Mock Drill Report
Mock Drill Report
LOCATION: ACADEMIC BLOCK WEST SIDE (Project- Azim Premji University, Bhopal)
DATE: 15/04/2023
TIME: 08:02 AM
Fire – Fire drill started at 08:02am. Emergency information were given by Site Supervisor by mobile phone to Emergency Contact
Person. Emergency response team member made the communication to directing the occupant to leave work location/ evacuate the work
area, and assemble at the safe assembly point. When all employee Engineer/Supervisor and Workers arrived at the assembly point.
Various rescue techniques were used by the ERT.A briefing was done on Fire and Emergency response during Fire Emergency.
How did the fire start- A laborer was quietly smoking beedi on the site, while the carpenter's work was going on next door. The wood caught
fire after the worker threw the beedi and the worker got caught in the fire while trying to extinguish the fire .
Emergency response team ready for action. 1.Evacuation team 2. First aid team 3. Fire Fighting team 4.
8:05 8:05
Rescue team 5. Observation team
All staff and workers reached at Assembly Point for Head Count. All activity were stopped 8:12 8:12
A Briefing was done informing about the Emergency Mock Drill scenario and the objective of the drill; we
addressed the workers about Fire Emergency. Safety Officer told the staff and workers about Emergency 8:13 8:17:30
Response Procedure and Hazards associated with their work
Casualty- NIL