Kaizen Owner Association Management

Services LLC

Themmar Investment LLC

Refurbishment of Themmar Building

Vol -3 – Bill of Quantities


BILL NO.1 - General Requirements
THEMMAR - 1
TOTAL
ITEM ITEM DESCRIPTION QUANTITY UNIT RATE PRICE
REF

General Requirements
Included in
A Allow for Performance security/Advance Security LS
Item supervision

Insurance of Contractor Equipment & Workmen's LS 12,000.00


B Item
Compensation Insurance
LS 6,000.00
C Third-party liability insurance Item
D Allow for local authorities charges and fees Included in
including permit fees. LS Item supervision
charges
SITE FACILITIES
D Temporary site office for the use of the Contractor LS Item 9,000.00
/Employer/ Employer representative and his
assistance including all furnishing, fittings, services,
Parking areas, and other related facilities, etc.

Health & Safety Works /Equipment & Security


E The contractor shall provide all necessary safety LS Item 30,000
requirements & equipmforring for the construction of
workers.

Construction Plant for Permanent Works

Allow for the necessary plant, equipment, and tools


F LS Item 15,000
for the proposed execution of the project

G Allow for providing all scaffolding and cradles LS Item

Protecting the Works


Allow for Protection of works from inclement
A LS Item 20,000.00
weather
B The contractor shall protect all existing services LS Item If 20,000.00
during the construction, and any damage to the require
existing services shall be made good by his own
cost. If any temporary or permanent rerouting of the
existing services is required, the contractor shall be
responsible for giving notice to the relevant
authorities and allowing for attendance.
C POWER & WATER ------ Item 0.0

Power and water requirements (Power and water are


available at the site. The contractor has to include only
co-ordination)

E Site Supervision & Engineering LS Item 65,000

The contractor allows for experienced & qualified


Staff for the proper supervision of construction of
the projects & part-time staff for other trades
according to the scope of works subject to the
approval of the Engineers

H Cleaning the Works LS Item 10,000


The contractor shall remove all rubbish at regular
intervals, provide protective casing and covering and
clean the works at completion.
CARRIED FORWARD

BROUGHT FORWARD

Shop drawings, As Built Drawings etc.


0.0
The contractor shall prepare and submit the "Shop
A Item
Drawings" as specified.
0.0
Allow for Providing the operating and Maintenance
B Item
Manuals as specified./
The contractor shall prepare all the "As built 0.0
C Item
drawings" as specified
Allow for Site mobilization and De-mobilization LS Item 12,000.00

The contractor shall allow to remove the all the


temporary facilities and make clean

Additional Items
The tenderer is to list any other obligations required LS
for the satisfactory completion of this section but not Item
10,000.00
mentioned herein, any items not listed be deemed
to be included. below shall

Total 1,89,000.00
THEMMAR - 1
Bill no.2 - Items of works
ITEM TOTAL
ITEM DESCRIPTION QUANTITY UNIT RATE
REF PRICE
Repairing of the delaminated surface of concrete
floor including all necessary sundries and
accessories to form complete system; but not 55.00 20,350.00
limited to below listed etc. complete;
Chipping and removing the existing concrete
Cleaning the existing steel
Corroded rebars to be replaced with new rebar
Apply one coat of corrosion inhibitor Supply and
1 apply of Micro concrete. 370 M2

Repair of wet Cracks


The crack shall be repaired by injecting with PU resin
as directed by the manufacturer in the leakage areas 60.00 2400.00
2 Location: Basement floor 40 LM

Repair of dry Cracks (0.1 to 0.15mm width):


3 The crack shall be repaired by rout and seal method with 79 LM 85.00 6,715.00
epoxy/polymer modified cement grouts

Removing the existing floor coating in parking floor


4 and repainting including parking lines and markings 5800 M2 44.00 255,200.00
using epoxy etc complete;
Repair, remove and re-fixing the existing expansion
5 joint including all necessary accessories to complete 120 LM 55.00 6,600.00
the works

Repair of surface cracks on external wall (0.1 to


6 0.2mm width) including all necessary sundries and 1210 M2 85.00 102850.00
accessories to form complete system;

Remove the existing internal wall painting in


parking floor and repaint with the approved material
7 as per manufacturer 3270 M2 25.50 83,385.00
recommendations etc. including all necessary sundries
and accessories to complete the works
Remove the existing internal ceiling painting in
parking floor and repaint with the approved material
8 as per manufacturer 5800 M2 24.00 139200.00
recommendations etc. including all necessary sundries
and accessories to complete the works
Remove the existing external wall painting and
repaint with the approved material as per manufacturer 36.00 327600.00
9 9100 M2
recommendations etc. including all necessary sundries
and accessories to complete the works
10 Repair of Cracks (More than 0.2 mm) 87 LM 45.00 3915.00
The crack shall be repaired by injecting with Epoxy
resin as directed by the manufacturer

Total
9,48,215.00
THEMMAR - 1
GENERAL SUMMARY

Bill no. DESCRIPTION TOTALAMOUNT (DHS)

Bill no.1 GENERAL REQUIREMENTS 1,89,000.00

Bill no.2 ITEM OF WORKS 9,48,215.00

11,37,215.00
TOTAL AMOUNT FOR THE PROJECT

TOTAL AMOUNT IN WORDS One Million One Hundred Thirty-


seven Thousand Two Hundred Fifteen
Page 6 of 6