Professional Documents
Culture Documents
Topic 4 Tender Procedure 02
Topic 4 Tender Procedure 02
PROCEDURE
1
Letter of invitation to tenderers
Checklist for submission of tender
Form of tender
Condition of contract
Specification
Bill of quantities
Tender drawings
Schedule of daywork rates
2
An invitation to contractor to submit offer
Consists of:
- A list of document issued
- The tender document fee charge
- Detail on tender submission date
- Penalty for withdrawal or failure to proceed
in the event of acceptance
- Any other necessary instruction
3
A list to help tenderer on their tender
submission documents
As a guide to avoid possibility of rejected
due to incompleteness
For example:
- Filling the specified forms or prices
- Schedule and appendices
4
One of the most important document in
tender submission
The following information must be filled:
- Tender sum
- Period of completion
- Tender validity period
- Alternative offer (if any)
- Express additional agreement (if any)
5
The detail on agreement between both
parties
For examples:
- If there is sectional completion required
- Rate of liquidated and ascertained damages
- Mode of payments, interim etc
- Minimum value of work to be executed prior
to payment
- Detail of insurances
- Advance payment, fluctuation price, on site
training (if any) 6
To define the work required in the project
Performance specification
Detail material and workmanship required
To assist contractor in pricing for work not
fully define in BQ and drawing
Normal practice will use standard
specification by industry and made
modification where necessary
7
A prime document in tender document
Serve as basis of tender sum & contract sum
Describe the material and workmanship of
the work
A tender without BQ will require tenderer to
measure the work based on drawings and
specification
BQ must be measure based on standard
SMM
8
Item under BQ:
- Preliminaries
- Preambles
- Measured works
- Summary of tender
9
A list of items of work priced per unit
Price used in conjunction of calculation price
for tendered works
An important for tender without BQ
As a guide for QS to do valuation of variation
works during construction
Also used for ‘re-measurement’ type of
contract
No standard form of schedule
10
Give an overview of nature and extent of the
work involved in the tender
Provide clear view and detail of the item
under BQ
Assist contractor to price accordingly
The drawing must as detail and complete as
possible
The actual content for tender drawing are
varies, most of it are:
- Site & location plan, floor plan, sections,
elevations, detailing etc 11
An invitation to public / certain class of work /
particular section of the public
Tender advertisement information:
12
Confirmation of allocation
Preparation of specification
EVALUATION of tenders
14
15
16
The usage of tender box:
- Tender box is used to place the tender
documents submitted by the contractor
- It is a lockbox marked with no. of project,
project name, date and time of tender opening
and the final submission date
- After closing date, tender box will be locked
and the documents will be kept in a room
- Tender documents will be opened after Board
of Tender Committee meetings
17
Offer is valid for acceptance of employer for
a reasonable period of time
All necessary activities towards the detail in
tender document need to be finalized before
the period end
Therefore, the tender process need to be
done in the stipulated time frame
18
However, this period can be extended by
applying writing request by employer to
the tenderer at least 2 weeks before expiry
– only agreeing tendered will be further
considered
Extension of validity period NOT ALLOW
the tenderer to revise their initial bids
19
ACCEPTANCE OF TENDER
Stages of acceptance:
• Issue letter of intent
• Pre-contract award meeting / negotiation
• Confirmation on funding
• Preparation and issuance of letter of
acceptance
• Acknowledgement of tender acceptance by
awarded tenderer
20
Revocation of acceptance:
- By communication of notice by tenderer
- By the lapse of time prescribed in tender for
acceptance
- By the failure of employer to fulfill any
condition
- By the death or mental disorder of the
tenderer or employer
The withdrawal by tenderer indirectly cause
financial loss to employer – EARNEST
MONEY as PENALTY at the time of tender
submission 21