Professional Documents
Culture Documents
10 WB140-2 Shop Manual
10 WB140-2 Shop Manual
Shop
Manual
WB140-2N
WB150-2N
BACKHOE LOADER
WB140-2N A20001
SERIAL NUMBERS and UP
WB150-2N A60001
This material is proprietary to Komatsu Utility Division and is not to be reproduced, used, or disclosed except in accordance
with written authorization from Komatsu Utility Division.
It is our policy to improve our products whenever it is possible and practical to do so. We reserve the right to make changes or
add improvements at any time without incurring any obligation to install such changes on products sold previously.
Due to this continuous program of research and development, periodic revisions may be made to this publication. It is recom-
mended that customers contact their distributor for information on the latest revision.
90 OTHER . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 90-1
Special publications, such as service tool, air conditioning and turbocharger service manuals are also
available as well as selected Operation and Service manuals in foreign languages.
The Publications listed below are available for this particular machine(s).
SHOP MANUAL
Chassis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . CEBM009802
Engine . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . WEBM4D9801
SAFETY MANUAL
Parts and Service Publications can only be acquired by authorized KOMATSU distributors using the
Komatsu America International Company Parts Inventory Processing System (PIPS) or the Extranet Lit-
erature Ordering System.
If the PIPS system is not available at the distributor location, then the following Requisition for Technical
Service Publications and Service Forms can be used. Form KDC91E is shown on the reverse side of this
page.
COMPANY NAME
SHIP TO PURCHASE ORDER NO.
ATTN.
COUNTRY
IMPORTANT - TO ASSURE SHIPMENT OF THE CORRECT PUBLICATION(S), THE MODEL NUMBER AND
MACHINE SERIAL NUMBER MUST BE SHOWN.
QTY. PUBLICATION FORM NO. PARTS BOOK PUBLICATION MODEL NUMBER SERIAL NUMBER
P-Paper DESCRIPTION
➥
M-Microfiche
The affected pages are indicated by using the following Mark Indication Action
marks. It is requested that necessary actions be taken to
these pages according to the table below. ❍ New page to be added Add
Mark Page Rev Mark Page Rev Mark Page Rev Mark Page Rev
Mark Page Rev Mark Page Rev Mark Page Rev Mark Page Rev
Mark Page Rev Mark Page Rev Mark Page Rev Mark Page Rev
Mark Page Rev Mark Page Rev Mark Page Rev Mark Page Rev
❍ 30-165 c
❍ 30-166 c
❍ 30-167 c
❍ 30-168 c
❍ 30-169 c
❍ 30-170 c
❍ 30-171 c
❍ 30-172 c
❍ 30-173 c
❍ 30-174 c
❍ 30-175 c
❍ 30-176 c
❍ 30-177 c
❍ 30-178 c
90-1
90-2
90-3
90-4
90-5
90-6
90-7
90-8
90-9
90-10
Special publications, such as service tool, air conditioning and turbocharger service manuals are also
available as well as selected Operation and Service manuals in foreign languages.
The Publications listed below are available for this particular machine(s).
SHOP MANUAL
Chassis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . CEBM009800
Engine . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . WEBM4D9801
SAFETY MANUAL
Parts and Service Publications can only be acquired by authorized KOMATSU distributors using the
Komatsu America International Company Parts Inventory Processing System (PIPS) or the Extranet Lit-
erature Ordering System.
If the PIPS system is not available at the distributor location, then the following Requisition for Technical
Service Publications and Service Forms can be used. Form KDC91E is shown on the reverse side of this
page.
COMPANY NAME
SHIP TO PURCHASE ORDER NO.
ATTN.
COUNTRY
IMPORTANT - TO ASSURE SHIPMENT OF THE CORRECT PUBLICATION(S), THE MODEL NUMBER AND
MACHINE SERIAL NUMBER MUST BE SHOWN.
QTY. PUBLICATION FORM NO. PARTS BOOK PUBLICATION MODEL NUMBER SERIAL NUMBER
P-Paper DESCRIPTION
➥
M-Microfiche
SAFETY NOTICE 00
Proper service and repair is extremely important for the safe operation of your machine. The service and repair techniques
recommended and described in this manual are both effective and safe methods of operation. Some of these operations
require the use of tools specially designed for the purpose.
To prevent injury to workers, the symbols and are used to mark safety precautions in this manual. The cautions accom-
panying these symbols should always be followed carefully. If any dangerous situation arises or may possibly arise, first con-
sider safety, and take the necessary actions to deal with the situation.
Mistakes in operation are extremely dangerous. Read the 1. Before adding oil or making repairs, park the machine
OPERATION & MAINTENANCE MANUAL carefully on hard, level ground, and block the wheels or tracks to
BEFORE operating the machine. prevent the machine from moving.
1. Before carrying out any greasing or repairs, read all the 2. Before starting work, lower blade, ripper, bucket or any
precautions given on the decals which are fixed to the other work equipment to the ground. If this is not possi-
machine. ble, insert the safety pin or use blocks to prevent the
work equipment from falling. In addition, be sure to
2. When carrying out any operation, always wear safety lock all the control levers and hang warning signs on
shoes and helmet. Do not wear loose work clothes, or them.
clothes with buttons missing.
● Always wear safety glasses when hitting parts with a 3. When disassembling or assembling, support the
hammer. machine with blocks, jacks or stands before starting
● Always wear safety glasses when grinding parts with a work.
grinder, etc.
4. Remove all mud and oil from the steps or other places
used to get on and off the machine. Always use the
3. If welding repairs are needed, always have a trained,
handrails, ladders or steps when getting on or off the
experienced welder carry out the work. When carrying
machine. Never jump on or off the machine. If it is
out welding work, always wear welding gloves, apron,
impossible to use the handrails, ladders or steps, use a
glasses, cap and other clothes suited for welding work.
stand to provide safe footing.
4. When carrying out any operation with two or more
workers, always agree on the operating procedure PRECAUTIONS DURING WORK 00
before starting. Always inform your fellow workers 1. When removing the oil filler cap, drain plug or hydrau-
before starting any step of the operation. Before starting lic pressure measuring plugs, loosen them slowly to pre-
work, hang UNDER REPAIR signs on the controls in vent the oil from spurting out. Before disconnecting or
the operator's compartment. removing components of the oil, water or air circuits,
first remove the pressure completely from the circuit.
5. Keep all tools in good condition and learn the correct
way to use them. 2. The water and oil in the circuits are hot when the engine
is stopped, so be careful not to get burned. Wait for the
6. Decide a place in the repair workshop to keep tools and oil and water to cool before carrying out any work on
removed parts. Always keep the tools and parts in their the oil or water circuits.
correct places. Always keep the work area clean and
make sure that there is no dirt or oil on the floor. Smoke 3. Before starting work, remove the leads from the battery.
only in the areas provided for smoking. Never smoke ALWAYS remove the lead from the negative (-) termi-
while working. nal first.
5. When removing covers which are under internal pressure or under pressure from a spring, always leave two bolts in posi-
tion on opposite sides. Slowly release the pressure, then slowly loosen the bolts to remove.
6. When removing components, be careful not to break or damage the wiring, Damaged wiring may cause electrical fires.
7. When removing piping, stop the fuel or oil from spilling out. If any fuel or oil drips on to the floor, wipe it up immediately.
Fuel or oil on the floor can cause you to slip, or can even start fires.
8. As a general rule, do not use gasoline to wash parts. In particular, use only the minimum of gasoline when washing elec-
trical parts.
9. Be sure to assemble all parts again in their original places. Replace any damaged part with new parts.
● When installing hoses and wires, be sure that they will not be damaged by contact with other parts when the machine is
being operated.
10. When installing high pressure hoses, make sure that they are not twisted. Damaged tubes are dangerous, so be extremely
careful when installing tubes for high pressure circuits. Also check that connecting parts are correctly installed.
11. When assembling or installing parts, always use the specified tightening torques. When installing protective parts such as
guards, or parts which vibrate violently or rotate at high speed, be particularly careful to check that they are installed cor-
rectly.
12. When aligning two holes, never insert your fingers or hand. Be careful not to get your fingers caught in a hole.
13. When measuring hydraulic pressure, check that the measuring tool is correctly assembled before taking any measure-
ments.
14. Take care when removing or installing the tracks of track-type machines. When removing the track, the track separates
suddenly, so never let anyone stand at either end of the track.
This shop manual has been prepared as an aid to improve the quality of repairs by giving the serviceman an accurate under-
standing of the product and by showing him the correct way to perform repairs and make judgements. Make sure you under-
stand the contents of this manual and use it to full effect at every opportunity.
This shop manual mainly contains the necessary technical information for operations performed in a service workshop. For
ease of understanding, the manual is divided into the following sections. These sections are further divided into each main
group of components.
GENERAL
This section lists the general machine dimensions, performance specifications, component weights, and fuel, coolant and
lubricant specification charts.
This section explains the structure and function of each component. It serves not only to give an understanding of the
structure, but also serves as reference material for troubleshooting.
This section explains checks to be made before and after performing repairs, as well as adjustments to be made at comple-
tion of the checks and repairs. Troubleshooting charts correlating “Problems” to “Causes” are also included in this section.
This section explains the order to be followed when removing, installing, disassembling or assembling each component,
as well as precautions to be taken for these operations.
MAINTENANCE STANDARD
This section gives the judgement standards when inspecting disassembled parts.
NOTICE
The specifications contained in this shop manual are subject to change at any time and without any advance notice. Contact
your distributor for the latest information.
VOLUMES 00
Revised pages are shown at the LIST OF REVISED PAGES
between the title page and SAFETY page.
Shop manuals are issued as a guide to carrying out repairs.
They are divided as follows: SYMBOLS 00
Chassis volume: Issued for every machine model So that the shop manual can be of ample practical use,
Engine volume: Issued for each engine series important places for safety and quality are marked with the
following symbols.
Electrical volume: Each issued as one to cover all models
Attachment volume: Each issued as one to cover all models
Symbol Item Remarks
These various volumes are designed to avoid duplication of Special safety precautions are
information. Therefore to deal with all repairs for any model, Safety necessary when performing the
it is necessary that chassis, engine, electrical and attachment work.
be available.
Special technical precautions or
other precautions for preserving
DISTRIBUTION AND UPDATING 00
★ Caution
standards are necessary when
performing the work.
Any additions, amendments or other changes will be sent to
your distributors. Get the most up-to-date information before Weight of parts or systems. Cau-
you start any work. tion necessary when selecting
Weight
hoisting wire or when working
FILING METHOD 00
posture is important, etc.
Places that require special atten-
1. See the page number on the bottom of the page. File the Tightening
tion for tightening torque during
pages in correct order. torque
assembly.
2. Following examples show how to read the page number:
Example: Places to be coated with adhe-
Coat
sives and lubricants etc.
10 - 3
Places where oil, water or fuel
Oil, water
must be added, and the capacity.
Item number (10. Structure and Function)
Places where oil or water must
Consecutive page number for each item Drain be drained, and quantity to be
drained.
3. Additional pages: Additional pages are indicated by a
hyphen (-) and numbered after the page number. File as
in the example.
Example:
10-4
10-4-1
Added pages
10-4-2
10-5
REVISIONS 00
HOISTING 00
can result. Hooks have maximum strength at the middle
portion.
WARNING! Heavy parts (25 kg or more)
must be lifted with a hoist etc. In
the DISASSEMBLY AND
ASSEMBLY section, every part
weighing 25 kg or more is indi-
cated clearly with the symbol
★ The recommended coating materials prescribed in the shop manuals are listed below.
Category Code Part No. Quantity Container Main applications, features
● Used to prevent rubber gaskets, rubber
LT-1A 790-129-9030 150 g Tube
cushions and cork plugs from coming out
● Used in places requiring an immediately
effective, strong adhesive.
20 g Polyethylene ● Used for plastics (except polyethylene,
LT-1B 790-129-9050
(2 pes.) container polypropylene, tetrafluoroethylene, and
vinyl chloride), rubber, metal and non-
metal.
● Features: Resistance to heat, chemicals
Polyethylene
LT-2 09940-00030 50 g ● Used for anti-loosening and sealant pur-
container
poses for bolts and plugs.
Adhesive:
790-129-9060
1 kg
(Set of adhesive ● Used as adhesive or sealant for metal, glass
LT-3 Hardening Can
and hardening or plastic.
agent:
agent)
500 g
Adhesives
Polyethylene
LT-4 790-129-9040 250 g ● Used as sealant for machined holes.
container
Holtz ● Used as heat-resisting sealant for repairing
790-126-9120 75 g Tube
MH 705 engine.
● Quick hardening type adhesive.
Three
Polyethylene ● Cure time: within 5 sec. to 3 min.
bond 179-129-9140 2g
container ● Used mainly for adhesion of metals, rub-
1735
bers, plastics and woods.
● Quick hardening type adhesive.
Aron- ● Quick cure type (max. strength after 30
Polyethylene
alpha 790-129-9130 50 g minutes).
container
201 ● Used mainly for adhesion of rubbers, plas-
tics and metals.
● Features: Resistance to heat, chemicals
Loctite Polyethylene
79A-129-9110 50 cc ● Used at joint portions subject to high tem-
648-50 container
perature.
● Used as adhesive or sealant for gaskets and
LG-1 790-129-9010 200 g Tube
packing of power train case, etc.
● Features: Resistance to heat
Gasket seal- ● Used as sealant for flange surfaces and bolts
ant at high temperature locations; used to pre-
LG-3 790-129-9070 1 kg Can vent seizure.
● Used as sealant for heat resistant gasket for
at high temperature locations such as engine
pre-combustion chamber, exhaust pipe.
vent squeaking).
disulphide
lubricant
The following charts give the standard tightening torques of bolts and nuts. Exceptions are given in DISASSEMBLY AND
ASSEMBLY.
mm mm Nm kgm
6 10 13.2 ±1.4 1.35 ±0.15
8 13 31.4 ±2.9 3.20 ±0.3
10 17 65.7 ±6.8 6.70 ±0.7
12 19 112 ±9.8 11.5 ±1.0
14 22 177 ±19 18 ±2.0
16 24 279 ±29 28.5 ±3
18 27 383 ±39 39 ±4
20 30 549 ±58 56 ±6
22 32 745 ±78 76 ±8
24 36 927 ±98 94.5 ±10
27 41 1320 ±140 135 ±15
30 46 1720 ±190 175 ±20
33 50 2210 ±240 225 ±25
36 55 2750 ±290 280 ±30
39 60 3280 ±340 335 ±35
mm mm Nm kgm
6 10 7.85 ± 1.95 0.8 ± 0.2
8 13 18.6 ± 4.9 1.9 ± 0.5
10 14 40.2 ± 5.9 4.1 ± 0.6
12 27 82.35 ± 7.85 8.4 ± 0.8
In the wiring diagrams, various colors and symbols are employed to indicate the thickness of wires. This wire code table will
help you understand WIRING DIAGRAMS.
Example: 05WB indicates a cable having a nominal number 05 and white coating with black stripe.
CLASSIFICATION BY THICKNESS 00
Copper wire
Nominal num- Cable O.D. Current rat-
Number of Dia. Of strand Cross section Applicable circuit
ber (mm) ing (A)
strands (mm) (mm)
0.85 11 0.32 0.88 2.4 12 Starting, lighting, signal etc.
2 26 0.32 2.09 3.1 20 Lighting, signal etc.
5 65 0.32 5.23 4.6 37 Charging and signal
15 84 0.45 13.36 7.0 59 Starting (Glow plug)
40 85 0.80 42.73 11.4 135 Starting
60 127 0.80 63.84 13.6 178 Starting
100 217 0.80 109.1 17.6 230 Starting
Circuits
Priority Classi- Charging Ground Starting Lighting Instrument Signal Other
fication
Code W B B R Y G L
Primary
1
Color White Black Black Red Yellow Green Blue
Code WR — BW RW YR GW LW
2 White & Black & Red & Yellow & Green & Blue &
Color —
Red White White Red White White
Code WB — BY RB YB GR LR
3 White & Black & Yel- Yellow & Green &
Color — Red & Black Blue & Red
Black low Black Red
Code WL — BR RY YG GY LY
Auxiliary
4 White & Red & Yel- Yellow & Green & Blue & Yel-
Color — Black & Red
Blue low Green Yellow low
Code WG — — RG YL GB LB
5 White & Red & Yellow & Green & Blue &
Color — —
Green Green Blue Black Black
Code — — — RL YW GL —
6 Yellow & Green &
Color — — — Red & Blue —
White Blue
The Conversion Table in this section is provided to enable simple conversion of figures. For details of the method of using the
Conversion Table, see the example given below.
EXAMPLE
● Method of using the Conversion Table to convert from millimeters to inches.
1. Convert 55 mm into inches.
A. Locate the number 50 in the vertical column at the left side, take this as 1, then draw a horizontal line from 1.
B. Locate the number 5 in the row across the top, take this as 2, then draw a perpendicular line down from 2.
C. Take the point where the two lines cross as 3. This point 3 gives the value when converting from millimeters to
inches. Therefore, 55 millimeters = 2.165 inches.
C. The original value (550 mm) was divided by 10, so multiply 2.165 inches by 10 (move the decimal one place to the
right) to return to the original value. This gives 550 mm = 21.65 inches.
2
Millimeters to inches 1 mm = 0.03937 in
0 1 2 3 4 5 6 7 8 9
0 0 0.039 0.079 0.118 0.157 0.197 0.236 0.276 0.315 0.354
10 0.394 0.433 0.472 0.512 0.551 0.591 0.630 0.669 0.709 0.748
20 0.787 0.827 0.866 0.906 0.945 0.984 1.024 1.063 1.102 1.142
30 1.181 1.220 1.260 1.299 1.339 1.378 1.417 1.457 1.496 1.536
40 1.575 1.614 1.654 1.693 1.732 1.772 1.811 1.850 1.890 1.929
3
50 1.969 2.008 2.047 2.087 2.126 2.165 2.205 2.244 2.283 2.323
1
60 2.362 2.402 2.441 2.480 2.520 2.559 2.598 2.638 2.677 2.717
70 2.756 2.795 2.835 2.874 2.913 2.953 2.992 3.032 3.071 3.110
80 3.150 3.189 3.228 3.268 3.307 3.346 3.386 3.425 3.465 3.504
90 3.543 3.583 3.622 3.661 3.701 3.740 3.780 3.819 3.858 3.898
50 1.969 2.008 2.047 2.087 2.126 2.165 2.205 2.244 2.283 2.323
60 2.362 2.402 2.441 2.480 2.520 2.559 2.598 2.638 2.677 2.717
70 2.756 2.795 2.835 2.874 2.913 2.953 2.992 3.032 3.071 3.110
80 3.150 3.189 3.228 3.268 3.307 3.346 3.386 3.425 3.465 3.504
90 3.543 3.583 3.622 3.661 3.701 3.740 3.780 3.819 3.858 3.898
50 110.23 112.44 114.64 116.85 119.05 121.25 123.46 125.66 127.87 130.07
60 132.28 134.48 136.69 138.89 141.10 143.30 145.51 147.71 149.91 152.12
70 154.32 156.53 158.73 160.94 163.14 165.35 167.55 169.76 171.96 174.17
80 176.37 178.57 180.78 182.98 185.19 187.39 189.60 191.80 194.01 196.21
90 198.42 200.62 202.83 205.03 207.24 209.44 211.64 213.85 216.05 218.26
50 13.209 13.473 13.737 14.001 14.265 14.529 14.795 15.058 15.322 15.586
60 15.850 16.115 16.379 16.643 16.907 17.171 17.435 17.700 17.964 18.228
70 18.492 18.756 19.020 19.285 19.549 19.813 20.077 20.341 20.605 20.870
80 21.134 21.398 21.662 21.926 22.190 22.455 22.719 22.983 23.247 23.511
90 23.775 24.040 24.304 24.568 24.832 25.096 25.361 25.625 25.889 26.153
50 10.998 11.281 11.438 11.658 11.878 12.098 12.318 12.528 12.758 12.978
60 13.198 13.418 13.638 13.858 14.078 14.298 14.518 14.738 14.958 15.178
70 15.398 15.618 15.838 16.058 16.278 16.498 16.718 16.938 17.158 17.378
80 17.598 17.818 18.037 18.257 18.477 18.697 18.917 19.137 19.357 19.577
90 19.797 20.017 20.237 20.457 20.677 20.897 21.117 21.337 21.557 21.777
50 361.7 368.9 376.1 383.4 390.6 397.8 405.1 412.3 419.5 426.8
60 434.0 441.2 448.5 455.7 462.9 470.2 477.4 484.6 491.8 499.1
70 506.3 513.5 520.8 528.0 535.2 542.5 549.7 556.9 564.2 571.4
80 578.6 585.9 593.1 600.3 607.6 614.8 622.0 629.3 636.5 643.7
90 651.0 658.2 665.4 672.7 679.9 687.1 694.4 701.6 708.8 716.1
100 723.3 730.5 737.8 745.0 752.2 759.5 766.7 773.9 781.2 788.4
110 795.6 802.9 810.1 817.3 824.6 831.8 839.0 846.3 853.5 860.7
120 868.0 875.2 882.4 889.7 896.9 904.1 911.4 918.6 925.8 933.1
130 940.3 947.5 954.8 962.0 969.2 976.5 983.7 990.9 998.2 1005.4
140 1012.6 1019.9 1027.1 1034.3 1041.5 1048.8 1056.0 1063.2 1070.5 1077.7
150 1084.9 1092.2 1099.4 1106.6 1113.9 1121.1 1128.3 1135.6 1142.8 1150.0
160 1157.3 1164.5 1171.7 1179.0 1186.2 1193.4 1200.7 1207.9 1215.1 1222.4
170 1129.6 1236.8 1244.1 1251.3 1258.5 1265.8 1273.0 1280.1 1287.5 1294.7
180 1301.9 1309.2 1316.4 1323.6 1330.9 1338.1 1345.3 1352.63 1359.8 1367.0
190 1374.3 1381.5 1388.7 1396.0 1403.2 1410.4 1417.7 1424.9 1432.1 1439.4
50 711.2 725.4 739.6 753.8 768.1 782.3 796.5 810.7 825.0 839.2
60 853.4 867.6 881.8 896.1 910.3 924.5 938.7 953.0 967.2 981.4
70 995.6 1010 1024 1038 1053 1067 1081 1095 1109 1124
80 1138 1152 1166 1181 1195 1209 1223 1237 1252 1266
90 1280 1294 1309 1323 1337 1351 1365 1380 1394 1408
100 1422 1437 1451 1465 1479 1493 1508 1522 1536 1550
110 1565 1579 1593 1607 1621 1636 1650 1664 1678 1693
120 1707 1721 1735 1749 1764 1778 1792 1806 1821 1835
130 1849 1863 1877 1892 1906 1920 19324 1949 1963 1977
140 1991 2005 2034 2048 2062 2077 2091 2105 2119
150 2134 2148 2162 2176 2190 2205 2219 2233 2247 2262
160 2276 2290 2304 2318 2333 2347 2361 2375 2389 2404
170 2418 2432 2446 2460 2475 2489 2503 2518 2532 2546
180 2560 2574 2589 2603 2617 2631 2646 2660 2674 2688
190 2702 2717 2731 2745 2759 2773 2788 2802 2816 2830
200 2845 2859 2873 2887 2901 2916 2930 2944 2958 2973
210 2987 3001 3015 3030 3044 3058 3072 3086 3101 3115
220 3129 3143 3158 3172 3186 3200 3214 3229 3243 3257
230 3271 3286 3300 3314 3328 3343 3357 3371 3385 3399
240 3414 3428 3442 3456 3470 3485 3499 3513 3527 3542
12
POWER TRAIN . . . . . . . . . . . . . . . . . . . . 10-3 3 SPOOL . . . . . . . . . . . . . . . . . . . . . . . 10-59
DESCRIPTION . . . . . . . . . . . . . . . . . . 10-3 BACKHOE CONTROL VALVE . . . . . . . 10-63
TRANSMISSION . . . . . . . . . . . . . . . . . . . 10-5 6 SPOOL . . . . . . . . . . . . . . . . . . . . . . . 10-63
DIAGRAM OF THE POWER TRAIN 10-5 7 SPOOL . . . . . . . . . . . . . . . . . . . . . . . 10-68
HYDRAULIC CONVERTOR- FOR TELESCOPIC ARM . . . . . . 10-68
TRANSMISSION CIRCUIT FOR HAMMER . . . . . . . . . . . . . . 10-68
DIAGRAM . . . . . . . . . . . . . . . . . . . . . 10-6 8 SPOOL . . . . . . . . . . . . . . . . . . . . . . . 10-71
DRIVE SHAFTS . . . . . . . . . . . . . . . . 10-15 FOR HAMMER AND
FORWARD AND REVERSE . . . 10-15 TELESCOPE ARM . . . . . . . . . . . 10-71
DRIVEN GEAR . . . . . . . . . . . . . 10-15 CLSS (CLOSED CENTER LOAD
4WD DRIVEN . . . . . . . . . . . . . . . 10-16 SENSING SYSTEM . . . . . . . . . . . . . . . . . 10-72
CONTROL VALVE BLOCK . . . . . . 10-17 CHARACTERISTICS . . . . . . . . . . . . 10-72
FRONT AXLE . . . . . . . . . . . . . . . . . . . . . 10-18 STRUCTURE . . . . . . . . . . . . . . . . . . . 10-72
DIFFERENTIAL . . . . . . . . . . . . . . . . 10-18 OPERATION . . . . . . . . . . . . . . . . . . . 10-73
FINAL REDUCTION - JOINT . . . . . 10-20 UNLOADING VALVE . . . . . . . . . . . 10-75
STEERING CYLINDER . . . . . . . . . . 10-22 FUNCTION . . . . . . . . . . . . . . . . . 10-75
REAR AXLE . . . . . . . . . . . . . . . . . . . . . . 10-24 OPERATION . . . . . . . . . . . . . . . . 10-75
DIFFERENTIAL . . . . . . . . . . . . . . . . 10-24 INTRODUCTION OF THE LS
FINAL REDUCTION . . . . . . . . . . . . 10-26 PRESSURE . . . . . . . . . . . . . . . . . . . . . 10-78
BRAKES . . . . . . . . . . . . . . . . . . . . . . 10-28 OPERATION . . . . . . . . . . . . . . . . 10-78
HYDRAULIC PUMP . . . . . . . . . . . . . . . 10-31 DELIVERY COMPENSATION . . . . 10-79
FUNCTION . . . . . . . . . . . . . . . . . . . . 10-36 INTRODUCTION . . . . . . . . . . . . 10-79
STRUCTURE . . . . . . . . . . . . . . . . . . 10-36 FUNCTION . . . . . . . . . . . . . . . . . 10-79
OPERATION . . . . . . . . . . . . . . . . . . . 10-37 OPERATION . . . . . . . . . . . . . . . . 10-79
PUMP OPERATION . . . . . . . . . . 10-37 LIFD CONTROL SYSTEM . . . . . . . . 10-82
CONTROL OF DELIVERY . . . . 10-38 FUNCTION . . . . . . . . . . . . . . . . . 10-82
PC VALVE, LS VALVE, SERVO OPERATION . . . . . . . . . . . . . . . . 10-82
PISTON . . . . . . . . . . . . . . . . . . . . . . . 10-39 LS DECOMPRESSION VALVE . . . . 10-83
LS VALVE . . . . . . . . . . . . . . . . . 10-40 DESCRIPTION . . . . . . . . . . . . . . 10-83
PC VALVE . . . . . . . . . . . . . . . . . 10-46 OPERATION . . . . . . . . . . . . . . . . 10-83
WORKING MODE SOLENOID PRESSURE CUT-OFF VALVE . . . . 10-84
VALVE . . . . . . . . . . . . . . . . . . . . . . . 10-51 DESCRIPTION . . . . . . . . . . . . . . 10-84
FUNCTION . . . . . . . . . . . . . . . . . 10-51 OPERATION . . . . . . . . . . . . . . . . 10-84
OPERATION . . . . . . . . . . . . . . . . 10-51 PRIORITY VALVE (ONLY FOR
STEERING UNIT . . . . . . . . . . . . . . . . . . 10-53 THE 2-3 SPOOL CONTROL
TECHNICAL DATA . . . . . . . . . . . . . 10-53 VALVE) . . . . . . . . . . . . . . . . . . . . . . . 10-85
OPERATION . . . . . . . . . . . . . . . . . . . 10-53 FUNCTION . . . . . . . . . . . . . . . . . 10-85
HYDRAULIC CIRCUIT . . . . . . . . . . . . . 10-54 SOLENOID VALVE . . . . . . . . . . . . . . . . 10-86
SHOVEL CONTROL VALVE . . . . . . . . 10-55 SOLENOID VALVE BLOCK ST1 -
2 SPOOL . . . . . . . . . . . . . . . . . . . . . . 10-55 DIFFERENTIAL LOCKING -
DESCRIPTION
● The driving power for the engine (1) is transmitted through the flywheel to the converter (2). The converter (2) uses
hydraulic oil to convert the torque transmitted by the engine (1) into driving power. The converter (2) transmits motion to
the drive shaft of the transmission (3) and to the drive shaft of the hydraulic pump (4).
● The transmission (3) has two hydraulically actuated clutches that can be selected by an electrically controlled gear selec-
tor. It also has a manual gear selection (four forward gears and four reverse gears).
● The driving power is transmitted from the transmission flanges (3) to the front (5) and rear (6) axles through the drive
shafts (7 and 8).
● The driving power transmitted to the front (5) and rear (6) axles is reduced by the differentials and then transmitted to the
planetary gear through the differential shafts.
TRANSMISSION
2. Propeller shaft 8. 3rd gear driven gear 14. Front output shaft
3. Reverse gear command clutch 9. 4th gear driven gear 15. Flange
4. Forward gear command clutch 10. 4WD drive gear 16. 2nd gear driven gear
5. Reverse gear idler shaft 11. 1st gear driven gear 17. Rear output shaft
5. 3rd and 4th selecting fork 11. 1st and 2nd gear selecting fork 17. Spring
a. Port reverse clutch 1. Reverse gear clutch (Z=29) 4. Reverse clutch piston
DRIVEN GEAR
1. Driven gear for 2nd gear (Z=43) 5. Driven gear for 3rd gear (Z=33)
4WD DRIVEN
1. Ball 9. Valve
8. Spring
DIFFERENTIAL
9. Bearing
Unit: mm
No Check Item Criteria Remedy
Standard clear-
Clearance Limit
1 Axle clearance ance
— —
2 Backlash of crown wheel and pinion 0.17 - 0.23 0.23 Adjust
3 Pinion preload (without seal ring) 92 - 137 cNm
Pinion crown wheel preload (without
4 95.9 - 142.9 cNm
seal ring)
Unit: mm
No Check Item Criteria Remedy
1 Hub rotation torque — Adjust
2 Drive shaft axle clearance — Replace
STEERING CYLINDER
Unit: mm
No Check item Criteria Remedy
Standard Tolerance Standard Clearance
Replace
Clearance between size Shaft Hole clearance limit
1 bushing
bushing and pin + 0.04
50 — 50.19 — — and pin
0
DIFFERENTIAL
1. Bearing 9. Bearing
8. Pin
Unit: mm
No Check item Criteria Remedy
Standard clearance Clearance limit
1 Axle clearance
— —
2 Backlash of crown wheel and pinion 0.17 - 0.23 0.23
Adjust
3 Pinion preload (without seal ring) 92 - 138 cNm
Pinion crown wheel preload (without
4 95.23 - 141.84 cNm
seal ring)
Unit: mm
No Check item Criteria Remedy
1 Hub rotation torque — Adjust
2 Drive shaft axle clearance — Replace
Unit: mm
No Check item Criteria Remedy
Standard size Repair limit
Installed Replace if
Free Installed Installed Free
1 Brake disc return spring load on damaged
installed length load installed
screw or
27 13 127 Nm 21 10 Nm deformed
2 Disc return spring 35 19 369 Nm 21 10 Nm
Standard thickness Minimum thickness
3 Disc thickness 0 Replace
5 3.3
– 0.15
1. Sleeve
2. Pin
3. Control rod
4. Spacer
5. Fork
6. Piston
7. Cover
8. Snap ring
3. Delivery control valve c. Port X2 - From the shovel control valve (Port LS)
Unit: mm
No Check item Criteria Remedy
1 Ball bearing loading 0 - 0.05 Adjust
Standard Tolerance Standard Clearance
Backlash between pis-
2 size Shaft Hole clearance limit
ton and cylinder
20 — 0.065
Backlash between pis-
3 0.15
ton and shoe
Standard value Maximum value
4 Drive shaft diameter
34.91
Standard size Repair limit
Free Installed Installed Free Installed
5 Spring
installed length load installed load
— 88.7 276 ± 12 N
PC Valve
8. Spool
9. Spring (internal)
Unit: mm
No Check item Criteria Remedy
Standard size Repair limit
Free Installed Free Installed
1 Spring Installed load
installed length installed load
— — — — —
Power regulation spring
2 125.4 ± 10 N
(external)
Power regulation spring
3 180.2 ± 12.5 N
(internal)
4 PC valve spring (external) 40.2 ± 2.8 N
5 PC valve spring (internal) 81.7 ± 14.5 N
6 LS valve spring (external) 81.7 ± 14.5 N
7 LS valve spring (internal) 40.2 ± 2.8 N
STRUCTURE
● The cylinder block (6) is supported and connected to the shaft (1) by the spline (a) and the shaft (1) is supported by the
front and rear bearings.
● The tip of the piston (6) is ball-shaped. The shoe (4) is caulked to it to form one unit in such a way that the piston (5) and
the shoe (4) together form a spherical bearing
● The swash plate (3) has a flat surface (A) and the shoe (4) remains pressed against this surface while sliding this surface
while sliding in a circular movement. The swash plate brings highly pressurized oil onto the cylindrical surface (B) fash-
ioned in the pump body (2), which means that the swash plate (3) slides on a hydrostatically-supported bearing.
● The pistons (5) performed their relative movements in an axial direction, inside cylindrical chambers fashioned in the cyl-
inder block (6).
● The oil is brought up to pressure in the chambers of the cylinder block (6) by the rotatory movement of the block itself.
The areas of pressure and suction are determined by the swash plate (7). The surface of the swash plate is so designed that
the oil pressure always remains within acceptable limits. The oil chamber is drawn in and discharged through holes in the
valve plate (7).
1. The cylinder block (7) rotates together with the shaft (1)
and the shoe (4) slides on the flat surface A. The swash
plate (3) moves along the cylindrical surface B. The angle
formed be-tween the center line of the shaft (1) and the
center line X of the swash plate (3) changes, thus modify-
ing the axial position of the pistons in relation to the cylin-
der block. The angle is known as the swash plate angle.
2. When the center line X of the swash plate (3) maintains the
angle in relation to the center line of the shaft (1), and
hence also of the cylinder block (6), the flat surface A acts
as a cam for the shoe (4). As the piston (5) rotates and
slides inside the cylinder block (6), it therefore creates a
difference between the volumes C and D which provokes
intake and discharge of the oil in quantities equal to the dif-
ference be-tween the volumes (D – C=delivery). In other
words, as the cylinder block (6) rotates, chamber D loses
volume while the volume of chamber C is increased, thus
provoking an in-take of oil. (The figure indicates the state
of the pump when the intake of chamber D and the delivery
of chamber C have been completed).
3. When the center line X of the swash plate (3) and the center
line of the cylinder block (6) are perfectly aligned (the
swash plate angle =0),the difference between the volumes
C and D within the cylinder block (6) becomes 0 and the
pump does not take in or deliver any oil. (In practice the
swash plate angle never =0)
3. Servo piston
LS Valve
4. Piston
5. Spring
● The LS valve controls the pump delivery according to the stroke of the control valve level, i.e., in function of the delivery
demands made by the actuators.
● The LS valve detects the actuator’s delivery needs by means of the differential pressure PLS existing between the pump
delivery pressure PP and the pressure PLS coming from the control valve. This reading permits control of the main pump
delivery Q. (PP, PLS and PLS are, respectively, the pump pressure, the Load Sensing pressure, and the difference in pres-
sure between these two values).
● In other words, the LS valve detects the pressure difference PLS generated by the passage of the oil flow through the sur-
face freed by the control valve spool, and controls the pump delivery Q so as to keep the pressure drop constant. It can
therefore be assumed that the pump delivery is proportional to the demands made known by the control valve.
● The pressure PLS of the LS coming from the control valve outlet passes into chamber a of the spring of the LS valve. The
pressure PP of the pump passes into chamber b of the opposite side.
● The piston rod movement (4) is determined by the combination of the force generated by the pressure PLS, the force of
the spring (6) and the force generated on the side opposite the piston rod by the pressure PP.
● Before the engine is started the servo-piston (3) is pushed to the right by the spring (1) (corresponding to the maximum
angle of the swash plate).
● If all the control valve spools are in their NEUTRAL position when the engine is started, the pressure PLS of the LS will
remain at 600 ± 200 kPa because no oil is flowing through the control valve. At the same time the pump pressure PP
increases and is maintained at a value of about 2.7 MPa.
● For this reason the piston (4) is thrust to the right and a passage is formed between the delivery lines c and d. This opening
enables the pump pressure PP to enter chamber X of the servo-piston (3). Although the pump pressure PP is always
passed into chamber Y of the servo-piston (2), since the force exerted by that pressure on piston (3) exceeds the force
exerted on piston (2), the servo-piston (1) moves to the right, i.e. towards the side of the minimum angle of the swash plate
2 when a control valve lever is activated
● When the control valve lever is moved out of its NEUTRAL position, the opening f is created, allowing an LS signal to be
generated.
● Until the PLS generates a force less than the force exerted by the spring (6) on the spool (4), the system will remain stable.
When the opening f is such as to provoke a reduction in PLS, the spool (4) moves to the left to form a passage between
delivery lines d and e. The chamber X loses pressure and the servo-piston causes the swash plate to move towards maxi-
mum displacement.
● Equilibrium is re-established in the system when the pressure PLS generates on the spool (4) the difference in force
exerted by the spring (6), and the passage between delivery lines c and d is reopened.
● When the control lever is moved to full stroke, in other words, when the spool opening reaches its maximum, the differ-
ence between the pump pressure PP and the LS pressure PLS becomes smaller (differential pressure PLS).
● The LS pressure PL introduced into the chamber a of the LS valve becomes about the same as the pump pressure PP and
the piston (4) is moved to the left by the combined forces generated by the pressure PLS and the spring (6). The piston
movement closes the delivery line c and forms a passage between lines d and e.
● The pressurized oil present in the chamber X of the servo-cylinder (3) flows through the lines d and e and reaches the
pump drainage chamber, so that the pressure in chamber X of the servo-cylinder (1) becomes equal to the drainage pres-
sure.
● The servo-piston (3) is thus moved to the right by swash plate movement due to the pressure PP in the chamber Y of the
servo cylinder (2). In other words, it is drawn in the direction of the increase in angle of the swash plate.
● When the control valve lever moves in very small increments towards the NEUTRAL position, i.e.when the control valve
opening f diminishes, the differential pressure PLS between the pump pressure PP and the LS pressure PLS increases.
● If the differential pressure PLS generates on the spool (4) a difference in force that exceeds the force exerted by the spring
(6), the spool moves to the right and a passage is formed between the delivery lines c and d. The pressure PP is introduced
into the chamber X and the swash plate moves towards its minimum angle.
● When the control valve lever performs small movements towards the position of maximum opening, i.e. when the opening
f of the control valve increases, the differential pressure PLS diminishes.
● If the differential pressure PLS generates on the spool (4) a force difference that does not exceed the force exerted by the
spring (6), the spool (4) moves to the left and a passage is formed between the delivery lines d and e. The chamber X loses
pressure and the servo piston provokes a movement of the swash plate towards maximum displacement.
● Equilibrium is re-established in the system when the pressure PLS generates on the spool (4) the difference in force
exerted by the spring (6), and hence the passage between delivery lines c and d is also reopened.
● Let A1 be the surface of the servo-piston (3), A2 the surface of the servo-piston (2), PEN the pressure acting on the piston
(1) and PP the pressure acting on the piston side (2).
● When pump delivery reaches the quantity demanded by the control valve, the pump pressure PP in chamber b of the LS
valve is in equilibrium with the combined forces of the LS pressure PLS in chamber a, and the force exerted by the spring
(6). Once equilibrium has been reached the piston (4) stops in the central position.
● In this condition the passage from chamber c to chamber d remains only slightly open in order to maintain pressure in
chamber d. A flow of oil is introduced into the servo-cylinder (3) at a pressure that balances the force generated by the
pump pressure PP in the cylinder (2). (PEN x A1=PP x A2)
● The stability of the equilibrium is guaranteed by a flow stabilized by the throttle g.
● The force of the spring (6) is regulated so that the piston (4) is in equilibrium when PP – PLS = 1.8 MPa.
● In practice, the pump flow is made proportional to the section of the opening of the control valve, which maintains the
differential pressure PLS = 1.8 MPa.
1. When the load on the actuators is heavy (high pump delivery pressure)
● When a higher delivery is required, the LS valve receives a signal from the control valve to bring the pump up to maxi-
mum displacement. When the swash plate moves it also moves the bushing (2) joined to it (by the pin (1)), which releases
the spring (3).
● As the pressure of the actuators increases, pressure also increases in the delivery line c. When the calibrated setting of the
spring (3) is reached, the piston rod (4) is thrust to the left and the passage between chamber b and the pump drainage
chamber a is opened.
● The opening of the passage between the chambers b and a generates a flow of oil and due to the calibrated hole (6), a pres-
sure P is generated between chambers f and g at the sides opposite the spool (5).(P =PP– PPC)
● When the value of PP exceeds the value of the spring loading (7) the spool (5) moves to the right opening the passage
between the delivery lines d and e and sending the pump pressure PP towards the servo-cylinder (8).
● The pressure PP introduced into chamber X of the cylinder (8) pushes it towards the minimum angle of the swashplate.
● When the piston (8) is pushed to the left the bushing (2) is also moved. The oil flow between the chambers b and a is re-
duced and the PPC pressure tends to approach the PP pressure value. The P decreases and the spool (5) is pushed to the
left by the force of the spring (7).
● Equilibriums reached when the force generated by the PP pressure, the force generated by the PPC pressure, and the force
of the spring (7) are all balanced. (The force generated by PP = the force generated by the PPC + the spring force (7))
● In this condition the passage from chamber d to chamber e remains only slightly open in order to maintain pressure in
chamber e. A flow of oil is introduced into the cylinder (8) at a pressure that balances the force generated by the pump
pressure PP acting on the cylinder (9). (PEN x A1 =PP x A2)
● The stability of this equilibrium is generated by a continuous stabilized flow from the throttle (10).
● When the load on the actuators diminishes and the pump delivery pressure PP drops, the PPC pressure also drops.
● The reduction in the PPC causes the spool (4) to move and the passage between chambers b, d and a is closed. The PPC
pressure and the PP pressure of the pump are equalized due to the interruption of the oil flow through the calibrated hole
(6) and P becomes zero (P =PP– PPC=0).
● The spring (7) pushes the spool (5) to the left closing the passage between the chambers d and e and opening the passage
between chambers e and g.
● The pressurized oil present in chamber X of the servo-cylinder (8) passes through chambers e and g and reaches the pump
drainage chamber, so that the pressure in chamber X of the servo-cylinder (7) becomes equal to the drainage pressure.
● Therefore the servo-piston (7) is caused to move by the PP pressure in chamber Y of the servo-cylinder (9), i.e. in the
direction of the increase in the angle of the swash plate.
OPERATION
1. WORKING MODE E
● During normal operation (Working mode E), the PC valve intervenes when a P1 is generated equal to the loading on the
spring (4).
● The P1 is generated by the calibrated hole (3) in the spool of the PC valve (2) when, at a determined pump delivery pres-
sure P1, the valve (1) puts the delivery line a into discharge, thus generating a flow in the delivery line a.
● When the solenoid valve (6) is commutated (Working Mode P) the pressurized oil coming from the pump changes its
route and passes through the throttle (5), which has a larger diameter than the calibrated hole (3).
● Because the throttle (5) has a larger diameter, the P2 generated is less than is needed to overcome the force generated by
the spring (4). The spool of the PC valve (2) is therefore pushed to the left by the force of the spring (4).
● This shift obliges the pump to increase displacement and the delivery. (See PC Valve for details)
● The increase in flow causes an increment of the P2 which, when the loading value of the spring is reached, allows the
spool to shift to the right.
TECHNICAL DATA
Steering unit type: LAGCSDS160P
Displacement: 160 cc/rev.
OPERATION
● The steering unit is composed of a control valve and a rotating oil dispenser, and is of the hydrostatic type.
● When the steering wheel is turned, the control valve sends oil from the pump P2 (by means of the rotating oil dispenser)
to one of the sides of the steering cylinder. The rotating dispenser ensures that the volume of oil supplied to the cylinder is
proportionate to the angle of rotation of the steering wheel.
● In the event of malfunction, the oil dispenser will function automatically as a hand-pump, thus guaranteeing emergency
steering.
2 SPOOL
Unit: mm
No Check item Criteria Remedy
Standard size Repair limit
Free Installed Installed
1 Check valve spring Installed load Free installed
installed length load
7. Compensator
Unit: mm
No. Check item Criteria Remedy
Standard size Repair limit
Free Installed Installed
1 Spool return spring Installed load Free installed
installed length load
3 SPOOL
a. Port D - To the hydraulic steering unit (Port P) l. Port B3 - To the auxiliary equipment (Right side)
b. Port A3 - To the auxiliary equipment (Left side) m. Port DLS - To the hydraulic steering unit (Port LS)
h. Port B1 - To the shovel raise cylinder (Head side) 6. Priority valve spring
Unit: mm
No Check Item Criteria Remedy
Standard size Repair limit
Free Installed Installed
1 Spool return spring Installed load Free installed
installed length load
Unit: mm
No. Check item Criteria Remedy
Standard size Repair limit
Free Installed Installed
1 Spool return spring Installed load Free installed
installed length load
6 SPOOL
a. Port P - From the pump (Port B) l. Port A5 - To the bucket cylinder (Head side)
b. Port T - To the hydraulic tank m. Port A4 - To the L.H. outrigger cylinder (Head side)
c. Port B1 - To the arm cylinder (Base side) n. Port A3 - To the R.H. outrigger cylinder (Head side)
d. Port B2 - To the arm L.H. swing cylinder (Base side) o. Port A2 - To the R.H Boom swing cylinder (Base side)
e. Port B3 - To the R.H. outrigger cylinder (Base side) p. Port A1 - To the arm cylinder (Head side)
f. Port B4 - To the L.H. outrigger cylinder (Base side) q. Port T1 - To the hydraulic tank
g. Port B5 - To the bucket cylinder (Base side) r. Port LS - To the pump (Port X2)
Unit: mm
No. Check item Criteria Remedy
Standard size Repair limit
Free Installed Installed
1 Spool return spring Installed load Free installed
installed length load
1. Ball 8. Plug
7. Anticavitation valve
Unit: mm
No. Check item Criteria Remedy
Standard size Repair limit
Free Installed Installed
1 Spool return spring Installed load Free installed
installed length load
Unit: mm
No. Check item Criteria Remedy
Standard size Repair limit
Free Installed Installed
1 Unloading valve spring Installed load Free installed
installed length load
FOR HAMMER
4. Plug
Unit: mm
No. Check item Criteria Remedy
Standard size Repair limit
Free Installed Installed
1 Spool return spring Installed load Free installed
installed length load
Unit: mm
No. Check item Criteria Remedy
Standard size Repair limit
Free Installed Installed
1 Spool return spring Installed load Free installed
installed length load
CHARACTERISTICS
The term CLSS means Closed center load Sensing System, which has the following characteristics:
A. high precision control that is independent of the load applied to the movement;
C. Ability to perform complex operations, guaranteed by control of oil flow in function of aperture surfaces of the shut-
tles;
STRUCTURE
● The CLSS system includes the variable flow pump, the control valve and the working equipment.
● The pump includes the main pump, the PC valve and the LS valve.
1. When the control valve is in the NEUTRAL position, the flow Q of the pump (due to the swash plate being in the mini-
mum angle position) is sent to the control valve. In these conditions, the pump delivery pressure PP is regulated to 2.7
MPa by the spring (2) inside the valve. (PP=PLS + spring load with PLS=600 kPa)
OPERATION
When the control is in NEUTRAL position
● On the two surfaces of the shuttle (1), the pump pressure PP acts on the right-hand side, while the LS signal with pressure
PLS acts on the left-hand side.
● Because a LS signal is generated with a pressure PS 600 ± 200 kPa, when the control valves in NEUTRAL position, the
pump delivery pressure PP is regulated by the combination of the pressure provided by the spring and the LS pressure
PLS.
● While the pump delivery pressure PP increases until it compensates for the loading on the spring (2) and for the LS pres-
sure 2.7 MPa, the shuttle (1) moves to the left and the PP circuit is put into communication with the tank circuit T.
● This system ensures that the pump delivery pressure PP stays regulated at 2.7 MPa.
● When final control are performed with the control valve, a pressure PLS is generated that pressurizing the spring cham-
ber, acts on the left-hand extremity of the valve (1). The actuator pressure is introduced into the LS circuit and then into
the spring chamber. As a result, the pump pressure PP tends to increase.
● When the differential pressure between the pump delivery pressure PP and the LS pressure PLS has the same value as the
loading on the spring (2) (2.1 MPa), the shuttle (1) moves to the left and the pump circuit PP puts itself into communica-
tion with the tank circuit T. Consequently the exceeding pump delivery Q, relative to the actuator request, is sent to the
tank circuit.
● The pump delivery pressure PP is regulated by the combination of the pressure provided by the spring (2.1 MPa) and by
the LS pressure PLS, i.e. when the pressure differential PLS reaches the value of 2.1 MPa.
● When the control valve shuttle is operated to execute a larger stroke, the opening section of the spool becomes larger and
the controlled delivery is larger. Because the control valve passage is large, the difference between the LS pressure PLS
and the pump delivery pressure PP is reduced up to 2.1 MPa (the LS pump valve setting).
● Because the differential pressure between the pump delivery pressure PP and the LS pressure PLS is not equal to the pres-
sure applied by the spring load (2) of 2.4 MPa, the shuttle (1) is pushed to the right.
● The result is the connection between the pump delivery circuit PP and the tank circuit T is excluded and the entire pump
delivery Q is sent to the actuator.
OPERATION
● When the shuttle (1) is activated, the pump pressure PP starts to flow into the actuator circuit through the duct b.
● At the same time the compensator (2) moves up so that the flow controlled by spool (1) can flow towards the actuator A.
(Check valve (4) do not allow any flow before the pressure in chamber c is higher than pressure in chamber b). Pressure
downstream spool (1) flows in the PLS circuit downstream the compensator valve through the orifice d.
● The PLS circuit of the LS is thus in communication with the tank circuit T by means of the LS decompression valve (3).
(See the description of the LS decompression valve).
● The system stabilizes when a pressure difference of 1.8 MPa is generated across the shuttle (1) between pump pressure PP
and PLS pressure.
FUNCTION
Compensation of actuator deliveries occurs when, during the simultaneous activation of two or more movements, the pressure
of one actuator drops lower than that of the other, and pump delivery, if not controlled, tends to be supplied the actuator oper-
ating at lower. (In the diagram the actuator on the left is requesting higher pressure).
OPERATION
1. When activating an actuator at a pressure lower than the one already working. (While operating actuator A starts operating
actuator B)
● Until the pressure PBV downstream from the shuttle (1) reaches the same value requested by actuator B, no oil passes.
● When the pressure requested by actuator B is exceeded, movement can commence. This creates a flow that adding to the
one controlled by spool (3) reduces the pressure upstream of spool (1) and (3) and therefore the P between PLS and PP.
● The pump compares the delivery pressures PP and PLS and senses that the difference P < 1.8 MPa. This variation in P
causes an increase in oil flow increasing the swash plate angle.
● Until the pump does not realize a P of 1.8 MPa, i.e. until the increase in oil flow compensates the requirements of the two
actuators, the pump will continue to increase delivery. When this differential is reached, the system will stabilize.
● The compensator (2) is moved upwards by the oil flow and stops when the aperture between the chambers a and b reduces
the passage sufficiently to reduce the pressure in chamber b to be sent to the actuator.
● If the actuator B needs to work at a higher pressure (PB>PA), the pressure PB will start to increase.
● Since pressure PB is increasing, the compensator (2) moves upwards to restore the P between the chambers a and b, and
therefore the P does not vary upstream or downstream from the shuttle (1).
● When pressure PB exceeds pressure PA, the compensator (2) is fully open and the pressure PB is introduced into the LS
circuit.
● The increase in pressure in the LS circuit obliges the pump to increase delivery until the P is restored to 1.8 MPa.
● Simultaneously, the increase in pressure upstream from the shuttle (3) generates an increase in P upstream and down-
stream from the shuttle. (PAV<PLS<PP)
● Because the pressure PLS which is equal to the pressure PB acts on the upper side of the compensator (4), and since the
pressure PAV is lower, the compensator (4) is pushed downwards.
● The compensator stops when the aperture between the chambers c and d generates a reduction of the passage sufficient to
reduce the pressure to be sent to the actuator, and to increase the pressure PAV until the P is restored to the 1.8 MPa nec-
essary for equilibrium.
● When an increased delivery is required by actuator A, i.e. when the shuttle (3) is asked to execute a bigger movement, the
section of the aperture increases.
● The increase in aperture provokes a drop in P between the two sides of the shuttles (2) and (3), because the flow, which
has remained unchanged until now, is divided between both the actuators.
● At the same time the pump senses the variation in P and increases the oil flow until the P is restored to P of 1.8 MPa
between the two sides of the shuttle (1) and the compensator (4) changes position in order to restore the P upstream and
downstream from the shuttle (3).
OPERATION
● When, during the simultaneous operation of more than one actuator, one of them needs a higher pressure and the charac-
teristics of the pump are exceeded, the pump guarantees a delivery limited by its calibration curve.
● At this point less oil than requested is distributed to all the actuators.
● Because the sections of the apertures remain unchanged, the pressure upstream and downstream from the shuttles drops.
Since the position of the compensator (4) is determined by the pressure of the LS signal, by the pressure PBV downstream
from the shuttle (3) and by the flow of oil needed for the movement, the compensator is pushed downwards by the higher
pressure in the upper chamber until the pressure PBV downstream from the shuttle becomes equal to the pressure PAV
downstream from the shuttle (1). This equalizes the pressure P of the shuttle (1).
● Thus the flow of each actuator is reduced by a percentage equal to the reduction or absence of pump delivery.
● In other words, when the request for performance is excessive, the system can nevertheless guarantee proportionality and
gradually for the movements in any load conditions.
● If an increase in delivery is requested, rather than an increase in pressure, and the characteristics of the pump are
exceeded, the system will function in the same way as described for the above case.
OPERATION
● When the LS pressure reaches chamber a of the valve, it generates a force that opposes the force of the spring (2).
● Until the force generated by the LS pressure exceeds the force of the spring (2) (LS pressure low) the shuttle (1) remains
at rest and oil flows through the calibrated orifice b in the tank circuit.
● When the force generated by the LS pressure exceeds the force of the spring (2), the shuttle is pushed upwards and the
passage c are closed. Oil continues to flow into the chamber d until the force generated by the pressure contained in cham-
ber d, together with the force of the spring (2), exceeds the force generated by the LS pressure.
● The shuttle is pushed downwards and passage c is opened.
● The system is in equilibrium (the shuttle is at rest) when the quantity of oil allowed to flow into the tank circuit is equiva-
lent to the quantity that generates a pressure difference P such that (PLSxS)=[(PLS1xS)+F] where: PLS=LS pressure
PLS1=LS pressure contained in chamber d S=section of the shuttle F=force of the spring.
OPERATION
● The pressurized oil of the LS reaches the chamber a of the valve.
● When the force generated by the LS pressure on the valve (1) exceeds the force of the spring (2), the valve (1) is pushed
upwards opening the passage between the chamber a and the tank circuit.
a. Port Y - To the raise cylinder (Head side) a. Port Y - To the arm cylinder (Head side)
b. Port A - From shovel control valve (Port A1) b. Port A - From backhoe control valve (Port B1)
c. Port X - To the raise cylinder (Base side) c. Port X - To the arm cylinder (Base side)
d. Port B - From shovel control valve (Port B1) d. Port B - From backhoe control valve (Port A1)
b. Port A - From shovel control valve (Port B2) Shovel dump: 23 MPa
Boom
1. Plug 9. Spool
3. Seal Displacement: 15 - 28 cc
4. Differential piston Maximum pressure: 15 MPa
5. Spring
6. Pump spring
7. Spring
8. Check valve
9. Ball
10. Seal
11. Pin
12. Seal
13. Seal
14. Seal
15. Ball
16. Spring
17. Seal
Unit: mm
No Check item Criteria Remedy
Standard size Repair limit
Free Installed Installed
1 Ball valve spring Installed load Free installed Replace if
installed length load
damaged
25 13 20 N 18-22 N
or
2 Spring 21 13 7.3 N 7.3 - 7.8 N deformed
3 Pump spring 91 60 72 N 65 - 79 N
4 Spring 14 7.3 4N 3.6 - 4.4 N
RAISE CYLINDER
DUMP CYLINDER
CHARACTERISTICS Unit: mm
DUMP CYLINDER
Unit: mm
Criteria
No Check item Cylinder Standard Tolerance Minimum Clearance Remedy
Size Shaft Hole clearance limit
-0.025 +0.064
Tolerance between Raise 50
-0.050 +0.025
0.05 0.114
1 piston rod and cylin- Replace
-0.025 +0.064
der head Dump 50 0.05 0.114
-0.050 +0.025
-0.050 +0.24
Tolerance between Raise 45 0.13 0.329
-0.089 +0.08
2 bushing and piston
-0.050 +0.24
rod mounting pin Dump 45 0.13 0.329 Replace
-0.089 +0.08
pin and
-0.038 +0.24
Tolerance between Raise 50 0.118 0.323 bushing
-0.083 +0.08
3 bushing and cylin-
der mounting pin -0.038 +0.24
Dump 50 0.118 0.323
-0.083 +0.08
BOOM
ARM
4. Cylinder 8. Piston
OUTRIGGERS
TELESCOPIC ARM
BOOM
ARM
BOOM SWING
Unit: mm
Criteria
No Check item Cylinder Standard Tolerance Minimum Clearance Remedy
size Shaft Hole clearance limit
-0.030 +0.076
Boom 60 0.06 0.136
-0.060 +0.030
-0.030 +0.076
Arm 60 0.06 0.136
Clearance -0.060 +0.030
between piston Arm with tele- -0.030 +0.076
1 60 0.06 0.136
head and cylinder scopic arm -0.060 +0.030
head -0.030 +0.076
Bucket 60 0.06 0.136
-0.060 +0.030
-0.025 +0.064
Boom swing 50 0.05 0.114
-0.050 +0.025
-0.050 +0.24
Boom 50 0.13 0.329
-0.089 +0.08
Tolerance -0.050 +0.24
Arm 45 0.13 0.329
between bushing -0.089 +0.08
2
and piston head -0.050 +0.24
mounting pin Bucket 50 0.13 0.329
-0.089 +0.08
Replace
-0.050 +0.119
Boom swing 50 0.13 0.208 pin and
-0.089 +0.080
bushing
-0.050 +0.24
Boom 50 0.13 0.329
Tolerance -0.089 +0.08
between bushing -0.050 +0.24
3 Arm 45 0.13 0.329
and cylinder -0.089 +0.08
mounting pin -0.050 +0.119
Bucket 45 0.13 0.208
-0.089 +0.080
Unit: mm
Criteria
No Check item Standard Tolerance Standard Clear- Remedy
size Shaft Hole clearance ance limit
Clearance between rotating
-0.060 +0.090
1 bushing and boom swing cyl- 55 .0120 - 0.196 —
-0.106 +0.060
inder bushing
Clearance between bushing Replace
-0.060 +0.190
2 and lower swing bracket rotat- 65 0.250 - 0.370 — bushing
-0.106 +0.264
ing pin and pin
Clearance between bushing
-0.060 +0.190
3 and upper swing bracket rotat- 65 0.250 - 0.370 —
-0.106 +0.264
ing pin
Standard size Limit size
4 Upper shim thickness 0
4.75 —
– 0.1
0
5 Central shim thickness 4.75 —
– 0.1
0
6 Lower shim thickness 4.75 —
– 0.1
Unit: mm
Criteria
No Check item Standard Tolerance Standard Clearance Remedy
Size Shaft Hole clearance limit
Clearance between link
-0.050 -0.080
1 bushings and bucket 40 0.130 - 0.329 —
-0.089 -0.240
mounting pin
Clearance between arm
-0.050 -0.080
2 bushings and bucket 40 0.130 - 0.329 —
-0.089 -0.240
mounting pin
Clearance between arm
-0.050 -0.080
3 bushings and lever 45 0.130 - 0.329 —
-0.089 -0.240
mounting pin
Clearance between
-0.050 -0.080
4 bushings and tilt lever 45 0.130 - 0.329 — Replace
-0.089 -0.240
mounting pin
Clearance between
-0.050 -0.080
5 bushings and arm 50 0.130 - 0.208
-0.089 -0.119
mounting pin
Clearance between
-0.038 -0.080
6 bushings and boom 50 0.118 - 0.202
-0.083 -0.119
mounting pin
Clearance between
-0.050 -0.080
7 bushings and outrigger 45 0.130 - 0.329 —
-0.089 -0.240
mounting pin
STANDARD
12 VALUE TABLES FOR ENGINE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20-3
STANDARD VALUE TABLE FOR CHASSIS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20-5
SPECIAL TOOLS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20-31
ENGINE SPEED . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20-32
VALVE CLEARANCE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20-33
COMPRESSION PRESSURE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20-34
FUEL INJECTION TIMING . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20-35
FAN AND ALTERNATOR DRIVE BELT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20-37
TENSION CHECK . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20-37
TENSION ADJUSTMENT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20-37
COMPRESSOR DRIVE BELT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20-38
CHECKING TENSION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20-38
TENSION ADJUSTMENT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20-38
ACCELERATOR PEDAL AND LEVER TRAVEL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20-39
ACCELERATOR PEDAL TRAVEL ADJUSTMENT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20-39
ACCELERATOR LEVER TRAVEL ADJUSTMENT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20-40
BRAKE PEDAL TRAVEL AND MICROSWITCHES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20-41
MASTER CYLINDER ROD ADJUSTMENT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20-41
MICROSWITCHES ADJUSTMENT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20-41
CHECKING ADJUSTMENT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20-41
BLEEDING AIR . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20-42
BLEEDING AIR FROM PUMP . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20-42
BLEEDING AIR FROM CYLINDERS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20-42
BLEEDING AIR FROM OIL TANK . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20-43
HYDRAULIC OIL TANK PRESSURIZATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20-43
RELEASING RESIDUAL PRESSURE FROM THE CIRCUITS . . . . . . . . . . . . . . . . . . . . . . . 20-43
BLEEDING AIR FROM THE BRAKING CIRCUIT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20-43
CHECKING AIR BLEEDING FROM BRAKING CIRCUIT . . . . . . . . . . . . . . . . . . . . . . . . . . 20-44
ATTACHMENTS HYDRAULIC CIRCUIT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20-45
INTRODUCTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20-45
TESTING AND SETTING GENERAL VALVES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20-48
FRONT SHOVEL CONTROL VALVE (2-3 SPOOLS) . . . . . . . . . . . . . . . . . . . . . . . . . . . 20-48
BACKHOE CONTROL VALVE (6-7-8 SPOOLS) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20-48
TESTING SECONDARY VALVES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20-48
SETTING MAIN AND SECONDARY VALVES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20-51
MAIN RELIEF VALVES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20-51
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20-51
SECONDARY VALVES B . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20-52
LOAD SENSING SIGNAL (LS VALVE) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20-53
LOAD SENSING VALVE ADJUSTMENT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20-53
STANDARD
12 VALUE TABLES FOR ENGINE
Machine Model WB140-2N (ASPIRATED)
Engine 4D106-1FA
Standard Permissible
Check Item Test Conditions Unit
Value Value
High idling rpm 2375±50 2325 – 2425
Engine Speed Low idling rpm 1050±50 1000 – 1100
Set idling rpm 2200 –
Exhaust Gas Sudden acceleration Bosch 0.9 1.2
Color At high idling speed index 0.5 0.8
Valve Intake valve (20°C) mm 0.20±0.05 Max. 0.25
Clearance Exhaust valve (20°C) mm 0.20±0.05 Max. 0.25
Compression
Oil temperature 69 – 72°C kg/cm² 34.97±1.02 28.04±1.02
Pressure
(Engine speed) rpm 250 250
(SAE30 oil)
Blow - By
Water temperature within operating range – –
Pressure mm H2O
At high idling speed – –
(SAE30 oil)
Max. idling (in cold state) kg/cm² Max. 5.9 Max. 5.9
Engine Oil
At set speed kg/cm² 4.48 3.97 – 4.99
Pressure
At low idling kg/cm² 1.02 Min. 1.02
Oil
Entire speed range °C 120 Max. 120
Temperature
Fuel Injection
B.T.D.C. degrees 12.5 11.5 – 13.5
Timing
Fan Belt Deflection when pressed with finger force
mm 10 10 – 15
Tension or approx. 10 kg
– – – –
– – – –
10 10 – 15 10 10 – 15
STANDARD
12 VALUE TABLE FOR CHASSIS
Engine 4D106-1FA
l a b c l a b c
All controls
(front bucket and
Control valve
backhoe) 41.5 8 8 – – – – –
mm
l a b c l a b c l a b c l a b c
41.5 8 8 – – – – – 41.5 8 8 – – – – –
41.5 8 8 – – – – – 41.5 8 8 – – – – –
85 60 – 110 85 60 – 110
50 35 – 65 50 35 – 65
70 50 – 90 70 50 – 90
15 10 – 20 15 10 – 20
30 20 – 40 30 20 – 40
15 10 – 20 15 10 – 20
30 20 – 40 30 20 – 40
80 60 – 100 80 60 – 100
12 10 – 14 12 10 – 14
4 3–4 4 3–4
8 6 – 10 8 6 – 10
8 6 – 10 8 6 – 10
3 2–4 3 2–4
30 Max. 60 30 Max. 60
239.63 239.63±7.14
(3rd spool) ✽
Boom 362 362±7.14
(raising) ✽ • Engine speed: 1500±50 rpm
• Oil temperatures: 45 – 50°C
Boom (lowering) 249.83 249.83±7.14
• Check one circuit at a time
kg/cm²
Arm (closing) 249.83 249.83±7.14
✽ Check on bench test
(do not check on the machine)
Boom swing 193.75 193.75±7.14
Measuring position
Complete working
equipment
250 400
(Tip lowering of
bucket teeth)
Front bucket
Boom cylinders
35 50
(cylinder out)
Backhoe
30 45 30 45
15 25 15 25
35 50 35 50
15 25 15 25
10 15 10 15
Outriggers 20 30
15 25 15 25
20 30 20 30
2.0
Boom Max. 8.0
Front bucket
(each cylinder)
1.6
Bucket Max. 6.0
(each cylinder)
separately.
2.0 2.0
Max. 8.0 Max. 8.0
(each cylinder) (each cylinder)
1.6 1.6
Max. 6.0 Max. 6.0
(each cylinder) (each cylinder)
Raised
bucket 3.6 3.1 – 4.1
Cylinders
extended out
Lowered
↕
Bucket on level • Engine speed: Max. 2.5 2.1 – 2.9
ground • Oil temperature: 45 – 55°C
Loader
• Speed up
Measuring position
Curled
2.5 2.1 – 2.9
Bucket
Cylinders out
↕
Dump
Cylinder in 3.2 2.7 – 3.7
• Engine speed: Max.
• Oil temperature: 45 – 55°C
• Speed up
Measuring position
sec.
Lifting ●
2.3 1.9 – 2.7
Boom
Work equipment speed
Cylinders in
↕
Lowered
Teeth bucket on
level ground • Engine speed: 1700 +0 50 rpm 1.6 1.2 – 2.0
• Oil temperature: 45 – 55°C
• Backhoe balanced
• Power mode
Measuring position
Opening
Cylinders in
↕
Closing ●
Cylinders in
↕
Curled
Measuring position
Right ●
3.5 3.1 – 3.9
Work equipment speed
Boom swing
Backhoe
Left ●
• Engine speed: 1700 +0 50 rpm 3.5 3.1 – 3.9
• Oil temperature: 45 – 55°C
• Arm horizontal
• Power mode
● The time referenced is for the cylinder stroke without the brake phase
NOTE: The engine speed (1700 0+50 rpm) has to be checked using the procedure described in paragraph
“ENGINE SPEED“ in this section of the manual.
Measuring position
Work equipment speed
Time lags
Boom 0 Max. 2
sec.
• Engine speed: Min.
• Oil temperature: 45 – 55°C
• With attachments fully extended, lower the
boom and check the elapsed time from the
beginning of the machine lifting until the bucket
is on level ground.
Measuring position
Arm 0 Max. 2
0 Max. 2 0 Max. 2
0 Max. 2 0 Max. 2
0 Max. 2 0 Max. 2
Measuring position
Bucket 0 Max. 2
Time lags
Outriggers 0 Max. 2
0 Max. 2 0 Max. 2
0 Max. 2 0 Max. 2
★ When measuring deliveries with the pump mounted on the machine, it becomes difficult to use the accelerator
to set the engine rpm to the test speed prescribed for the pump. Measure the delivery with the engine set to
2200 rpm, and perform a proportional calculation to find the delivery value required for the test.
★ When measuring deliveries with the pump mounted on the machine, it becomes difficult to use the accelerator
to set the engine rpm to the test speed prescribed for the pump. Measure the delivery with the engine set to
2200 rpm, and perform a proportional calculation to find the delivery value required for the test.
★ When measuring deliveries with the pump mounted on the machine, it becomes difficult to use the accelerator
to set the engine rpm to the test speed prescribed for the pump. Measure the delivery with the engine set to
2200 rpm, and perform a proportional calculation to find the delivery value required for the test.
★ When measuring deliveries with the pump mounted on the machine, it becomes difficult to use the accelerator
to set the engine rpm to the test speed prescribed for the pump. Measure the delivery with the engine set to
2200 rpm, and perform a proportional calculation to find the delivery value required for the test.
SPECIAL
12 TOOLS
Measurement check point Symbol Code Name Qty Note
Commercially
Valve clearance A 1 Feeler gauge 1 –
available
1 Compression gauge 1 Kit Yanmar
Compression gauge B ATR800208
2 Adapter 1 TOL-97190080
Commercially
1 Multi-scale tachometer 1 20 – 4000 rpm
available
Engine speed C
ATR800060
2 Stroboscopic tachometer 1 6 – 30000 rpm
Only for Europe
Commercially
Oil and water temperature D 1 Digital thermometer 1 -50 – 1200°C
available
Commercially
1 Pressure gauge 2 Full scale 61.2 kg/cm²
available
Commercially
2 Pressure gauge 1 Full scale 255 kg/cm²
available
Commercially
3 Pressure gauge 1 Full scale 408 kg/cm²
E available
Hydraulic pressure Commercially
4 Pressure gauge 1 Full scale 612 kg/cm²
available
5 Servo control kit
Differential digital 1 0-1020 kg/cm²
6 ATR800200 pressure gauge
Only for Europe
1 Flow-meter 1 Delivery 0-300 l/min.
F
2 Pipe fitting kit 1 –
Air bleeding G 1 ATR201490 Tank cap 1 Pump air bleeding
Commercially
Hand brake L 1 Spring dynamometer 1 Full scale 20 kg
available
Commercially
1 Maintenance station 1 For coolant R134a
available
Commercially Sampling every 15 sec-
Air-conditioning unit M 2 Thermometer-hygrometer 1
available onds
Commercially
3 Leak detector 1 For coolant R134a
available
ENGINE
12 SPEED
WARNING! When checking engine speed be careful. Do
not touch high temperature parts or get caught in rotating
parts.
VALVE
12 CLEARANCE
★ Measurement conditions:
• Engine: Cold
★ Adjust clearance between valves and rocker levers as follows:
Unit: mm
Engine Intake – exhaust
With cold 4D106-1FA 0.30±0.05
engine S4D106-1FH 0.30±0.05
S4D106-1FA 0.30±0.05
★ Firing order: 1-3-4-2-1..... at 180° steps.
Adjusting procedure
★ Check that valve insert G is laying flat on the valve stem and
that it is not worn.
• If valve inserts G are damaged, replace them with new
ones.
• Make sure that inserts fit and lay flat on the valve stem.
4. Place feeler gauge A1 between the insert and the rocker lever to be
adjusted. Rotate the tappet F until the rocker lever touches the feel-
er gauge.
COMPRESSION
12 PRESSURE
WARNING! When measuring the compression pressure
be careful not to get caught in the cooling fan, alternator
belt or in any other rotating parts. For this measurement
the engine should be at operating temperature. Take every
precaution against burns.
★ Measurement conditions:
FUEL
12 INJECTION TIMING
★ Check fuel injection timing of No. 1 cylinder by means of No. 1 de-
livery valve of injection pump.
1. Rotate crankshaft using engine pulley and put No. 1 cylinder piston
at top dead centre (TDC).
S4D106-1FA:12.5° ±1°
S4D106-1FH:12.5° ±1°
FAN
12 AND ALTERNATOR DRIVE BELT
TENSION CHECK
1. Push fan belt B at the midway point between alternator C and the
pulley d operating the water pump. Check the deflection. With a
pressure of 10 kg, deflection should be 10 – 15 mm; if not, the belt
needs adjustment. With a new belt, deflection should be 7 – 9 mm.
TENSION ADJUSTMENT
1. Loosen alternator mounting bolt d and adjustment plate mounting
bolt e.
★ If belt has been replaced, check tension again after about 20 hours
of operation.
COMPRESSOR
12 DRIVE BELT
CHECKING TENSION
1. Push fan belt b at midway point between compressor c and pulley
d. Check the deflection. With a pressure of 10 kg, deflection
should be 7 – 10 mm. If not, the belt needs adjustment.
TENSION ADJUSTMENT
1. Loosen mounting bolt e of the eccentric f.
★ If belt has been replaced, check tension again after about 20 hours
of operation.
ACCELERATOR
12 PEDAL AND LEVER TRAVEL
★ Measurement conditions:
ACCELERATOR
12 LEVER TRAVEL ADJUSTMENT
1. Remove mat and lateral cover B.
2. Loosen nut c and tighten the end lever travel bolt d a few turns.
6. Bring engine to low idle and check accelerator lever idling speed
adjustment by pushing the lever to the end of its stroke.
BRAKE
12 PEDAL TRAVEL AND MICROSWITCHES
★ Measurement conditions:
• Engine stopped
• Machine with attachments on ground
1. Check that pedal B is at stopper c and the pedals height matches
side view “A” measurement. If necessary, correct the height by ad-
justing stopper c.
2. Tighten the adjusting rod F one turn (360°) and lock it with nut E.
MICROSWITCHES ADJUSTMENT
1. Loosen microswitch locking nuts G.
CHECKING ADJUSTMENT
1. Verify the below measurements as shown in the figure.
BLEEDING
12 AIR
BLEEDING AIR FROM PUMP
★ Bleeding air from pump is necessary: (make sure pump is full of
oil)
1. Fill the hydraulic tank with oil and install plug G1.
6. While slowly depressurizing the hydraulic tank, check the oil level.
Add oil as necessary to maintain the proper level.
7. Start the engine and run it for few minutes before bleeding air from
the whole system.
1. Start the engine and run it at high idling speed for about 5 min. to
warm up the oil and pressurize hydraulic system.
2. Return engine to low idling speed, extend and retract the piston 4-5
times.
4. Repeat above operation (starting with Step 2.) for all cylinders.
BLEEDING
12Repeat
air bleedingaboveAIR FROM(starting
is obtained
operation OIL TANK
from point 2) for all cylin.he
1. Put the machine in oil level check position and remove the tank
plug. If necessary add oil to reach the correct level.
2. After stopping the engine wait for a few minutes until the air bub-
bles on oil surface disappear.
★ Avoid increasing the engine speed until after completing all air
bleeding procedures and after the pressurization of oil tank.
★ After air bleeding procedures, operate engine at low idling
speed for about 10 minutes before starting to work.
RELEASING RESIDUAL PRESSURE FROM THE
CIRCUITS
1. Put work attachments on level ground, stop the engine.
3. Slowly loosen the oil filler from the tank to remove any residual pressure.
★ Check that oil without air bubbles flows out from bleeding
screw (2).
10. Repeat same operations for the other braking unit.
★ Frequently check the oil level in the tank and refill it when the
level approaches minimum.
★ After bleeding the air, reinstall safety plugs on the screws (2) .
CHECKING AIR BLEEDING FROM BRAKING CIR-
CUIT
1. Start the engine and lower the backhoe outrigger and force them
downwards in order to raise the rear wheels.
3. Return the machine to neutral and lower it. Stop the engine.
5. Insert pedal lock pin and applying the same mass verify the mea-
sure “D”.
★ “D” measure with one pedal pushed: not less than 165 mm
★ “D” measure with both pedals pushed: not less than 170 mm
ATTACHMENTS
12 HYDRAULIC CIRCUIT
INTRODUCTION
• The machine is equipped with two control valves having the following functions:
• Control valve No. 1 (2-3-spools): For front work attachments control.
• Control valve No. 2 (6-7-8-spools): For rear work attachments control.
• The two control valves are protected against overpressure by a main relief valve (general or pressure cut-off valve)
with adjustable setting.
• Control valves are fed by delivery pump P1.
• Delivery pump P1 is controlled by a priority valve (internal to control valve No. 1) when the steering unit is used.
(For breaker)
Control Port
Breaker (L. H. side) A7
TESTING
12 AND SETTING GENERAL VALVES
(Pressure cut-off valve or main relief valve)
★ Measurement conditions:
• Engine: stopped and at operating temperature
• Hydraulic oil: 55–60 °C
• Parking brake: applied
FRONT SHOVEL CONTROL VALVE (2-3 SPOOLS)
2. Start the engine, bring the accelerator pedal up to max. speed and
check the nominal pressure of the main relief valve (pressure cut-
off valve) by forcing the front bucket to rise to the end of its stroke.
★ Nominal pressure:
WB140-2N: 189±7.14 kg/cm²
WB150-2N: 204±7.14 kg/cm²
BACKHOE CONTROL VALVE (6-7-8 SPOOLS)
2. Start the engine, bring the hand accelerator lever up to max. speed
and check the nominal pressure of the main relief valve (pressure
cut-off valve) while forcing the bucket into maximum curl position
(or forcing the raising of the boom to the end of its stroke).
★ Nominal pressure:
WB140-2N: 211±7.14 kg/cm²
WB150-2N: 224±7.14 kg/cm²
★ If the main relief valve pressures do not correspond to the
nominal values, they must be reset (See “TESTING AND
SETTING GENERAL VALVES“).
TESTING SECONDARY VALVES
★ Measurement conditions:
2. Start the engine and bring the hand accelerator lever up to 1050
rpm.
3. Set the main relief valve f (pressure cut-off) to a value 30.6 kg/cm²
higher than the maximum pressure to be tested.
4. Check secondary valve g single movement pressure. Refer to the following tables for cylinder and movement.
WARNING! The secondary backhoe boom lifting valve pressure must be checked and set only during
bench testing.
Setting 2-spool control valve secondary valves
Unit: kg/cm²
Cylinder and movement Port Setting WB140-2N Setting WB150-2N
Lifting A1 — —
Loader arm
Lowering B1 — —
Curled A2 239.63±7.14 239.63±7.14
Front bucket
Dump ★ B2 178.45±7.14 178.45±7.14
★ This pressure can be set without modifying the general valve pressure.
Unit: kg/cm²
Cylinder and movement Port Setting WB140-2N Setting WB150-2N
Lifting A1 — —
Loader arm
Lowering B1 — —
Curled A2 239.63±7.14 239.63±7.14
Front bucket
Dump ★ B2 178.45±7.14 178.45±7.14
A3 239.63±7.14 239.63±7.14
Optional attachment
B 239.63±7.14 239.63±7.14
★ This pressure can be set without modifying the general valve pressure.
Unit: kg/cm²
Cylinder and movement Port Setting WB140-2N Setting WB150-2N
Closing A1 249.83±7.14 249.83±7.14
Arm
Opening B1 — —
Left A2 193.75±7.14 193.75±7.14
Boom swing
Right B2 193.75±7.14 193.75±7.14
Up A3 — —
Left outrigger
Down B3 — —
Up A4 — —
Right outrigger
Down B4 — —
Dump A5 — —
Bucket
Curled B5 249.83±7.14 249.83±7.14
Lifting ★ A6 262±7.14 262±7.14
Boom
Lowering B6 249.83±7.14 249.83±7.14
★ This pressure can only be set during bench testing.
Unit: kg/cm²
No. of spools Cylinder and movement Port Setting WB140-2N Setting WB150-2N
Left A7 173.35±7.14 173.35±7.14
Breaker
Right ★ B7 — —
7
In A7 — —
Telescopic arm
Out B7 — —
Left A7 173.35±7.14 173.35±7.14
Breaker
Right ★ B7 — —
8
In A8 — —
Telescopic arm
Out B8 — —
★ This pressure can be set without modifying the general valve pressure.
★ If valve pressure indications do not correspond to those listed, proceed to the next Step.
• Front shovel: Force the front bucket to rise to the end of its
stroke.
• Backhoe: Force the bucket into maximum curl position or
force the raising of the boom to the end of its stroke.
4. Adjust pressure with adjusting screw E.
★ The pressure must be set while the control lever (for the cylinder
being tested) is forced to the end of its stroke.
2. Loosen locknut d.
Locknut:..................................................................10±1 N·m
LOAD
12 SENSING SIGNAL (LS VALVE)
★ Measurement conditions:
4. Start the engine and bring it to 1050±50 rpm, without any machine
movement (lever in neutral position), read the ∆P pressure.
2. Loosen locknut f.
Locknut:...................................................................... 21 N·m
UNLOADING
12 VALVE
★ Measurement conditions:
4. Start the engine and bring it to 1050±50 rpm, without any machine
movement (lever in neutral position), read the ∆P pressure.
UNLOADING
12 VALVE FUNCTION
★ Measurement conditions:
4. Start the engine at low idle and without any machine movement,
check pressure on both gauges.
7. If, in spite of cleaning the valve E, the value still does not fall with-
in the tolerance limits of 21.41±1.02 kg/cm², install a new valve.
PRIORITY
12 VALVE
★ Measurement conditions:
• Engine: stopped and at working temperature.
• Hydraulic oil: 55 – 60 °C.
• Parking brake applied
TESTING PRIORITY VALVE OPERATION
1. Connect a pressure gauge E2 (255 kg/cm²) to the pressure adapter
b of the backhoe control valve.
2. Start the engine and bring it to the idling speed of 1500±50 rpm.
4. Slightly turn the steering wheel and check that pressure increases.
5. Continue turning the steering wheel to the end of a full turn and
check that while forcing the steering wheel, pressure increases to
the normal value.
Plug:........................................................................... 20 N·m
7. Start the motor, execute several steering manoeuvres. If the fault is not corrected, replace the complete steering column
with a new one.
STEERING
12 CONTROL SYSTEM PRESSURE
★ Measurement condition:
2. Start the engine and bring it to idle speed 1500±50 rpm. Turn the
steering wheel from end to end.
3. Force the steering wheel to the end of its rotation and check the
pressure.
4. Check the pressure at the other end of the steering direction as well.
SETTING
If the pressure is not within permissible limits, reset the pressure on the
upper valve D of the steering unit.
1. Remove plug E.
BRAKE
12 SYSTEM
★ Measurement condition:
• Engine: stopped
• Machine: on solid and level ground, with equipment raised and
safety devices engaged.
• Brake pedals: independent, with the fluid container level at
maximum.
System testing is in two parts:
5. Push the brake pedal corresponding to the pump and bring the cir-
cuit up to a pressure of approximately 122.36 kg/cm².
2. Connect the tee between delivery line f and the braking group.
4. Operate the brake pump to feed pressure into the circuit to a maxi-
mum pressure of 153±5.1 kg/cm².
ENGINE
12 SPEED UNDER LOAD
★ Measurement conditions:
2. Speed test with the torque converter and the hydraulic system under
stress.
TESTING
12 WITH THE TORQUE CONVERTER UN-
DER STRESS
1. Start the motor at MIN. Engage the highest FORWARD gear and
apply the brake firmly.
● If the revolutions of the engine are lower than the permissible limit,
check the condition of the air filter, the engine compression, the
timing, the injection pump, and the valve clearances.
POWER
12 TRAIN GROUP
The power train group can be used to perform pressure tests on the in-
ternal hydraulic circuit. These are useful for identifying malfunctions.
★ Test conditions:
• Engine: stopped.
• Brake pedals: connected by a cotter pin.
• Machine: on solid and level ground with the equipment raised
and safety devices engaged.
PREPARING THE MACHINE
1. Prepare the tachometer C1 to measure the engine rpm.
2. Start and heat the engine and all the fluids up to working tempera-
ture. Make sure that the power train oil reaches a temperature of
80±5 °C.
3. With the engine at MIN (idling), check the pressure on the pressure
gauge E6.
CLUTCH
12 ENGAGEMENT PRESSURE
1. Remove the access plate from the cab floor.
3. Start and heat the engine and all the fluids up to working tempera-
ture. Make sure that the power train oil reaches a temperature of
80±5 °C.
4. With the engine at MIN (idling) check the pressure on the pressure
gauge E6.
8. Repeat the same test for the FORWARD gear, reading the pressure
from the orifice protected by plug P18.
• If the pressures are different for the two travel directions, there
is a loss of pressure on the clutch piston with lowest pressure.
POWER
12 TRAIN CLUTCHES
★ Test conditions:
• Engine: stopped.
• Brake pedals: connected by a cotter pin.
• Machine: on solid and level ground with the equipment raised
and safety devices engaged.
★ This test must be performed after having checked the pressures of
the power train group.
TESTING
1. Start and heat the engine and all the fluids up to working tempera-
ture. Make sure that the power train oil reaches a temperature of
80±5 °C.
2. With the engine in idling, accelerate to MAX. Check that the revo-
lutions remain within permissible limits. (See “ENGINE SPEED“)
★ If the revolutions are higher than the permissible limits, the clutch-
es are worn, and must be replaced.
SENSOR
12 FOR RETURN TO DIG DEVICE
★ Adjustment conditions:
4. Loosen screw F and move bracket G towards the rear until the sen-
sor is completely free of rod D.
5. Start the engine and allow it to idle. Adjust the position of bracket
G until sensor C is engaged.
★ When the rod contacts the sensor, warning lamp H will be acti-
vated.
6. Secure bracket G position by tightening the screw.
CAUSES
12 OF HYDRAULIC DRIFT
★ If working attachments have hydraulic drift, check if the drift is due
to the cylinder gaskets or the control valve.
★ Test conditions:
3. Disconnect hoses B and C from the lift cylinders D and plug them.
4. Plug the lift cylinder base side. Apply a temporary hose to the head
side to catch any oil leakage.
5. Start the engine and retract the bucket until the teeth tilt 15° above
horizontal.
6. Stop the engine and check bucket link position for 5 minutes.
8. Remove the plug (installed earlier in Step 4) from the base side of
one cylinder.
9. Start the engine and retract the bucket until the teeth tilt 15° above
horizontal.
10. Stop the engine and check the bucket position for 5 minutes.
1. Position the bucket on level ground and tilt the teeth up about 15°.
Put 1500 kg of weight into the bucket.
4. Plug the dump cylinder base side. Apply a temporary hose to the
head side to catch any oil leakage.
6. Stop the engine and check the bucket teeth position for 5 minutes.
8. Remove from one of the cylinders the plug installed on the cylinder
base side in Step 3.
10. Stop the engine and check the position of the bucket teeth for 5
minutes.
• If the bucket teeth turn, the drift is due to the gasket seals of the
plugged cylinder.
11. Repeat Steps 7 through 10 to test the other cylinder.
BACKHOE
12
★ Test condition:
• Backhoe aligned
• Lifted outriggers
BOOM TESTING
1. Position the machine with its arm in vertical position with the bot-
tom of the bucket resting on level ground.
5. Apply a temporary hose to the base side to catch any oil leakage.
7. Stop the engine and check the boom position for 5 minutes.
ARM TESTING
1. Position the machine with its arm fully extended with the bucket
opening and teeth on the ground.
6. Stop the engine and check the arm position for 5 minutes.
BUCKET TESTING
1. Position the machine with the bucket arm vertical and the bottom of
the bucket resting on level ground.
5. Plug the bucket cylinder hole on the base side and attach a tempo-
rary hose to the head side to catch any oil leakage.
7. Stop the engine and check the bucket position for 5 minutes.
OUTRIGGER TESTING
1. Position the machine with its arm in vertical position with the bot-
tom of the bucket resting on level ground.
3. Without forcing them, lower the outriggers onto the support stands.
6. Plug the cylinder base side c. Apply a temporary hose to the head
side to catch any oil leakage.
7. Start the engine. Use force on the boom to raise the machine and re-
move the support stands supporting the outriggers.
AIR-CONDITIONING
12 UNIT
★ Test conditions:
Ambient
20 25 30 35
temperature °C
Outgoing air
6–8 8–10 8–12 9–14
temperature °C
9. If the average value of the temperature measured does not fall with-
in the values given in the table, it will be necessary to thoroughly
check the unit.
CHECKING
12 THE UNIT
Check the unit after the Steps 1., 2., 3., 4. and 6. of the preceding para-
graph.
A diagnosis of faults in the unit is based upon the working pressures.
When the pressures do not fall within the values given in the following
table, the causes must be found by checking the high-pressure (H.P.)
and low pressure (L.P.) pressure gauges.
FRONT
12 AXLE
Wheel vibration; front tire resistance; half shaft breakage.
CAUSES REMEDY
Incorrect installation Correct installation
Replace the differential in case it does not survive any of the test phas-
Defective axle
es
Remove excessive weight and redistribute load following instructions
Overloading/incorrect weight distribution
related to the vehicle
Different rotation radius of the tires Replace the tire or adjust pressure to have the same radius on both tires
Bent half shaft Replace half shaft
No differential action; jamming while steering.
CAUSES REMEDY
Incorrect installation Correct installation
Replace the differential in case it does not survive any of the test phas-
Defective axle
es
Broken half shaft Replace half shaft
Bent half shaft Replace half shaft
Steering is difficult; vehicle goes straight while trying to turn it.
CAUSES REMEDY
Incorrect installation Correct installation
Replace the differential in case it does not survive any of the test phas-
Defective axle
es
Remove excessive weight and redistribute load following instructions
Overloading/incorrect weight distribution
related to the vehicle
Different rotation radius of the tires Replace the tire or adjust pressure to have the same radius on both tires
Broken half shaft Replace half shaft
Excess noise
CAUSES REMEDY
Incorrect installation Correct installation
Replace the differential in case it does not survive any of the test phas-
Defective axle
es
Remove excessive weight and redistribute load following instructions
Overloading/incorrect weight distribution
related to the vehicle
Different rotation radius of the tires Replace the tire or adjust pressure to have the same radius on both tires
Bent or broken half shaft Replace half shaft
Incorrect wheel adjustment Verify group integrity and wheel side bearings
Contamination in the axle box or incorrect assembly Look for foreign particles. Check for proper assembly of the various
of parts parts of the axle.
Friction noise
CAUSES REMEDY
Incorrect installation Correct installation
Replace the differential in case it does not survive any of the test phas-
Defective axle
es
Bent or broken half shaft Replace half shaft
Check the condition of the ring gear, pinion gear, bearings, etc. Re-
Damaged or worn out axle parts
place when necessary.
Contamination in the axle box or incorrect assembly Look for foreign particles. Check for proper assembly of the various
of parts parts of the axle.
Incorrect adjustment of bevel gear set.
Parts of the transmission worn out. Replace or adjust as required.
(transmission gears, U joint, etc.)
Intermittent noise
CAUSES REMEDY
Ring gear damaged Replace bevel gear set
Differential box bolts loosened Tighten to torque
Constant noise
CAUSES REMEDY
Ring gear teeth or pinion damaged Replace bevel gear set
Worn out bearings Replace
Pinion spline worn out Replace
Bent half shaft Replace
REAR
12 AXLE
Wheel vibration; front tire resistance; half shaft breakage.
CAUSES REMEDY
Incorrect installation Correct installation
Replace the differential in case it does not survive any of the test phas-
Defective axle
es
Remove excessive weight and redistribute load following instructions
Overloading/incorrect weight distribution
related to the vehicle
Different rotation radius of the tires Replace the tire or adjust pressure to have the same radius on both tires
Bent half shaft Replace half shaft
Excess noise
CAUSES REMEDY
Incorrect installation Correct installation
Replace the differential in case it does not survive any of the test phas-
Defective axle
es
Remove excessive weight and redistribute load following instructions
Overloading/incorrect weight distribution
related to the vehicle
Different rotation radius of the tires Replace the tire or adjust pressure to have the same radius on both tires
Bent or broken half shaft Replace half shaft
Incorrect wheel adjustment Verify group integrity and wheel side bearings
Contamination in the axle box or incorrect assembly Look for foreign particles. Check for proper assembly of the various
of parts parts of the axle.
Friction noise
CAUSES REMEDY
Incorrect installation Correct installation
Replace the differential in case it does not survive any of the test phas-
Defective axle
es
Bent or broken half shaft Replace half shaft
Check the condition of the ring gear, pinion gear, bearings, etc. Re-
Damaged or worn out axle parts
place when necessary.
Contamination in the axle box or incorrect assembly Look for foreign particles. Check for proper assembly of the various
of parts parts of the axle.
Incorrect adjustment of bevel gear set.
Parts of the transmission worn out. Replace or adjust as required.
(transmission gears, U joint, etc.)
Intermittent noise
CAUSES REMEDY
Ring gear damaged Replace bevel gear set
Differential box bolts loosened Tighten to torque
Constant noise
CAUSES REMEDY
Ring gear teeth or pinion damaged Replace bevel gear set
Worn out bearings Replace
Pinion spline worn out Replace
Bent half shaft Replace
TRANSMISSION
12
Noise
CAUSES REMEDY
Damaged converter Replace
Damaged oil pump Replace
Aeration/Cavitation Check oil level
Seizing (broken gears, shafts, bearings, etc.) Check/Repair/Replace
Worn clutch plates Replace
Irregular actuation
CAUSES REMEDY
Damaged control valve Replace
Electrical system fault Repair/Replace
Worn clutch plates Replace
Damaged converter Replace
Low oil temperature (high oil viscosity) Wail for oil to reach operating temperature (stall test)
Overheating See "Overheating"
Damaged hydraulic system Repair/Replace
DISASSEMBLY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-92
ASSEMBLY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-93
AXLE HOUSING AND BRAKES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-96
DISASSEMBLY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-96
BRAKE CONTROL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-99
DISASSEMBLY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-99
ASSEMBLY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-105
BRAKE AND AXLE HOUSING . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-107
ASSEMBLY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-107
RING GEAR AND CARRIER . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-112
DISASSEMBLY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-112
PINION DISASSEMBLY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-112
PINION ASSEMBLY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-115
DIFFERENTIAL CARRIER . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-118
ASSEMBLY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-118
RING AND PINION SET UP . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-119
ASSEMBLY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-119
FRONT BUCKET BOOM CYLINDERS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-126
REMOVAL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-126
INSTALLATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-127
FRONT BUCKET TILT CYLINDER . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-128
REMOVAL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-128
INSTALLATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-129
FRONT BUCKET . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-130
REMOVAL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-130
INSTALLATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-131
FRONT WORKING EQUIPMENT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-132
REMOVAL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-132
INSTALLATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-133
BACKHOE CONTROL VALVE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-134
REMOVAL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-134
INSTALLATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-135
BACKHOE BOOM CYLINDER . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-136
REMOVAL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-136
INSTALLATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-136
BACKHOE ARM CYLINDER . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-138
REMOVAL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-138
INSTALLATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-139
TELESCOPIC ARM CYLINDER . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-140
REMOVAL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-140
INSTALLATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-141
BACKHOE BUCKET CYLINDER . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-142
REMOVAL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-142
INSTALLATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-143
OUTRIGGER CYLINDERS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-144
REMOVAL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-144
INSTALLATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-145
BACKHOE SWING CYLINDERS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-146
REMOVAL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-146
INSTALLATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-147
CYLINDERS (FRONT BUCKET RAISE AND TILT, BOOM, ARM, OUTRIGGERS, AND
TELESCOPIC ARM) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-148
DISASSEMBLY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-148
ASSEMBLY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-150
CYLINDER (BOOM SWING) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-154
DISASSEMBLY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-154
ASSEMBLY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-155
BOOM SAFETY CYLINDER . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-158
REMOVAL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-158
INSTALLATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-159
BACKHOE WORK EQUIPMENT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-160
REMOVAL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-160
INSTALLATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-161
BACKHOE BUCKET . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-162
REMOVAL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-162
INSTALLATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-162
BACKHOE ARM . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-164
REMOVAL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-164
INSTALLATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-165
TELESCOPIC ARM (COMPLETE) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-166
REMOVAL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-166
INSTALLATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-167
INNER ARM . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-168
REMOVAL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-168
INSTALLATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-169
INNER ARM GUIDES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-170
REMOVAL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-170
INSTALLATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-170
BACKHOE BOOM . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-172
REMOVAL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-172
INSTALLATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-173
BACKHOE SWING BRACKET . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-174
REMOVAL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-174
INSTALLATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-175
BACKHOE OUTRIGGERS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-176
REMOVAL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-176
INSTALLATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30-177
B. Any special techniques applying only to the installation procedures are marked The same mark is placed after
the relevant step in the removal procedure to indicate which step in the installation procedure it applies to.
Example Explanation
WARNING
Safety precaution to be observed when performing an operation.
Special technique during assembly or installation (note that this symbol is left-
aligned)
Specifications.
1. General precautions when carrying out installation or removal (disassembly or assembly) of units given together as PRE-
CAUTIONS WHEN CARRYING OUT OPERATION, be sure to follow these precautions when performing the opera-
tion.
2. List of special tools: For details of the description, part number and quantity of any tools that appear in the operation pro-
cedure, See “SPECIAL TOOLS” on page 30-8..
Remark
A procedure that must be observed when performing a certain operation.
REMOVAL PRECAUTIONS
• Unless indicated otherwise, always lower all work equipment down until it rests firmly on the ground.
• Always trap and recycle all coolants and oils. Be sure your containers are large enough.
• Cap, cover or plug any openings to prevent dirt or debris from entering when you remove a component or part.
• Before removing a cylinder, secure the ram in a retracted position.
• Before removing or disassembling any parts, mark the order in which they came apart.
• When removing hydraulic couplings, always support the line or hose you are removing it from to avoid twisting or kink-
ing the line.
• When removing any lines always tag the line with a reference tag or mark as to where it is to be installed.
• When using eye bolts to lift an item be sure the eye bolt is installed all the way in the part you will be lifting.
• When removing a part in a wet attachment, be sure you have the proper drain pans to catch any residual fluids.
• Keep your work area clean and organized at all times.
INSTALLATION PRECAUTIONS
• Always use the specified torque when tighten nuts or bolts. Never dry torque a fastener, always lubricate the fastener
before torquing it.
• Never use impact tools to start a nut or bolt. Always start nuts and bolts by hand first.
• Secure all cotter keys according to the instructions listed.
• When using adhesives on surfaces or fasteners, be sure the surface is clean and free of oil, dirt or grease.
• Clean all parts before installing them.
• Be sure snap rings are installed correctly and firmly in place.
• When installing a component always follow the tightening pattern for multiple fasteners.
SPECIAL TOOLS
Procedure Symbol Code Description Q.ty Notes
ATR200620
Cylinder disassembly
1 See Attachment 1
and assembly
960119000
Plunger 40 2
Hydraulic
Plunger 45 2
press Assembly cylinder
2
Commercially and ram bushings
Plunger 50 2
available
Plunger 75 2
See
Bushing 1
960117005 To calibrate piston
3
shims
See
Bushing support 1
960117006
Plunger 40 1
Hydraulic
Plunger 50 1
press
8 Dust seal assembly
Commercially
Plunger 55 1
available
Plunger 60 1
Expander 70 1
Expander 80 1
See Expander 85 1
960117002
9 Expander 95 1 Piston gasket assembly
960117003
960030002 Expander 100 1
Expander 110 1
Expander 115 1
Commercially
Air conditioning unit B 1 Recycle station 1 Recycle refrigerant
available
1 CA715027 Plunger 1
2 CA119030 Wrench 1
3 CA119099 Wrench 1
4 CA715022 Wrench 1
5 CA119225 Plunger 1
9 CA715021 Plunger 1
10 CA119230 Plunger 1
Disassembly and
assembly of C 11 CA715087 Plunger 1
front axel
12 CA715163 Plunger 1
13 CA715164 Plunger 1
14 CA715034 Plunger 1
15 CA119055 Plunger 1
16 CA715396 Plunger 1
17 CA119043 Plunger 1
18 CA715087 Plunger 1
19 CA715035 Plunger 1
20 CA715026 Plunger 1
21 CA119143 Plunger 1
3 CA119099 Wrench 1
4 CA715022 Wrench 1
5 CA715380 Kit 1
8 CA715167 Plunger 1
9 CA715028 Plunger 1
10 CA715391 Plunger 1
Disassembly and
E
assembly of rear axel 11 CA119033 Interchangeable handle 1
12 CA715056 Kit 1
13 CA715055 Kit 1
14 CA715466 Plunger 1
15 CA119187 Plunger 1
16 CA715467 Plunger 1
17 CA715026 Plunger 1
18 CA119143 Plunger 1
ENGINE COMPONENTS
Remark
As for removal, installation, disassembly and assembly of engine components (see the "ENGINE SHOP MANUAL".
GOVERNOR ASSEMBLY
THERMOSTAT ASSEMBLY
TURBOCHARGER ASSEMBLY
LOCKING PROCEDURES
In illustration (A) the front end loader cylinder lock (1) must be
used any time you will be performing maintenance on the machine
with the front end loader raised. To use the cylinder lock:
2. Using both hands lower the lock unit (1) down from it’s storage
position and remove it from the lift arm.
3. Raise the front end loader unit completely in the air extending
the lifting cylinders.
5. Insert the safety pin (2) completely into the pre-drilled holes
and lock the pin in place with the smaller pin provided.
6. Slowly lower the front end loader unit until it makes contact
with the cylinder lock.
STARTER MOTOR
REMOVAL
1. With the front end loader raised and secured in place, stop the
engine and set the parking brake.
2. Cut off the electrical supply to the system using the main electrical
disconnect switch (1).
5. Loosen the two bolts (4) holding the starter in place and
carefully remove the starter motor (5)
Remark
Do not let the starter hang by the wiring harness, damage to
the wiring may result. Remove the wiring first before removing
the starter motor.
INSTALLATION
• Carry out installation in the reverse order of removal.
ALTERNATOR
REMOVAL
1. With the front end loader raised and secured in place, stop the
engine and set the parking brake.
2. Cut off the electrical supply to the system using the main electrical
disconnect switch (1).
4. Disconnect the exciter cable (3), the connector (4) and (5)
7. Push the alternator (9) toward the engine to remove belt (10).
8. Once the belt (10) is off the alternator, remove support bolt (7) and
lift alternator (9) from the mounting boss.
INSTALLATION
• Carry out installation in the reverse order of removal.
★ Adjust the fan belt tension. For details, see section 20 "TESTING AND ADJUSTMENT".
REFRIGERANT COMPRESSOR
• This procedure is only for machines equipped with an air condition-
ing system.
REMOVAL
1. With the front end loader raised and secured in place, stop the
engine and set the parking brake.
5. Loosen idler pulley bolt (5) and remove belt (6) from compressor.
8. Carefully lift the compressor (7) from the mounting boss along with
the heat shield (14)
INSTALLATION
• Carry out installation in the reverse order of removal.
★ Adjust the compressor belt tension. For details, see section 20 "TESTING AND ADJUSTMENT".
2. Remove the battery cover (1) from the fuel tank (2) housing.
3. Loosen the battery hold down (3) and move the battery (4) out-
wards. Lift the protective flap (5) if needed.
4. Remove the negative (-) terminal clamp first and then the positive
(+) terminal clamp next.
6. Turn the switch (7) over and remove the cables (9) and (10)
★ Make a note of the cable attachment locations.
INSTALLATION
• Carry out installation in the reverse order of removal.
1. When installing the battery cables, hook the positive (+) cable up
first then the negative (-) cable next. Adjust the engine hood guide
(11).
FRONT COUNTERWEIGHT
REMOVAL
2. Loosen the front mounting bolts (1) slightly first. Using a forklift,
position the forks into the openings on the counterweight (2).
3. Tilt the forks back slightly and remove the mounting bolts (1) and
washers (3) carefully.
INSTALLATION
• Carry out installation in the reverse order of removal.
RADIATOR
REMOVAL
1. Remove the engine hood and gas struts (1) first. See “ENGINE
HOOD AND OPERATORS CAB” on page 30-28.
7. Disconnect upper radiator hose (10) and lower radiator hose (11)
from radiator (9)
9. Loosen oil cooler hoses (13) and (14) to allow hydraulic oil to drain
from cooler. When cooler is empty, remove hoses and cap or plug
the ends.
10. Remove plug (16) and drain the transmission oil cooler (17). When
completely drained, disconnect the hoses (18) and cap or plug the
ends.
11. Disconnect the fan shroud (19) from the radiator (9) and slide the
shroud towards the engine.
INSTALLATION
• Carry out installation in the reverse order of removal.
• Once fluid levels are all correct, start the engine and allow it to idle at a low RPM to circulate fluids.
• Bring the engine RPM up to about 1700 RPM for one minute.
• Stop the engine and check for leaks.
REFRIGERANT CONDENSER
REMOVAL
1. Remove the engine hood and gas struts (1) first. See “ENGINE
HOOD AND OPERATORS CAB” on page 30-28.
4. Once system is completely discharged, remove lines (3) and (4) and
cap them immediately.
7. Remove mounting bolt (5) and lift out the condenser (6).
INSTALLATION
• Carry out installation in the reverse order of removal.
★ Re-charge the air conditioning system.
1. Remove the engine hood and gas struts first. See “ENGINE HOOD
AND OPERATORS CAB” on page 30-28.
3. Loosen oil cooler hoses (4) and (5) to allow hydraulic oil to drain
from cooler. When cooler is empty, remove hoses and cap the ends.
4. Remove mounting bolts (7) that hold oil cooler (6) to radiator (8)
5. Remove nuts and washers (9), then remove support mounting (10)
INSTALLATION
• Carry out installation in the reverse order of removal.
1. Remove the engine hood and gas struts first. See “ENGINE HOOD
AND OPERATORS CAB” on page 30-28.
2. Loosen the clamp (1) from the hose (2) on the radiator (3)
3. Remove the four nuts (4) and remove the oil cooler (5)
INSTALLATION
• Carry out installation in the reverse order of removal.
• Once fluid levels are all correct, start the engine and allow it to idle at a low RPM to circulate fluids.
• Bring the engine RPM up to about 1700 RPM for one minute.
• Stop the engine and check for leaks.
MUFFLER
REMOVAL
1. Loosen the exhaust clamp (1) and remove it from the stack pipe (2)
2. Remove the four bolts (6) and remove the complete muffler (7).
INSTALLATION
• Carry out installation in the reverse order of removal.
★ Replace all gaskets with new.
EXHAUST STACK
REMOVAL
1. Loosen the exhaust clamp (1) and remove it from the stack pipe (2)
2. Remove the three lower bolts (3) from the pipe flange (4)
3. Holding the exhaust stack (7), remove the last bolt from the mount-
ing.
INSTALLATION
• Carry out installation in the reverse order of removal.
ENGINE HOOD
REMOVAL
1. Open hood (1) and remove safety pins (2), then disconnect gas
struts (3).
3. Remove bolts (4) from the bracket and lift hood (1) straight up and
out.
INSTALLATION
• Carry out installation in the reverse order of removal.
★ Check the hood striker (5) alignment. Adjust if necessary.
OPERATORS CAB
REMOVAL
WARNING! Be sure all work equipment is lowered to the ground. Turn the electrical supply off
using the disconnect switch. On machines equipped with air conditioning, capture
and recycle all refrigerants before proceeding with any removal procedures.
1. Disconnect the throttle linkage and accelerator pedal cable (1) from
the injection pump mounting support (2).
2. Disconnect the parking brake cable (4) and the differential lock
tube (5) from the rear axel (3). Cap the opening.
3. Disconnect the brake lines (6) from the rear axle (3).
★ Cap the openings and mark the line locations and lines.
★ Cap the openings and mark the line locations and lines.
5. Disconnect the steering valve lines (8, 9 and 10) from the valve.
★ Cap the openings and mark the line locations and lines.
7. Disconnect the five connectors (14) from the sensor, the speed con-
trol connector (15) and the solenoid connector (16) from the trans-
mission.
15. Remove the lower left guard from the bottom of the cab and discon-
nect connector (31) from the fuel level indicator.
16. Remove the floor mat (32) and fender trim piece (33).
★ Push the boot on the shiftier lever (34) down into the trim piece
(33).
18. Remove the self-locking nuts (37) and the four fasteners that secure
the cab in place.
19. Disconnect hoses (38) and (39) from the control valve (40) and cap
all openings.
20. Remove the protective plugs and install two eyebolts "A" into the
threaded holes on the cab.
21. Using the tool shown in the illustration, carefully lift the cab (41)
off the frame.
22. Slowly raise the cab making sure the electrical leads and control
levers clear the chassis frame.
INSTALLATION
• Carry out installation in the reverse order of removal.
★ Bleed the air from the brake system. For details, see section 20
"TESTING AND ADJUSTMENT".
★ Bleed the air from the steering circuit. For details, see section 20 "TESTING AND ADJUSTMENT".
REMOVAL
★ On machines equipped with air conditioning, capture and recy-
cle refrigerants first, then proceed with removing the system.
4. Disconnect heater hoses (5) and (6) and cap hose openings.
6. Disconnect piping (11) and (12) from expansion valve (9) and dryer
(10). Cap all openings.
8. Remove the four fasteners (13) and remove the unit (3) carefully.
INSTALLATION
• Carry out installation in the reverse order of removal.
★ Re-charge the air conditioning system.
1. Start the engine and check for leaks and system operation.
FUEL TANK
REMOVAL
1. Remove the lower left guard shield (1) from the cab.
2. Remove tank fill cap (2) to facilitate draining the fuel tank if
needed.
3. Remove hose clamp support nut (4) and move hoses out of the way.
5. Remove the battery cover (1) from the fuel tank (2) housing.
6. Disconnect (13) the fuel level indicator connector (12) and supply
pump connector (14).
7. Loosen the battery hold down (3) and move the battery (4) out-
wards. Lift the protective flap (5) if needed.
8. Remove the negative (-) terminal clamp first and then the positive
(+) terminal clamp next.
10. Disconnect the supply and return lines (15) and (16) and cap openings.
★ Mark hose locations and hoses for proper reassembly.
12. Support the fuel tank (3) and remove the four retaining bolts (19).
INSTALLATION
• Carry out installation in the reverse order of removal.
1. Bleed air from the fuel circuit then start the engine.
HYDRAULIC TANK
REMOVAL
2. Remove the lower right guard (1) and step plate (2).
3. Remove the fill plug (3) and prepare to drain the hydraulic tank (4).
4. Disconnect the lower suction line (5) and hoses (6) from the tank
(1). Cap or plug all openings.
5. Disconnect the upper lines (7), (8) and (9) and remove the check
valve (10) and T- adapter piece (11).
6. Support the tank (4) and remove the four retaining bolts (12).
INSTALLATION
• Carry out installation in the reverse order of removal.
1. Bleed air from the hydraulic circuit then start the engine. For details, see section 20 "TESTING AND ADJUSTMENT".
★ Stop the engine and check oil level.
1. Lower all work equipment to the ground and turn the electrical sup-
ply off.
★ On machines equipped with air conditioning, capture and recycle refrigerants first, then proceed with disconnecting
the system.
9. Lift gearshift boot (3) and disconnect de clutch switch (4). Remove
transmission shiftier lever (5).
14. Disconnect the load sensing line (12) and the delivery line (13)
from valve (14). Cap or plug all openings.
15. Disconnect the transmission unit (15), solenoid valve (17), connec-
tors (16), ground strap (18), oil cooler lines (19) and the wiring har-
ness clamps (20). Cap or plug all openings.
19. Disconnect cable (26) from cold start equipment, cab heater hose
support (27) and fuel tank back-flow line (28)
20. Disconnect the throttle and accelerator cables (29) from the support
(30).
21. Disconnect the fuel lines (32) from the water separator (31) and cap
or plug all openings.
27. Remove support shield (42) and slide it back towards the engine.
28. Disconnect the muffler clamp (1) from the pipe (2).
30. Apply slight tension to the chains and measure and adjust them for
a proper lift.
31. Loosen and remove nuts (47) from support grommets (48) and
remove bolts (49).
INSTALLATION
• Carry out installation in the reverse order of removal.
★ Fill the pump housing and lines. For details, see section 20 "TESTING AND ADJUSTMENT".
2. Start the engine, bleed the fuel system and check for leaks in all systems.
PISTON PUMP
REMOVAL
1. Lower all work equipment to the ground and turn the electrical sup-
ply off.
4. Disconnect suction hose (2) and drain line (3) from piston pump
(1). Cap or plug all openings.
5. Disconnect delivery line (4) and load sensing signal line (5). Cap or
plug all openings.
9. Remove two mounting bolts (8) and then carefully remove pump
(1).
INSTALLATION
• Carry out installation in the reverse order of removal.
★ Fill the pump housing and lines. For details, see section 20 "TESTING AND ADJUSTMENT".
TRANSMISSION
REMOVAL
1. Lower all work equipment to the ground and turn the electrical sup-
ply off.
5. Lift the gearshift boot (1) and disconnect connector (2) from the
dialectic switch. Remove the gear shift lever (3).
8. Remove cover (6) and six retaining bolts (7) from flex plate (8) and
flywheel.
13. Remove nuts (15), bolts (16), and rubber grommets (17)
14. Remove transmission support (18) and attach support brackets "C".
15. Using lifting tool "B" and spacers "A" secure the transmission in
place with mountings "C".
17. Carefully slide transmission (20) back and lower it until it is all the
way down on the jack.
INSTALLATION
• Carry out installation in the reverse order of removal.
★ Fill the pump housing and lines. For details, see section 20 "TESTING AND ADJUSTMENT".
through
TORQUE CONVERTER
REMOVAL
1. Lower all work equipment to the ground and turn the electrical supply off.
6. Carefully slide the converter (1) off the transmission (2) input shaft.
INSTALLATION
• Carry out installation in the reverse order of removal.
★ When installing the converter on to the input shaft, rotate the converter to the right then left while holding it square
with the shaft until it slides in place. Be sure it is seated in the bell housing.
★ Do not force the converter into the transmission housing, damage to the front pump may result. Once the converter is
in place, retain it in place to keep it from falling out transmission.
.
Remark
If you will be using a new or rebuilt converter, be sure to fill the converter with transmission fluid before
installing it in to the transmission.
STEERING COLUMN
REMOVAL
1. Lower all work equipment to the ground and release all residual
hydraulic pressure from the system.
3. Disconnect the five supply lines (2) from the steering valve (1). Cap
or plug any openings.
5. Raise the column boot (4) and disconnect the connectors (5) and (6)
7. Remove the steering column bolts (9) and remove the complete
steering unit (9).
INSTALLATION
• Carry out installation in the reverse order of removal.
1. Start the engine and bleed the air from the system.
2. Raise column boot (1) and disconnect connectors (2) and (3).
3. Remove right cover (4) that hold switches (5) and (6).
5. Remove horn button (8), then steering wheel nut and washer (9).
7. Remove switches (5) and (6) complete with there protective sleeve.
INSTALLATION
• Carry out installation in the reverse order of removal.
2. Remove cap (1) from master cylinder (2) and siphon brake fluid
from the reservoir.
5. Remove the retaining clip (4) that holds the delivery lines (5) in place.
6. Disconnect the brake lines (5) from the master cylinder (6).
7. Remove four mounting bolts (7) and carefully remove master cylinders (6).
★ If only one master cylinder is to be removed, disconnect pressure equalizing line (8).
INSTALLATION
• Carry out installation in the reverse order of removal.
1. Adjust pedal rods (9) to allow full return of the master cylinder pis-
ton
3. Start the engine and operate the machine to test the brakes.
1. Lower all work equipment to the ground and turn the electrical sup-
ply off.
3. Remove floor mat (1) and slide lever boots (2), (3), and (4) up.
6. Disconnect control valve supply and delivery lines (9), (10), (11),
load sensing line (12), and steering line (13). Cap or plug all open-
ings.
★ Be sure to tag or mark line locations and valve body locations
for reassembly.
INSTALLATION
• Carry out installation in the reverse order of removal.
1. Start engine and use the front bucket to raise the machine and front
wheels.
2. Place two stands "A" and some blocks beneath the chassis.
3. Slowly lower the machine onto the blocks, checking that the
wheels remain at least 5 cm (2 in) above the ground.
5. Stop the engine and eliminate residual pressure from all circuits.
For details, see section 20 "TESTING AND ADJUSTMENT".
9. Disconnect lines (5) from the steering cylinder and plug them to
prevent entry of impurities.
10. Disconnect lubrication tube (6) for axle oscillation pin (7).
11. Position a jack "B" and some blocks "C" beneath the axle. Raise
the jack until the blocks under axle arms (3).
★ It should be possible to lower the jack 10 cm (4 in) in order to
disengage axle from the fulcrum supports.
13. Install an eyebolt into the central hole of axle pivot pin (7). Extract
the axle pin.
INSTALLATION
• Carry out installation in the reverse order of removal.
★ Bleed the air from the Load Sensing circuit. For details, see section 20 "TESTING AND ADJUSTMENT".
2. Perform a few steering manoeuvres in both directions to bleed air from the steering circuit.
STEERING CYLINDER
DISASSEMBLY
1. Remove tie rod end (3) nut from steering knuckle and press tie rod
end from the steering knuckle assembly.
★ Don’t beat on end of the threaded tie rod end.
2. Remove tie rod end (4) by loosing nut (5) with a suitable wrench,
then check its condition.
3. Remove bolts (6) from the end cap, then slide the cylinder (7) out
of its housing. If necessary, use a rubber hammer.
★ Remove only parts that need to be overhauled and/or replaced.
4. Remove cylinder end cap (B) from cylinder barrel (10). Remove
the cylinder end cap and rod (9) from the cylinder barrel.
5. Remove all seals and o-rings (11), both from the cylinder end cap
and rod.
ASSEMBLY
1. Assemble new seal rings (1) onto the end cap (2), piston (3), and
cylinder body (4).
3. Install tie rods (5) to ends of the cylinder and tighten with torque
wrench.
4. Instal steering cylinder into the axel, with tie rods (5), already
assembled on the ends.
6. Assemble and tighten the steering cylinder fastening bolts (6) with
torque wrench.
7. Align the tie rod ends (5) so they can be inserted into the steering
knuckle.
★ It is important to unscrew locking nut (7) to perform this oper-
ation
8. Insert tie rod end (8) into the steering knuckle, on the axel housing.
Assemble and tighten lock nut (9) with torque wrench.
9. Tighten lock nut (7) of tie rod (5) only when the toe-in adjustment
has been carried out.
TOE ADJUSTMENT
1. Place two equal one meter long linear bars "A" on the wheel sides
and lock them with two lug nuts on the wheel hub studs.
★ The two bars should be centered in the middle so they are per-
pendicular to the supporting surface and parallel to the pinion
shaft axis. Align the two bars.
2. Measure the distance in mm "M" between the bar ends with a tape
measure.
A. After adjusting, tighten the lock nuts on the tie rod ends.
2. Adjust the alignment tool to 50° and position it on the long bar.
Using the alignment tool adjust the tie rod ends until both wheels
match at a 50° angle.
3. Adjust the steering stop retainer, tighten or loosen special stops (1)
on the steering knuckle, locking them in place with locknut (2).
★ Steer completely towards other side and repeat the same oper-
ations.
WHEEL HUB
OUTER PLANETARY DISASSEMBLY
★ Before draining the oil, position wheel hub (1) with plug (2) in the
upper position and loosen it in order to eliminate any possible inner
pressure, then remove it completely. Turn the wheel hub upside
down till the hole is in the lowest point. Drain the oil completely.
1. Remove fastens (3) and two stud bolts (4) from the planetary car-
rier with a standard wrench.
★ Do not ruin threads of the two stud bolts.
2. Remove planetary carrier from the wheel hub. Position the plane-
tary carrier on a workbench and check its wear conditions.
2. Insert planetary gear (1), rollers (2), upper thrust washers (3), snap
rings (4), and plate (5) onto the planetary carrier pins.
1. Remove steel snap ring (1) from axle shaft (2) by using a suitable
snap ring pliers.
2. Remove and collect the lock ring, sleeve (3), and spacer (4) from
the axle shaft.
4. In order to remove wheel carrier group (6) from its housing, install
at least two fastening screws (5) into the threaded extraction holes
"A".
6. Remove steel lock ring (7) and wheel carrier (6) from planetary
ring gear (8).
★ Check wear conditions of the components.
8. Remove hub (10), using levers and a hammer to facilitate the oper-
ation.
★ Collect bearing cone (11).
9. Position the hub on a flat surface and take seal (12) out.
★ Discard the seal.
10. Take bearing cups (11) and (13) out, on both sides of the hub, using
a hammer and a suitable tool.
11. Remove bearing cone (13) from the steering knuckle housing end,
using a suitable extractor.
ASSEMBLY
2. Insert seal (14) into wheel hub (11) with special tool D21 and a
hammer.
4. Assemble wheel hub (11) on steering knuckle (7) and install the
other bearing cone (12) into position.
6. Preassemble the wheel carrier group (17) and (18) with special
lock ring (19) as shown.
8. Drive the dowel bushings (16) completely flush with the carrier
surface using special tool D1 and a hammer. Assemble wheel car-
rier (20) with bolts (21) and tighten.
9. In the case bearings (22) and (23) are substituted, verify that mea-
surements "A", "B", and "C" are within limits.
10. Slide spacer (24) onto the axle shaft, install sleeve (25) and assem-
bly lock ring (26) by inserting it at the end of the splined hub and
pushing it into its housing.
1. Remove fasteners (14) from upper (15) and lower (16) king pin.
★ Before removing the king pins, secure the steering knuckle
with a hoist or any other supporting device.
3. Remove steering knuckle (17) from the axle beam and short shaft
(18) of the U-Joint.
4. Position swivel housing (17) on a flat surface and take seal (19) out
with a lever.
★ Discard the seal.
5. Invert steering knuckle (17) and take bushing (20) out, using a
hammer and driver.
ASSEMBLY
1. Install bushing (1) into steering nickel (2) with special tool D17
and a hammer or press.
2. Install seal (3) into housing (2) with special tool D18 and a ham-
mer.
★ Fill 3/4 of the cavity with grease.
3. Position lower king pin (4) on a workbench and assemble the cone
(5) with special tool D19. Shim under the bevelled washer on the
upper part. Generously grease the king pin housing with specified
grease.
5. Secure steering knuckle (7) with a rope. Lubricate seal lip and pro-
tect splined end of the axle shaft by wrapping it with thin adhesive
tape to avoid damage to the seal. After assembly, remove the adhe-
sive tape. Assemble steering knuckle on to the axle.
6. Assemble the two king pins, upper (9) and lower (8), then tighten
retaining bolts (10).
2. Take seal (2) out of the axle housing with a pry bar.
★ Discard the seal.
3. Remove cup springs (4) and (8) from the king pin housing in the
axle housing end.
6. Take upper (5) and lower (6) bushings out of king pin housing (7)
with a suitable puller.
ASSEMBLY
1. Install two new bushings (1) (assemble the longer bushing from
pinion side) and two new seal rings (2) into the unit by using spe-
cial tools "D12" and "D13".
2. Assemble upper king pin bushings (3) and (4) on the axle flange
with special tool "D14" and a hammer.
★ To make the assembly easier, it is suggest to cool the ball bear-
ing cup at a temperature less than -100° C (-148° F).
3. install bushing (5) into the axle housing with special tool D15 and a
hammer.
4. Install seal (6) in the steering knuckle with special tool D16 and a
hammer.
★ Fill 3/4 of the cavity with grease.
5. Lubricate bushing (5) and seal lip (6). Insert CV-Joint (7) inside
the axle housing.
★ Be careful not to damage the seal.
REMOVAL
1. Remove fasteners (l) and nut (2) from flange (3). Using a small
chisel, detach the oil seal cover just enough to fit a lever.
2. Remove oil seal cover from the central beam assembly, using two
levers.
3. Remove seal (4) from the oil seal cover, using a suitable tool.
INSTALLATION
1. Install seal (8) in pinion cover (9) with special tool "D11".
4. Before mating the two surfaces make sure they are perfectly clean.
Spread a film of Loctite 510 on the contact surface between the
axle housing and differential carrier. Position differential carrier
(11) on the axle housing. Install and tighten the bolts (12) to the
prescribed torque.
1. Remove two lock bolts (7) to remove two lock retainers (8).
2. Before removing bolts, mark bearing caps (9) and the differential
carrier with permanent reference marks to avoid inverting them
when reassembling the unit. Mark the area between adjustment
nuts and the differential carrier as well.
PINION DISASSEMBLY
5. Collect two washers (5), crush sleeve (6), and the bearing cone (7).
★ Discard the crush sleeve
7. To remove the inner cone of tapered roller bearing (13) from the
pinion (8), using a standard puller and tapered jaw (12).
4. Split the planetary carrier into two halves complete with the com-
ponents.
7. Remove bearing (5) from carrier half (4), using two levers or a
three hold puller.
ASSEMBLY
1. Assemble the new tapered roller bearings (l) on half cases (2),
using special tool "D10" and a hammer.
PINION SET UP
WARNING! Komatsu recommends that all o-rings and seals be replaced with new before assembly.
ASSEMBLY
2. Install the outer bearing cups (1) and (2), using special tool D5 and
a hammer.
Remark
Be sure to install the tapered ends facing away from the
housing.
4. Insert the false pinion with D6, together with its bearings and nut
(4), in the housings. Tighten until all the backlash is eliminated.
8. Install shim (8) onto pinion (7) and press inner bearing (1) using
tool D9.
★ Chamfer on inner diameter of shim must face the gear teeth.
9. Install washer (9), new crush sleeve (10), and then the second
washer (9).
11. Insert new lock washer (11) and new lock nut (4) on the pinion end.
12. Tighten the nut, using wrench "D3" and for pinion retainer "D4".
★ Torque setting is given by the pre loading measurement on
bearings. Tighten the nut gradually.
★ If torque is excessive, the spacer must be replaced and the pro-
cedure repeated. When you check the preload, it is advisable to
tap slightly both pinion end with a soft hammer, to help set the
bearings.
13. Wind a wire line round the pinion, uniformly and without overlap-
ping. Connect it to a load meter and check rotational force "P"
force required to rotate the shaft.
★ Force should be that needed for continual rotation.
★ Do not take into consideration the initial starting force.
14. Using the tools mentioned in step "13", tighten lock nut (4) taking
rotational torque measurements at intervals until the indicated
force "P" has been obtained.
P = 9.2 to 13.7 Nm (7 to 10 lbf ft)
If maximum permissible value is exceeded, a new spacer must be
installed, and all the bearing pre-loading operations must be
repeated.
2. Place the differential bearing caps (3) and bolts in their correct
location. Check the reference marks. Tighten bolts (4) slightly.
3. Assemble the two adjustment ring (5) into the differential support
with tool "D2". Preload the differential bearings slightly. Tap
lightly with a soft hammer to properly set the bearings in position.
★ Take care not to reverse the nuts; align the previously traced
reference marks.
A. Coat both surfaces of the teeth and ring gear with a layout blu-
ing.
10. Torque bolts (4) after ring and pinion set-up is complete.
11. Once adjustments have been completed, install the adjuster locks
(6) and bolts (7).
REAR AXLE
REMOVAL
1. Lower outriggers (l) in order to raise the rear wheels (2) approxi-
mately 5 cm (2 in).
4. For safety, rest the backhoe bucket with back resting on the ground,
keeping the arm vertical. Also lower front bucket on the ground.
5. Stop engine and completely release any residual pressures from all
the circuits. (For-details, see section "2O TESTING AND
ADJUSTMENTS").
6. Disconnect parking brake cable (4) and differential lock tube (5)
from rear axle (3).
★ Plug all openings to prevent entry of impurities.
10. Place jacks "B" and some blocks beneath axle (3). Raise the jack
until the blocks can be positioned under the axle.
★ Loosen nuts (9) and plates (10) that secure the axle.
★ It should be possible to lower the jack by approximately 20 cm
(8 in).
11. Remove lock nuts (9), plates (10), and mounting bolts (11).
12. Lower the jack until axle (3) is disengaged from the chassis.
INSTALLATION
• Carry out installation in the reverse order of removal.
★ Adjust stroke of the parking brake lever. For details, see section 20 "TESTING AND ADJUSTMENT".
★ Bleed air from the brake circuits. For details, see section 20 "TESTING AND ADJUSTMENT".
Lock nuts (9) for securing axle: 570 Nm (420 lbf ft)
DISASSEMBLY
★ Before draining the oil, position the hub with plug in the upper
position and loosen it in order to eliminate any possible inner pres-
sure, then remove the plug completely.
★ Turn the hub upside down till the hole at the lowest point.
★ Drain the oil completely.
2. Remove planetary carrier (2) from wheel hub (3). Place the plane-
tary carrier on a table and check its wear conditions.
4. To replace planetary gears (5), remove bolt (6) and washers (7) and
(8).
★ Treat pin (9) with care.
5. Remove planetary gear (5) from its seat, taking care not to lose
rollers (10) thrust washer (11) and (12).
★ If pins (13) on the pinion gears are in poor condition, replace
the entire planetary train.
★ If half shaft stop (14) is worn, replace the entire planetary car-
rier.
2. Insert all the rollers (3) into planetary gears (4), then add two thrust
washers (5) and (6).
★ The first thrust washer must be aligned with the dowel pin.
3. Attach planetary gears (4) with bolts (7) and tighten with a torque
wrench.
1. Remove the short shaft. Remove bolts (1) from the wheel and hub
lock ring (2).
2. To remove hub lock ring (2) from its housing, install two of the
bolts (1) in the threaded extraction holes "A".
3. Remove hub lock ring gear (2), together with the planetary ring
gear (3).
4. Remove steel ring (4) and hub (2) from planetary set (3).
5. Only if necessary, remove centering bushings (5) from the hub lock
ring gear with a hammer and special tool El.
7. Place the hub on a flat surface, and remove seal (8) with a lever.
★ Discard seal (8).
8. Remove bearing cups (9) and (10), on both sides of the hub, using a
hammer and a suitable tool. Remove bearing cone (10) from the
housing end, using a suitable extractor.
.
ASSEMBLY
1. Place wheel hub (1) on a work bench and install the two cups of
taper roller bearings (2) and (3) in position using special tool E17
under a press or with a hammer.
2. Using special tool E18 and a hammer insert seal (4) into the wheel
hub.
3. Assemble the cone of taper roller bearing (3) onto the end of axle
housing (5).
4. Assemble wheel hub (1) onto the end of axle housing (5), then
install the cone of taper roller bearing (2) into position.
6. Preassemble wheel carrier group (8), planetary ring gear (9), with
special snap ring (10) as shown.
7. Assembly wheel carrier group (8) onto wheel hub (1) using the two
projecting bushings (7) as dowel pins.
8. Insert wheel carrier bolts (11), with special tool E1 and a hammer
force the two projecting bushings (7) to the carrier surface level.
Then using a torque wrench tighten bolts (11).
2. In order to replace the axle housing, bushing (2) must be cut with a
chisel.
★ Do not ruin the bushing seat
7. Remove o-ring (4) from oil passage and check its condition.
Remove the long axle shaft (5) and sleeve. Remove the snap ring
from the sleeve.
9. Remove plates (7) and counter disk (8) being careful as to how the
different parts are positioned.
10. Remove brake splined sleeve (9), locating the indent position.
★ The brake splined sleeve should be reassembled in the same
position and order as before disassembling.
13. Remove o-ring (13) from its housing and discard it.
14. Remove o-ring (14) from the two oil supply holes and discard
them.
BRAKE CONTROL
DISASSEMBLY
2. Loosen locknut (1) and remove the adjusting screw on the support
bracket (2). Remove the adjusting screw.
5. Place alignment marks on lever (4) and shaft (6) for use during re-
installation.
8. Remove spring 7.
12. Place alignment mark on cam (11) near the set screw (12), align
with top of the roll pin, for use during assembly.
14. Remove the shaft set screw (13), be careful not to lose ball (14).
18. Remove the brake mechanism upper bolts (17), then remove
springs (18) and bushings (19)
22. Remove and discard o-rings (26) and (27) from piston (25).
26. Removing bearing cup (31) with a hammer and suitable tool.
ASSEMBLY
2. When the shaft is inserted into the cam, align the reference marks
with cam setscrew (4) hole.
10. Insert spacer (11), washer (10), and spring (12) on the shaft end.
11. Using the reference marks placed during disassembly, insert brake
control lever (13).
1. Insert the first odd shaped brake plate (1), in the indicated position
compared to the cam position.
2. Check to be sure that the friction discs and plates do not show any
sign of burning, if so, replace them. Also check friction disc wear,
and replace if required.
★ Friction disc thickness: minimum 4.03 mm (0.159 in)
4. Insert long half shaft (5) into axle housing (6). Position lock ring
(7) on the inner seat of sleeve (8). Then insert sleeve (8) onto long
half shaft (5).
★ Sleeve (8) must be inserted with the inner lock ring (7) resting
against long half shaft (5).
5. Before assembling the axle ends, check the reference marks made
at disassembly.
6. Using special tool E15, drive bushing (9) into the seat on the axle
end housing.
8. Connect axle end housing to the flange with bolts (10) and tighten
with a torque wrench.
9. Lubricate the lip of seal (11), and using special tool E16 insert into
the seat of axle housing.
10. Insert short half shaft (12) into the axle assembly.
11. To set the brake, put the system under pressure. Use compressed air
at high pressure blown through the breather.
★ The brake system (piston, discs, self adjustment kit, and brake
mechanism return kit) should be set before moving the brake
control levers.
14. Release the brake control levers, insert bolt (13) and washers (14).
Tighten with a torque wrench.
16. Check to be sure that in the rest position, the measurement between
the middle of connection holes at the lever ends is higher than the
minimum value of 320 mm (12.598 in).
18. Tighten adjusting bolts (17) the same distance to reach the range
for the levers in rest position. 320 - 329.5 mm (12.598 - 12.972 in)
1. Place the differential in a vise, remove all the bolts (1) from ring
gear (2).
★ This will free both carrier housing halves, be careful not to
drop the internal components.
2. Separate the carrier case halves (3) complete with the components.
★ Mark the two case halves before separation, in order to reas-
semble them in the same position as before separation.
PINION DISASSEMBLY
1. Remove snap ring (1) and slide flange (2) off, then remove o-ring
(3) and shim (4).
5. Remove tabbed washer (7), then remove pinion (8) out of its hous-
ing by tapping with a hammer (with a soft material head) on the
splined end.
6. Remove washers (9), crush sleeve (10), and tapered roller bearing
cones (11).
★ Always replace crush sleeve (10) with new when reassem-
bling.
7. Remove bearing cone (12) from the end of the pinion (8) using a
suitable extractor.
8. Remove adjusting shim (13) placed under the bearing, and check
its wear condition.
10. Extract differential lock fork (22) from the central housing.
★ Check the integrity of all components disassembled.
11. Take the roller bearing cups out of the housing (23), using a ham-
mer and drift pin.
PINION ASSEMBLY
WARNING! Komatsu recommends that all o-rings and seals be replaced with new before assembly.
2. Using the special tools included in kit E5, insert the tapered roller
bearing cups into their housings.
3. Measure the distance using the special tools in kits E5 and E6,
respectively called "false pinion" and "false differential case".
4. Insert the "false pinion" together with bearings (2) and (3) and nut
(4), in housing for the bearings. Tighten till the backlash is elimi-
nated.
5. Check for correct positioning of the right and left flanges, using the
reference marks on them and the housing. Assemble the two brake
flanges (5), and install them with bolts (6) M14 X 120.
6. Insert the "false differential case" with E6 into the housing to mea-
sure the distance.
★ Check that the false case is inserted into both brake flange
housings (5).
X-V=S
9. Remove the false pinion, bearings (2) and (3), and nut (4) from the
housing (1). Disassemble the false differential case from flanges
(5), then remove the bolts and flanges.
10. Install shim (8) onto pinion (7), and press the inner bearing (2),
using special tool E8.
★ Always use new crush sleeve.
11. Insert pinion (7) into the housing (1) and second bearing cone (3)
into the pinion end.
★ Use special tool E8 and a hammer to install bearing into posi-
tion.
13. Install the nut, using special tools wrench E3 and pinion retainer
E4.
★ Torque setting is given by the pre load measurement on the
bearings.
★ Tighten the nut step by step.
★ If it is tightened too much, replace the crush sleeve with new
and repeat the procedure.
14. Carry out the pre load measurement "P" of the pinion roller bear-
ings, using a dynamometer with the cord wound on the 34.87 mm
(1.373 in) diameter of the pinion spline.
★ This adjustment is carried out by increasing the torque setting
gradually, being careful not to exceed it.
★ All pre loads should be measured without the seal.
15. Once the preload value is obtained, lock the nut using a hammer
and punch.
DIFFERENTIAL CARRIER
ASSEMBLY
3. Position ring gear (3), apply loctite 270 (on the bolt threads), then
tighten bolts (4).
1. Position the flange on a flat surface and using special tool E10,
interchangeable handle E11 and a hammer, install the cup of
tapered roller bearing (1) into position.
2. Locate brake piston (3). Push pin (2) into the self adjustment hous-
ing till they are level with the piston supporting inner surface.
Insert o-rings (4) and (5) on the piston. Lubricate the surface, pis-
ton flange with a light layer of grease.
6. Insert the oil vent tube, then insert differential locking fork into the
housing.
★ Do not invert the locking fork assembly position.
7. Lubricate and insert new o-ring (11) on the flange, then assemble
the left flange to the housing.
9. Before adjusting the ring gear bearings pre load, fasten the brake
cylinders with two bolts (M14 X 120).
Once the adjustments have been made, remove the M14 X 120
bolts.
★ Assemble the differential housing with its relative compo-
nents.
10. Position the flange housing on a flat surface, then insert the differ-
ential housing.
12. Insert spring (20) and bushing (21) onto shaft (12), working in the
housing on the opposite side of the gear, assemble snap ring (22) in
its housing.
13. Insert piston (24) with o-rings (23) and (25) into cylinder (27).
Assemble o-ring (26) onto cylinder (27), then insert the support
into the housing fastening them with bolts (28) and tighten with a
torque wrench.
★ Lubricate all the o-rings, piston, and inner surface of the cylin-
der with oil.
14. Push lock ring (13) onto the differential locking devise (12), by
working in the housing on the bevel gear side. Then let lock ring
(13) slide along shaft (12) with a suitable tool. Insert spacer (15)
and spring (16) onto the shaft. Lubricate o-ring (17) with oil and
assemble to cap (18). Assemble cap (18) to the housing at the flat-
tened end of the shaft with two bolts (19).
Perform the adjustment on the two ring gear nuts with special tool
E2. Adjust the nuts remembering that:
• If the measured backlash is less than the given tolerance range,
tighten the nut from the side opposite to the ring gear and
loosen the opposite one the same distance.
• If the measured backlash is higher than the given tolerance
range, tighten the nut from the side of the ring gear and loosen
the opposite one the same distance.
17. Once the pinion ring gear backlash has been adjusted, also check
that there is a minimum pre load on the differential housing bear-
ings. Repeat the sequence till the correct backlash is reached.
18. Once the pinion gear backlash has been established, measure the
total pre load "T" of the bearings (pinion ring gear system), using
a dynamometer whose cord "B" is wound on diameter 34.87 mm
(1.373 in) of the pinion spline shaft.
★ Force required: (P+3.73) < T < (P+5.55) daN P = the force
found for the pinion
★ The force should be that of continual rotation. Do not take the
thrust force into consideration.
A. Tighten both the lock nuts to the same extent to increase the
force "T".
B. Loosen both lock nuts to the same extent to decrease force "T".
20. Check the centering of contact area using the following procedure:
A. Coat both surfaces of the ring gear with lay out bluing.
21. Insert retainer nut (29), turning the gear nut slightly to align it with
the retainer. Tighten bolt (30) of the nut with a torque wrench.
23. Coat the seal lip and o-ring with, then insert them on the pinion
shaft together with shim, new o-ring, and install flange. Secure the
assembled parts with snap ring (4).
1. Sling cylinder (1), insert blocks (A) between boom (2) and fulcrum
lever spacer (3).
2. Remove the snap ring and the internal spacer for piston attachment pin (4).
3. Remove pin (4) in order to free piston head (5), but leave fulcrum
lever (3) attached.
5. Disconnect hydraulic hoses (6) and (7), then plug them to prevent
the entry of impurities.
★ Start the engine and run at low idle, operate the control levers and extend the rod to align the pin holes.
1. Start the engine and bleed air from the cylinders. For details, see section 20 "TESTING AND ADJUSTMENT".
★ After bleeding the cylinders, check the oil level
REMOVAL
2. Place a sling around cylinder (5) and insert block (A) between
spacer (6) of the ram fulcrum lever (7) and link (8).
3. Remove the snap ring and internal retaining spacer for cylinder
attachment pin (9).
7. Disconnect hydraulic hoses (13) and (14), then plug them to pre-
vent the entry of impurities.
INSTALLATION
• Carry out installation in the reverse order of removal.
• Install the hoses without twisting or interference.
★ Start the engine and run at low idle, operate the control levers and extend the ram to align the pin holes.
1. Start the engine and bleed air from the cylinders. For details, see section 20 "TESTING AND ADJUSTMENT".
★ After bleeding the cylinders, check the oil level
FRONT BUCKET
REMOVAL
WARNING! Stop the machine on level ground, lower all work equipment to the ground, and shut off
the engine. Then apply the parking brake and put blocks under the wheels to prevent the
machine from moving.
3. Start the engine, put the machine in reverse gear, and back up to
disengage boom (6).
INSTALLATION
• Carry out installation in the reverse order of removal.
• Install the hoses without twisting or interference.
★ Start the engine and run at low idle, operate the control levers and extend the ram to align the pin holes.
WARNING! When aliening the position of the pin hole use a bar. NEVER insert your fingers in the
pin hole.
REMOVAL
2. Disconnect boom cylinders (2) from boom (1) and rest them on
wooden blocks (A) placed on the front axle.
3. Open front hood (3) and remove bolts (4) that lock the axle pivot
pins to the boom (1). Close the front hood.
5. Using a puller, remove the axle oscillation pins (5) of boom (1).
6. Start the engine, put the machine into reverse gear, back the
machine up, until the boom is disengaged and clears.
INSTALLATION
• Carry out installation in the reverse order of removal.
• Install the hoses without twisting or interference.
★ Start the engine and run at low idle, operate the control levers and extend the cylinder ram to align the pin holes.
WARNING! When aliening the position of the pin hole use a bar. NEVER insert your fingers into
the pin hole.
• Start the engine and bleed air from the cylinders. For details, see section 20 "TESTING AND ADJUSTMENT".
★ After bleeding the cylinders, check the oil level
REMOVAL
1. Swing the backhoe completely to the right of the machine, rotate
the boom approximately 45° to the right.
2. Lower outriggers to the ground, open the bucket and rest the arm
on a block, keeping it perpendicular to the ground.
3. Rest the bucket on the ground, release the backhoe plate and shut
the engine off.
4. Remove lower window (1) from the cab, and completely raise the
upper window.
6. Raise control lever boots (3), remove bolts (4) and cover (5).
★ If any optional devises have been installed, unhook spool com-
mand tie rod (6), pedal (7), and support (8).
9. Sling control valve (10), and attach to a hoist. Apply slight tension
to the sling.
10. Remove four mounting bolts (13), then remove control valve (10).
INSTALLATION
• Carry out installation in the reverse order of removal.
• Install the hoses without twisting or interference.
★
• Start the engine and bleed air from the load sensing circuits and from hydraulic circuits of all the actuators. For details, see
section 20 "TESTING AND ADJUSTMENT".
★ After bleeding the cylinders, check the oil level
REMOVAL
1. Remove the lubrication grease fitting and the extension.
3. Sling boom cylinder (4), and attach to a hoist. Apply slight tension
to the sling.
6. Disconnect hydraulic hoses (7) and (8), then plug them to prevent
entry of impurities.
INSTALLATION
30-136 2 WB140-2N WB150-2N
DISASSEMBLY AND ASSEMBLY BACKHOE BOOM CYLINDER
• Carry out installation in the reverse order of removal.
• Install the hoses without twisting or interference.
★ Start the engine and run at low idle, operate the control levers and extend the ram to align the pin holes.
WARNING! When aliening the position of the pin hole use a bar. NEVER insert your fingers into
the pin hole.
• Start the engine and bleed air from the cylinders. For details, see section 20 "TESTING AND ADJUSTMENT".
★ After bleeding the cylinders, check the oil level
REMOVAL
1. Extend arm (1) completely and fully open bucket (2).
★ Lower arm (3) until the joint between the arm and boom is
resting on stand (A) about 90 cm (35 in) high, and the tip of
arm (1) is resting on block (B) about 10 cm (4 in) high (as
shown). Rest the bucket teeth on the ground.
2. Sling arm cylinder (4), and attach to a hoist. Apply slight tension to
the sling.
5. Disconnect hydraulic hoses (8) and (9), then plug them to prevent
entry of impurities.
INSTALLATION
• Carry out installation in the reverse order of removal.
• Install the hoses without twisting or interference.
★ Start the engine and run at low idle, operate the control levers and extend the ram to align the pin holes.
WARNING! When aliening the position of the pin hole use a bar. NEVER insert your fingers into
the pin hole.
• Start the engine and bleed air from the cylinders. For details, see section 20 "TESTING AND ADJUSTMENT".
★ After bleeding the cylinders, check the oil level
REMOVAL
1. Extend arm (1) completely.
★ Lower arm (1) until is resting on stand (A) about 40 cm. (16
in) high. Extend telescopic arm (2) until it is resting on block
(B), and rest the bucket teeth on the ground.
2. Stop the engine and release cylinder (3) pressure by moving the
command pedal several times.
3. Sling arm cylinder (3), and attach to a hoist. Apply slight tension to
the sling.
7. Disconnect hydraulic hoses (6), (7), (8), and (9), then plug them to
prevent entry of impurities.
INSTALLATION
• Carry out installation in the reverse order of removal.
• Install the hoses without twisting or interference.
★ Start the engine and run at low idle, operate the control levers and extend the ram to align the pin holes.
WARNING! When aliening the position of the pin hole use a bar. NEVER insert your fingers into
the pin hole.
• Start the engine and bleed air from the cylinders. For details, see section 20 "TESTING AND ADJUSTMENT".
★ After bleeding the cylinders, check the oil level
REMOVAL
1. Extend arm (1) completely and fully open bucket (2).
★ Lower arm (3) until the joint between the arm and boom is
resting on stand (A) about 90 cm (35 in) high, and the tip of
arm (1) is resting on block (B) about 10 cm (4 in) high (as
shown). Rest the bucket teeth on the ground.
2. Stop the engine and release the pressure in cylinder (4) by moving
the control lever several times.
3. Sling arm cylinder (4), and attach to a hoist. Apply slight tension to
the sling.
INSTALLATION
• Carry out installation in the reverse order of removal.
• Install the hoses without twisting or interference.
★ Start the engine and run at low idle, operate the control levers and extend the ram to align the pin holes.
WARNING! When aliening the position of the pin hole use a bar. NEVER insert your fingers into
the pin hole.
• Start the engine and bleed air from the cylinders. For details, see section 20 "TESTING AND ADJUSTMENT".
★ After bleeding the cylinders, check the oil level
OUTRIGGER CYLINDERS
REMOVAL
2. Sling outrigger cylinder (1), and attach to a hoist. Apply slight ten-
sion to the sling.
★ Leave hoses and tubes free.
3. Remove nut (2) and bolt (3). Then draw out pin (4) until the ram
head is disengaged.
5. Disconnect hydraulic hoses (6) and (7), then plug them to prevent
entry of impurities.
INSTALLATION
• Carry out installation in the reverse order of removal.
• Install the hoses without twisting or interference.
★ Start the engine and run at low idle, operate the control levers and extend the ram to align the pin holes.
WARNING! When aliening the position of the pin hole use a bar. NEVER insert your fingers into
the pin hole.
• Start the engine and bleed air from the cylinders. For details, see section 20 "TESTING AND ADJUSTMENT".
★ After bleeding the cylinders, check the oil level
REMOVAL
WARNING! Position the backhoe with the equipment centered, arm vertical, and back of the bucket
resting on the ground.
WARNING! Stop the machine on level ground, lower all work equipment to the ground, and shut off
the engine. Then apply the parking brake and put blocks under the wheels to prevent the
machine from moving.
1. Stop the engine and release cylinder pressure by moving the con-
trol levers several times.
3. Disconnect hydraulic hoses (4) from cylinder (3), then plug them
to prevent entry of impurities.
4. Remove bolts (5), then vertically remove upper support (6) of the
cylinder mounting.
6. Rotate the cylinders to disengage ram ends from swing bracket (9),
then remove cylinders (3).
INSTALLATION
• Carry out installation in the reverse order of removal.
• Install the hoses without twisting or interference.
1. Mount cylinders (3) and upper support (6). Secure support (6) with
four bolts (5).
3. Start the engine and swing the boom in order to center one of two pins (8). Secure the 1st pin with bolt (7). Repeat this
step for the other pin.
WARNING! When aliening the position of the pin hole use a bar. NEVER insert your fingers into the
pin hole.
• Start the engine and bleed air from the cylinders. For details, see section 20 "TESTING AND ADJUSTMENT".
★ After bleeding the cylinders, check the oil level
DISASSEMBLY
1. Place cylinder (1) on special tool A1.
2. Using special wrenches A4, A5, and A6 unscrew gland nut (4) and
extract it from cylinder (1).
7. For boom cylinder piston ram remove ball bearings (8) and cushion
plunger (9).
Arm 55 mm
Bucket 55 mm
Outriggers 65 mm
Telescopic Arm 46 mm
★ The seals, dust seals, and guide rings can not be reused. Discard
and replace with new.
★ Carefully check piston hexagon (11). If both caulked areas show
wear, the piston hexagon must be replaced.
ASSEMBLY
★ Be extremely careful not to damage the seals and sliding surfaces.
★ Prepare each individual component before final assembly.
D. Mount o-ring (15) and the anti-extrusion ring (16) on the out-
side of the gland nut.
C. For boom and outrigger pistons only, insert o-ring (28) into the
internal seat.
D. Gauge the diameter of seal (25) for piston (11), mount the
group under a press using tool A3 for the piston diameter.
A. Only for front bucket raise and tilt, boom, arm, bucket, and
outrigger cylinders: Using a press and special tool A2 with the
appropriate diameter, insert bushing (37) into ram (6).
B. Mount bushing A10 of the correct diameter onto the tip of pis-
ton ram (6).
C. Lightly lubricate gland nut seals (4) and slide the group onto
piston ram (6).
E. Remove bushing A10 and mount piston (11) and lock nut (36)
from the tip of cylinder ram (6).
★ Grease the piston threads.
G. Screw the complete piston (11) onto piston ram (6), and secure
it with a torque wrench.
H. Caulk piston (11) to correspond to the slot in cylinder ram (6) not previously used.
4. Cylinder assembly.
C. Mount the two halves of special tool A11 with the appropriate
diameter at the mouth of cylinder body (4).
D. Mount the cylinder body (4) and cylinder ram assembly (6) on
fixture A1.
F. Mount the first guide ring (27) onto the cylinder. Insert part of
the piston into tool A11. For the boom cylinder only: Mount
the second guide ring (27) and fully insert the piston.
★ Insert the piston slowly, in order to calibrate guide rings
(27) without damaging them.
H. Bring cylinder body (4) into position, insert gland nut (1), and
tighten by hand for several turns.
DISASSEMBLY
1. Place cylinder (1) on fixture A1. Engage the fulcrum pins into the suitable support.
2. Using special wrench A6, loosen and completely extract gland nut (2) from cylinder (1).
8. Raise the part caulked for safety purposes, then using special tool A7 unscrew piston (5).
★ Carefully check piston (5). If both caulked areas show wear, the piston must be replaced.
9. Remove snap ring (6) from the piston, then remove ring (7) and scraper ring (8).
★ Make a note for order of assembly for ring (7).
10. Using a puller, remove swing bushings (9) from the cylinder axle oscillation pins.
11. Disassemble the groups by removing all the seals, guard rings, guide rings, and the piston fulcrum bushings.
★ Discard the seals, guard rings, and guide rings. They must be replaced with new.
ASSEMBLY
★ Be extremely careful not to damage the seals and sliding surfaces.
★ Prepare each individual component before final assembly.
3. Mount o-ring (13), anti-extrusion ring (14), and last o-ring (15) of
the front seal.
C. Insert scraper ring (7) and secure the group with snap ring (6).
D. Mount bushing A10 of the correct diameter onto the tip of pis-
ton ram (4).
E. Lightly lubricate gland nut gasket (2) and slide the group onto
piston ram (4).
F. Lubricate o-ring seal (22) and screw piston (5) onto piston ram
(4) by hand several turns.
G. Position the group on tool A1 and tighten the piston (5) with
round prong wrench A7.
A. Secure gland nut (1) to fixture A1. Engage the pivot pins in the suitable support.
C. Mount the two halves of special tool A11 with the appropriate diameter at the mouth of cylinder body (4).
F. Wind the first guide ring (19) around the piston and insert part of the piston into tool A11. Wind the second guide ring
(19) and fully insert the piston.
★ Insert the piston slowly, in order to calibrate guide rings (27) without overheating them.
G. Insert gland nut (2) and tighten it by hand for several turns
H. Using special wrench A6, tighten the gland nut all the way.
K. Using a press and appropriate tool A2, mount swing bushings (9).
REMOVAL
4. Disconnect hydraulic hose (4) that feeds cylinder (5), then plug it
to prevent entry of impurities.
INSTALLATION
• Carry out installation in the reverse order of removal.
• Install the hose (4) without twisting or interference.
1. Start the engine and perform several lock and release manoeuvres to fill the safety cylinder and bleed air from the unit.
For details, see section 20 "TESTING AND ADJUSTMENT".
REMOVAL
1. Extend the arm completely and fully open the bucket. Lower the
equipment until it is resting on the ground.
3. Remove bracket (2) located inside the boom. Disconnect hoses (1)
from the arm cylinder, then plug them to prevent entry of impuri-
ties.
★ Mark hoses to prevent exchanging positions during reconnec-
tion.
5. Sling work equipment (4), and attach to a hoist. Apply slight ten-
sion to the sling.
INSTALLATION
• Carry out installation in the reverse order of removal.
• Install the hoses without twisting or interference.
★ Start the engine and run at low idle, operate the control levers and extend the ram to align the pin holes.
WARNING! When aliening the position of the pin hole use a bar. NEVER insert your fingers into
the pin hole.
• Start the engine and bleed air from the cylinders. For details, see section 20 "TESTING AND ADJUSTMENT".
★ After bleeding the cylinders, check the oil level
BACKHOE BUCKET
REMOVAL
1. Remove safety pin (1) and connecting pin (2) between bucket (3)
and tie rams (4).
2. Remove safety pin (5) then pin (6) that attaches bucket (3) to arm
(7).
INSTALLATION
• Carry out installation in the reverse order of removal.
★ Start the engine and run at low idle, operate the control levers and extend the ram to align the pin holes.
WARNING! When aliening the position of the pin hole use a bar. NEVER insert your fingers into
the pin hole.
BACKHOE ARM
REMOVAL
1. Remove the bucket. See “BACKHOE BUCKET” on page 30-162.
3. Remove lock nut (2) with washers, pin (3), and levers (4).
4. Start the engine and bring the arm into a vertical position, then
lower it to the ground.
5. Stop the engine and release the residual pressure arm cylinder (5).
6. Sling arm cylinder (5), and attach to a hoist. Apply slight tension to
the sling. Remove Bolt (6) and pin (7), then rest cylinder (5) on
block (A).
8. Sling arm (9), and attach to a hoist. Apply slight tension to the
sling. Remove bolts and pin (10).
INSTALLATION
• Carry out installation in the reverse order of removal.
WARNING! When aliening the position of the pin hole use a bar. NEVER insert your fingers into
the pin hole.
★ Completely tighten lock nut (2), then back off one half turn.
★ Start the engine and run at low idle, operate the control levers and extend the ram to align the pin holes.
WARNING! When aliening the position of the pin hole use a bar. NEVER insert your fingers into
the pin hole.
REMOVAL
WARNING! Stop the machine on level ground, lower all work equipment to the ground, and shut off
the engine. Then apply the parking brake and put blocks under the wheels to prevent the
machine from moving.
3. Remove lock nut (2) with the washer, pin (3), then cylinder link
(4).
WARNING! Loosen the oil filler cap slowly to release the pressure inside the hydraulic tank. Then
operate the control levers several times to release the remaining pressure in the
hydraulic lines.
4. Disconnect telescopic arm hoses (5) and (6), the bucket cylinder
hoses (7) and (8), then the auxiliary equipment hoses (9) and (10).
Plug the hoses to prevent entry of impurities.
★ Mark hydraulic hoses (5), (6), (7), (8), (9), and (10) before
separation, in order to reassemble them in the same position as
before separation.
6. Remove the telescopic arm the same as the standard backhoe arm.
See “BACKHOE ARM” on page 30-164.
INSTALLATION
• Carry out installation in the reverse order of removal.
WARNING! When aliening the position of the pin hole use a bar. NEVER insert your fingers into
the pin hole.
★ Completely tighten lock nut (2), then back off one half turn.
INNER ARM
REMOVAL
4. Remove lock nut (4) with washer, pin (5), and links (6).
7. Stop engine and loosen the upper guide adjustment bolts, then the
lower guide adjustment dowel bolts by several turns. Refer to step
7 of “INNER ARM GUIDES” on page -170
★ Loosen the adjustment bolts on both sides.
WARNING! When aliening the position of the pin hole use a bar. NEVER insert your fingers into
the pin hole.
★ Completely tighten lock nut (4), then back off one half turn.
3. Rest outer arm (2) on a trestle (A) about 80 cm (32 in) high.
4. Loosen and remove adjustment bolts (3) with lock washers, then
remove upper guides (4).
6. Slowly raise inner arm (1) until it rests on the supporting surfaces
of the upper guides (4).
7. Loosen nuts (5), then remove lower guide adjustment dowel bolts
(6).
INSTALLATION
• Carry out installation in the reverse order of removal.
1. Adjust the clearances, keeping inner arm (1) aligned with outer
arm (2). For details, see section 20 "TESTING AND ADJUST-
ING."
BACKHOE BOOM
REMOVAL
1. Remove the backhoe arm. See “BACKHOE ARM” on page 30-
164.
3. Start the engine, lower the boom and rest it on a wooden block on
the ground.
6. Sling boom (3) as shown, and attach to a hoist. Apply slight tension
to the sling.
7. Take out snap rings, remove pin (4), then lift and remove boom (3)
INSTALLATION
• Carry out installation in the reverse order of removal.
WARNING! When aliening the position of the pin hole use a bar. NEVER insert your fingers into
the pin hole.
1. Start the engine and bleed air from the cylinders. For details, see section 20 "TESTING AND ADJUSTMENT".
★ After bleeding the cylinders, check the oil level
REMOVAL
1. Remove the backhoe work equipment. See “BACKHOE WORK
EQUIPMENT” on page 30-160.
2. Remove screws (1) and pins (2) that connect swing cylinder (3).
6. Remove bolts (9) and (10), then remove swing bracket axle oscilla-
tion pins (11) and (12).
7. Remove swing bracket (8), being careful not to lose or damage the
clearance adjustment shims (13).
INSTALLATION
• Carry out installation in the reverse order of removal.
WARNING! When aliening the position of the pin hole use a bar. NEVER insert your fingers into
the pin hole.
1. Start the engine and bleed air from the cylinders. For details, see
section 20 "TESTING AND ADJUSTMENT".
★ After bleeding the cylinders, check the oil level
BACKHOE OUTRIGGERS
REMOVAL
INSTALLATION
• Carry out installation in the reverse order of removal.
WARNING! When aliening the position of the pin hole use a bar. NEVER insert your fingers into
the pin hole.
ELECTRICAL SCHEMATIC
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
R/N1
R-N1
N1
N1
N1
N1
N1
N1
N1
N1
N1
N1
R-N1 M-V1 R/N1
N1
N1
N1
L1.5 B-R1.5 A-N1
G-R1
R/N1
A-N1
G1
N1
R/N1
R/N1
R/N1
R/N1
R/N1
R/N1
R/N1
R/N1
R/N1
R/N1
R1
N1
R1
H19
N1
A2.5 G2.5 A-N1 A-R1 A-R1 L-G1.5 R/N1
H10
H12
H13
H14
H22
H24
H25
HA2
H11
H23
WINDSHIELD P1- P3 - P4 -
H9
A A-R1 2 2 6 7 9
H33 H34 A
57
57
1 9 8 5 10
H1 H2 H3 H4 H5 H6 H7
59c
59c
WIPER MOTOR 1 0 1 0
R1
OFF ACC
R1 ACC BR R2 C
1 0
1 9
1 0
1 9
1 0
1 9 1 0 1 9
H20 H32 H21 H30 M
H17 H18
ST
rpm q t∞
NOT CONNECTED S i S i S i NOT CONNECTED
+ +
10
4
S3A 5 10
S4A 7
S6 B +
N1 31
6 3 1 3 5 10
N1 31
5 10 5 10 5 10 5 10
NOT CONNECTED
G/N1
R1
M-N1
Z-N1
A-V1
B/N1
A-B1
M-N1
M-N1
S3L
V-B1
A/V1
V-B1
G-R1
G-R1
Z/B1
L/N1
A-G1
R-V1
R/N1
H/N1
R/N1
B/R1
A/N1
S1
V-N1
B1
S1
V1
V-N1
A1
V-N1
S1L S4L S5L
L/N1
G1
G1
B-R1
N1
R-N1.5
B-R1
B-R1
G-N1
B-R1
A/R1
B-G1
B-G1
L/B1
5 4 3 2 1
0A001283
R6
X24
L-B1
3
6 5 4 3 2 1 2 1
X41
A-R1
XS
2
Z/N1
R/N1
A-N1
G1
N1
G-N1
N1
X33
7
B L-G1.5
A-R1
6
G-N1
B
5
A/R1 4
N1 A-N1 3
B-G1 V-N1
1
2
B-G1 V-N1
1
N1
N1
N1
N1
N1
N1
N1
N1
N1
N1
N1
N1
6
27
A-R1 0A003016 0A001945
A-B1
M-N1
M-N1
G2.5
R-N1.5
G-R1
B/N1
B-R1.5
5
A2.5
A2.5
Z/N1
V-B1
L1.5
L/N1
Z/B1
L/B1
M-V1
A-G1
G1
R6
A-N1
B-R1
R-V1
R/N1
H/N1
R1
R1
N1
N1
N1
V1
S1
A1
G1
N1
1
S1A
0
21 20 19 18 17 16 15 14 13 12 11 10 9 8 7 6 5 4 3 2 1 8 7 6 5 4 3 2 1 5 4 3 2 1
C 4 3 2 1
C
1
X15
Z-N1
X17
X26
X31
Z-B1
R/N1
X18 S10
A-R1
R-N1.5
M-V1
R-G1
B-R1.5
A-G1
G/N1
G/N1
G-R1
A-N1
R/N1
H/N1
R-V1
B/N1
A-B1
L1.5
X29
G2.5
Z/N1
V-B1
C-L1
S-G1
L/N1
Z/B1
N2.5
A2.5
A2.5
L/B1
R6
V1
S1
A1
G1
G1
N1
R1
R1
N1
N1
C-L1
V-N2.5
N0.5
L0.5
N1
R-V1 R-V1
B1
V2.5
A1.5
B1.5
V2.5
N1
B1
5
HEATING MOTOR
N1
M-V1 M-V1 N1
K05 S1 0A003260
M1
4 2
L-B1 3
L-B1
86 87a 87 X39 NOT CONNECTED M/N1
1
A1 A1
S27
V2.5
V2.5
15/1 30/3 L/6 15/1 30/3 L/6
A-B1
2
A-B1 L0.5 Y6 86 87 2 3 4 Y3 0 1 0 1
15/1 30/3 L/6
1
N0.5
C
B
NOT NOT S3 NOT
GEAR SHIFT
R/N1
R/N1
H-G1.5
X45
N0.5
N
C-N1
X25
B-N1
B-N1
R1.5
S-G1
S-G1
X20
N1
N1
S2
L4
V/N1
V/N1
K06
N1
2
3
Z1.5
0A002211 C-N1
A-R1
I
15
4 15 I
H-R1 N1
V-N2.5
V-N2.5
53M 53M
N2.5
5
B-N1
V2.5
B1.5
A1.5
T
C-L1
0 MA
T
D XD2 31
31 D
MI
X19
SM2
A1 A1
9
A-B1 8 A-B1
V-B1 B/V1 C-L1
7
6
H1
C-N1
M-V1 5 M-V1
SM3
R-V1 4 R-G1
3
G/N1 2 G/N1 X28
G/N1 1
G/N1
12 C/B1
JOYSTICK
SM4
11
M-V1 10
G-V1
54D
9
N1 N1
L
8
C-L1
54S
7 M/N1
C-N1
SM6 SM5
6
31
M-B1
49
5
E M/N1
4 E
LIGHTS SWITCH
C/B1
3
C-B1 C-B1
57/58
2
30
N1 M-N1
1 1
A/B1
2
56b
C1
3
V1.5 M-V1
4
G-V1.5 M-N1
56a
5
A-G1
6
L1 B-R1
7 1
H-N1.5 B/R1 C-N1
8 2
FLASHER UNIT
R-N1.5 A-N1
9 3
A1
1
4
L1
XD1 5
6
N1 Y1
7
L/N1
8
2
R-G1
9
A/N1 N1
10
A-G1
11
F 12
A-B1
A/B1
V/N1 F
13
EV4
SX
H-G1.5
G-V1.5
R-N1.5
H-N1.5
R-N1.5
DX
B-R1.5
M-N1
H-R1
A-G1
V-B1
H/N1
Z/N1
A-R1
R/N1
B-R1
Z/B1
R1.5
L/N1
V1.5
L/B1
Z1.5
S1
V1
L1.5
G1
C1
N1
X40
Z-N1
A-V1
A-V1
M-N1
A/V1
G1.5
Z-B1
H-L1
C-L1
R-G1
G-R1
G-N1
M-B1
M/N1
G-R1
R-N1
G-V1
A2.5
A2.5
A-R1
A-N1
R/N1
B-N1
R-V1
R-V1
S1
V-N1
B1
X27
G1
R1
N1
R-N1.5
H-L1
G-N1
A-N1
G1
N1 N1 N1
X32
6
V/N1 V/N1
X9
X8
X5
5
X2
H15
H1 C/B1
4
R-N1.5
XC1 C-B1
N1.5
B/N1
B/V1
N2.5
N2.5
N2.5
2
N1
L0.5
N1.5
1 2 3 4 5 6 7 8 9 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 1 2 3 4 5 6 7 8 9 10 11 1 2
HA4 M-N1 M-N1
N1
N1
N1
N1
N1
N1
N1
N1
N1
N1
N1
1
+15
NAME DESCRIPTION
X21
X30
N1
N1.5
N1.5
EV1 OPENED GRAB SOLENOID VALVE
N1
N1
RADIO TO
N
C-B1
K3 R26 1 2 3 1 2
CONDITIONING
A-V1
G2.5
EV2
B-R1
CLOSED GRAB SOLENOID VALVE POWER SUPPLY EV1
R1
86 87a 87
D14
R6
D4
L4
KIT
B/N1
B/V1
R-N1.5
N1
DIFFERENTIAL LOCK SOLENOID VALVE
N1.5
G EV3 1/4W
D20 G
REAR 1^ BOOM UNLOCK SOLENOID VALVE 85 30 4 3 2 1
EV4 N1
N2.5
N1.5
X14
X12
N1
N1
N1
N1
N1
F1A LOW BEAM FUSE 15A
L26 1 2 3 M-N1
F1B
K9 M5
RIGHT TRAFFIC LIGHT FUSE 3A R31 EV3
S24
D19
+
B-R1.5
D18
A-V1
G2.5
R1.5
+15 M
F1C LEFT TRAFFIC LIGHT 3A +15
L4
R4
R C
F2A ROTATING LAMP FUSE 10A L12 L22 L19 L14 L13 D5 L11 L17 L18 L20
RELAIS "K4" NOT
K7 R5 COPNNECTED R3 F3A 0A000571 N1
F2B RADIO CABIN LAMP FUSE 7.5A R27 F3C 1/4W
86 87a 87 1/4W 7.5A
F2C WARNING FUSE 10A 1/4W 7.5A F2C R12 F6C R22 F5C R19 F4A R14 F3B R13 F2B R11 F5A R17 F5B R18 F6A R20 S19
D8 1/4W 1/4W 1/4W 1/4W 1/4W 1/4W 1/4W
F3A STARTING FUSE 7.5A 1/4W 1/4W 7.5A 15A 15A 15A
85 30 L5 10A 10A 15A
7.5A 7.5A
L3
SWITCH+WARNING LIGHT+RETURN TO DIG FUSE 7.5A
R4
F3B 1/4W
OPTIONAL VALVE FUSE 7.5A L27
A-N1.5
F3C
D17
D16
D15
H H
H/N1
+30 +15 +15 +15 +15 +30 +15 +15 +15
D21
L4
D22
0A002248
S1
F4A 4WD VALVE-WINDSHIELD WIPER/WASHER FUSE 7.5A
V1
V-B1
F4B FORWARD-REVERSE SPEED FUSE 10A
N1.5
N1
N1
N1
N1
6 5
N1.5
N1
N1
N1
N1
N1
N1
L15 +30
K8
H1 PREHEATING WARNING LIGHT K6 85 30
86 87a 87
R25 F7C R6 F2A R10 F1C L7 F1B L8 XAD
86 87a 87 1/4W 1/4W 1/4W Z-B1
H10 CONVERTER OIL HIGH TEMPERATURE WARNING LIGHT 7.5A 10A 3A 3A l
J D7
Z/B1 J
H11 4WD WARNING LIGHT F1A R28 D9 85 30 R7 R8 -
R2
85 30
1/4W L25 D12 L6 L10 1/4W 1/4W
H12 FUEL RESERVE WARNING LIGHT K2 K1 15A
1/4W R1 F4C X13
R9
R29
86 87a 87
H13 KOMATSU LOGO LIGHT
D3
86 87a 87
D1 1/4W
L21 L24 L4
l
L4
R16 1/4W
L28 -
H14 KOMATSU LOGO LIGHT
85 30 L2 85 30 1/4W
15A
D10
1/4W
R21 F7B R24 XT2 KT2
H15 CIGARETTE LIGHTER LAMP
L29 L9 N1
CABIN LAMP
J2 L1 F6B 1/4W
10A
1/4W
D11 R4 X11 R4 G/N1
1 53S
H16 L16 R4 R4 R4
2 15
1 2 3 P4 7.5 01170827 +30
G2.5
1
G2.5
R-V1
M1
3
H17 FRONT WORKING LAMP 2 4 53M
3 31
H18 FRONT WORKING LAMP
1 2 3 4 5 6 7 8 9 1 2 3 4 5 6 7 8 9 10 11 +15 +15 1 2 3 4 5 6 7 8 9 1 1
H19 BEACON LAMP
X1
X6
X3
N1.5
R-N1.5
A-N1.5
A-G1
S-N1
V-B1
Z/N1
Z-B1
N1.5
H/N1
B-R1
B-N1
S1
V1
H-L1
Z-B1
H-R1
V-N1
0A000405
G/N1
H21 REAR WORKING LIGHT
X10
H22
Z/B1
INDICATORS WARNING LIGHT
A-N1.5 1
A-N1.5
Z-B1
H-R1
H28
N1
N1
G2.5
Z-B1 Z-B1
B-N1
9
M-V1 M-V1
H29 LEFT FRONT INDICATOR
B-N1
10
11 B-N1
ENGINE WATER HIGH TEMPERATURE WARNING LIGHT R-V1 R-V1
H3 A-V1
12
13 A-V1
X38
X41
M-V1
C-L1
H32 REAR RIGHT INDICATOR
N1
H33 REAR RIGHT LIGHT
X44
X43
N1
N1
N1
1 2
H4 ENGINE OIL PRESSURE WARNING LIGHT
Z-N1.5
A-G1
H-N1
L-B1
S-N1
S26 Y5 Y4 Y2
N1
N1
A-B1
N1.5
N1.5
H-N1
B-R1
X42
A1
H5 AIR FILTER WARNING LIGHT
t
X22
X23
H-N1
S16
M10
H6 HYDRAULIC OIL FILTER WARNING LIGHT
B A
S18
X37
X36
S17 N1
M10
B1.5
R10
M-V1
C-L1
B-R1
1 2 l
M-V1
-
R4
L4
H8 OPTIONAL WARNING LAMP
FUG4
FUG2
FUG3
1 2 1 2
K07 K02
N1.5
N1.5
N2.5
N1.5
N1.5
N1.5
B-R1
B-R1
86 87a 87
N1
N1
N1
N1
M S28 85 30 M
HA2 BUZZER OPTIONAL WASHER PUMP 0A002932 0A002211
60A 80A 30A 80A
H29 H28 NOT CONNECTED 85 30
C-L1
H-N1
HA3 REAR HORN
M10
N1
N1
HA4 BUZZER
Z-B1
B-R1
K01 STARTER RELAY R50
XT1 KT1
K02 PREHEATING RELAY N1
G2.5
Z/N1
R10
R10
1 53S
B-R1
K03 FUEL SHUT OFF RELAY G1
2 53M
S13 - l
B/R1
3
XA
15
K05 RETURN TO DIG RELAY
N1.5
K06 P2 S2L X14 FRONT LINE-CROSS LINE 4 WAY CONNECTOR X4 MONITOR 11 WAY CONNECTOR
N1
N1
N1
POWER ECONOMY UNIT HOUR COUNTER WINDSHIELD WIPER-WASHER SWITCH ON LAT. DASHBOARD 30 50
D+
R50
B/R1
M1 G2
B1.5
K07 GEAR RELAY P3 FUEL LEVEL INDICATOR S3A FRONT WORKING LIGHT SWITCH ON FRONT DASHBOARD X15 START KEY 4 WAY CONNECTOR X40 FLASHER UNIT 13 WAY CONNECTOR M 30
G W
N K03 N
K1 FORWARD SPEED RELAY P4 WATER TEMPERATURE INSTRUMENT S3L BEACON SWITCH ON LAT. DASHBOARD X16 CONDITIONER CLUTCH 2 WAY CONNECTOR XC1 12 VOLT CURRENT INTAKE
G1 3
86 87
K2 REVERSE SPEED RELAY R30 HEATING START S4 BLOWER MOTOR SWITCH X17 LATERAL DASHBOARD 21 WAY CONNECTOR X42 SWITCH GEAR 2 WAY PACKARD U
12Vcc 31 85 30
K3 4 WHEELS DRIVE RELAY( SHUTTLE ONLY) R31 FUEL LEVEL SENDER S4A WARNING SWITCH ON FRONT DASHBOARD X18 FRONT CABLE 5 WAY CONNECTOR X43 RELAY DIFFERENTIAL LOCK 2 WAY AMP
B1.5
G1
K5 LOW BEAM RELAY R32 WATER TEMPERATURE SENDER S4L HORN SWITCH ON LAT. DASHBOARD X19 FRONT DASHBOARD 9 WAY CONNECTOR X44 SWITCH GEAR SIGNAL 2 WAY YASAKI
K6 S1 S5L X2 LIGHTS SWITCH AND GEAR SHIFT LINE 9 WAY CONNECTOR X45 POWER ECONOMY UNIT CONNECTOR
N50
MAIN BEAM RELAY ECONOMY POWER PUSH BUTTON OPTIONAL SWITCH ON LAT. DASHBOARD
K7 LIGHTS SWITCH RELAY S10 HAMMER BUTTON S6 STARTING SWITCH X20 BLOWER MOTOR 4 WAY CONNECTOR X5 CABIN COMMAND 11 WAY CONNECTOR
XAM
X21 FUEL LEVEL INDICATOR 3 WAY CONNECTOR X6 N1.5 N1.5 Y0
K8 HORN RELAY S13 BATTERY STOP SWITCH SM2 CONTROL-SQUARE BUTTON SOLENOID VALVES LINE 9 WAY CONNECTOR
R-N1.5
1
2
R-N1.5
B1.5 B1.5
K9 FLASHER UNIT S15 HAND BRAKE SWITCH SM3 CLOSED GRAB BUTTON X22 WINDSHIELD WASHER PUMP 2 WAY CONNECTOR X7 NOT CONNECTED 9 WAY CONNECTOR 3
KT1 FUEL SHUT OFF TIMER S16 BRAKE OIL LOW LEVEL SWITCH SM4 CONVERTER DETACHMENT BUTTON X23 OPTIONAL 2 WAY CONNECTOR X8 LATERAL DASHBOARD 17 WAY CONNECTOR
KT2 PREHEATING TIMER S17 PEDAL SWITCH SM5 OPENED GRAB BUTTON X24 WINDSHIELD WIPER 4 WAY CONNECTOR X9 FRONT DASHBOARD 17 WAY CONNECTOR
O O
M1 STARTER MOTOR S18 PEDAL SWITCH SM6 DIFFERENTIAL LOCK BUTTON X25 POWERED BLOWER MOTOR 2 WAY CONNECTOR XA GENERATOR 2WAY CONNECTOR
M2 WASHER PUMP S19 STOP LIGHT SWITCH Y0 FUEL SHUT OFF SOLENOID VALVE X26 REAR LINE 8 WAY CONNECTOR XAD DIODE 2 WAY CONNECTOR
WIRING COLOURS
M3 WINDSHIELD WIPER MOTOR S1A 4 WD SWITCH ON FRONT DASHBOARD Y1 ECONOMY POWER SOLENOID VALVE X27 VALVES LINE 6 WAY CONNECTOR XAM FUEL SHUT OFF VALVE 3 WAY CONNECTOR
A LIGHTBLUE
M4 BLOWER MOTOR S1L REAR WORKING LIGHT SWITCH ON LAT. DASHBOARD Y2 4 WD SOLENOID VALVE X28 JOYSTICK 12 WAY CONNECTOR XD1 LIGHTS SWITCH 9 WAY CONNECTOR B WHITE
C ORANGE
M5 FUEL PUMP S2 REAR 1^ BOOM UNLOCK SWITCH Y3 PLATE UNLOCK SOLENOID VALVE X29 CONVERT DETACHMENT BUTTON 2 WAY CONNECTOR XD2 GEAR SHIFT 5 WAY CONNECTOR G YELLOW
X3 FRONT LINE 11 WAY CONNECTOR XS H GREY
M8 WINDSHIELD WIPER MOTOR S20 STOP LIGHT SWITCH Y4 FORWARD SPEED SOLENOID VALVE MULTIFUNCTION INSTRUMENT 6 WAY CONNECTOR
L BLUE
H3 ENGINE WATER HIGH TEMPERATURE WARNING LIGHT S21 ENGINE WATER HIGH TEMPERATURE SWITCH Y5 REVERSE SPEED SOLENOID VALVE X30 FUEL PUMP 2 WAY CONNECTOR XT1 FUEL SHUT OFF TIMER 4 WAY CONNECTOR M BROWN
N BLACK
M1 STARTER MOTOR S22 AIR FILTER BLOCKED SWITCH Y6 RETURN TO DIG SOLENOID VALVE X31 CABIN 5 WAY CONNECTOR XT2 PREHEATING TIMER 4 WAY CONNECTOR R RED
X32 RADIO POWER 2 WAY CONNECTOR S PINK
M2 WASHER PUMP S23 ENGINE OIL LOW PRESSURE SWITCH XC1 CIGARETTE LIGHTER
V GREEN
M3 WINDSHIELD WIPER MOTOR S24 FUEL GAUGE X1 FRONT LINE(ENGINE) 11 WAY CONNECTOR X33 WINDSHIELD WIPER AND BEACON 7 WAY CONNECTOR Z VIOLET
P P
M4 BLOWER MOTOR S26 CONVERT. OIL HIGH TEMPERATURE SWITCH X10 FRONT LINE-ENGINE LINE 13 WAY CONNECTOR X36 RIGHT FRONT INDICATOR WAY CONNECTOR EXAMPLE:
M5 FUEL PUMP S27 NPN SENSOR X11 POWER 3 WAY CONNECTOR X37 LEFT FRONT INDICATOR WAY CONNECTOR G/V ->YELLOW/GREEN
(TRANSVERSE COLOURS)
M8 WINDSHIELD WIPER MOTOR S28 GEAR SWITCH X12 FRONT LINE-CROSS LINE 3 WAY CONNECTOR X38 FORWARD-REVERSE SPEED VALVES 4 WAY CONNECTOR
G-V ->YELLOW-GREEN
S2A X39 PROXIMITY 3 WAY CONNECTOR (LONGITUDINAL COLOURS)
P1 RPM INSTRUMENT WINSHIELD WIPER-WASHER SWITCH ON FRONT DASHBOARD X13 FRONT LINE-ENGINE LINE 2 WAY CONNECTOR
RKZ05020
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
87
1 9
86
1 0
K04
0 86 87a 87
5 10
CONNECT WITH PRESETTING SOCKET
INSIDE LATERAL DASHBOARD 85 30
9 5 10 1
85
X58 X56 X57 X56
30
G-V1
N1
X54 3° FAN SPEED RELAY
H-G1 CONNECT TO "S4" POSITION "1"
(BLOWER MOTOR SPEED SWITCH )
85 30 A LIGHTBLUE
X16
85 30 86 87 CONNECT WITH PRESETTING A B WHITE
X55 CONNECTOR NEAR GENERATOR X16
X55 X55 X55 B
C ORANGE
N1 V-N1 G YELLOW
V-N1 N BLACK
G-V1 R RED
S PINK
2 1 2 1
V GREEN
YELLOW GREEN
K04 3° FAN SPEED RELAY X56 A/C SWITCH SWF CONNECTOR
K10 COMPRESSOR ELECTROMAGNETIC CLUTCH CONTROL RELAY X57 AMP 1 WAY CONNECTOR HEATER/CONDITIONING
M4 FAN MOTOR
MOTOR UNIT
X58 AMP 1 WAY CONNECTOR
S40 A/C SAFETY SYSTEM PRESSURE SWITCH X62 SAFETY PRESSURE SWITCH AMP MINITIMER 4 WAY CONNECTOR
X53 AMP 1 WAY CONNECTOR X16 COMPRESSOR ELECTROMAGNETIC CLUTCH 2 WAY CONNECTOR
X54 FEMALE FASTON X20 HEATER/CONDITIONING MOTOR UNIT AMP 4 WAY CONNECTOR
STATE OR PROVINCE:
DEPARTMENT: COUNTRY:
NAME: FAX:
BOOK DISCRIPTION
MACHINE MODEL & S/N:
PROBLEM:
CORRECTIVE ACTION: