1) The monthly report from a design engineer provides an update on 9 ongoing projects.
2) For each project, it summarizes the current status of engineering drawings and site work.
3) Immediate and balance drawings to be released on site are also noted for proper project progress tracking.
1) The monthly report from a design engineer provides an update on 9 ongoing projects.
2) For each project, it summarizes the current status of engineering drawings and site work.
3) Immediate and balance drawings to be released on site are also noted for proper project progress tracking.
1) The monthly report from a design engineer provides an update on 9 ongoing projects.
2) For each project, it summarizes the current status of engineering drawings and site work.
3) Immediate and balance drawings to be released on site are also noted for proper project progress tracking.
Design Engineer: MR. NIKHIL POOJARY Month : December Date: 28.12.2021
Drawing Status VFC Site Work Status Drawings to be released on site Sr. No. Job no. Project Name As per previous report As per current report As per previous report As per current report Immediate drawings Balance drawings
1 9077 Bhavik Empire Revision In ETABS Model
2 9162 Runwal Garderns MLCP ETABS Mode
Runwal Garderns MLCP 1st to 3 9162 SAFE Model 6th Floor 4 9241 Sunteck Avenue 2 Revised ETABS Model
5 9277 Runwal Arcade Revised ETABS Model
6 9086 Runwal BWR Revised ETABS Model
7 9373 Runwal Garden Phase 5 T42 Revision In ETABS Model Ongoing
8 9373 Runwal Garden Phase 5 T40 Revision In ETABS Model Ongoing
9 9373 Runwal Garden Phase 5 T39 Revision In ETABS Model Ongoing