LET.00xx - NOD No. Xx-Interior Design TCSS Room - 05052023 r2

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 6

Our Ref.

: EVD/EKVE/TCSS/AZSB/10200423/LET/00xxx
Date : 3 MAY22 1724 February APRILFEBRUARY 2023

AHMAD ZAKI SDN BHD.


EKVE Site Office,
Lot 2824, Jalan Kuari, Bt. 12, Hulu Langat,
43100 Kajang,
Selangor Darul Ehsan.
Tel: 03 – 2698 7171
Fax: 03 – 2694 8181

Attn: Encik Mohd Fauzi Mat Ruding (Project Manager)

Dear Sir,
EAST KLANG VALLEY EXPRESSWAY (EKVE) PROJECT
Supply, Install, Testing and Commissioning of Traffic Control and Surveillance System
(TCSS) (Code: BY96)
Re: Notice of Delay (“NOD”) No. 1675 - Rework due to Stolen Defect and Vandalismed –
Optical Fiber Optic (Hulu Langat)Interior Design Works for Central Computer System
& TCSS Room.

With reference to the above mentioned matter, we would like to notify Ahmad Zaki SdnZaki Sdn Bhd
(“AZSB”) that the completed Interior Design (“ID”) for Central Computer System & TCSS Room
located at Ampang Control Room hTCSS Fiber optic cable 48CID works hads been damagedstolen and
vandalized at Bandar Mahkota CherasHulu Langat and Hulu Langat (from CH7020CH9940-
CH104008560) by third partyAmpang Control rRoom . A copy of theAn official Letter Incident report
appendedreport have been submitted to your office on xxxxxxx18th April 2023. Enclosed Kindly refer to
in Attachment 1 for the official Incident Report and Attachment 2 for the mainlineID, drawing for your
reference.

In view of theDue to aforesaid incident, , we would like to highlight that , it has it will affected our
progress of work. As a result, it will cause an additional cost for rectification and replacement workof
such damage. We foresee that the rectification works will have e delay might be occurred for in re-
installation works and also had time implication on completion of works work program and time impact.
Hence, we come out withkindly refer to our summary of work activities planning and duration of time of
each task as shown in Table 1, for your review and perusal.

No Task Approximate
Duration

1 Procurement of equipment and delivery to site48C Armored 51 weekss6 weeks


Fiber Optic cables deliverySand down the existing laminated
on TV wall.
2 Sand down the existing laminate on the TV wall. 1 week
32 Remove existing Fiber optic cable inside median NJB and 1 week1 week
undergroundTo dismantle wooden stripe on the TV wall.
43 Install 48 Cores Outdoor Armored Fiber Optic Cables 2 weeks2 weeks
inclusive of splicing, termination, pigtails, splice enclosures
and the related items necessary to complete the
installationTo install new laminated and wooden wood on
TV wall.
54 To checking lamp wiring and adjustment of downlight and 1 week
T8 lamp.
65 To paint ceiling and related touch up work and painting 1 week
ceiling.
Table 1

The overall timeline for the above mentioned activities is enclosed in Attachment 3 for your reference.

Please take note thatPlease be informed that , these this duration is based on approximate only and
subject to change upon getting of will starts upon we get instruction and approval and instruction
byconfirmation from AZSB.

Hence, please consider there will be delayed to deliver and install it at site. Hope this is well informed
and trust the above clarify our position in this matter.

Thank you.

Yours faithfully,
EV-DYNAMIC SDN. BHD.

W.C. YAP
Project Manager
Enclosure(s)
1. Attachment 1 –Letter of Site Survey Report (Ref: EVD/EKVE/TCSS/AZSB/0123/LET/0002)Incident Report No. EKVE/IR/276
2. Attachment 2- W/EKVE/TCSS/CC/ID/0002
3. Attachment 3- Estimated timeline

CKY/YWC/OCS/HCT/MC/AM/NR
ATTACHMENT 1
Letter of Incident Report (EKVE/IR/276)
ATTACHMENT 2
Site Survey ReportTCSS Control Room
Drawing
ATTACHMENT 3
Estimated Timeline