Professional Documents
Culture Documents
CHAPTER 4 Levelling PDF
CHAPTER 4 Levelling PDF
CHAPTER 4 Levelling PDF
CHAPTER 4 - OUTCOMES
Be able to explain the difference between a level plane and horizontal plane.
Be able to level a line of points, calculate the closing error, adjust the closing
error and distribute the misclosure using the "rise and fall" method with full
arithmetic checks if you are given the necessary instruments and an assistant.
If given the necessary instruments and assistant, be able to determine the level
of the underside of a bridge, soffit, etc.
Know how to do levelling in such a way that possible errors can be detected and
/ or avoided.
Chapter 4 - Page 1 of 21
LEVELLING
CHAPTER 4 - LEVELLING
INTRODUCTION
In Surveying Technology (Part 1), only the first method of levelling will be dealt
with.
4.2 DEFINITIONS
1. Level Plane: A plane where all points are normal (perpendicular) to the
direction of gravity as indicated by a freely suspended plumb
line. It is therefore not a flat plane, and because of the
various components of the earth's surface, it does not have a
regular shape.
Chapter 4 - Page 2 of 21
LEVELLING
2. Level Line: Is a line lying in the level plane and is thus normal to the
direction of gravity at all points.
1. Back Sight: The first reading taken on the staff after setting up the
instrument. A back sight is always taken on a point with a
known or assumed height.
5. Fall: The amount by which a point is lower than the preceding point. A
fall is denoted by an increased reading on the staff.
Chapter 4 - Page 3 of 21
LEVELLING
10. Reduced Level: The height of a point above (or below) datum - usually
mean sea level.
11. Rise: The amount by which a point is higher than the preceding point. A
rise is denoted by a smaller staff reading.
Chapter 4 - Page 4 of 21
LEVELLING
Chapter 4 - Page 5 of 21
LEVELLING
4.4.1 Exercise 1
2. When booking an inverted staff reading, it is entered in the field book with
a negative sign (another convention is to draw a bar above the reading).
The reading is thus allocated a minus sign. The calculations continue in
the normal way, taking the sign into account.
4. Each inverted reading is denoted by a minus sign and the rise or fall
calculated accordingly. In the sketch, the rise from TBM A to point X is:
1,342 - (-3,405) = 4,747.
Chapter 4 - Page 6 of 21
LEVELLING
6. Enter the readings shown in the sketch above, into the levelling sheet
below and reduce it to determine the rise or fall.
Chapter 4 - Page 7 of 21
LEVELLING
4.4.3 Exercise 2
Chapter 4 - Page 8 of 21
LEVELLING
4.4.4 Exercise 3
A 1,230 9,990
B 2,040
C -3,250
D 2,050 2,030
E 1,880 9,340
Chapter 4 - Page 9 of 21
LEVELLING
INTRODUCTION
The method that we have used up to now is known as the "rise and fall"
method.
This is a very suitable method for the reduction of your levelling fieldwork
when you determine the heights of for example bench marks.
2. It is also used to set out levels for excavations or for fillings such as layer
work of roads.
3. The height of the collimation line must be calculated for each instrument
set-up.
7. The correction is carried out using the same method as for the "rise and
fall" method.
Chapter 4 - Page 10 of 21
LEVELLING
Chapter 4 - Page 11 of 21
LEVELLING
4.5.9 Exercise 4
Ʃ = ………………… ↔ Ʃ = ……………………
Chapter 4 - Page 12 of 21
LEVELLING
4.5.9 Exercise 5
A 1,730 25,730
B -2,420
C 1,830
D 1,860 2,060
E 1,430
F -2,080
G 2,430 1,630
H 0,780
J -2,010 -1,920
K 1,200
L 1,890 26,120
Chapter 4 - Page 13 of 21
LEVELLING
4.5.9 Exercise 6
Chapter 4 - Page 14 of 21
LEVELLING
1. The staff should be fully extended and clamped. Keep the bottom of the
staff free of dirt that could cause incorrect readings.
2. The staff should be held vertical for all readings. Use a staff bubble or
wave the staff slowly to and from the instrument - observe the lowest
reading.
3. Ensure that all points used as change points are suitable, alternatively,
use a footplate.
4. Take care that the staff is held in exactly the same position for the back
sight as it was for the foresight.
5. If the staff bearer is not ready for the observation, turn the staff face away
from the observer.
1. Use a straight leg tripod (non adjustable) tripod for very precise work.
2. Carry the instrument resting on one shoulder, except where trees and
branches are present where the instrument should be cradled under one
arm with the instrument forward.
3. When setting up the instrument, apply force on the tripod shoe spurs to
force the tips of the tripod firmly into the ground. On concrete surfaces,
increase the distance between the tripod legs to increase stability.
4. When the instrument is set up on the side of a hill, place two tripod legs
downhill and the third leg uphill. Level the instrument by manipulating the
third leg.
8. Check that the instrument stays level and that the compensator is
operating.
Chapter 4 - Page 15 of 21
LEVELLING
9. Keep staff readings above ½ m from the ground to help to minimise the
effect of refraction on the readings.
1. Collimation error
2. Parallax
Focus the cross-hairs first and then focus the image of the
object.
Ensure that the tripod is in stable and sturdy condition, that is,
tighten all nuts and screws on the tripod regularly.
1. The Bubble
Ensure that the bubble is properly adjusted (it should stay inside the
circle).
2. Staff
2. Use a footplate to ensure that the back sight and foresight are
taken on the same point.
Chapter 4 - Page 16 of 21
LEVELLING
Chapter 4 - Page 17 of 21
LEVELLING
1.1. In a flat terrain a test line, between 40 to 60 m long is selected and divided
into two equal sections of length.
1.2. A levelling staff is set up at A and B. The instrument is set up at I1 first and
readings observed to A and B.
Chapter 4 - Page 18 of 21
LEVELLING
Chapter 4 - Page 19 of 21
LEVELLING
Distances:
1 - A 60 m 1 - B 60 m
2-A 5m 2 - B 125 m
Readings:
1 - A 1,920 1 - B 2,345
2 - A 1,535 2 - B 1,900
1. Determine the collimation error of the level and express it in mm/m and
state if the instrument is reading too low or too high.
Chapter 4 - Page 20 of 21
LEVELLING
Chapter 4 - Page 21 of 21