City Engineering Office (Civil Engineer) – Immersion Task

Width Height Length Unit Answer


F1C1 800mm 1000mm 800mm 2 1.28 m3
Excavation Wf 300mm 600mm 3000mm 1 0.54 m3
EVTOTAL 1.82 m3
F1 800mm 200mm 800mm 2 0.256 m3
Volume of C1 200mm 2700mm 200mm 2 0.216 m3
Concrete Wf 300mm 150mm 3000mm 1 0.135 m3
CVTOTAL 0.607 m3
Below F1 0.128 m3
Volume of Below Wf 0.09 m3
Grave #G 0.607 m3
GVTOTAL 0.825 m3

Other Solutions:
Excavation Cost of Labor = # of Laborers x # of day x 427 Php
# of Laborers = 3

# of days = EVT/0.3/# of Laborers

# of days = 1.82/0.3/3

# of days = 2

Excavation Cost of Labor = 3 x 2 x 427 Php


Excavation Cost of Labor = 2, 562 Php
To get the number of Cement (Sack), Gravel (Cubic Meters), and Sand (Cubic meters)
# of Cement (Sack) = CVT x 9 = 0.607 x 9 = (5.463) or 6 Sacks
# of Gravel (Cubic Meters) = CVT x 1= 0.607 x 1 = 0.607 m3
# of Sand (Cubic Meters) = CVT x 0.5 = 0.607 x 0,5 = 0.3035 m3
8 12-mm bars are needed and 12 10-mm bars are needed
(1.85) or 2 kg of tire wires are needed
Thickness = 1: CHB = 37
4 - 4mm. Thk × 38mm× 38mm angle bar is needed per unit
1 – 2 in GI pipe u