POW Rehabilitation of Agribusiness, Tourism and Knowledge Management Office (ATK)
POW Rehabilitation of Agribusiness, Tourism and Knowledge Management Office (ATK)
DEPARTMENT OF AGRICULTURE
REGIONAL FIELD OFFICE III
CITY OF SAN FERNANDO, PAMPANGA
Project Title: Rehabilitation of Agribusiness, Tourism and Knowledge Management Office (ATK)
Category: Rehabilitation
Brgy/Mun/Province: Brgy. Paraiso, Tarlac City
Total Project Cost: Php 55,676.91
Physical Target: 471.62 Sq.m
Project Duration: 6 c.d.
Implementn. Mode: By Contract
Project Description: Area (sq.m.) Heavy Equipment Needed Light Equipment Needed Technical Personnel
Structure, Interior Wall Area 293.25 Owned Leased Description Owned Leased Description Description
2 Laborer
Item No. Scope of Work % Weight Quantity Unit Unit Cost Total
Prepared by:
1
Name of project: Rehabilitation of Agribusiness, Tourism and Knowledge Management Office (ATK)
Location: Brgy. Paraiso, Tarlac City
1003 CARPENTRY WORKS - 1,265.65 819.74 2,085.39 7,650.00 9,735.39 1,460.31 973.54 608.46 12,777.70 1 61,072
1032 PAINT WORKS - 5,969.06 3,866.06 9,835.12 22,850.00 32,685.12 4,902.77 3,268.51 2,042.82 42,899.22 1 109,474
Total - 7,234.71 4,685.80 11,920.51 30,500.00 42,420.51 6,363.08 4,242.05 2,651.28 55,676.91 55676.91 83,500
0.00 14,402
DPWH: D.O No. 197 Series of 2016 13,256.41
Estimated Direct Cost (EDC) Indirect Cost % for OCM & Profit Total Indirect Cost
Php OCM Profit % for OCM &
(% of EDC) (% of EDC) Profit
Up to 5M 15 10 25
Above 5M up to 50M 12 8 20
Above 50M up to 150M 10 8 18
Above 150M 8 8 16
OCM 15%
What to USE?
Profit 10%
13,256.41
2
ITEM No.: 1032 UNIT: sq.m.
DESCRIPTION: PAINT WORKS QUANTITY: 471.62
3
ITEM No.: 1003 UNIT: sq.m.
DESCRIPTION: CARPENTRY WORKS QUANTITY: 4.50
4
Name of Project: Rehabilitation of Agribusiness, Tourism and Knowledge Management Office (ATK)
Location: Brgy. Paraiso, Tarlac City
BACK UP COMPUTATION
for Ceiling
Note:
1 L / 12 sq m (Cover of paint)
1 tin = 16 L
1 gallon = 4 L