600 micron seive and
conforming to
requirement if IRC:SP:98-2013.
RATE FOR CONVEYANCE OF MATERIALS
ITEM NO-1. Conveyance of Materials by Ten Tonne Trucks including loading & unloading.

Bricks 23cm= 2500 nos


Bricks 25cm= 2000 nos Cement concrete & fly ash blocks
Rough stone, metal, khoa, chips,
400mmx200mmx200mm= 300 nos 400mmx150mmx200mm= Iron, Grills, Cement, Bitumen, A.C
sand, surki, quarry rubbish, moorum
Distance to be carried 400 nos 400mmx100mmx200mm= 600 nos sheet, GCI Sheet & Paint etc(per
laterite stone, washed gravel, flyash
300mmx200mmx150mm= 550 nos 300mmx150mmx150mm= 1000 kg) Wood (per 1.25 cum)
& earth (Per 1 cum)
730 nos 300mmx100mmx150mm= 1100 nos All Kinds of tiles =
180 Sqm (per truck)

Railway station
1 2 3 4
Up to 5 Km 149.67 967.27 175.50
Every Extra Km beyond 5 8.80 39.62 8.23
Km and up to 50 Km.
Every extra Km beyond 50 6.22 31.87 6.99
Km

Note : Extra percentage to be allowed over the rates


1. For earthen roads or village tracks or cross country tracks, 20 % extra may be allowed on the certificate of Executive
Engineer after his inspection and duly approved by Superintending Engineer.

2. For declared ghat road, add extra length of ghat road portion.
TERIALS
cks including loading & unloading.

Bulky materials like


Iron, Grills, Cement, Bitumen, A.C
Machineries, generators,
sheet, GCI Sheet & Paint etc(per
concrete pipe & furniture
1000 kg) Wood (per 1.25 cum)
etc (per Truck)

Other Places
5 6
161.72 1320.57 5.37 1320.57

8.23 40.67
1830.15

6.99 31.87
11154.5
14305.22
28610.44
71
May 8 mm 10 mm 12 mm 16 mm 20 mm 25 mm Total (6 nos)
Rate per piece 440.00 668 957.00 1699.00 2655.00 4149.00
1 peice in kg
(1 pice = 12 mtr) 4.74 7.40 10.66 18.94 29.63 46.27
rate per 1kg 92.83 90.27 89.77 89.70 89.61 89.67
rate per 1mt 92830.00 90270.00 89770.00 89700.00 89610.00 89670.00 541850.00
Avg including
GST Excluding GST
-18%

90308.33 76532.48

You might also like