Professional Documents
Culture Documents
Hal Furnace - Quote 2500kg 04192018 - Rev1 PDF
Hal Furnace - Quote 2500kg 04192018 - Rev1 PDF
Issued by:
Flavio Rueda
Proposal number:
04192018rev1
Date: 4/19/2018
1|Page
Strictly private and confidential © 2015 Pyrotek Inc.
Pyrotek Apodaca – 5008 Decada Ave. Milenium Industrial Park – 66600 Apodaca, N.L., MX
CONFIDENTIALITY
This document contains confidential and proprietary technical information of Pyrotek Inc., and is provided
solely for tendering purposes to with the understanding that its contents in whole or in part will not be divulged
to a third party without prior written consent of Pyrotek.
1. Pyrotek will provide engineering and manufacture for an Under Heated holding furnace. The
furnace capacity is 2500 Kg
2. The new complete lower unit will consist of a pre-cast working liner, back up liner, insulation
package and fabricated steel shell
3. Complete insulated Dip well cover that is operated by a manual hand-winch system
4. Complete insulated Heat well cover that is operated by a manual hand-winch system
5. Complete insulation Fill well cover that is pneumatically operated using a mechanical hand valve
6. Complete insulated cleaning cover which will be manually removed for cleaning/degassing.
7. Complete insulated Filter cover with a filter access cap for use with a BPF (Bonded-Particle Filter)
Plate
8. A BPF Plate
9. Three (3) 15kW heaters, producing a total of 45kW power capacity in the furnace
10. Each heater will be supplied with an over-temperature protection thermocouple.
11. A drain, with a mechanically operated plug mechanism
12. Metal level detection
13. There will be a junction box mounted on the furnace for signals and power.
14. One 60kVA Transformer (Must supply 90 amps)
15. Electrical Controls will be in a control panel, which will include:
a. Main lockable fused disconnect
b. 3 Phase power present indicator
c. 3 independent heater over temperature controls
d. 3 Watlow SCR’s
e. 3 contactors
f. Heater over temperature warning alarms
g. Metal temperature high/low warning alarms
h. Tower light and horn
i. 3 Heater Voltage meters
j. 3 Heater current meters
k. Control power on/off switch
l. Heater power on/off switch
m. A lamp check
2|Page
Strictly private and confidential © 2015 Pyrotek Inc.
Pyrotek Apodaca – 5008 Decada Ave. Milenium Industrial Park – 66600 Apodaca, N.L., MX
n. Alarm silence
o. Flange Mount 72”x39.5”x18” NEMA 12 Enclosure
p. Flange Mount disconnect handle and associated hardware
q. Electrical Interlock
r. Limit Controllers
s. SCR’s controllers
3|Page
Strictly private and confidential © 2015 Pyrotek Inc.
Pyrotek Apodaca – 5008 Decada Ave. Milenium Industrial Park – 66600 Apodaca, N.L., MX
4|Page
Strictly private and confidential © 2015 Pyrotek Inc.
Pyrotek Apodaca – 5008 Decada Ave. Milenium Industrial Park – 66600 Apodaca, N.L., MX
• Furnace assembly
• Liner
5|Page
Strictly private and confidential © 2015 Pyrotek Inc.
Pyrotek Apodaca – 5008 Decada Ave. Milenium Industrial Park – 66600 Apodaca, N.L., MX
• Liner wells
6|Page
Strictly private and confidential © 2015 Pyrotek Inc.
Pyrotek Apodaca – 5008 Decada Ave. Milenium Industrial Park – 66600 Apodaca, N.L., MX
• Heater cover
7|Page
Strictly private and confidential © 2015 Pyrotek Inc.
Pyrotek Apodaca – 5008 Decada Ave. Milenium Industrial Park – 66600 Apodaca, N.L., MX
SECTION 2 – Pricing
Electric Supply Installation, including electric supply and thermocouples cables $ 11,814.00
(20 meters considered)
8|Page
Strictly private and confidential © 2015 Pyrotek Inc.
Pyrotek Apodaca – 5008 Decada Ave. Milenium Industrial Park – 66600 Apodaca, N.L., MX
SECTION 3 – General Notes
9|Page
Strictly private and confidential © 2015 Pyrotek Inc.
Pyrotek Apodaca – 5008 Decada Ave. Milenium Industrial Park – 66600 Apodaca, N.L., MX
SECTION 4 – Estimated Schedule
1. Delivery of the equipment 16 weeks after receipt of signed approval drawings for 1 furnace. This
schedule is subject to change by negotiation upon placement of a purchase order.
2. Upon receipt of a purchase order, Pyrotek will provide a detailed Gantt chart for the total project. This
schedule will be a living document subject to revision based on the final scope of supply and the
engineering phase of the project.
3. Customer is welcome to witness the final system check at Pyrotek – Mexico prior to shipment. Pyrotek
will provide Customer with scheduled inspection dates. If customer is not available on schedule dates, the
final delivery is subject to change based on customer availability.
Progress Payments
10 | P a g e
Strictly private and confidential © 2015 Pyrotek Inc.
Pyrotek Apodaca – 5008 Decada Ave. Milenium Industrial Park – 66600 Apodaca, N.L., MX
SECTION 4 – Appendix
All Terms and Conditions of Sale associated with this equipment are enclosed with this proposal. These
Terms and Conditions are the only Conditions of Sale that shall constitute the agreement for this sale.
Any changes to these conditions must be agreed to in writing by Pyrotek. We also reserve the right to
review the prices, delivery etc., if changes occur through delays not of our own making or any change in
specification. Terms and conditions subject to change. The most current terms and conditions are available
at:
This proposal shall be open for acceptance for a period of 21 days from the date indicated on the front of
this document. If this proposal is not accepted within the 21 day period, all terms of this proposal including
but not limited to pricing, will be subject to change.
Delivery
Warranty
Warranty as per Pyrotek Engineered Systems Conditions of Sale of Goods and Services apply to this sale.
The warranty on the relines is the same as below minus the control system.
In Summary:
• Steel Shell – 36 month warranty
• Heater Sheaths – 3 month warranty
• Heater Elements – 3 month warranty
• Refractory lining – 12 month warranty
• Control system – 12 month warranty
• Consumables – No warranty
Consumable parts list (subject to change based on final design):
• Drain Cones
• Bath Thermocouples
• Heater Thermocouples
• Thermocouple protection tube
11 | P a g e
Strictly private and confidential © 2015 Pyrotek Inc.
Pyrotek Apodaca – 5008 Decada Ave. Milenium Industrial Park – 66600 Apodaca, N.L., MX
ACCEPTANCE
Signed
................................... .................................
Contact
………………………………..
Printed Name and position
...................................
12 | P a g e
Strictly private and confidential © 2015 Pyrotek Inc.
Pyrotek Apodaca – 5008 Decada Ave. Milenium Industrial Park – 66600 Apodaca, N.L., MX