The document contains information about excavation volumes, concrete volumes, and gravel volumes needed for a construction project. It lists the dimensions and volumes needed to excavate 1.82 cubic meters of material and pour 0.607 cubic meters of concrete. It also states that 0.825 cubic meters of gravel will be needed. It provides calculations to determine the number of days and cost of labor for excavation, and amounts of cement, gravel, and sand required based on the concrete volume.
The document contains information about excavation volumes, concrete volumes, and gravel volumes needed for a construction project. It lists the dimensions and volumes needed to excavate 1.82 cubic meters of material and pour 0.607 cubic meters of concrete. It also states that 0.825 cubic meters of gravel will be needed. It provides calculations to determine the number of days and cost of labor for excavation, and amounts of cement, gravel, and sand required based on the concrete volume.
The document contains information about excavation volumes, concrete volumes, and gravel volumes needed for a construction project. It lists the dimensions and volumes needed to excavate 1.82 cubic meters of material and pour 0.607 cubic meters of concrete. It also states that 0.825 cubic meters of gravel will be needed. It provides calculations to determine the number of days and cost of labor for excavation, and amounts of cement, gravel, and sand required based on the concrete volume.
Other Solutions: Excavation Cost of Labor = # of Laborers x # of day x 427 Php # of Laborers = 3
# of days = EVT/0.3/# of Laborers
# of days = 1.82/0.3/3
# of days = 2
Excavation Cost of Labor = 3 x 2 x 427 Php
Excavation Cost of Labor = 2, 562 Php To get the number of Cement (Sack), Gravel (Cubic Meters), and Sand (Cubic meters) # of Cement (Sack) = CVT x 9 = 0.607 x 9 = (5.463) or 6 Sacks # of Gravel (Cubic Meters) = CVT x 1= 0.607 x 1 = 0.607 m3 # of Sand (Cubic Meters) = CVT x 0.5 = 0.607 x 0,5 = 0.3035 m3 8 12-mm bars are needed and 12 10-mm bars are needed (1.85) or 2 kg of tire wires are needed Thickness = 1: CHB = 37 4 - 4mm. Thk × 38mm× 38mm angle bar is needed per unit 1 – 2 in GI pipe u