Professional Documents
Culture Documents
Unit 7
Unit 7
Unit 7
7.1 INTRODUCTION
Project management entails designing, ordering, expediting, inspection,
transportation of materials and equipment in an orderly sequence and then erecting
them in different geographical locations and commissioning them into viable
operating plants A large project, in totality, may appear to he very gigantic and
complicated. Management of projects by network analysis provides an integrated
technique of planning and control by breaking the entire project into various
packages (systems) which are further blown into various functional components like
mechanical, piping, civil, structural, electrical, instrument, etc. Each of these
functions is further divided into design and indenting, ordering and payment,
expediting and inspection, transportation and storage, erection and commissioning.
Network analysis of projects leads to prioritisation of all activities such that work on
the longest delivery items-is started first, followed by not-so-long delivery items,
followed by medium delivery items and ultimately followed by short delivery items
and so on. For any functional area also, schedule, blown up item-wise. is as shown
below:
Figure 1:
Figure 7.2
While doing this, projects can also be further classified geographical area wise on the
following lines
Within Battery Limits
38 Battery Limits refers to the main plant and equipment and may comprise of-
(a) Plant I (or Main Building I) Materials and Equipment
(b) Plant II (or Main Building II)
Outside Battery Limits
These may he further grouped into -
a) Process Utilities such as
1. Raw Water including intake water works from canal, river etc. or tubewells
2. Filtration Plant
3. Cooling Towers
4. Chilled Water
5. Distilled Water
6. Boilers and Steam Pipelines
7. Fuel Oil System
8. Petrol, Oil, Lubricants etc.
9. Incoming Power Supply and Distribution
10. Power Substations and Switch Rooms
11. Raw Material Storages of various kinds
12. Packaging Material Storage
13. Stores for Maintenance and Spare Parts
14. Specialised Stress within Production Department
15. Storage of Safety Equipment
16. Storage of Dresses and Uniforms
17. Storage of Stationery
18. Storage for Laboratory Chemicals
19. Finished Product Warehouse
20. Workshops for Civil, Mechanical. Electrical and Instruments
21. Laboratories for Testing Raw Materials. in-stage production materials,
packaging materials and finished products
22. Fire Fighting System including Fire Engine/Tender
23. Inward Material receiving bay and area
24. Outward despatch bay and shipping area
(b) Amenities such as
1. Office Building
2. Training Centre
3. Security Office at the entrance gates for materials, workmen. st'f etc.
4. Time Office
5. Change Rooms. Washrooms, Lockers, Toilets etc.
6. Canteens and Rest Rooms
7. Roads, Culverts and Drains
8. Street Lighting etc.
All main plants process utilities, amenities etc. are inter - connected through service
pipelines, power-cables etc. Proper well defined cut-off lines must he decided before
hand so that responsibilities of individual persons get defined without any gaps and
overlaps.
Each of the process utility or amenity may have all or few of the above six
components. For example, project management responsibility of a general purpose
office building or store may vest in a member of civil engineering group who would
in turn have to seek assistance from other disciplines like electrical engineering for
power/electrification works within the proposed office, stores etc. Similarly, for
office equipment, furniture, instruments etc., help of specialist functions as
appropriate may be sought. 39
Project Planning and Scheduling Activity 1
…………………………………………………………………………………………
…………………………………………………………………………………………
…………………………………………………………………………………………
…………………………………………………………………………………………
T =A+L+B-
Overall
Where A = Minimum time required to design, indent and order the longest delivery
item
B = Minimum time required for the longest delivery item to be erected and
commissioned
Figure 7.3
7.10 SUMMARY
Materials and equipment play important role in project management, because the
procurement of these requires 80-85 per cent of the overall project duration.
Management of projects through network analysis incorporates a systematic and
compresive approach to materials management. Effective material management
ensures right materials, in the right of quantity at the right time, at the right place and
at the right price.
The overall project duration is dependent upon the congest delivery items of
materials and equipments. Hence possible courses of actions are to be followed in
beating the critical path. Construction schedules shall have to he worked out in
greater details so as to optimize the engagement of expensive construction machines
and materials.
43