PETROSERVE INTERNATIONAL
Rev. No.: 00
PURCHASE REQUEST (PR) FOR TANK FABRICATION Date:03-Mar-2023
TECHNICAL DETAILS
Refer attached Tank data summary for the Tank dimension & weight (Apprx.) details.
APPLICABLE SPECIFICATIONS:
• Tank Datasheet (all tanks)
• 32-SAMSS-030 : Manufacture of Small Metallic Atmospheric Storage Tanks
• SAES-A-004 : General Requirements for Pressure Testing
• SAES-A-007 : Hydrostatic Testing Fluids and Lay-Up Requirements
• SAES-A-206 : Positive Material Identification (PMI)
• SAES-H-001 : Coating Selection and Application Requirements for Industrial Plants and Equipment
• SAES-H-101V : Approved Saudi Aramco Data Sheets - Paints and Coatings
CERTIFICATES REQUIRED:
As per Applicable Form 175-325100, Inspection and Testing Requirements and other Applicable
Specification
SCOPE OF WORK:
• Refer scope matrix section in line with below listed points.
• All the Tank materials will be free issued by SHI. Vendor to unload the materials in vendor’s facility.
• Vendor scope is to cutting, material preparation, fabrication, Welding, pickling and passivation, NDE &
other testing.
• Dish Head forming shall be done/ arranged by vendor in vendor scope.Plate will be free issued by SHI.
• Tank Fabrication shall be as per approved drawings provided by SHI complying ARAMCO quality
requirements.
• Inspection and testing shall be as per approved ITP.
• Vendor shall provide/qualify WPS, PQR, Weld map and welder qualification certificates for Tank welding.
• All free issued materials shall be properly segregated and stored in designated area. SS & CS material shall
be separately stored.
• All consumables like welding rod, cutting wheels, etc, shall be in vendor scope.
Page: 01 of 03 PSI.PMT.FRM.07/B
PR No: 7700XX
PETROSERVE INTERNATIONAL
Rev. No.: 00
PURCHASE REQUEST (PR) FOR TANK FABRICATION Date:03-Mar-2023
• Cutting, edge preparation, fit -up, welding, pickling and passivation shall be carried out in vendor’s facility.
• Any sub-contracting activity out of vendor’s facility shall be intimated to SHI in advance and to obtain
approval.
• All required equipment/setup for carrying out the entire job shall be arranged by vendor such as crane,
forklift, welding machine, etc
• Vendor to consider all the materials/instruments/devises required for the inspections & testing (incl.
Hydrotest) in the vendor scope.
• Supervising and controlling fabrication team within agreed delivery schedule in vendor’s scope.
• Vendor shall update the fabrication status periodically in SHI provided progress report format.
• Vendor shall provide inspection forecast schedule to SHI as required.
• Vendor shall carryout the quality checks and provide the reports and notify SHI QC before 07 working
days for inspection (or agreed in the PIM).
• Vendor shall preserve, pack, and load the Tanks as per procedure and to load the tanks safely on to the
trailer for the delivery. Trailer will be arranged by SHI.
• Actual fabrication drawings will be provided later / after award of PO.
Scope Matrix
Scope of Work
S/N Activity
Sub-Con. SHI
1 Pre-inspection meeting ✓ ✓
2 WPS, PQR and Weld Map preparation & submission ✓
3 Material receipt, Handling & marking ✓
4 Material receiving inspection ✓ ✓
5 Fabrication Activities ✓
6 Fabrication Supervision ✓
7 NDE Activities & Quality inspection/tests ✓
8 Inspection notification in advance ✓
9 Pickling & Passivation ✓
TANK FABRICATION
10 Tank material supply (pipes, fittings, valves, etc.) ✓
Fabrication consumables supply (Welding items, cutting wheels, grinding
11 ✓
wheels, wire brush, etc.)
Tank fabrication (Marking, Cutting, Traceability transfer, Drilling, Grinding, Fit
12 ✓
up, Welding, Etc.)
13 Name plate fixing & Tank labelling ✓
14 Hydrostatic Test with Material ✓
Page: 02 of 03 PSI.PMT.FRM.07/B
PR No: 7700XX
PETROSERVE INTERNATIONAL
Rev. No.: 00
PURCHASE REQUEST (PR) FOR TANK FABRICATION Date:03-Mar-2023
REPORTS/RECORDS
16 Custody material report (Free issue material) ✓
17 Master Production Schedule - Fabrication (Initial stage) ✓
18 Internal Production Schedule - Tank fabrication ✓
19 Production Progress report – daily & weekly ✓
20 Inspection forecast schedule - Tank fabrication ✓
21 Inspection / test report / records preparation, validation, and submission ✓ ✓
22 Manufacturing Record Book preparation & submission ✓ ✓
23 Issue of As-Built Drawing ✓
NOTE:
• The tank data summary sheet is only for the bidding purpose. There might be minor positive/negative
changes in the IFC drawing.
• Vendor to quote unit price on per kg basis. Final job prices will be based on the actual material quantity
and on re-measurable basis.
Page: 03 of 03 PSI.PMT.FRM.07/B