Professional Documents
Culture Documents
Project Planning
Project Planning
WBS Code WBS Name BL1 Start BL1 Finish BL Project Material BL Project Labor BL ProjectTotal Cost S O N D J F M A M J J A S O N D J F M A M J J A S O
Cost Cost 1 2 0 3 1 2 1 0 1 2 1 0 1 0 1 0 2 0 2 0 2 0 2 1 2 0 2 1 2 1 3 1 2 1 0 1 3 2 0 1 0 2 0 2 0 2 0 2 0
P-001 BASEMENT CONSTRUCTION PLANNING 03-Apr-23 18-Jun-24 $369,630.00 $263,648.00 $633,278.00 03-Apr-23 18-Jun-24
P-001.1 SUB-STRUCTURAL WORK 03-Apr-23 10-Feb-24 $192,120.00 $248,561.60 $440,681.60 03-Apr-23 10-Feb-24
P-001.1.1 PILING AND SHEET PILE WORK 03-Apr-23 11-May-23 $9,000.00 $11,640.00 $20,640.00 03-Apr-23 11-May-23
P-001.1.2 EXCAVATIONAND BRACING WORK 11-May-23 04-Jul-23 $33,600.00 $22,440.00 $56,040.00 11-May-23 04-Jul-23
P-001.1.3 B2 SLAB WORK 20-Jun-23 26-Oct-23 $98,760.00 $65,463.20 $164,223.20 20-Jun-23 26-Oct-23
P-001.1.4 B1 SLAB WORK 26-Oct-23 22-Dec-23 $24,360.00 $44,890.80 $69,250.80 26-Oct-23 22-Dec-23
P-001.1.5 GF SLAB WORK 22-Dec-23 10-Feb-24 $26,400.00 $104,127.60 $130,527.60 22-Dec-23 10-Feb-24
P-001.2 SUPPER-STRUCTURAL WORK 12-Feb-24 18-Jun-24 $177,510.00 $15,086.40 $192,596.40 12-Feb-24 18-Jun-24
P-001.2.1 1F 12-Feb-24 14-Mar-24 $44,377.50 $3,771.60 $48,149.10 12-Feb-24 14-Mar-24
P-001.2.1.1 Column Work 12-Feb-24 21-Feb-24 $10,475.00 $866.00 $11,341.00 12-Feb-24 21-Feb-24
P-001.2.1.2 Slab and Beam 21-Feb-24 14-Mar-24 $33,902.50 $2,905.60 $36,808.10 21-Feb-24 14-Mar-24
P-001.2.2 2F 14-Mar-24 15-Apr-24 $44,377.50 $3,771.60 $48,149.10 14-Mar-24 15-Apr-24
P-001.2.2.1 Column Work 14-Mar-24 25-Mar-24 $10,475.00 $866.00 $11,341.00 14-Mar-24 25-Mar-24
P-001.2.2.2 Slab and Beam 25-Mar-24 15-Apr-24 $33,902.50 $2,905.60 $36,808.10 25-Mar-24 15-Apr-24
P-001.2.3 3F 16-Apr-24 17-May-24 $44,377.50 $3,771.60 $48,149.10 16-Apr-24 17-May-24
P-001.2.3.1 Column Work 16-Apr-24 25-Apr-24 $10,475.00 $866.00 $11,341.00 16-Apr-24 25-Apr-24
P-001.2.3.2 Slab and Beam 25-Apr-24 17-May-24 $33,902.50 $2,905.60 $36,808.10 25-Apr-24 17-May-24
P-001.2.4 RF 17-May-24 18-Jun-24 $44,377.50 $3,771.60 $48,149.10 17-May-24 18-Jun-24
P-001.2.4.1 Column Work 17-May-24 28-May-24 $10,475.00 $866.00 $11,341.00 17-May-24 28-May-24
P-001.2.4.2 Slab and Beam 28-May-24 18-Jun-24 $33,902.50 $2,905.60 $36,808.10 28-May-24 18-Jun-24
MATERIAL LIST
No. Floor Scope Activity Unit QTY Rate (M) Amount (USD) Remark
LABOR LIST
Work Productivity Group Labor QTY Wage Wage Duration Total Amount Rate Labor
Scope Activity Manpower Remark
Unit Skill Non-Skill Total Unit $/day $/hour Days USD USD
Formwork
Worker-11 $ 15.00 $ 1.88
Activity ID Activity Name Original Start Finish PredecessorsBL1 Material Cost BL1 Labor Cost BL1 Total Cost
Duration
P-001 BASEMENT CONSTRUCTION PLANNING 304 03- Apr-23 18- Jun-24 $369,630.00 $263,648.00 $633,278.00
P-001.1 SUB-STRUCTURAL WORK 216 03- Apr-23 10- Feb-24 $192,120.00 $248,561.60 $440,681.60
P-001.1.1 PILING AND SHEET PILE WORK 27 03- Apr-23 11- May-23 $9,000.00 $11,640.00 $20,640.00
A1000 Piling Process 20 03- Apr-23 01- May-23 $3,600.00 $7,200.00 $10,800.00
A1010 Sheet pile Process 7 02- May-23* 11- May-23 A1000 $5,400.00 $4,440.00 $9,840.00
P-001.1.2 EXCAVATION AND BRACING WORK 37 11- May-23 04- Jul-23 $33,600.00 $22,440.00 $56,040.00
A1020 1st Layer Excavation 5 11- May-23 18- May-23 A1010 $1,200.00 $4,800.00 $6,000.00
A1030 1st Layer Bracing Installation 10 19- May-23 02- Jun-23 A1020 $6,000.00 $4,440.00 $10,440.00
A1040 2nd Layer Excavation 5 02- Jun-23 09- Jun-23 A1030 $10,800.00 $2,400.00 $13,200.00
A1050 2nd Layer Bracing Installation 10 09- Jun-23 24- Jun-23 A1040 $8,400.00 $6,000.00 $14,400.00
A1060 3rd Layer Excavation 7 24- Jun-23 04- Jul-23 A1050 $7,200.00 $4,800.00 $12,000.00
P-001.1.3 B2 SLAB WORK 88 20- Jun-23 26- Oct-23 $98,760.00 $65,463.20 $164,223.20
A1070 Pile head Cutting 14 20- Jun-23 10- Jul-23 A1060 $9,600.00 $14,400.00 $24,000.00
A1080 Footing Process 10 11- Jul-23 25- Jul-23 A1070 $12,000.00 $2,888.00 $14,888.00
A1090 Backfill for Beam 5 25- Jul-23 01- Aug-23 A1080 $4,800.00 $4,188.00 $8,988.00
A1100 Beam Casting 10 01- Aug-23 16- Aug-23 A1090 $2,880.00 $25,200.00 $28,080.00
A1110 Backfill for B2 Slab 7 16- Aug-23 25- Aug-23 A1100 $54,000.00 $7,317.60 $61,317.60
A1120 Lean concrete/WP 12 26- Aug-23 12- Sep-23 A1110 $6,000.00 $3,600.00 $9,600.00
A1130 B2 Casting with 300mm Wall 15 13- Sep-23 04- Oct-23 A1120 $1,080.00 $2,952.00 $4,032.00
A1140 WP and Backfill for Wall 5 04- Oct-23 11- Oct-23 A1130 $4,800.00 $1,200.00 $6,000.00
A1150 2nd Strut Removal 10 12- Oct-23 26- Oct-23 A1140 $3,600.00 $3,717.60 $7,317.60
P-001.1.4 B1 SLAB WORK 39 26- Oct-23 22- Dec-23 $24,360.00 $44,890.80 $69,250.80
A1160 Column, Wall, RW Casting 10 26- Oct-23 09- Nov-23 A1150 $10,440.00 $5,604.00 $16,044.00
A1170 B1 Casting with 300mm Wall 12 10- Nov-23 27- Nov-23 A1160 $5,880.00 $3,288.00 $9,168.00
A1180 WP and Backfill for Wall 7 28- Nov-23 07- Dec-23 A1170 $5,640.00 $30,000.00 $35,640.00
A1190 1st Strut Removal 10 07- Dec-23 22- Dec-23 A1180 $2,400.00 $5,998.80 $8,398.80
P-001.1.5 GF SLAB WORK 35 22- Dec-23 10- Feb-24 $26,400.00 $104,127.60 $130,527.60
A1200 Column, Wall, RW Casting 10 22- Dec-23 05- Jan-24 A1190 $14,400.00 $1,257.60 $15,657.60
A1210 GF Slab Casting 1 05- Jan-24 06- Jan-24 A1200 $4,800.00 $44,982.00 $49,782.00
A1220 WP and Backfill 7 08- Jan-24 17- Jan-24 A1210 $2,400.00 $47,714.40 $50,114.40
A1230 Sheet Pile Removal 7 17- Jan-24 27- Jan-24 A1220 $2,400.00 $4,174.80 $6,574.80
A1240 Backfill with compaction 10 27- Jan-24 10- Feb-24 A1230 $2,400.00 $5,998.80 $8,398.80
P-001.2 SUPPER-STRUCTURAL WORK 88 12- Feb-24 18- Jun-24 $177,510.00 $15,086.40 $192,596.40
P-001.2.1 1F 22 12- Feb-24 14- Mar-24 $44,377.50 $3,771.60 $48,149.10
P-001.2.1.1 Column Work 7 12- Feb-24 21- Feb-24 $10,475.00 $866.00 $11,341.00
A1400 Rebar Work 5 12- Feb-24 19- Feb-24 A1240 $4,250.00 $570.00 $4,820.00
A1410 Formwork Work 3 15- Feb-24 20- Feb-24 A1400 $1,125.00 $240.00 $1,365.00
A1420 Concrete Work 1 20- Feb-24 21- Feb-24 A1410 $5,100.00 $56.00 $5,156.00
P-001.2.1.2 Slab and Beam 15 21- Feb-24 14- Mar-24 $33,902.50 $2,905.60 $36,808.10
A1370 Formwork Work 6 21- Feb-24 01- Mar-24 A1420 $12,652.50 $1,653.60 $14,306.10
A1380 Rebar Work 10 26- Feb-24 11- Mar-24 A1370 $11,900.00 $1,140.00 $13,040.00
A1390 Concrete Work 2 12- Mar-24 14- Mar-24 A1380 $9,350.00 $112.00 $9,462.00
P-001.2.2 2F 22 14- Mar-24 15- Apr-24 $44,377.50 $3,771.60 $48,149.10
P-001.2.2.1 Column Work 7 14- Mar-24 25- Mar-24 $10,475.00 $866.00 $11,341.00
A1430 Rebar Work 5 14- Mar-24 21- Mar-24 A1390 $4,250.00 $570.00 $4,820.00
A1440 Formwork Work 3 19- Mar-24 22- Mar-24 A1430 $1,125.00 $240.00 $1,365.00
A1450 Concrete Work 1 23- Mar-24 25- Mar-24 A1440 $5,100.00 $56.00 $5,156.00
P-001.2.2.2 Slab and Beam 15 25- Mar-24 15- Apr-24 $33,902.50 $2,905.60 $36,808.10
A1520 Formwork Work 6 25- Mar-24 02- Apr-24 A1450 $12,652.50 $1,653.60 $14,306.10
A1530 Rebar Work 10 29- Mar-24 12- Apr-24 A1520 $11,900.00 $1,140.00 $13,040.00
A1540 Concrete Work 2 12- Apr-24 15- Apr-24 A1530 $9,350.00 $112.00 $9,462.00
P-001.2.3 3F 22 16- Apr-24 17- May-24 $44,377.50 $3,771.60 $48,149.10
P-001.2.3.1 Column Work 7 16- Apr-24 25- Apr-24 $10,475.00 $866.00 $11,341.00
A1460 Rebar Work 5 16- Apr-24 23- Apr-24 A1540 $4,250.00 $570.00 $4,820.00
A1470 Formwork Work 3 19- Apr-24 24- Apr-24 A1460 $1,125.00 $240.00 $1,365.00
A1480 Concrete Work 1 24- Apr-24 25- Apr-24 A1470 $5,100.00 $56.00 $5,156.00
P-001.2.3.2 Slab and Beam 15 25- Apr-24 17- May-24 $33,902.50 $2,905.60 $36,808.10
A1550 Formwork Work 6 25- Apr-24 04- May-24 A1480 $12,652.50 $1,653.60 $14,306.10
A1560 Rebar Work 10 30- Apr-24 14- May-24 A1550 $11,900.00 $1,140.00 $13,040.00
A1570 Concrete Work 2 15- May-24 17- May-24 A1560 $9,350.00 $112.00 $9,462.00
P-001.2.4 RF 22 17- May-24 18- Jun-24 $44,377.50 $3,771.60 $48,149.10
P-001.2.4.1 Column Work 7 17- May-24 28- May-24 $10,475.00 $866.00 $11,341.00
A1490 Rebar Work 5 17- May-24 24- May-24 A1570 $4,250.00 $570.00 $4,820.00
A1500 Formwork Work 3 22- May-24 25- May-24 A1490 $1,125.00 $240.00 $1,365.00
A1510 Concrete Work 1 27- May-24 28- May-24 A1500 $5,100.00 $56.00 $5,156.00
P-001.2.4.2 Slab and Beam 15 28- May-24 18- Jun-24 $33,902.50 $2,905.60 $36,808.10
A1580 Formwork Work 6 28- May-24 05- Jun-24 A1510 $12,652.50 $1,653.60 $14,306.10
A1590 Rebar Work 10 01- Jun-24 15- Jun-24 A1580 $11,900.00 $1,140.00 $13,040.00
A1600 Concrete Work 2 15- Jun-24 18- Jun-24 A1590 $9,350.00 $112.00 $9,462.00
Activity ID Activity Name Original Duration BL1 Start Start BL1 Finish Finish Activity BL1 Material Cost BL1 Labor Cost BL1 Total Cost Actual Total Cost Remaining Total Cost
Status
P-001 BASEMENT CONSTRUCTION PLANNING 304 03-Apr-23 03-Apr-23 A 18-Jun-24 18-Jun-24 $369,630.00 $263,648.00 $633,278.00 $0.00 $633,278.00
P-001.1 SUB-STRUCTURAL WORK 216 03-Apr-23 03-Apr-23 10-Feb-24 10-Feb-24 $192,120.00 $248,561.60 $440,681.60 $0.00 $440,681.60
P-001.1.1 PILING AND SHEET PILE WORK 27 03-Apr-23 03-Apr-23 11-May-23 11-May-23 $9,000.00 $11,640.00 $20,640.00 $0.00 $20,640.00
A1000 Piling Process 20 03-Apr-23 03-Apr-23 01-May-23 01-May-23 Not Started $3,600.00 $7,200.00 $10,800.00 $0.00 $10,800.00
A1010 Sheet pile Process 7 02-May-23 02-May-23* 11-May-23 11-May-23 Not Started $5,400.00 $4,440.00 $9,840.00 $0.00 $9,840.00
P-001.1.2 EXCAVATION AND BRACING WORK 37 11-May-23 11-May-23 04-Jul-23 04-Jul-23 $33,600.00 $22,440.00 $56,040.00 $0.00 $56,040.00
A1020 1st Layer Excavation 5 11-May-23 11-May-23 18-May-23 18-May-23 Not Started $1,200.00 $4,800.00 $6,000.00 $0.00 $6,000.00
A1030 1st Layer Bracing Installation 10 19-May-23 19-May-23 02-Jun-23 02-Jun-23 Not Started $6,000.00 $4,440.00 $10,440.00 $0.00 $10,440.00
A1040 2nd Layer Excavation 5 02-Jun-23 02-Jun-23 09-Jun-23 09-Jun-23 Not Started $10,800.00 $2,400.00 $13,200.00 $0.00 $13,200.00
A1050 2nd Layer Bracing Installation 10 09-Jun-23 09-Jun-23 24-Jun-23 24-Jun-23 Not Started $8,400.00 $6,000.00 $14,400.00 $0.00 $14,400.00
A1060 3rd Layer Excavation 7 24-Jun-23 24-Jun-23 04-Jul-23 04-Jul-23 Not Started $7,200.00 $4,800.00 $12,000.00 $0.00 $12,000.00
P-001.1.3 B2 SLAB WORK 88 20-Jun-23 20-Jun-23 26-Oct-23 26-Oct-23 $98,760.00 $65,463.20 $164,223.20 $0.00 $164,223.20
A1070 Pile head Cutting 14 20-Jun-23 20-Jun-23 10-Jul-23 10-Jul-23 Not Started $9,600.00 $14,400.00 $24,000.00 $0.00 $24,000.00
A1080 Footing Process 10 11-Jul-23 11-Jul-23 25-Jul-23 25-Jul-23 Not Started $12,000.00 $2,888.00 $14,888.00 $0.00 $14,888.00
A1090 Backfill for Beam 5 25-Jul-23 25-Jul-23 01-Aug-23 01-Aug-23 Not Started $4,800.00 $4,188.00 $8,988.00 $0.00 $8,988.00
A1100 Beam Casting 10 01-Aug-23 01-Aug-23 16-Aug-23 16-Aug-23 Not Started $2,880.00 $25,200.00 $28,080.00 $0.00 $28,080.00
A1110 Backfill for B2 Slab 7 16-Aug-23 16-Aug-23 25-Aug-23 25-Aug-23 Not Started $54,000.00 $7,317.60 $61,317.60 $0.00 $61,317.60
A1120 Lean concrete/WP 12 26-Aug-23 26-Aug-23 12-Sep-23 12-Sep-23 Not Started $6,000.00 $3,600.00 $9,600.00 $0.00 $9,600.00
A1130 B2 Casting with 300mm Wall 15 13-Sep-23 13-Sep-23 04-Oct-23 04-Oct-23 Not $1,080.00 $2,952.00 $4,032.00 $0.00 $4,032.00
Started
A1140 WP and Backfill for Wall 5 04-Oct-23 04-Oct-23 11-Oct-23 11-Oct-23 Not Started $4,800.00 $1,200.00 $6,000.00 $0.00 $6,000.00
A1150 2nd Strut Removal 10 12-Oct-23 12-Oct-23 26-Oct-23 26-Oct-23 Not Started $3,600.00 $3,717.60 $7,317.60 $0.00 $7,317.60
P-001.1.4 B1 SLAB WORK 39 26-Oct-23 26-Oct-23 22-Dec-23 22-Dec-23 $24,360.00 $44,890.80 $69,250.80 $0.00 $69,250.80
A1160 Column, Wall, RW Casting 10 26-Oct-23 26-Oct-23 09-Nov-23 09-Nov-23 Not Started $10,440.00 $5,604.00 $16,044.00 $0.00 $16,044.00
A1170 B1 Casting with 300mm Wall 12 10-Nov-23 10-Nov-23 27-Nov-23 27-Nov-23 Not Started $5,880.00 $3,288.00 $9,168.00 $0.00 $9,168.00
A1180 WP and Backfill for Wall 7 28-Nov-23 28-Nov-23 07-Dec-23 07-Dec-23 Not Started $5,640.00 $30,000.00 $35,640.00 $0.00 $35,640.00
A1190 1st Strut Removal 10 07-Dec-23 07-Dec-23 22-Dec-23 22-Dec-23 Not Started $2,400.00 $5,998.80 $8,398.80 $0.00 $8,398.80
P-001.1.5 GF SLAB WORK 35 22-Dec-23 22-Dec-23 10-Feb-24 10-Feb-24 $26,400.00 $104,127.60 $130,527.60 $0.00 $130,527.60
A1200 Column, Wall, RW Casting 10 22-Dec-23 22-Dec-23 05-Jan-24 05-Jan-24 Not Started $14,400.00 $1,257.60 $15,657.60 $0.00 $15,657.60
A1210 GF Slab Casting 1 05-Jan-24 05-Jan-24 06-Jan-24 06-Jan-24 Not Started $4,800.00 $44,982.00 $49,782.00 $0.00 $49,782.00
A1220 WP and Backfill 7 08-Jan-24 08-Jan-24 17-Jan-24 17-Jan-24 Not Started $2,400.00 $47,714.40 $50,114.40 $0.00 $50,114.40
A1230 Sheet Pile Removal 7 17-Jan-24 17-Jan-24 27-Jan-24 27-Jan-24 Not Started $2,400.00 $4,174.80 $6,574.80 $0.00 $6,574.80
A1240 Backfill with compaction 10 27-Jan-24 27-Jan-24 10-Feb-24 10-Feb-24 Not Started $2,400.00 $5,998.80 $8,398.80 $0.00 $8,398.80
P-001.2 SUPPER-STRUCTURAL WORK 88 12-Feb-24 12-Feb-24 A 18-Jun-24 18-Jun-24 $177,510.00 $15,086.40 $192,596.40 $0.00 $192,596.40
P-001.2.1 1F 22 12-Feb-24 12-Feb-24 A 14-Mar-24 14-Mar-24 $44,377.50 $3,771.60 $48,149.10 $0.00 $48,149.10
P-001.2.1.1 Column Work 7 12-Feb-24 12-Feb-24 A 21-Feb-24 21-Feb-24 $10,475.00 $866.00 $11,341.00 $0.00 $11,341.00
A1400 Rebar Work 5 12-Feb-24 12-Feb-24 A 19-Feb-24 19-Feb-24 In Progress $4,250.00 $570.00 $4,820.00 $0.00 $4,820.00
A1410 Formwork Work 3 15-Feb-24 15-Feb-24 20-Feb-24 20-Feb-24 Not Started $1,125.00 $240.00 $1,365.00 $0.00 $1,365.00
A1420 Concrete Work 1 20-Feb-24 20-Feb-24 21-Feb-24 21-Feb-24 Not Started $5,100.00 $56.00 $5,156.00 $0.00 $5,156.00
P-001.2.1.2 Slab and Beam 15 21-Feb-24 21-Feb-24 14-Mar-24 14-Mar-24 $33,902.50 $2,905.60 $36,808.10 $0.00 $36,808.10
A1370 Formwork Work 6 21-Feb-24 21-Feb-24 01-Mar-24 01-Mar-24 Not Started $12,652.50 $1,653.60 $14,306.10 $0.00 $14,306.10
A1380 Rebar Work 10 26-Feb-24 26-Feb-24 11-Mar-24 11-Mar-24 Not Started $11,900.00 $1,140.00 $13,040.00 $0.00 $13,040.00
A1390 Concrete Work 2 12-Mar-24 12-Mar-24 14-Mar-24 14-Mar-24 Not Started $9,350.00 $112.00 $9,462.00 $0.00 $9,462.00
P-001.2.2 2F 22 14-Mar-24 14-Mar-24 15-Apr-24 15-Apr-24 $44,377.50 $3,771.60 $48,149.10 $0.00 $48,149.10
P-001.2.2.1 Column Work 7 14-Mar-24 14-Mar-24 25-Mar-24 25-Mar-24 $10,475.00 $866.00 $11,341.00 $0.00 $11,341.00
A1430 Rebar Work 5 14-Mar-24 14-Mar-24 21-Mar-24 21-Mar-24 Not Started $4,250.00 $570.00 $4,820.00 $0.00 $4,820.00
A1440 Formwork Work 3 19-Mar-24 19-Mar-24 22-Mar-24 22-Mar-24 Not Started $1,125.00 $240.00 $1,365.00 $0.00 $1,365.00
A1450 Concrete Work 1 23-Mar-24 23-Mar-24 25-Mar-24 25-Mar-24 Not Started $5,100.00 $56.00 $5,156.00 $0.00 $5,156.00
P-001.2.2.2 Slab and Beam 15 25-Mar-24 25-Mar-24 15-Apr-24 15-Apr-24 $33,902.50 $2,905.60 $36,808.10 $0.00 $36,808.10
A1520 Formwork Work 6 25-Mar-24 25-Mar-24 02-Apr-24 02-Apr-24 Not Started $12,652.50 $1,653.60 $14,306.10 $0.00 $14,306.10
A1530 Rebar Work 10 29-Mar-24 29-Mar-24 12-Apr-24 12-Apr-24 Not Started $11,900.00 $1,140.00 $13,040.00 $0.00 $13,040.00
A1540 Concrete Work 2 12-Apr-24 12-Apr-24 15-Apr-24 15-Apr-24 Not Started $9,350.00 $112.00 $9,462.00 $0.00 $9,462.00
P-001.2.3 3F 22 16-Apr-24 16-Apr-24 17-May-24 17-May-24 $44,377.50 $3,771.60 $48,149.10 $0.00 $48,149.10
P-001.2.3.1 Column Work 7 16-Apr-24 16-Apr-24 25-Apr-24 25-Apr-24 $10,475.00 $866.00 $11,341.00 $0.00 $11,341.00
A1460 Rebar Work 5 16-Apr-24 16-Apr-24 23-Apr-24 23-Apr-24 Not Started $4,250.00 $570.00 $4,820.00 $0.00 $4,820.00
A1470 Formwork Work 3 19-Apr-24 19-Apr-24 24-Apr-24 24-Apr-24 Not Started $1,125.00 $240.00 $1,365.00 $0.00 $1,365.00
A1480 Concrete Work 1 24-Apr-24 24-Apr-24 25-Apr-24 25-Apr-24 Not Started $5,100.00 $56.00 $5,156.00 $0.00 $5,156.00
P-001.2.3.2 Slab and Beam 15 25-Apr-24 25-Apr-24 17-May-24 17-May-24 $33,902.50 $2,905.60 $36,808.10 $0.00 $36,808.10
A1550 Formwork Work 6 25-Apr-24 25-Apr-24 04-May-24 04-May-24 Not Started $12,652.50 $1,653.60 $14,306.10 $0.00 $14,306.10
A1560 Rebar Work 10 30-Apr-24 30-Apr-24 14-May-24 14-May-24 Not Started $11,900.00 $1,140.00 $13,040.00 $0.00 $13,040.00
A1570 Concrete Work 2 15-May-24 15-May-24 17-May-24 17-May-24 Not Started $9,350.00 $112.00 $9,462.00 $0.00 $9,462.00
P-001.2.4 RF 22 17-May-24 17-May-24 18-Jun-24 18-Jun-24 $44,377.50 $3,771.60 $48,149.10 $0.00 $48,149.10
P-001.2.4.1 Column Work 7 17-May-24 17-May-24 28-May-24 28-May-24 $10,475.00 $866.00 $11,341.00 $0.00 $11,341.00
A1490 Rebar Work 5 17-May-24 17-May-24 24-May-24 24-May-24 Not Started $4,250.00 $570.00 $4,820.00 $0.00 $4,820.00
A1500 Formwork Work 3 22-May-24 22-May-24 25-May-24 25-May-24 Not Started $1,125.00 $240.00 $1,365.00 $0.00 $1,365.00
A1510 Concrete Work 1 27-May-24 27-May-24 28-May-24 28-May-24 Not Started $5,100.00 $56.00 $5,156.00 $0.00 $5,156.00
P-001.2.4.2 Slab and Beam 15 28-May-24 28-May-24 18-Jun-24 18-Jun-24 $33,902.50 $2,905.60 $36,808.10 $0.00 $36,808.10
A1580 Formwork Work 6 28-May-24 28-May-24 05-Jun-24 05-Jun-24 Not Started $12,652.50 $1,653.60 $14,306.10 $0.00 $14,306.10
A1590 Rebar Work 10 01-Jun-24 01-Jun-24 15-Jun-24 15-Jun-24 Not Started $11,900.00 $1,140.00 $13,040.00 $0.00 $13,040.00
A1600 Concrete Work 2 15-Jun-24 15-Jun-24 18-Jun-24 18-Jun-24 Not Started $9,350.00 $112.00 $9,462.00 $0.00 $9,462.00
Activity ID Activity Name BL1 Material Cost BL1 Labor Cost BL1 Total Cost Planned Total Cost Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
P-001 BASEMENT CONSTRUCTION PLANNING $369,630.00 $263,648.00 $633,278.00 $10,368.00 $25,459.20 $49,767.09 $37,883.15 $93,676.16 $9,840.64 $19,684.80 $31,655.59 $41,527.08 $114,772.75 $34,868.57 $43,723.08 $43,723.08 $46,673.76 $29,655.05
P-001.1 SUB-STRUCTURAL WORK $192,120.00 $248,561.60 $440,681.60 $10,368.00 $25,459.20 $49,767.09 $37,883.15 $93,676.16 $9,840.64 $19,684.80 $31,655.59 $41,527.08 $114,772.75 $6,047.14
P-001.1.1 PILING AND SHEET PILE WORK $9,000.00 $11,640.00 $20,640.00 $10,368.00 $10,272.00
A1000 Piling Process $3,600.00 $7,200.00 $10,800.00 $10,368.00 $432.00
A1010 Sheet pile Process $5,400.00 $4,440.00 $9,840.00 $9,840.00
P-001.1.2 EXCAVATION AND BRACING WORK $33,600.00 $22,440.00 $56,040.00 $15,187.20 $36,738.51 $4,114.29
A1020 1st Layer Excavation $1,200.00 $4,800.00 $6,000.00 $6,000.00
A1030 1st Layer Bracing Installation $6,000.00 $4,440.00 $10,440.00 $9,187.20 $1,252.80
A1040 2nd Layer Excavation $10,800.00 $2,400.00 $13,200.00 $13,200.00
A1050 2nd Layer Bracing Installation $8,400.00 $6,000.00 $14,400.00 $14,400.00
A1060 3rd Layer Excavation $7,200.00 $4,800.00 $12,000.00 $7,885.71 $4,114.29
P-001.1.3 B2 SLAB WORK $98,760.00 $65,463.20 $164,223.20 $13,028.57 $33,768.87 $93,676.16 $9,840.64 $13,908.96
A1070 Pile head Cutting $9,600.00 $14,400.00 $24,000.00 $13,028.57 $10,971.43
A1080 Footing Process $12,000.00 $2,888.00 $14,888.00 $14,888.00
A1090 Backfill for Beam $4,800.00 $4,188.00 $8,988.00 $7,909.44 $1,078.56
A1100 Beam Casting $2,880.00 $25,200.00 $28,080.00 $28,080.00
A1110 Backfill for B2 Slab $54,000.00 $7,317.60 $61,317.60 $61,317.60
A1120 Lean concrete/WP $6,000.00 $3,600.00 $9,600.00 $3,200.00 $6,400.00
A1130 B2 Casting with 300mm Wall $1,080.00 $2,952.00 $4,032.00 $3,440.64 $591.36
A1140 WP and Backfill for Wall $4,800.00 $1,200.00 $6,000.00 $6,000.00
A1150 2nd Strut Removal $3,600.00 $3,717.60 $7,317.60 $7,317.60
P-001.1.4 B1 SLAB WORK $24,360.00 $44,890.80 $69,250.80 $5,775.84 $31,655.59 $31,819.37
A1160 Column, Wall, RW Casting $10,440.00 $5,604.00 $16,044.00 $5,775.84 $10,268.16
A1170 B1 Casting with 300mm Wall $5,880.00 $3,288.00 $9,168.00 $9,168.00
A1180 WP and Backfill for Wall $5,640.00 $30,000.00 $35,640.00 $12,219.43 $23,420.57
A1190 1st Strut Removal $2,400.00 $5,998.80 $8,398.80 $8,398.80
P-001.1.5 GF SLAB WORK $26,400.00 $104,127.60 $130,527.60 $9,707.71 $114,772.75 $6,047.14
A1200 Column, Wall, RW Casting $14,400.00 $1,257.60 $15,657.60 $9,707.71 $5,949.89
A1210 GF Slab Casting $4,800.00 $44,982.00 $49,782.00 $49,782.00
A1220 WP and Backfill $2,400.00 $47,714.40 $50,114.40 $50,114.40
A1230 Sheet Pile Removal $2,400.00 $4,174.80 $6,574.80 $6,574.80
A1240 Backfill with compaction $2,400.00 $5,998.80 $8,398.80 $2,351.66 $6,047.14
P-001.2 SUPPER-STRUCTURAL WORK $177,510.00 $15,086.40 $192,596.40 $28,821.43 $43,723.08 $43,723.08 $46,673.76 $29,655.05
P-001.2.1 1F $44,377.50 $3,771.60 $48,149.10 $28,821.43 $19,327.67
P-001.2.1.1 Column Work $10,475.00 $866.00 $11,341.00 $11,341.00
A1400 Rebar Work $4,250.00 $570.00 $4,820.00 $4,820.00
A1410 Formwork Work $1,125.00 $240.00 $1,365.00 $1,365.00
A1420 Concrete Work $5,100.00 $56.00 $5,156.00 $5,156.00
P-001.2.1.2 Slab and Beam $33,902.50 $2,905.60 $36,808.10 $17,480.43 $19,327.67
A1370 Formwork Work $12,652.50 $1,653.60 $14,306.10 $13,829.23 $476.87
A1380 Rebar Work $11,900.00 $1,140.00 $13,040.00 $3,651.20 $9,388.80
A1390 Concrete Work $9,350.00 $112.00 $9,462.00 $9,462.00
P-001.2.2 2F $44,377.50 $3,771.60 $48,149.10 $24,395.41 $23,753.69
P-001.2.2.1 Column Work $10,475.00 $866.00 $11,341.00 $11,341.00
A1430 Rebar Work $4,250.00 $570.00 $4,820.00 $4,820.00
A1440 Formwork Work $1,125.00 $240.00 $1,365.00 $1,365.00
A1450 Concrete Work $5,100.00 $56.00 $5,156.00 $5,156.00
P-001.2.2.2 Slab and Beam $33,902.50 $2,905.60 $36,808.10 $13,054.41 $23,753.69
A1520 Formwork Work $12,652.50 $1,653.60 $14,306.10 $10,968.01 $3,338.09
A1530 Rebar Work $11,900.00 $1,140.00 $13,040.00 $2,086.40 $10,953.60
A1540 Concrete Work $9,350.00 $112.00 $9,462.00 $9,462.00
P-001.2.3 3F $44,377.50 $3,771.60 $48,149.10 $19,969.39 $28,179.71
P-001.2.3.1 Column Work $10,475.00 $866.00 $11,341.00 $11,341.00
A1460 Rebar Work $4,250.00 $570.00 $4,820.00 $4,820.00
A1470 Formwork Work $1,125.00 $240.00 $1,365.00 $1,365.00
A1480 Concrete Work $5,100.00 $56.00 $5,156.00 $5,156.00
P-001.2.3.2 Slab and Beam $33,902.50 $2,905.60 $36,808.10 $8,628.39 $28,179.71
A1550 Formwork Work $12,652.50 $1,653.60 $14,306.10 $8,106.79 $6,199.31
A1560 Rebar Work $11,900.00 $1,140.00 $13,040.00 $521.60 $12,518.40
A1570 Concrete Work $9,350.00 $112.00 $9,462.00 $9,462.00
P-001.2.4 RF $44,377.50 $3,771.60 $48,149.10 $18,494.05 $29,655.05
P-001.2.4.1 Column Work $10,475.00 $866.00 $11,341.00 $11,341.00
A1490 Rebar Work $4,250.00 $570.00 $4,820.00 $4,820.00
A1500 Formwork Work $1,125.00 $240.00 $1,365.00 $1,365.00
A1510 Concrete Work $5,100.00 $56.00 $5,156.00 $5,156.00
P-001.2.4.2 Slab and Beam $33,902.50 $2,905.60 $36,808.10 $7,153.05 $29,655.05
A1580 Formwork Work $12,652.50 $1,653.60 $14,306.10 $7,153.05 $7,153.05
A1590 Rebar Work $11,900.00 $1,140.00 $13,040.00 $13,040.00
A1600 Concrete Work $9,350.00 $112.00 $9,462.00 $9,462.00
$150,000.00 $1,000,000.00
$120,000.00 $800,000.00
$90,000.00 $600,000.00
$60,000.00 $400,000.00
$30,000.00 $200,000.00
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024
$8.33 $1,000,000.00
$6.67 $800,000.00
$5.00 $600,000.00
$3.33 $400,000.00
$1.67 $200,000.00
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024