Professional Documents
Culture Documents
Earth Dam Construction Method Statement
Earth Dam Construction Method Statement
) Dams
ONB No: MWDS/PSU/W/06/2023
MINISTRY OF WATER DEVELOPMENT AND SANITATION
ZAMBIA
METHODOLOGY
The listed activities will be cardinal as they kick start the whole project. Both plant and personnel will be
brought to site at mobilization stage. List of plant/Equipment and key personnel and the organization
structure are shown below.
GALNET CONSTRUCTION LIMITED shall make own arrangements for accessing electric power, water and
all other services. We understand that no direct payment will be made for the provisional of electricity, water
and other services by the employer. The cost thereof is in the rates and amounts contained in our tender for
the various items of work for which these services are required.
Fuel
In order to ensure the continuity of construction, the storage capacity of the fuel depot will be designed by
GALNET CONSTRUCTION LIMITED. The depot will be located near the main camp.
Security
GALNET CONSTRUCTION LIMITED's shall provide 24hrs security on site for the project duration.
1. The Project Manager shall be responsible for overall execution, quality, and safety of the Project.
The PM will review and approve upon satisfaction, the Methodology of Execution for works, to the
required Quality in a safe manner acceptable to all stakeholders.
2. The Site Engineer will be responsible for the execution of the individual activity to the required
quality, in accordance to the Approved Method Statement, in a safe manner acceptable to all
concerned.
3. The Surveyor will be key in ground controls and ensuring the dam is built at the selected location and
to the correct dimensions and height according to the drawings and specifications.
4. The Construction Technician shall ensure that the workforce is aware of procedures of executing the
activity and that the activities are per approved method statement.
Below is the typical organization structure of the project. The project will comprise of several general, Skilled
and operators.
Organization Structure
Project
Manager
Site
Surveyor
Engineer
Construction
Technician
Artisans
List Plant/Equipment
1 Excavator 1
2 Water Bowser 1
3 Tipper Truck 3
4 Sheep-foot Roller 1
5 Bulldozer 1
6 Front end loader 1
7 Concrete Mixer 1
8 Surveying Equipment 1 Set
9 Grader 1
10 Field Testing Equipment (Compaction and 1 Set each
Soil Classification)
All the equipment will be mobilized to the project at the same time before the project commences.
2.0 SURVEYING METHODOLOGY
The GALNET CONSTRUCTION LIMITED will engage a specialized private company to carryout soil
investigations and testing.
A topographical survey of the area will also be conducted by surveyors and project levels will be established
that will allow for cuts and fills on the project.
2.1 INTRODUCTION
A clear and adequate survey methodology is important for any Project to attain its stated quality standards
and expectations within time and cost. The Surveyors carrying out various setting out task must be clear of
the procedures to follow to ensure the setting-out is done correctly the first time to avoid costly rectifications
of the works.
This method statement summarizes the method of surveying as will be carried out in the contract for
construction of the Mbaswa Dam.
. The summary includes notes on the process and equipment to be used.
2.2 METHOD
a) General: The following shall be the sequence of operations during the process of surveying on the
above mentioned project.
b) Survey Instrument/Equipment Maintenance: The equipment used for all survey works i.e. Total
Station, Automatic levels, nylon and Steel Tapes, staff, plumb-bobs, verticality bubbles, etc shall be
checked and adjusted as may be necessary. The equipment shall be serviced by authorized
dealers. A record of instrument/equipment calibration certificates shall be furnished to the Engineer.
c) Carrying out OGL survey to verify existing Ground Levels: The stripped levels or ground levels are
now picked for use on quantity calculation.
d) Setting-out of Levels for earthworks is be done using modern precise automatic levels and staffs
which are in good adjustment. After concreting the bench marks and reference pegs we carry out a
three line leveling so as to have revised levels for use when controlling or checking. Independent
checks are also carried-out on all setting out to ensure that it is error free.
Every time a layer is completed, levels are taken and recorded on level check sheets. This is before dumping
for the next layer commences. This way a record is kept of the levels for all subsequent layers done during
construction and these are checked each time a layer level has been attained. These levels are controlled by
the use of boning rods. The levels taken and recorded are then submitted to the Engineers for their record
also. The Surveyor shall keep record of all original field sheets, checks and reduced levels.
3.0 CONSTRUCTION METHODOLOFY
GALNET CONSTRUCTION LIMITED shall check the condition and accuracy of all reference and level
beacons and satisfy himself that they have not been disturbed and are true with regard to position and level.
A beacon that has been disturbed shall not be used until its true position and level have been re-established
and the new values have been certified by the Engineer. The GALNET CONSTRUCTION LIMITED shall
thereafter be held entirely responsible for the protection of all reference and level beacons.
3.2 SCOPE
This method statement covers the construction, fill and compaction of various zones of the dam
3.3 MATERIALS
GALNET CONSTRUCTION LIMITED shall use the materials as specified in the contract and will conduct
testing to ensure the right materials are used. The material to be used for each zone are
3.3.1 Selected impervious core : Zone I
The selected impervious material in this zone shall consist of cohesive clay/ sandy clay/ clayey sand with a
Plasticity Index (P.I.) of between 8 and 15, with a mean greater than 10. The material shall contain no
pebbles greater than 50 mm. The mean clay content must be more than 15%.
The material shall be obtained from the clayey deposits in the dam basin, indicated as possible clay borrow
areas on the Drawings.
3.5 TESTING
3.5.1 Taking and testing of samples
GALNET CONSTRUCTION LIMITED shall for the duration of the Contract conduct density control tests using
a nuclear density testing apparatus with a qualified technician to operate the device. GALNET
CONSTRUCTION LIMITED shall also provide a Calibration Certificate for the device.
GALNET CONSTRUCTION LIMITED may use this device to conduct his routine density control and moisture
content control tests. It does, however, not exempt him from his responsibility to achieve the specified density
and moisture content. GALNET CONSTRUCTION LIMITED shall conduct moisture content control tests in
his laboratory to check the results obtained from the nuclear device.
The frequency with which these routine density and moisture content control tests shall be conducted shall
be, on average, one set per main zone per four layers of placed material at roughly 50 m intervals along the
embankment.
GALNET CONSTRUCTION LIMITED shall make the device available to the Engineer for his control tests
whenever the engineer wants to conduct his own tests.
The costs of any control tests conducted by the Engineer which do not conform to the requirements shall be
for GALNET CONSTRUCTION LIMITED’s account
3.5 PROTECTION AND MAINTENANCE
It shall be ensured that the completed layers are protected against rain and flood water. Maintenance shall
include, the immediate repair of any damage or defects that may occur.
5.1 INTRODUCTION
This method statement covers the manufacture, transportation, placing and testing of concrete that will be
used on the contract for construction of Mbaswa Dam. The summary includes notes on materials to be used
and their storage, quality of concrete, measurement of materials, mixing, placing and compacting concrete,
falsework/formwork and surface finish, construction joints, curing and protecting concrete, weather
considerations, quality and workmanship, equipment requirements and, safety of workers and protective
clothing.
5.2 MATERIALS
a) Cement:
All cement used on Site shall comply with SANS 50197-1 for CEM I 42,5. From the Zambian market, this
shall either be Portland Limestone Cement from Lafarge or Zambezi Portland Cement.
Cement shall be used in the order in which it is received. GALNET CONSTRUCTION LIMITED shall
always have at its disposal on the Site a minimum stock of cementitious materials sufficient for 2 weeks
normal work and unless approved by the Engineer, cement kept in storage for longer than 8 weeks shall
not be used in the Works. The Contractor shall endeavour to obtain all cementitious materials supplies
from the same factory or source.
b) Aggregates:
Both the coarse (20mm crushed stones) and fine (sand) aggregates shall be of approved quality i.e.
grading and shape, complying with the requirements of SABS 1083 or equivalent and shall fall within set
limits for drying shrinkage in accordance with SABS 836, flakiness Index and Aggregate Crushing Value
as determined by TMH 1 Method B3, and the Fineness Modulus of the fine aggregate.
The aggregates shall be clean and free of dust, clay, organic matter and any other deleterious matter.
c) Water:
Water shall be clean portable fresh water, free from detrimental concentrations of chemicals and organic
impurities such as acids, alkalis, salts and sugar that could impair the durability and strength of concrete
or the imbedded steel.
d) Admixtures
No admixtures or curing agents shall be used in this project without the approval of the Project Manager.
e) Steel Reinforcements:
Mild steel shall be according to SANS 920 - Type A 250 MPa yield and high yield stress steel according
to SANS 920 - Type C, Class 2, Grade 1, 450 MPa yield.
Welded steel fabric for concrete reinforcement shall be according to SABS 1024.
For each consignment of steel reinforcement delivered to site, the product certificate from a
recognized testing authority shall be submitted to the Client to confirm compliance with project
specifications.
f) Pre-cast Concrete Materials: The following specified pre-cast materials shall be nused in the
project; Standard kerb stones of various specified sizes.
a) Cement: Cement will be stacked closely and neatly (to heights not exceeding 12 bags) in the
storage shed for a period not exceeding 8 weeks. Cement from Lafarge and Zambezi shall
be stacked separately in the order that they are delivered. It shall be ensured that cement
bags are not in contact with the ground or walls of the storage shed.
Cement on site shall be stored covered in strong waterproof fabric sheets or polythene
sheets.
b) Aggregates: The concrete stones (20 mm) shall be properly stored to avoid
contamination.
c) Storage Capacity: Adequate storage for cement, aggregates and water shall be made
available so as to avoid any interruptions to the progress of work occasioned by lack of
materials.
d) Unsuitable Material: Deteriorated, contaminated and damaged materials shall not be used in
any concrete works, but shall be removed from site immediately it is discovered that the
material is unsuitable.
5.4 CONCRETE QUALITY
a) Concrete Strength: The classes of concrete specified in the Contract and our mix
designs are as tabulated below;
Characteristi
Maximum c 28-Day
Clas WATER:CEMEN
Size of Cube
s of Design Application T RATIO
Coarse Crushing
concr Mix Strength
Aggregate
ete (Mpa)
(mm)
Blinding of culvert
10/19 1:4:8 19 10 0.50
bedding
Culvert surround &
15/19 1:3:6 19 15 bedding, Blinding of 048
foundation for bridge
Concrete backfill on
20/19 1:2:4 19 20 culverts, Guide Posts 0.48
and Marker Posts
Culvert toewalls &
keywalls ,Head &
wingwalls, Inlet &
outlet structures;
25/19 1:2:3 19 25 0.46
bridge abutments,
piers, lining for open
drains, backfill below
chutes, edge beams
If there are any changes in the material sources, type or sizes for any constituent material for
concrete, samples, product certificates and a statement of the proposed mixed proportions shall be
submitted for the approval of the Resident Engineer before starting any concrete works.
Product Certificates shall also be submitted for approval for each consignment of cement.
QUANTITIES: ONE CEMENT BAG MIX
For routine quality control, a minimum of four 150mm x 150mm x 150mm concrete test cubes shall
be sampled for testing for a full days work, as and when required by Resident Engineer. Samples of
aggregates and concrete cubes shall be taken at random as directed by the Resident Engineer. A
minimum of six steel moulds shall be provided.
The cement and aggregates be used for the concrete works shall be measured by the batch using a batch
box of size 300mm x 300mm x 400mm. Water shall be measured by volume while the reinforcement will be
as per specifications. Cement will be supplied in standard bags, and each bag will be assumed to be 50kg
5.6 MIXING
Concrete shall be mixed by mechanical batch mix and this shall be done with the approval of the Engineer.
The amount of water shall be sufficient to give a good workable mix and produce the specified strength as
described above.
The mixing water for each batch shall be measured, either by mass or by volume accurate to 3% of the
required quantity.
Where damp aggregate is used, the quantity of water added to the mix shall be adjusted to make allowances
for the moisture already in the stones and/or sand.
Discharging of concrete from mixer
Discharge of concrete from mixer shall be carried out at a minimum slope of 1:3 and not exceeding 1:2 to
avoid segregation of materials in the mix. The mixer shall be washed thoroughly before any concrete is
mixed and whenever it is stopped running for more than 30 minutes, to get rid of any built-up material in the
drum, loader and blades. A standby mixer shall be provided whenever it is important for casting to continue
without interruption.
Notice will be issued to the Resident Engineer 24hrs before placing of concrete for approval.
REMOVING THE FALSEWORK AND FORMWORK: Falsework and formwork shall not be removed before
concrete has attained sufficient strength to support its own weight and any other loads which may be
imposed on it.
Tab 6206/1 to 6203/3 SATCC shall provide a general guidance on the minimum periods of time for specific
situations.
SURFACE FINISHES: It shall be ensured that surface finishes comply with the specified classes. All surface
defects noted after removal of formwork shall be remedied as directed by the Resident Engineer.
Generally all works will be supervised by a Site Engineer, who shall ensure that safe environment is always
maintained, and that on-site safety procedures are followed at all times.
The Site Engineer shall see to it that adequate measures are taken to warn and protect road users and
construction workers. He shall instruct all supervisors and foremen in safety measures including traffic
control and use of clean standard temporary road signs
The Safety Officer shall conduct regular on-site inspections of works, equipment, tools and personnel. He
shall also hold regular safety meetings with all work groups to discuss and instruct in safety, and shall
produce weekly reports to Management.
Good working and handling practices shall be ensured on site
All workers shall be provided with such protective clothing such as hand gloves, overall suits, boots, reflective
jackets and dust masks. Where necessary, workers will also be provided with helmets.
Only suitable hand tools and devices, free from any defect, shall be used.
Only experience operators shall be used to operate such equipment, as concrete mixer, compressor, etc.
Falsework, formworks and scaffolding shall sufficiently and rigidly be secured in position before placing of
concrete as described in 8) above.
5.14 PERSONNEL
Working Force
1 Concreting Construction Technician
1 Overseer for each 10 Workmen
1 Concrete Mixer Operator
2 Bricklayers
1 to 2 Steel Fixers
10 to 20 General Workers
2 Traffic Controllers
The dam’s outlet pipe shall be 355 mm OD High Density Polyethylene (HDPE) Class PE100 PN6
suitable for butt-welding manufactured complying with SANS 533:1982 and 1995 superseded in parts
by SABS ISO 4427:1996
6.1 Construction
6.1.2 Testing
6.1.2.1 General
All pipes shall be hydraulically tested after their installation but prior to their encasement. The pipes
under the dam wall shall be retested hydraulically 7 days after the pipe encasement has been
completed.
PROJECT COMPLETTION
GALNET CONSTRUCTION LIMITED shall upon completion conduct a comprehensive completion
survey of the Mbaswa Dam, its spillway, roads, outlet works and dam basin, which shall link into the
existing survey everywhere where construction activities have disturbed or changed something. This
survey shall be sufficiently detailed to provide a 0.5 m contour interval on the dam wall and a 1 m
contour interval in the dam basin. Details concerning all structures constructed as part of the Contract
shall be provided. The survey shall be submitted in *.xyz format with “break lines” to be utilised in Civil
3D, as well as a contour plan in *.dwg format (AutoCAD 14 or later version).