“CO N S TR UC TIO N O F B U S T E R MIN A L AT M U N D LA

N A Y T A , IN DO R E (M.P )”

( P R O G R E S S R E P O RT )

1
CONSTRUCTION OF
NAME OF WORK BUS TERMINAL AT
: MUNDLA
NAYTA,INDORE

NAME OF CONTRACTOR:
OMPRAKASH AMARNATH

NAME OF
CONSULTANT (PMC DOSHI CONSULTANTS PVT LTD
& DESIGN)
TENDER
AMOUNT/ Rs.10.76 Cr. / Rs.9.66 Cr.
CONTACT
AMOUNT

WORK DONE Rs.4.87 Cr.

TENDER RATE 10.17% BELOW

AGREEMENT NO. 62/2019-20/IDA

TIME LIMIT 09 MONTHS (270 DAYS)I/C


RAINY SEASON

ACTUAL DATE OF START 01.08.2020

EXPECTED DATE
28.2.2022
OF COMPLETION

2
Name of work: Construction of BusTerminal at MundlaNaytaIndore

Total land area: 2.2 Hect.

PROVISIONS FOR BUSTERMINAL AT MUNDLA NAYTA

1. Considering 18hour terminal operation estimated no. of buses


will be 600.

2. Total 15 bays

3. Departure &Arrival Halls are designed considering footfall of


approximately 30,000 passengers everyday and 3000
passengers during peak hours.
4. Separate entry/exit for passenger and Buses.
5. Provision of separate parking facilities for:

a. 2-wheeler ( 1.75 sqm @ ECS )


b. Taxi/ car parking ( 25sqm @)ECS )

6. Separate Public toilet facility in parking area.


a) Open drains with MS grating.

A) Terminal Building/ Arrival Bays/ Departure Bays Platforms

□ Ground Floor: Total Area ( 1378 SQM )


a) Separate offices entry.
b) 09 ticketing counters ( Area : 7.84 sqm Each ) .
c) 300 seats waiting area

3
g) Facilities like Clock room, Police Room, Medical room,
Staff
Room, Administration room, Help desk, VIPlounge, Women
Lounge and store room.

h) Total 14 Shops at ground floor, which


consists of

1. 9 -Shops: 2.8m x 3.75m (10.5 sqm each)

2. 3 -Shops: 3.8m x 2.8m (10.64 sqm each)

3. 2 -Shops: 2.8m x 3.9m (10.92 sqm each)


b) One restaurants (Total area for Restaurant- 56.55 sqm
Which consists of
1. 1 food outlets: (56.55 sqm each)
k) Separate toilets for men and women

□ First floor: (Area-326.09 sqm)


a) 14 Offices.
1. 2 - Offices: 3.5m x 3.8m (13.3 sqm each)

2. 1 - Office: 3.5m x 3.9m (13.65 sqm each)

3. 1 - Office: 3.5m x 4.2m (14.7 sqm each)

4. 3 - Offices: 3.5m x 4.3m (15.05 sqm each)

5. 1 - Office: 3.5m x 7.7m (26.95 sqm each)

6. 5 - Office: 5.8m x 6.8m (27.84 sqm each)

7. 1 - Office: 8.8m x 6.8m (59.84 sqm each)

4
d) Separate toilets for men and women

Apart from that there are two staircases.

□ Terrace Floor

(1nos- OHWT on terminal Building – 30KL)

□ Under ground water tank Near Terminal Building-100KL

(90KL+10KL)

□ fire fighting controls are provided against fire

safety.

□ Building designed with Green Building concepts.

□ Roofing of building is done by Pre painted galvalume sheets


& Polycarbonate sheets for light ventilation supportedover
tubular sections at 9m height.
□ Pickup and drop point at entrance of building.
B) Control room and security room at Ground floor
Of building.

D) Sewerage Treatment Plant -100KLD capacity

5
AREA STATEMENT

S.n Land Development Area Unit Site Area Ground


Percentage Coverage

1 Bus Bays & Parking

a Idle Parking Bay ( 45+15 no. 1532 SQM 7.3%


)
2 Pathway Area 1473 SQM 7.06%

3 Terminal Building(1378 SQM) 1378 6.6% 6.6%

a Ground Floor 1011 SQM

b First Floor 362.09 SQM

4 Other Small Buildings

a Public Toilet (GC 170 SQM 0.81%


Exempted)
5 Surface Parking Areas 1366 SQM 6.6%

7 Dedicated Green Areas 3745 SQM 17.95%

8 Open Area (Roads, Ramps 11201 SQM 53.7%


& Walkways)

TOTAL 20865 SQM 100.00% 6.6%

6
FINANCIAL PROGRESS REPORT UPTO DEC 2021
Name of work:- Construction of Bus Terminal at Nayta Mundla, Indore

Name of Client:- Indore Development Authority, Indore

Name of Consultants:- Doshi Consultants Pvt. Ltd. Indore

Name of Contractor:- M/s OMPRAKASH AMARNATH

W/o no & dater:-1608 FOUR/Account 19-20

Actual date of starting:- 01-AUG-2020 Stipulated date of completion:- April 2021


Stipulated date of completion:-
Cost of Project 9.665 Cr. Total Land area 2.20 Hect
April 2021
Land available for working is around 1.65 Hect. On Considering Land Availablity 70% only…

Stipulated date of completion due


Cost of Project 7.249 Cr. Land area for working 1.65 Hect to Covid Reasons and Land
availiblity issue: Feb 2022

Total Months 19

PARTICULAR Amount

PROJECT COST 7.249 CR

Upto date Financial Progress Till 31st Dec 2021 (Appox) 5.57 CR

% OVERALL FINANCIAL PROGRESS W.R.T PROJECT COST 76.84 %