SERV 27_03032014 Rev1

Reference
M-file M ....
ENGINE TYPE 16VDZC
ENGINE SERIAL Nr
PLANT/VESSEL/LOCO Plant
Expected Commissioning Period
Expected Trials Period
INSTALLATION CONDITIONS BEFORE START COMMISSIONING
! Important note Request for commissioning engineer at minimum 4 weeks in advance
Before arrival next items must have been finished
When finished mark mentioned item as þ
Engine room works
þ Major cutting, grinding and welding works must have been finished
þ Engine room ventilation must have been finished
þ Engine room equipped with floor plates
Engine foundation and alignment
þ Engine foundation according prescriptions
þ Epoxy resin poured and dried NOT DONE
Epoxy had been done for the engine foundation soon after the installation
þ Elastic feet installation according prescriptions
þ Engine disc springs/washers installed and foundation bolts M27 x L tightened on couple
q Engine alignment report checked by ABC-Engineering Final Due
Engine installation piping and hydraulic circuit connections
þ Air inlet and gas outlet system Not complete
Installation of air inlet system is on hold due to below reasons
a. Installation held by Shining Star Engineer.
b. Horizontal air duct filters not delivered yet by Shining Star
c. Dimensions of flange delivered with tapper air duct are not compatible needs replacement
Gas outlet system installation is in progress, shall be completed by tomorrow
Note: Gas outlet system needs modification, as supplied flanges were mismatched with actual required

þ Fuel system Not complete

Fuel system is complete, except one modification for cooling of fuel in return line

a.Installation done upon instruction of Shining Star Engineer.

b. Required material for modification is available, modification shall be completer by tomorrow

þ Cooling water system Not complete

Required 4 air vents recommended by commissioning engineer

a. Required material is available at site, installation shall be done on Sunday .


þ Lubrication oil system
þ Starting air system Not complete
Starting air system already been completed, only required instruments are remaining
a. Installation done upon instruction of Shining Star Engineer.
commissioning engineer required increment in the size of supplied air line from half inch to one inch
C. Modification already in progress and will be completed by Sunday
Auxiliaries piping installation and electrical connections
þ Electrical Standby pumps Not complete
There is no standby pump, only one pump is available and installed
þ Pre-lubrication pump Not complete
Installation already completed, commissioning Engineer required modification for control system
Required modification shall be done by Shining Star Engineer
þ Fuel system
þ Pre-lubrication pump Not complete
Repeated, check answer above
þ Starting air compressor, air bottles, water filter and lubricator Not complete
Already Answer Above
q Alarm, Safety and monitoring system DMU1 or similar To be done by Comm. tea For elec team
According to the checklist needs to be done by Commissioning Engineer
Electrical cable and wiring connection
q Engine electrical connections and wiring To be done by Comm. tea For elec team
According to the checklist needs to be done by Commissioning Engineer
a. According to the instruction of Shining Star Engineer only one single(8 core) cable was required,
which already installed
b. Required cables recommended by comm engineer already been procured by Kafou, with
expected delivery by coming Tuesday
þ Auxiliaries electrical connections and wiring To be done by Comm. tea For elec team
According to the checklist needs to be done by Commissioning Engineer
a. According to the instruction of Shining Star Engineer only one single(8 core) cable was required,
which already installed
b. Required cables recommended by comm engineer already been procured by Kafou, with
expected delivery by coming Tuesday

þ Electrical Panels connections and wiring To be done by Comm. tea For elec team
According to the checklist needs to be done by Commissioning Engineer
a. According to the instruction of Shining Star Engineer only one single(8 core) cable was required,
which already installed
b. Required cables recommended by comm engineer already been procured by Kafou, with
expected delivery by coming Tuesday
þ 50/60 Hz AC voltage and 24V.DC available
Alarm, safety and monitoring wiring connections
q On/off contacts engine and auxiliaries To be done by Comm. team
q Analog sensors engine & auxiliaries To be done by Comm. team
Only engine filling after check installation piping and approval of Commissioning Engineer.
þ Filling of cooling water, lube oil, fuel, air bottle Not done
Lube oil, cooling water already been procured by Kafou and shall be delivered by Sunday
Note: Initial recommended lube oil was not available in KSA, alternative lube oil with same specs
been procured upon approval of comm engineer

Please return a duly completed check list to request a commissioning engineer by email or fax.

T + 32 9 267 00 00 E service@abcdiesel.be F + 32 9 267 00 67


Signature Client Date