Professional Documents
Culture Documents
Government of India Ministry of Railway
Government of India Ministry of Railway
Government of India
Ministry of Railway
Techno-feasibility report
On
Parallel Operation of double circuit transmission lines
from GSS to TSS on Indian Railway
Report Number:
TI/REPORT/0086
Feb, 2011
Prepared by
Page: 0 of 22
Report Number: Techno-feasibility report on Parallel Operation of double circuit
TI/REPORT/0086 transmission lines from GSS to TSS on Indian Railway.
INDEX
SN Description Page
Number
1. Introduction 2
2. Status on IR 2
3. Statutory requirements & role of utility 3
4. Reduction in copper losses 3
5. Requirement of additional equipment &protection relay in TSS due to 4
Paralleling of TR line
6. Recommendations for protection requirement with parallel operation of 5
transmission lines.
7. Line capacitance 7
8. Comparison of single & parallel incoming transmission line systems 7
9. Summarized conclusion 9
Annexure
Page: 1 of 22
Report Number: Techno-feasibility report on Parallel Operation of double circuit
TI/REPORT/0086 transmission lines from GSS to TSS on Indian Railway.
1. Introduction
In order to ensure continuity of supply under all conditions, as per Para 10201 of ACTM, the
high voltage feed to the traction Sub stations is recommended either from two sources of power
or by a double circuit transmission line, so that even if one source/transmission line fails, the
other remains in service.
Number of places over IR traction supply metering is done at Grid Sub Stations (GSS),
therefore Railways have to pay utilities for the I2R (copper) losses caused on account of the
transmission lines. These losses can be reduced by parallel operation of the both incoming
transmission lines. Railway Board vide letter No. 2010/RE/161/11 dated 17-05-10 advised
RDSO to study this issue and submit a report to Board.
This report prepared under above background covers the benefits (in terms of reduction in
copper losses) & difficulties (in terms of loss of redundancy, changes in TSS equipment and
protection/fault segregation needed) likely to occur with the parallel operation of the two
incoming HV transmission lines.
1.1 Status on IR
There are number of variations in incoming power supply arrangements adopted on IR in terms
of:
a. Metering location (GSS/TSS).
b. Length of incoming transmission lines.
c. Single/double incoming circuit apart from different layouts of equipment and availability of
PTs and isolators on HV side.
d. GSS & TSS in adjoining compounds.
e. 3-phase supply from utility & transmission line network owned & maintained by Railways
(Line in Line out arrangement) e.g. NCR, ER & SER etc.
f. Feeding Post type of arrangement with only 25 kV interrupters in railway control.
In view of the above there are number of TSS layouts e.g. Type-III, IV up to Type-X. This
report considers paralleling of incoming HV transmission line circuits only for Type-III, VII,
VIII and Type-IX of TSS layouts as per drawing numbers TI/DRG/PSI/
TSSLO/RDSO/00003/02/0, TI/DRG/PSI/TSSLO/ RDSO/00007/02/0, TI/DRG/PSI/TSSLO/
RDSO/00008/02/0 & TI/DRG/PSI/TSSLO/RDSO/00009/02/0 respectively.
In 2008-2009 RDSO collected technical details from all electrified Railways pertaining to
metering location (TSS/GSS) and distance of transmission line etc. and the same is placed at
Annexure-II.
From the data collected from 10 Zonal Railways for 261 traction metering points it can be seen
that at about 88 locations metering is being done at TSS while for rest it is at GSS. The
distance between the GSS and TSS is very important and from the table in Annexure-II, it can
be seen that it varies from 0 to 40kms.
This report shall especially be of importance for locations on IR, where metering is being done
at GSS with long transmission lines and with high load factor.
Page: 2 of 22
Report Number: Techno-feasibility report on Parallel Operation of double circuit
TI/REPORT/0086 transmission lines from GSS to TSS on Indian Railway.
1.2.1.1 If the traction metering is by a “Interface metering” arrangement under open access
then clause 7–(1)-(D) should be referred for location of meter wherein metering location is to
be decided by the appropriate regulatory commission.
1.2.2 Suitable protective equipment for detecting & clearing of faults on transmission lines
are installed at the Grid sub-stations (sending end) by utilities. Railways shall have to interact
with their respective utility for technical details of transmission line & protection relays
provided for both independent incoming circuits.
The consent of the utility shall be required for paralleling at TSS end because of following
reasons:
- The total fault current at the fault location in case of paralleling shall be nearly doubled and
therefore transmission line conductor’s ratings should support this.
- Fault on any one of the transmission line may result into shut down of both the lines
therefore a suitable procedure (between utility & Railways) will have to be devised for
isolation of faulty line, restoration of supply and power block procedures based on the
protection scheme jointly agreed.
- Any fault on the transmission line will have to be cleared by both circuit breakers (scheme-I)
at GSS feeding for each line hence relay settings shall have to be modified accordingly (for
protection scheme as suggested in Para 3.4.1 below). Utility’s consent shall be necessary for
both scheme-1 or if unit protection scheme (scheme-II) as suggested in Para 3.4.2 below is to
be adopted.
- Utility must confirm that both the transmission lines are fed from same source and there is no
appreciable voltage or phase difference between the two otherwise circulating currents shall
result.
Page: 3 of 22
Report Number: Techno-feasibility report on Parallel Operation of double circuit
TI/REPORT/0086 transmission lines from GSS to TSS on Indian Railway.
In this report the load data of different TSS available with RDSO was analyzed to find out the
average loading. The load factors of TSSs were found varying between 13% to 51% and
therefore copper losses have been calculated for an average load factor of 30% (Details at
Annexure-IV). Moreover it is assumed that nearly equal current distribution takes place in the
both transmission lines (half of the load current is shared by each line).
As per Annexure –II, out of 238 TSS the 70% are having distance between TSS and GSS less
than 5km, 11% between 5 to 15 kms, 15% between 15 to 50 km & 4% of TSS are having
distance of more than 50 km therefore calculations below have been done for 5, 15 and 50 kms.
3.2 In the present arrangement, to parallel both transmission lines or for changing over the
supply to traction transformers from one circuit to another, an isolator has been provided
(except Type-VII & VIII designs of TSS layouts where no such provision is there) however if
paralleling is considered then a circuit breaker along with isolator on both side of CB shall
have to be essentially provided.
3.3 The CB provided shall have to be controlled from remote control centre (RCC) for fast
isolation & restoration of supply. A joint procedure for the same has to be devised with the
utility (refer Para 1.2.2 above).
Page: 4 of 22
Report Number: Techno-feasibility report on Parallel Operation of double circuit
TI/REPORT/0086 transmission lines from GSS to TSS on Indian Railway.
3.4.1Scheme-I
The scheme proposed is depicted in Figure-1 below. A Circuit Breaker has to be provided in
place of the isolator for paralleling. The settings of protection relays provided by utility shall
have to be re-adjusted considering the parallel operation of both transmission lines as explained
below.
3.4.1.1Both the outgoing CBs at grid substation (for each transmission line) shall have to trip in
case of fault in any one of the transmission line circuits. Two separate under voltage relays
actuated from the PT’s connected to each incoming line shall have to be provided in TSS. In
case of tripping of power supply from GSS both of these relays shall pick up and shall cause
opening of the paralleling CB at TSS. The paralleling CB at Railways end shall have no
automatic re-closing feature.
3.4.1.2 Supply end CB’s of GSS shall auto re-close after definite time delay. The faulty line CB
will trip again and lockout while CB feeding healthy transmission line shall stay live.
3.4.1.4 Control circuit (local & remote) shall be designed in such a way that Railways shall
have facility to close paralleling CB as per the requirement. If traction transformer feeding the
traction load is connected to faulty transmission line, Railways shall have to interact with the
utility and open corresponding isolator and energize the selected traction transformer from
other transmission line for feeding traction load as per the usual practice.
Figure:1
Page: 5 of 22
Report Number: Techno-feasibility report on Parallel Operation of double circuit
TI/REPORT/0086 transmission lines from GSS to TSS on Indian Railway.
The scheme suggested herein is based on the supply arrangement proposed by Tata Power
supply Co. for Mumbai suburban area.
3.4.2.1 Separate CB’s shall have to be provided for both incoming transmission lines at
Railways TSS.
3.4.2.2 The Fiber Optic based differential protection (in addition to back up protections like
Definite time OCR, REF and DPR at GSS end) shall have to be provided individually for both
lines and in case of fault, only the faulty line CBs (i.e. grid substation and Railway end) shall
trip and disconnect the faulty line only.
3.4.2.3 This protection scheme shall require dedicated Fiber Optic communication channel,
additional protection relays, CB’s, CT’s, PT’s and modifications to the control & relays panel.
Figure:2
3.4.3 Above schemes suggested should not be implemented for Line in Line out (LILO) power
supply arrangements (Type-IV, V, VI & X) because with Scheme-I, the paralleling of both
incoming circuits may result in to more time requirement for restoration of power supply after
segregation of the faulty line thereby affecting the power supplies of number of TSSs
connected in series. Similarly if Scheme-II is adopted for LILO arrangement, the complexity of
protection scheme, higher fault levels, fault isolation and space required for additional CB’s.
Page: 6 of 22
Report Number: Techno-feasibility report on Parallel Operation of double circuit
TI/REPORT/0086 transmission lines from GSS to TSS on Indian Railway.
3.4.4 If both the traction transformers at TSS are to be operated in parallel along with
paralleling of incoming HV circuits, with protection Scheme-I suggested in Para 3.4.1 above,
then in case of faults on any one of the HV circuits, reverse feeding of power through traction
transformers may occur thereby causing difficulty in segregation of faulty circuit therefore in
such cases paralleling of incoming HV transmission line circuits is not recommended.
(iii) No protection equipment Protection scheme shall have to be revised. See Para 3.0
needed at Railways end. above, otherwise segregation of faulty line in case of
fault shall take more time.
Page: 7 of 22
Report Number: Techno-feasibility report on Parallel Operation of double circuit
TI/REPORT/0086 transmission lines from GSS to TSS on Indian Railway.
Scheme-I
S.N. Equipment Quantity Unit Rate in Total Cost in Rs.
Rs. (Approx.)
1. 132 kV double pole Circuit Breaker 01 8,00000.00 8,00000.00
2. 132 kV double pole Isolator 01 2,00000.00 2,00000.00
S. Length of Yearly energy save in Per unit rate Total saving in Rs.
No transmission unit ( In 12 months )
line (Per day unit save * 365)
1. 5km 21.59*365= 7880.35 5.0 39401.00
2. 15km 64.76*365=23637.4 1,18187.00
3. 50km 215.89*365=78799.85 3,93999.00
5.1.3 It may be seen from above that implementation of Scheme-I is simpler and economical
while Scheme-II provides a technically superior and less operator dependent solution but at a
higher cost.
6.2 Metering for billing purpose for traction load on IR is being done at TSS as well as at GSS.
Theoretically paralleling of incoming HV transmission line (only for metering locations at
GSS) shall result into savings of energy charges on account of reduction in Cu losses (refer
Para 2.0). The calculations done above are indicative using average values however Railways
should study the actual loading pattern and then calculate the likely savings on account of
reduction in Cu losses using actual transmission line data (dc resistance, length of line etc.). If
implementation of either of the above suggested protection scheme is economically justifiable
then it may be implemented.
6.3 Consent & coordination of the utility is essential in implementing any arrangement of
parallel operation of incoming HV transmission lines (refer Para 1.2.2).
6.4 Changes shall be required in equipment, protection scheme and operational (coordination
procedures with utilities) arrangements at TSS (refer Para 3.0).
6.5 Paralleling should only be considered for substations with long transmission lines so as to
clearly justify benefits in terms of reduction in copper losses with reference to the expenditure
to be incurred on up gradation of substation and protection equipment.
Page: 9 of 22
Report Number: Techno-feasibility report on Parallel Operation of double circuit
TI/REPORT/0086 transmission lines from GSS to TSS on Indian Railway.
Annexure –I
Page: 10 of 22
Report Number: Techno-feasibility report on Parallel Operation of double circuit
TI/REPORT/0086 transmission lines from GSS to TSS on Indian Railway.
Annexure-II
DISTANCE
RLY DIV TSS METERING POINT BETWEEN GSS &
TSS
Page: 11 of 22
Report Number: Techno-feasibility report on Parallel Operation of double circuit
TI/REPORT/0086 transmission lines from GSS to TSS on Indian Railway.
Page: 12 of 22
Report Number: Techno-feasibility report on Parallel Operation of double circuit
TI/REPORT/0086 transmission lines from GSS to TSS on Indian Railway.
Page: 13 of 22
Report Number: Techno-feasibility report on Parallel Operation of double circuit
TI/REPORT/0086 transmission lines from GSS to TSS on Indian Railway.
Page: 14 of 22
Report Number: Techno-feasibility report on Parallel Operation of double circuit
TI/REPORT/0086 transmission lines from GSS to TSS on Indian Railway.
Page: 15 of 22
Report Number: Techno-feasibility report on Parallel Operation of double circuit
TI/REPORT/0086 transmission lines from GSS to TSS on Indian Railway.
Page: 16 of 22
Report Number: Techno-feasibility report on Parallel Operation of double circuit
TI/REPORT/0086 transmission lines from GSS to TSS on Indian Railway.
Page: 17 of 22
Report Number: Techno-feasibility report on Parallel Operation of double circuit
TI/REPORT/0086 transmission lines from GSS to TSS on Indian Railway.
Annexure-III
7. Locations of meters.-
(1) The location of interface meters, consumer meters and energy accounting and audit
meters shall be as per the Table given below :
Provided that the generating companies or licensees may install meters at additional
locations in their systems depending upon the requirement.
Table
Page: 18 of 22
Report Number: Techno-feasibility report on Parallel Operation of double circuit
TI/REPORT/0086 transmission lines from GSS to TSS on Indian Railway.
or
(i) The consumer meter shall be installed by the licensee either at consumer premises or outside
the consumer premises:
Provided that where the licensee installs the meter outside the premises of the consumer, then
the licensee shall provide real time display unit at the consumer premises for his information
to indicate the electricity consumed by the consumer:
Page: 19 of 22
Report Number: Techno-feasibility report on Parallel Operation of double circuit
TI/REPORT/0086 transmission lines from GSS to TSS on Indian Railway.
Provided further that for the billing purpose, reading of consumer meter and not the display
unit shall be taken into account.
(ii) In the event the Appropriate Commission allows supply of electricity directly from a
generating company to consumer on a dedicated transmission system, the location of the
meter will be as per their mutual agreement.
(i)Generating Stations
(1) At the stator terminal of the generator;
(2) On HV and LV sides of the station and the unit auxiliary transformers;
(3) On feeders to various auxiliaries.
(ii)Transmission System
All incoming and out going feeders (If the interface meters do notexist).
(iii)Distribution System
(1) All incoming feeders (11 kV and above);
(2) All outgoing feeders (11 kV and above);
(3) Sub-Station Transformer including Distribution Transformer – Licensee may provide the
meter on primary or secondary side or both sides depending upon the requirement for energy
accounting and audit.
Page: 20 of 22
Report Number: Techno-feasibility report on Parallel Operation of double circuit
TI/REPORT/0086 transmission lines from GSS to TSS on Indian Railway.
Annexure-IV
Railways TSS Avg. Load in MVA Load factor = 100 x Avg load/max load
Page: 21 of 22
Report Number: Techno-feasibility report on Parallel Operation of double circuit
TI/REPORT/0086 transmission lines from GSS to TSS on Indian Railway.
Annexure – V
Page: 22 of 22