COST COMPARISON OF SLAB/FOUNDATION PER PANEL

WITHOUT BEAM RAFT WITH BEAM RAFT


ELEMENT UNIT RATE
180 THK Amount (RM) 200 THK Amount (RM) 175 THK Amount (RM)
Grade 30 Slab concrete m3 380.00 2.88 1,094.40 3.2 1,216.00 1.01 383.04
Rebar for slab - T10 kg 4.00 37 148.00 37 148.00 26.5 106.00
Rebar for slab - T12 kg 4.00 144.6 578.40 121.4 485.60 -
Drop panel/raft beam concrete m3 380.00 0.6 228.00 0.6 228.00 2.43 923.40
Rebar drop panel/raft beam -T12 kg 4.00 46.3 185.20 45.3 181.20 85.2 340.80
Rebar drop panel/raft beam -T16 kg 4.00 - - 91 364.00
Formwork m2 55.00 18.4 1,012.00 18.4 1,012.00 18.41 1,012.55
3
Excavation m 10.00 3.48 34.80 3.8 38.00 4.25 42.48
2
50mm lean concrete m 20.00 16 320.00 16 320.00 10.89 217.80
2
0.2mm thk polythene sheet m 10.00 16 160.00 16 160.00 7.29 72.90
Total 3,760.80 3,788.80 3,462.97

SUMMARY OF STEEL POUNDAGE

ELEMENT UNIT 180THK 200THK 175THK


3
Total Concrete m 3.48 3.80 3.44
Total Rebar kg 227.90 203.70 202.70
3
Steel poundage kg/m 65.49 53.61 58.96

*Note : Construction time for raft beam is 20% longer than raft without beam.