Implementation Time Plan

Measurement Survey Work

Percentage Month 1 Month 2 Month 3


No. Job Deskription
(%) Week Week Week
1 Mobilization 9.13 1 2 3 4 5 6 7 8 9 10 11 12
2 Preparatory work 3.20 9.13 100.000
97.375
3 Benchmark Creation & Observation 13.65 3.20 87.639 91.194
4 Aerial & Lidar Photos 21.45 6.82 6.82 78.176
5 Stakeout & Row Benchmarking 29.54 5.36 5.36 5.36 5.36 68.713
59.250
6 Drawing Shop Drawing 17.78 53.343 5.91 5.91 5.91 5.91 5.91
7 Reporting 5.25 42.073 3.56 3.56 3.56 3.56 3.56
36.709
31.346
2.63 2.63
19.1575

Total 100.00%
Progress Plan 19.158 12.188 5.364 5.364 11.271 5.907 9.463 9.463 9.463 3.556 6.181 2.625
Total Cumulative Progress Plan 19.1575 31.346 36.709 42.073 53.343 59.250 68.713 78.176 87.639 91.194 97.375 100.000
Actual Progress 0 0 0 0 0 0 0 0 0 0 0 0
Actual Progress Cumulative Tota 0 0 0 0 0 0 0 0 0 0 0 0