ITP For Soil Replacement and Backfilling PDF
ITP For Soil Replacement and Backfilling PDF
Item Activity Characteristic to be Verified Reference Acceptance Verifying Device/tools Freq. Inspection Code
Document Criteria/Tolerance Document
1 2 3 4
1.0 Submission
Item Activity Characteristic to be Verified Reference Acceptance Verifying Device/tools Freq. Inspection Code
Document Criteria/Tolerance Document
1 2 3 4
2.1 Sieve analysis Determination of different Project ASTM D 6913 Material Sieve Once for H R M
soil components and grain specs. and test report analysis each soil
size relevant equipment source
codes
2.2 Proctor Determination of optimal Project ASTM D 698 Material Modified Once for H R M
moisture content specs. and test report proctor each soil
relevant moulds and source
codes rammers
2.3 Atterberg limits Determination of liquid and Project ASTM D 4318 Material Atterberg Once for H R M
plastic limits. specs. and test report limits each soil
relevant equipment source
codes
2.4 Chemical Determination of potentially Project ASTM C 1580 Material Chemical Once for H R M
analysis soluble sulphates or chlorides specs. and test report analysis each soil
at replacement soil and PH relevant equipment. source
value codes
3.0 Tests
Inspection Code: 1: LEEDS ECO QC 2: RMC 3: Subcontractor 4: EMMAR MISR
Item Activity Characteristic to be Verified Reference Acceptance Verifying Device/tools Freq. Inspection Code
Document Criteria/Tolerance Document
1 2 3 4
3.1 Sand cone test Determination of soil density Project ASTM D1556M Material Sand cone 1 sample for H R M
specs. and test report equipment each 100m2
relevant For soil
replacement 95%
codes
of max. dry
density.
For backfilling
90% of max dry
density.
4.0 Inspection
4.1 Survey setting Checking the boundaries, Project According to Inspection Total On going
out works coordinates and levels for specs. & geotechnical Request station
each layer as per approved drawings report H H M
shop drawing.
Inspection Code: 1: LEEDS ECO QC 2: RMC 3: Subcontractor 4: EMMAR MISR
Item Activity Characteristic to be Verified Reference Acceptance Verifying Device/tools Freq. Inspection Code
Document Criteria/Tolerance Document
1 2 3 4
4.2 Soil compaction Checking soil compaction for Project According to Inspection NA On going
visual inspection each layer specs. & geotechnical request
drawings report H H M