Choke manifold test offline with the rig HP testing unit

Preparation
- The Tool Pusher or the Night Pusher (PIC) must inspect and approve the installation before the test
procedure is started and operates all valves to ensure they are working properly.

- Cold work permit to be issued and JSA discussed with the parties involved in the testing job.
-Pre job meeting with the personnel involved. Barrier tape around the Choke manifold and close area
access, according with GSP Procedures Manual.

- Connect testing line (cementing line) to valve #3.


REMARK: Through the cementing manifold we can connect the high pressure pump, instead
cementing pump.

- Fill up Choke Manifold with Sea Water.


When you have return through the poor boy to the flow line, stop the pump.

-Always apply the pressure step by step.

Put back the choke manifold valves in drilling position

NB: The test pressure applied must not exceed the working pressure of the choke manifold and
valves.

Perform all testing of choke manifold equipment in accordance with specifications. The Company
Man’s signature provides final approval that a valid test of equipment was performed.