Schedule B - 8259
Schedule B - 8259
Schedule B - 8259
1. INTRODUCTION
1.1 This Schedule establishes the scope of the WORK to be performed by CONTRACTOR
under this CONTRACT, and describes or references in Attachment I of this Schedule
“B” the technical requirements that CONTRACTOR shall satisfy or adhere to in
accomplishing the WORK.
1.2 Because of the technical nature of the documents referenced in this Schedule “B”,
these documents have not been translated into Arabic. CONTRACTOR and COMPANY
agree to be bound by the English text.
2. SCHEDULE REQUIREMENTS
CONTRACTOR shall achieve Final Acceptance of the WORK by Twenty (20) Gregorian
Months from Contract Signing Date (“Final Acceptance Date”). Separable portions of
the WORK specified in Attachment II to this Schedule “B” shall be completed by the dates
specified therein (“Critical Milestone Dates”).
COMPANY shall furnish only the materials, and construction and installation tools and
equipment listed in Paragraphs 3.1 and 3.2 below for use by CONTRACTOR in performing
the WORK. COMPANY will furnish these items on “as is where is” basis. CONTRACTOR
shall provide all equipment and personnel necessary to load them from a COMPANY facility
or facilities or elsewhere as specified by COMPANY, and to transport and unload them to the
WORK SITE.
These tools and equipment will remain COMPANY property. On completion of the WORK or
at any other time as directed by the COMPANY REPRESENTATIVE, CONTRACTOR shall
return them (along with unused COMPANY-supplied materials, if any) in as good condition
as when received (wear and tear excepted), during COMPANY normal working hours, to
COMPANY-designated location or locations; provided, however, that such designated
locations are no farther from the WORK SITE than the original point of COMPANY issue of
such items.
3.1.1 Plant Tags, 6.35 CM X 2.54 CM or 4.445 CM X 1.112 CM, for each individual
item of equipment and independent components to be tagged. Normally,
the COMPANY Plant Tags are made of brass; however, COMPANY may issue
Plant Tags made from other material in cases where brass tag is not
suitable for a particular type of equipment.
COMPANY shall furnish only the following construction and installation tools and
equipment for use by CONTRACTOR in performing the WORK:
B-1
Schedule “B” – Undeground Transmission Line Construction HV
No PROJECT PORTIONS, With Optional WORK
First Edition (April 2016) Supersedes:
NOTHING
CONTRACTOR shall design and engineer; procure, supply and deliver to the WORK
SITE all equipment and materials and start-up; perform quality management,
factory inspection/testing, and all associated work and services; construct, install,
test and commission; and put into service until final handing over to COMPANY, in a
satisfactorily working and operating condition, the CONNECTION OF AL
JANADRIYAH S/S 8259, IN RIYADH CITY as described below in accordance
with the Scope of Work and Technical Specifications, PTS # 22CC1088:
Ite
Particulars
m Item Description
No.
a Voltage Level 132kV
b Number of 132kV Undeground Cable Circuit 1
c Names of Circuit 8121-8259
d Names of Connecting Substations S/S 8121 and S/S 8259
CT-921813 Sheet 1 to 1
e 132kV Cable Route Plan Drawing No.
Rev.0
f Approximate Route Length of Circuit 3.5km
g Number of Conductors per Phase 1 Core
h Size of Copper Conductor 1200 mm²XLPE
i Number and type, and approximate length of 96 Single Mode Latest
underground Fiber Optic Cables (to be installed ITU-T G.652,
along the 132kV Power Cables route) 3.5km
132kV SF6 Sealing Ends for XLPE 1200mm2
2 Sets
J cable (1 Set consists of three sealing ends)
k Requirements for thrustboring/Horizontal As per Route Drawing
Directional Drilling, Concrete Encased CT-921813 Sheet 1 to 1
Ductbanks and Sand Ductbanks, and Handhole Rev.0
System at road crossings
As per Route Drawing
Requirements for associated survey and civil
l CT-921813 Sheet 1 to 1
works
Rev.0
Etc.
B-2
Schedule “B” – Undeground Transmission Line Construction HV
No PROJECT PORTIONS, With Optional WORK
First Edition (April 2016) Supersedes:
4.2 New 132 KV U/G Cable Circuit 9046-8259
Ite
Particulars
m Item Description
No.
a Voltage Level 132kV
b Number of 132kV Undeground Cable Circuit 1
c Names of Circuit 9046-8259
d Names of Connecting Substations BSP 9046 and S/S 8259
CT-921813 Sheet 1 to 1
e 132kV Cable Route Plan Drawing No.
Rev.0
f Approximate Route Length of Circuit 12.4km
g Number of Conductors per Phase 1 Core
h Size of Copper Conductor 1200 mm²XLPE
i Number and type, and approximate length of 96 Single Mode Latest
underground Fiber Optic Cables (to be installed ITU-T G.652,
along the 132kV Power Cables route) 12.4km
132kV SF6 Sealing Ends for XLPE 1200mm2
2 Sets
J cable (1 Set consists of three sealing ends)
k Requirements for thrustboring/Horizontal As per Route Drawing
Directional Drilling, Concrete Encased CT-921813 Sheet 1 to 1
Ductbanks and Sand Ductbanks, and Handhole Rev.0
System at road crossings
As per Route Drawing
Requirements for associated survey and civil
l CT-921813 Sheet 1 to 1
works
Rev.0
Etc.
The detailed Scope of Work for Protection Requirements ,refere Substation of PTS #
22CN1087.
Gassing and degassing at substation at existing BSP S/S 9046 (132 kV Side), S/S
8121, and new S/S 8259 shall be done, Gassing and Degassing WORK, including
electrical tests is the Transmission Line CONTRACTOR’S responsibility but it should
be carried out under supervision of a Specialist Qualified & Authorized representative
of GIS Manufacturer or as approved by COMPANY.
B-3
Schedule “B” – Undeground Transmission Line Construction HV
No PROJECT PORTIONS, With Optional WORK
First Edition (April 2016) Supersedes:
As per the details given in Clause 4.04 of Section III of PTS # PTS # 22CC1088.
4.7.1 “Start-Up Spare Parts” are defined as spare parts or components, which
may be required during testing and commissioning up to Preliminary
Acceptance of the PROJECT at the WORK SITE.
4.7.2 CONTRACTOR shall provide all start-up spare parts for the PROJECT required
during testing and commissioning up to Preliminary Acceptance of the
PROJECT pursuant to Paragraphs 2.1.4 and 6.1 of Schedule “A” of this
CONTRACT.
4.7.3 The compensation payable to CONTRACTOR for provision of all these items
is included in the CONTRACT Price set forth in Paragraph 1.1 of Schedule
“C” and specifically included in the relevant material/equipment price
components indicated in Pricing Attachment to Schedule “C” of this
CONTRACT.
4.7.4 CONTRACTOR shall deliver these start-up spare parts along with the
materials/equipment for the PROJECT.
4.7.6 Prior to the start of testing and commissioning, CONTRACTOR shall ensure
that it has at the WORK SITE sufficient quantity of all start-up spares, which
may be required during testing and commissioning up to Preliminary
Acceptance of the PROJECT.
4.7.7 All unused start-up spare parts will be turned over to COMPANY on
Preliminary Acceptance.
B-4
Schedule “B” – Undeground Transmission Line Construction HV
No PROJECT PORTIONS, With Optional WORK
First Edition (April 2016) Supersedes:
a) In-Factory Theoretical & Practical Training During Manufacturing
of Equipment
No. of
Item
Equipment Name Trainees for Course Length
No.
this contract
Under Ground Cable
1 (UGC Training ) for 5 26 days
Maintenance
Under Ground Power
2 3 5 days
Cables
Joints, Terminations &
3 Assessories for Power 5 12 days
Cables for Engineers.
CONTRACTOR shall also provide the items listed below. The compensation
payable to CONTRACTOR for provision of these items is included in the lump
sum CONTRACT Price set forth in Paragraph 1.1 of Schedule “C” and
indicated in Pricing Attachment to Schedule “C” of this CONTRACT.
B-5
Schedule “B” – Undeground Transmission Line Construction HV
No PROJECT PORTIONS, With Optional WORK
First Edition (April 2016) Supersedes:
These equipment, which shall remain the property of the
CONTRACTOR after the completion of the PROJECT, shall include,
but not be limited to, the following:
Item
Amenities Qty Unit
No.
Refer to Paragraph 3.12 of SOW/TS,
1 1 Lot
PTS # 22CC1088.
All cost and expenses in connection with such visits by the COMPANY
REPRESENTATIVES is included in the lump sum CONTRACT Price set forth in
Paragraph 1.1 of Schedule “C”.
B-6
Schedule “B” – Undeground Transmission Line Construction HV
No PROJECT PORTIONS, With Optional WORK
First Edition (April 2016) Supersedes:
5. SUMMARY OF DOCUMENTS
This Schedule “B” includes all of the documents listed below, which are hereby made part of
this CONTRACT.
This Schedule “B” includes all the Drawings, Standards, Specifications and
Calculation Sheets indicated in Attachment I to this Schedule “B”, which by
reference are made part of this CONTRACT.
This Schedule “B” includes the Scope of Work and Technical Specifications, which by
reference is made part of this CONTRACT.
A. COMPANY Letter(s)
B. CONTRACTOR Letter(s)
B-7
Schedule “B” – Undeground Transmission Line Construction HV
No PROJECT PORTIONS, With Optional WORK
First Edition (April 2016) Supersedes:
5.3.2 Minutes of the Bid Clarification Meeting(s) (“The Minutes”)
This Schedule “B” includes the Instructions to Bidders for Commercial Proposal,
Instructions to Bidders for Technical Proposal, and the following pre-bid clarification
letters and addenda to the Bid Documents, which were issued to CONTRACTOR
during the preparation of its Commercial Proposal and Technical Proposal for this
CONTRACT, and which by reference are made part of this CONTRACT:
B-8
Schedule “B” – Undeground Transmission Line Construction HV
No PROJECT PORTIONS, With Optional WORK
First Edition (April 2016) Supersedes: