Professional Documents
Culture Documents
CE2CBM-2022 - 23-Quality in Construction Projects PDF
CE2CBM-2022 - 23-Quality in Construction Projects PDF
Meeting specification
Factory production
Product meeting this
control.
standard will have a Certificate issued
Declaration of Performance. after 3rd party audit
Specification
Validation
Design
Procurement
Build
Inspection
Testing
Commissioning
Handover
Aftercare
A well managed project have these elements being co-ordinated from Day 1
• New build.
• Ground conditions
• Underground Service locations
Insert footer on Slide Master 14
Construction quality journey
Design
• Quality checks
• 3 D model clash detection
• Drawing review and approval
• Technical submittal
• Sample approval
• Bench marking
• Inspected against:
• Drawings
• Specifications
• Standards
• Benchmarks
• Manufactures installation standards
Insert footer on Slide Master 22
Construction quality journey
Inspection/snagging and improvements
Share with
others Amend plans,
retrain etc.
• Integrity testing
• Slump
• Electrostatic
• CCTV of drainage
• Air test
Client specification
Act Plan
Remedial action Production of ;
Request for change Detailed construction programme
Design improvements Detailed design development
Retraining Quality Strategy
Material reselection Sample / Benchmark approvals
Project specific training
Check Do
Insert footer on Slide Master 31
Continuous improvement
Client specification
Act Plan
Make design or production Production of Benchmark
changes to ensure that schedule
product meets
requirements
Check Do
Insert footer on Slide Master 32
Quality Assurance Vs Quality Control
Assurance.
• all the planned and systematic activities implemented within the
quality system that can be demonstrated to provide confidence that a
product or service will fulfil requirements for quality
Control.
• the operational techniques and activities used to fulfil requirements
for quality
Assurance (Verification)
• Structural engineers report
• A structural engineer should
verify that structural elements of the
design are safe and meet the relevant
regulatory standards.
Control (Validation)
• Weld integrity test
• Ultra sonic,
• Dye penetration
• X-ray/ NDT
Assurance (Verification)
• Geotechnical survey confirms
ground conditions
• Technical submittal for
proposed concrete mix.
• The piling Inspection and Test
Plan identifies each
characteristic that is critical to
the performance of the pile.
Control
• Concrete cube test
• Steel CARE certificate
• GPS location
• Integrity testing
Poor communication.
• The guys in the suits don’t talk to the guys in the boots.
• Result, wrong drawings, wrong materials, not to standard etc.
• Poor materials.
Initial
estimated cost
£6M
• Supporting cables
failed during
construction
• No workers were
under the deck at the
time
It could have
been fatal.
Insert footer on Slide Master 44
Quality Assurance of Materials
What can go wrong
Poor specification.
Design and Build “Employers Requirement” (ER) asked for “Single drainer
stainless steel sink”.
The contractor provided the cheapest from the local supplier for £40
The client really wanted a high specification Franke that cost £250 !