NATIONAL STANDARDS

TCVN 8828: 2011


CONCRETE - NATURAL MOISTURIZER REQUIREMENTS
Concrete - Requirements for natural moist curing
Preface
TCVN 8828: 2011 replaces ISO 5592: 991 and converted from TCXDVN 391: 2007 in accordance e ị nh
in paragraph 1 of Article 69 of the Law on Standards and Technical Regulations and point a
warehouse Arab n 1, Article 7 of Decree No. 127/2007 / ND-CP dated 01/8/2007 of the
ph composting regulations detailing the implementation of some articles of the Law on standards and
technical regulations.
ISO 8828: 2011 by the Association of Industrial Concrete compiled Vietnam, the Ministry of Construction
proposed, the Directorate for Standards, Metrology and Quality th ẩ m the Ministry of Science and
Technology announced.

CONCRETE - NATURAL MOISTURIZER REQUIREMENTS


Concrete - Requirements for natural moist curing
1. Scope of application
Main targets ẩ n specifies requirements b Arab Street ẩ m self course for concrete structures and
reinforced concrete bear direct impact of climatic factors Vietnam in s Arab n manufacturing and
construction public.
2. References
The following references are required for the application of this standard. For the record referenced
documents in the b stain is applied b ả n yet. For referenced documents not recorded in the b stain is
applied session b her n the latest, including the b ả n amended and supplemented (if c ó ).
ISO 4506, Water for b ê concrete and mortar - Technical Requirements
TCXD 191 1996 * , B ê concrete and concrete materials - Terminology and definitions.
TCXDVN 305:2004*, Massive concrete - Code of construction and acceptance.
3. Terms and definitions
The terms in t iêu this standard is defined as follows:
3.1 . Bao Duo ng natural moisture (Moist air curing)
Th moisturizing process ư wall for concrete trans in terms of the impact on local climate factors. Can
make sure the balance ỡ ng ẩ m naturally by investment ớ i water directly onto the surface of the
concrete, coated materials ẩ m old female ớ c , spray, or coating the material water on the calf cardboard
(see TCXD 191:1996).
3.2 . Strengthen the security support to term (Critical curing strength)
Value for compressive strength of concrete at the time of stop the security balance ỡ ng natural moisture,

symbol , single position t í nh is % intensity b ê cardboard at the age of 28 days and


nights,% R 28 (see TCXD 191:1996).
3.3. Th er i guarantee period maintenance required (Essential curing time)
Time calculated from the start of maintenance ẩ m natural for t ớ i when b ê serve residents er ng

maintenance of tipping, denoted , is the day unit.


3.4 . B Arab Street initially (Initial curing)
The process of keeping the concrete does not evaporate the water in no kh í without th To watering
moisture directly onto the concrete surface.
3.5 . B Arab Street next (Subsequent curing)
Moisturizing process to limit the concrete evaporation into the atmosphere since the start of irrigation
water on the concrete surface until the stop process b Arab o natural moisturizer.
3.6 . B ề face h in (Open surface)
Structural concrete surfaces can evaporate water into the air.
4. General provisions
4.1. Maintenance process ẩ m nature should be carried out continuously immediately after finishing the
concrete surface until the stop process b Arab Street.
4.2. Specifications characteristic to assess the balance mode to ON g moist self pediatric ê n of concrete
are:

- Extreme curing intensity ;

- The guarantee period d om e om e necessary .

Which parameters are decided , while parameters identified e ị nh based on parameters


t Commissioner under specific climates.
5. Climatic zoning according to concrete moisture curing requirements
According to c ầ u technical maintenance ẩ m nature of concrete, the territory of our country is divided
into three climatic zones typically the A, B and C , with boundaries e ị Geography, named season and
th er time of the year indicated in B Arab Table 1.
6. Requires natural moisturizing maintenance
6.1. Security balance process ỡ ng natural moisture ph â n into 2 phases: initial maintenance and low
maintenance ỡ ng ti ế p follow. This two-stage continuous steps in succession without interruption,
k To since finishing finished surface of the concrete until the concrete gain critical maintenance intensity.
6.2. Stage b ả o initial support
This phase c ầ n with concrete measures to ensure the water does not evaporate under the effect of the
medicine ế u local climate factors (such as sun, wind, temperature and humidity kh í ). A. Oh ng time not
to mechanical forces acting on the concrete surface.
Table 1 - Climatic zoning according to the natural moisture curing requirements of concrete

Climates sure
Time of year, in
residual ỡ ng ẩ m Location geographical Season name
months
concrete
Region A From Dien Chau district Wet rainy 4¸9
(Nghe An) p in place. season
10 ¸ 3
Dry season
RED region East Truong Son from Dry season 2¸7
Dien Chau to Ninh Thuan
Rainy season 8 ¸ 11
region C Rest , how g OM Dry season 12 ¸ 4
West Highlands and co b Q
Rainy season 5 ¸ 11
U ng South.
Ti ế Operation b ả o Initial support is as follows:
Concrete after shaping government done to right b ề the openings in the material has been made ẩ m
(with the appropriate material or material available). This time does not affect mechanical forces and
private not ớ i water directly onto the concrete surface t umbrella ng to avoid damaged concrete
surfaces. When you need light watering can water l ê n the v é t ph
whether tempering moisture. Government can also concrete b Q U ng the country as a plastic material,
v Arab i canvas, or spraying water vapor barrier created. As for pro à t t sir o membrane on the concrete
surface, the spraying is done according to the instructions of the s Arab n production of film forming
agent. You can also use spray equipment to spray nư ớ c mist directly onto the concrete surface without
ph incubated concrete.
The government ẩ m b ề concrete stage b Arab Street initially nh  t necessarily have to t hi managed to
go ề tumor conditions dehydrate quickly (like having the hot sun, kh í Weather n ó ng dry, kh í Weather
wind Laos). The School er ng others can not deny the b ê cardboard, but monitor e To ensure that limited
concrete b ị dehydration, avoid cracking the concrete surface.
The moisturizing concrete stage initial maintenance lasts until the concrete reaches a strength value n é n
certain guarantee watering can directly ti ế p face b ê tone without causing damage harmful. Time
e To achieve this intensity during the rainy season ẩ m in Zone A and the season in Region B and C is
about (2.5 ¸ 5) h; in dry season in Zone A is approximately (5 ¸ 8) of concrete curing h
t Commissioner under t í nh of concrete quality and characteristics of the times ti ế t. At the School er ng
may determine this point b Q U ng way of ớ i th ử water on face b ê cardboard, n ế u th  y b ề face
b ê cardboard not b ị damaged l à , when it began to phase maintenance next.
6.3. The next maintenance phase
Proceed immediately after the initial maintenance period. This is the stage need water to keep ẩ m
continuous all openings of the concrete surface until it stops the process of maintenance.
6.3.1. For concrete using Portland cement and Portland cement mixed to generally cross-old female ớ c
moisturizing for all b ề the openings of concrete structures for t ớ i when concrete reaches strength value

protection balance ỡ ng t ớ i term and time b ả o M c ầ n set as follows:


a) For a heavy concrete information er ng, high-grade concrete, concrete waterproofing, self compacting
concrete: not less than specified in the B Arab Table 2, t Uy regional climate and season.
b) For lightweight aggregate concrete, fiber reinforced concrete scattered: Time needed maintenance
decreased by 1 day compared to gi á values in Table 2. Particularly rainy season in areas B and C do not
balance ớ i dates night in Table 2.
c) For foam concrete and aerated concrete: The required curing time is increased by 1 day and night
compared to the level specified in Table 2.
d) For the concrete of the structure will be affected regularly by h óa substances, concrete building
structures in coastal areas within 1 km t í nh from the water's edge and concrete in h Arab i e virtual o. If
no separate provisions of the design, the maintenance time required is y increase by 1 day e ê m above
the levels specified in Table 2 .
e) For large block concrete:
Massive concrete structures of industrial and consumer products (such as silo foundation, nails chimney,
foundation m á y, wall and vault, etc .. retaining wall): In addition to the requirements of design, b
time she o M c ầ n set not less than 7 days and nights, regardless of the climate and season. Watering
and heat dissipation measures for bulk concrete in the next curing period should be carried out according
to the guidance of TCXDVN 305:2004.
Large concrete dams: Follow requirements set k of power and industrial or construction measures were
approved.
f) For v ớ i roller compacted concrete:
Roller compacted concrete for pavement or yard: the required curing time shall not be less than that
specified in Table 2.
Roller compacted concrete for large dams: Follow design requirements or approved construction
methods. A device that sprays water into a mist can be used on the concrete surface immediately after
compaction of each layer. The spray was conducted rolling l ê n under layers apart. When stopping
construction, the last layer of pouring is watered and cured for not less than 7 days and nights.
6.3.2. For v ớ i concrete using Portland cement x dull and portland pozzolan: Th yeah i moist
maintenance period increased by 1 day compared with provisions in Table 2.
6.3.3. For cement concrete closed r eat slowly, or retarding additives: Th er i needed time maintenance
increased by 1 day compared to regulations in B Arab ng 2.
Table 2 - Level Residential value er ng d indemnities UO ng tipping and maintenance time c ầ n set to b ê cardboard

th heavy box ng often

M memory specified value not


less h Matt n
Climates Maintenance ẩ m Th er Time in years, in
Name m ù a
b ê cardboard months
day and
, %R 28
night
Region A The rainy 4¸9 50 ¸ 55 3
season ẩ m
10 ¸ 3 40 ¸ 50 4
Dry season
RED region Dry season 2¸7 55 ¸ 60 4
Rainy season 8¸1 35 ¸ 40 2
region C Dry season 12 ¸ 4 70 6
Rainy season 5 ¸ 11 30 first
6.3.4. For concrete using fast curing cement, or using fast curing admixture: Follow point b in 6.3.1.
6.4. In phase sure residue ỡ ng ti ế p accordance with th To min incubation ẩ m or min incubation moist
surface b ê cardboard. For areas with hot, dry climates or with Laotian winds, mulching will be effective to
reduce the number of watering times per day and limit cracking of the concrete surface.
Hits watering day t Lt depending on the local climate, so that the surface b ê tone is always
wet. The t network meeting water moisturizing c ầ n is maintained both day and night to e Arab m telling
b ề concrete surface always kept ẩ m, avoiding b ị to dry in e ê m.
In phase balance protection ỡ ng subsequent immersion can perform on concrete instead of water to
keep ẩ m.
6.5. Water used for irrigation keep ẩ m b ề concrete need th oa chronic medical ê u requirements of ISO
4506: 1987. May also To use river water, water h oh pond kh umbrella ng impurities harmful for the
concrete to be low maintenance ỡ ng moist b ê cardboard.
6.6. When's she n products b ê cardboard or construction of concrete using the vest she i techniques to
increase curing b ê tones to soon remove the formwork (as h à p steam, steaming by energy burp ng sun,
electricity etc .. engaging with) the process said residual ỡ ng next should be done until the concrete
reaches the critical intensity maintenance under 6.3. When removing the formwork that b ê cardboard
balance has not reached the intensity sure ỡ ng tipping must ti ế p continue TUO i water protection
residual ỡ ng t moist until the concrete cell ng achieve the specified critical curing strength .