1 Methodology
A
For the best results in electrical installation design it is recommended to read all the
chapters of this guide in the order in which they are presented.
Service connection
This connection can be made at:
B – Connection to the MV utility distribution b Medium Voltage level
network A consumer-type substation will then have to be studied, built and equipped. This
substation may be an outdoor or indoor installation conforming to relevant standards
and regulations (the low-voltage section may be studied separately if necessary).
Metering at medium-voltage or low-voltage is possible in this case.
C - Connection to the LV utility distribution b Low Voltage level
network The installation will be connected to the local power network and will (necessarily) be
metered according to LV tariffs.
H - LV switchgear: functions & selection The performance required by the switchgear will determine its type and
characteristics.
The use of cascading techniques and the discriminative operation of fuses and
tripping of circuit breakers are examined.