FIELD 

DENSITY TEST (BY SAND REPLACEMENT METHOD)
Project Date of Sampling
Contractor Date of Testing
Area/Building Ref Dwg No
Location/Grid Layer/Level
Layer N o: M.D.D. :

Layer Thickness : O.M.C. :

Trial No 1 2 3 4 5 6

Weight of sand before pouring (W1) (gm)

Weight of sand after pouring (W2) (gm)

Weight of sand in cone (W3) (gm)

Weight of sand in hole (Wb)=W1-W2-W3


(gm)
Volume of hole (v)=Wb/Sd (cc)
Weight of wetsoil from hole (Ww) (gm)
Wet Density of soil (Yb)=Ww/V(gm/cc)

Container No.
Weight of wet soil + Container(gm)
Weight of Dry s oil + Co ntainer(gm)
Weight of water (gm)
Weight of Dry S oil (gm)
Wt. of container (gm)
Moisture Content (%)
Dry Density (Yd) = y/{1+Wc/100} (gm/cc)
Degree of Compaction = (Yd/Ydmax)× 100 (%)
Average Degree of compaction
Acceptance Criteria
REMARKS: Accepted/ Rejected/ Accepted with comments

TBPL ITC
Date & Time Date & Time

FIELD DENSITY TEST (BY CORE CUTTER METHOD)
Project Date of Sampling
Contractor Date of Testing
Area/Building Ref Dwg No
Location/Grid Layer/Level
Layer N o: M.D.D. :

Layer Thickness : O.M.C. :

Trial No 1 2 3 4 5 6

Weight of core cutter = W1 (gm)

Weight of core cutter + s oil sample = W2 (gm)

Weight of wet soil sample(Ww) = W2-W1


(gm)
Volume of core cutter (cc)
Wet D ens ity of soil s ample (Y) = Ww/Vv
(gm/cc)
Container No.
Weight of wet soil + Container(gm)
Weight of Dry s oil + Co ntainer(gm)
Weight of water (gm)
Weight of Dry S oil (gm)
Wt. of container (gm)
Moisture Content (Wc) (%)
Dry Density (Yd) = y/{1+Wc/100} (gm/cc)
Degree of Compaction = (Yd/Ydmax)× 100 (%)
Average Degree of compaction
Acceptance Criteria
REMARKS: Accepted/ Rejected/ Accepted with comments

TBPL ITC
Date & Time Date & Time

SIEVE ANALYSIS OF COARSE AGGREGATE (20MM)
Project Date of Sampling
Contractor Date of Testing
Source/Location Qty of Sample
Vehicle no. Tested by

IS S IEV E SIZE WEIGH T % WEIG HT CUM ULATIVE


(MM ) RETAINED RETAIN ED % RETA INED % PAS SING LIM ITS AS P ER IS

40 100

20 85-100

10 0-20

4.75 0-5

P AN

REMARKS: Accepted/ Rejected/ Accepted with comments

TBPL ITC
Date & Time Date & Time

SIEVE ANALYSIS OF COARSE AGGREGATE (10MM)
Project Date of Sampling
Contractor Date of Testing
Source/Location Qty of Sample
Vehicle no. Tested by

IS S IEV E SIZE WEIGH T % WEIG HT CUM ULATIVE % PAS SING LIM ITS AS P ER IS
(MM ) RETAINED RETAIN ED % RETA INED

12.5 100

10 85-100

4.75 0-20

2.36 0-5

P AN

REMARKS: Accepted/ Rejected/ Accepted with comments

TBPL ITC
Date & Time Date & Time

SIEVE ANALYSIS OF FINE AGGREGATE
Project Date of Sampling
Contractor Date of Testing
Source/Location Qty of Sample
Vehicle no. Tested by
%
P ASS ING (as per IS )
WEIG HT % WEIG HT CUM ULATIVE LIMITS
IS S IEV E SIZE RETAIN ED AS
(G MS) RETAIN ED % RETA INED PER IS
As per Zone-I Zone-II Zone- III Zone-IV
Tes t
10MM 100 100 100 100

4.75M M 90-100 90-100 90-100 95-100

2.36M M 60-95 75-100 85-100 95-100

1.18M M 30-70 55-90 75-100 90-100

600Micron 15-34 35-59 60-79 80-100

300Micron 5-20 8-30 12-40 15-50

150Micron 0-10 0-10 0-10 0-15

Silt Volume Cylinder Max .-8%

REMARKS: Accepted/ Rejected/ Accepted with comments

TBPL ITC
Date & Time Date & Time

FLAKINESS/ELONGATION INDEX OF COARSE AGGREGATE
Project Date of Sampling
Contractor Date of Testing
Source/Location Qty of Sample
Vehicle no. Tested by
IS SIEVE S IZE
(MM) S IZE O F AGG REG ATE
Weight of Aggregate Retained Weight of A ggregate Retained
Between Gauge Remarks
Between Gauge (gm) W (gm) W
S . No. Pass ing Retained

1 31.5 25

2 25 20

3 20 16

4 16 12.5

5 12.5 10

6 10 6.3

Total Weight

F lakines s/Elongation Index (W1/Wx100)

REMARKS: Accepted/ Rejected/ Accepted with comments

Contractor ITC
Date & Time Date & Time

SIEVE ANALYSIS OF GSB (Granular Sub-base)
Project Date of Sampling
Contractor Date of Testing
Source/Location Qty of Sample
Vehicle no. Tested by

IS S IEV E SIZE WEIG HT % WEIGH T CUMU LA TIV E


RETAIN ED % P ASS ING LIMITS A S PER IS
(MM ) (gm) RETAINED % RETAIN ED

53 100

26.5 70-100

9.5 50-80

4.75 40-65

2.36 30-50

0.425 15-25

0.075 3-10

REMARKS: Accepted/ Rejected/ Accepted with comments

TBPL ITC
Date & Time Date & Time

SIEVE ANALYSIS OF WMM (Wet Mix Macadam)
Project Date of Sampling
Contractor Date of Testing
Source/Location Qty of Sample
Vehicle no. Tested by

IS S IEV E SIZE WEIG HT % WEIGH T CUMU LA TIV E


(MM ) RETAIN ED RETAINED % RETAIN ED % P ASS ING LIMITS A S PER IS
(gm)

53 100

45 95-100

22.4 60-80

11.2 40-60

4.75 25-40

2.36 15-30

0.600 8-22

0.075 0-5

REMARKS: Accepted/ Rejected/ Accepted with comments

TBPL ITC
Date & Time Date & Time

AGGREGATE IMPACT VALUE
Project Date of Sampling
Contractor Date of Testing
Source/Location Qty of Sample
Vehicle no. Tested by
N os of Blows- Height of F all-
Sieve range -10MM to 12.5M M 15 380MM

Description Trail-1 Trial-2 Trial-3 Trial-4 Remarks

Weight of Container (gm)

Weight of container + aggregate (gm)

a) Weight of Aggregate before tes ting (gm)

b) Weight of Aggregate retained on 2.36mm sieve (gm)

c) Weight of Aggregate passing on 2.36mm s ieve (gm)

Aggregate Impact Value (%) c/a*100

Average AIV (%)

REMARKS: Accepted/ Rejected/ Accepted with comments

TBPL ITC
Date & Time Date & Time

You might also like