PROJEK PEMBESARAN DAN MENAIKTARAF LAPANGAN TERBANG SULTAN ISMAIL PETRA, KOTA BHARU. KELANTAN
CLIENT'S BRIEF OF REQUIREVENTS (CBOR)
vi Approved standard title block.
Factory Acceptance Test for Major Equipment
All Factory Acceptance Test shall be witnessed by the Employer,
Project Engineering Consultant (PEC) and Mechanical and Electrical
Consultant.
If overseas visits are required, all necessary expenditure shall deem
to be included ie. Return economy class airfare, accommodation,
food, local transportation, out-of-pocket expenses etc. for 3
representatives from Employer including PEC
Factory Acceptance test report for the major equipment shall contain
the following information:
i Reference to specification and internationally/ recognized
standards.
i, Extract if relevant section of test standard.
ili, Procedure in carrying out tests.
iv. List of calibrated measuring instruments and gauges.
v. Calibration report for measuring instruments and gauges from
recognized institute or laboratory.
vi. A plot of measured performance data against manufacturer's
published performance curves.
vi. Signature of manufacture’s engineer who conducted the test.
vii
ignatureofProject Engineering
Consultantwhowitnessedthetest(if applicable).
P6-25