Procedure for Temporary Connection - LT / HT Line

START

Applicant submits application in prescribed format


and Rs. 1000 for LT supply and Rs. 10,000 for HT/
EHT supply

Application form
Yes No
complete

Applicant notified of deficiency in


Application accepted application and rectifies the same
immediately

Licensee checks for Applicant to clear dues


Yes
previous dues on the of the premise
premise

No Yes
Licensee examines technical Applicant clears
feasibility of connection requested the dues
No

Technically Application Rejected


yes
No feasible
Demand note (Consumption security and
material security) issued to applicant within 5
Application Rejected citing days for LT and 15days for HT/EHT
reasons within 5 days for LT
and 15days for HT/EHT

Customer pays the fee


No Yes
within 5 days

Licensee carries out the


Application Rejected work for energisation

Temporary Connection
granted for maximum 3
months

STOP